WORK_SPECIFICATIONS-ATTACHMENT_2.pdf
PDF 2 MB Posted
- Solicitation number
- HSCG85-16-Q-P45T58
About this file
SPECIFICATIONS - ATTACHMENT 2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PRICING_SCHEDULE-COBB-ATTACHMENT_1-REV-AMEND_0002.xlsx | XLSX spreadsheet | |
| AMEND_NO_0002_-P45T58.pdf | ||
| NON_DISCLOSURE_AGREEMENT-ATTACHMENT_6.docx | DOCX document | |
| AMEND_NO_01_-P45T58.pdf | ||
| RFQ-P45T58-GEORGE_COBB-FINAL-AMEND_01.docx | DOCX document | |
| RFQ-P45T58-GEORGE_COBB-FINAL.docx | DOCX document | |
| RFQ-P45T58-GEORGE_COBB-FINAL.docx | DOCX document | |
| SECTION_B_PRICING-ATTACHMENT_1.xlsx | XLSX spreadsheet | |
| GOVERNMENT_PROPERTY_REPORT-ATTACHMENT_3.docx | DOCX document | |
| Past_Performance_Information_Form-ATTACHMENT_4.docx | DOCX document | |
| Request_for_Clarification-ATTACHMENT_5.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC GEORGE COBB (WLM 564)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2016
Developed By: Robert K Woods2
(Rev-0, 30 July 2015)
USCGC GEORGE COBB (WLM-175) DRYDOCK AVAILABILITY FY2016
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property ................................................................................. xi Consolidated List of Critical Inspection Items ........................................................................................... xii Principal Characteristics - TENDER ......................................................................................................... xiii General Requirements WORK ITEM 1: Hull Plating (U/W Body), Inspect WORK ITEM 2: Appendages (U/W), Leak Test WORK ITEM 3: Appendages (U/W) - Internal, Preserve WORK ITEM 4: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 5: Tanks (Hydraulic Oil Stowage and Service), Clean and Inspect WORK ITEM 6: Tanks (Potable Water), Clean and Inspect WORK ITEM 7: Tanks (Lube Oil), Clean and Inspect WORK ITEM 8: Tanks (Ballast), Clean and Inspect WORK ITEM 9: Voids (Accessible), Clean and Inspect WORK ITEM 10: Tanks (Dirty Oil and Waste), Clean and Inspect WORK ITEM 11: Z-Drive Propulsion Units, Overhaul WORK ITEM 12: Z-Drive Propulsion Unit, Renew (Drydock) WORK ITEM 13: SW Heat Exchangers, Clean, Inspect and Hydro WORK ITEM 14: Fathometer Transducer, General Maintenance WORK ITEM 15: Underwater (Speed) Log Transducer(s), Overhaul WORK ITEM 16: Sea Valves and Waster Pieces, Overhaul or Renew WORK ITEM 17: Sea Strainers - Duplex (All Sizes), Overhaul WORK ITEM 18: Sea Bay, Preserve - Partial WORK ITEM 19: Sea Bay, Clean and Inspect WORK ITEM 20: Sea Bay, Preserve 100% WORK ITEM 21: Compressed Air Receivers and System Valves (All), Clean, Inspect, Hydro and Lift . 91 WORK ITEM 22: Thruster Unit (General), Overhaul WORK ITEM 23: Hydraulic Chain Stoppers, Inspect and Test WORK ITEM 24: Anchor Chain(s) and Ground Tackle, Inspect and Repair WORK ITEM 25: Towing Bitts, Chocks, and Fairleads, Inspect and Test WORK ITEM 26: Grey Water Holding Tank(s), Clean and Inspect WORK ITEM 27: Sewage Holding Tank(s), Clean and Inspect WORK ITEM 28: Sewage Piping, Clean and Flush WORK ITEM 29: Tanks (Ballast), Preserve “100%” WORK ITEM 30: Tanks (Ballast), Preserve “Partial” WORK ITEM 31: Chain Locker, Preserve 100% WORK ITEM 32: Tanks (Dirty Oil and Waste), Preserve “100%” WORK ITEM 33: Tanks (Dirty Oil and Waste), Preserve “Partial” WORK ITEM 34: Tanks (Grey Water Holding), Preserve “100%” WORK ITEM 35: Tanks (Grey Water Holding), Preserve “Partial” WORK ITEM 36: Tanks (Sewage Holding), Preserve “100%” WORK ITEM 37: Tanks (Sewage Holding), Preserve “Partial” WORK ITEM 38: Tanks (Sewage Vacuum Collection), Preserve “100%” WORK ITEM 39: Tanks (Sewage Vacuum Collection), Preserve “Partial” WORK ITEM 40: Accessible Void(s), Preserve “Partial” WORK ITEM 41: Tanks (Potable Water), Preserve “100%” WORK ITEM 42: Tanks (Potable Water), Preserve “Partial” iii (Rev-0)
WORK ITEM 43: U/W Body, Preserve (Partial - Condition A) WORK ITEM 44: U/W Body, Preserve (Partial - Condition B) WORK ITEM 45: U/W Body, Preserve (Partial - Condition C) WORK ITEM 46: Cathodic Protection / Zinc Anodes, Renew WLM-175 WORK ITEM 47: Drydock WORK ITEM 48: Temporary Services, Provide - Cutter WORK ITEM 49: Sea Trial Performance, Support, Provide WORK ITEM 50: Main Mast, Preserve - Partial WORK ITEM 51: Compartment Insulation (General), Renew WORK ITEM 52: Buoy Deck Cleats, Modify WORK ITEM 53: Hull Plating (U/W Body), Ultrasonic Testing WORK ITEM 54: Tanks (MP Fuel Stowage and Overflow), Clean and Inspect WORK ITEM 55: Hull Plating Freeboard (Buoy Port Areas), Preserve WORK ITEM 56: Hull Plating Freeboard, Preserve - Partial WORK ITEM 57: Hull Plating Freeboard, Preserve “100%” WORK ITEM 58: Equipment Foundations, Preserve WORK ITEM 59: Internal Fume-Tight Joiner Door and Frame, Renew WORK ITEM 60: Deck Drain & Sounding Caps, Repair WORK ITEM 61: Sewage Vent Pipe, Renew WORK ITEM 62: Vent Duct Insulation, Renew WORK ITEM 63: Heat Pump 5 Bulkhead, Preserve WORK ITEM 64: Searchlights, Repair WORK ITEM 65: U/W Body, Preserve (100%) iv (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 170-1, Rev H; Mast Arrangement & Details
Coast Guard Drawing 175 WLM 114-001, Rev D, Shell Appendages
Coast Guard Drawing 175 WLM 180-005, Rev K, Foundations Hull Block 940
Coast Guard Drawing 175 WLM 184-001, Rev-, CRP-V850 Transducer Adapter Ring
Coast Guard Drawing 175 WLM 184-001, V850 Transducer Adaptor Ring
Coast Guard Drawing 175 WLM 201-001, Rev C, Machinery Spaces Arrangement
Coast Guard Drawing 175 WLM 243-2, Rev F, Propulsion Shaft Arrangement
Coast Guard Drawing 175 WLM 245-001, Rev A, Propeller
Coast Guard Drawing 175 WLM 245-002, Rev A, Z-Drive Propeller Details, Modified Design
Coast Guard Drawing 175 WLM 245-1, Rev A, Propeller
Coast Guard Drawing 175 WLM 256-001, Rev H, Seawater Cooling System Diagram
Coast Guard Drawing 175 WLM 256-003, Rev D, Seawater Cooling System FR 61 Forward
Coast Guard Drawing 175 WLM 256-004, Rev J, Sea Water Cooling System Arrangements and Details
Coast Guard Drawing 175 WLM 256-004, Rev J, Sheets 5 and 13, Seawater Cooling System A & D, Hull Blocks 940-970
Coast Guard Drawing 175 WLM 256-005, Rev -, Z-Drive Lube Oil Heat Exchanger Tube Bundle, Replacement and Piping Mods
Coast Guard Drawing 175 WLM 256-012, Rev A, Auxiliary Seawater System Piping Mods
Coast Guard Drawing 175 WLM 256-013, Rev -, Sea Bay Thermometer Installation
Coast Guard Drawing 175 WLM 505-003, Rev A, Sea Connection Arrangements vi (Rev-0)
Coast Guard Drawing 175 WLM 506-001, Rev G, Overflows, Air Escapes & Sounding Tubes Diagram
Coast Guard Drawing 175 WLM 533-006, Rev D, Independent Tank Potable Water Hb 950
Coast Guard Drawing 175 WLM 541-001, Rev H, Fuel Oil System Diagram
Coast Guard Drawing 175 WLM 541-006, Rev C, Independent Tanks, Emergency Generator Day Tank
IIP:7-1
Coast Guard Drawing 175 WLM 551-001, Rev H, Compressed Air System Diagram
Coast Guard Drawing 175 WLM 556-001, Rev L, Hydraulic System Diagram
Coast Guard Drawing 175 WLM 561-001, Rev J, Z-Drive Hydraulic System Diagram
Coast Guard Drawing 175 WLM 573-050, Rev A, Hydraulic Piping Installation for Chain Stopper
Coast Guard Drawing 175 WLM 573-051, Rev B, Chain Stopper Structural Modifications for Hydraulic Roller Assembly
Coast Guard Drawing 175 WLM 581-001, Rev E, Anchor Handling System Arrangement
Coast Guard Drawing 175 WLM 582-001, Rev D, Mooring and Towing, A & D
Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage & Waste Water System Diagram
Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage and Waste Water System Diagram
Coast Guard Drawing 175 WLM 593-009, Rev E, Independent Tanks, Sewage Holding Tank
Coast Guard Drawing 175 WLM 601-001, Rev L, General Arrangement and Inboard and Outboard Profiles
Coast Guard Drawing 175 WLM 601-001, Rev P, General Arrangement and Inboard and Outboard Profiles
Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Drawings (552-564)
Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Drawings 552-564
Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans
Coast Guard Drawing 175 WLM 601-003, Rev L; Booklet Of General Drawings 552-564
Coast Guard Drawing 175 WLM 601-1, Rev N, Arrangement, Inboard And Outboard Profiles
Coast Guard Drawing 175 WLM 633-001, Rev D, Cathodic Protection
Coast Guard Drawing 175 WLM 635-001, Rev F, Hull Thermal & Acoustic Insulation Schedule
Coast Guard Drawing 175 WLM 635-001, Rev F, Hull Thermal and Acoustic Insulation Schedule
Coast Guard Drawing 175 WLM 801-001, Rev A, Hull Lines
Coast Guard Drawing 175 WLM 801-003, Rev A, Curves of Form
Coast Guard Drawing 175 WLM 801-006, Rev H, Docking Plan
Coast Guard Drawing 175 WLM 801-006, Rev J, Docking Drawing
Coast Guard Drawing 175 WLM 801-019, Rev C, Shell Expansion
Coast Guard Drawing 175-WLM 505-1, Rev C, General Requirements for Piping Systems
Coast Guard Drawing 175-WLM 506-1, Rev G, Overflows, Air Escapes & Sounding Tubes Diagrams
Coast Guard Drawing 175-WLM 506-9, Rev A, Sewage Tank Vent Mods
Coast Guard Drawing 175-WLM 508-1, Rev B, Piping & Machinery Insulation
Coast Guard Drawing 175-WLM 509-1, Rev A, Duct, Trunk, & Machinery Insulation Details
Coast Guard Drawing 175-WLM 528-2, Rev H, Weather Deck Drains Diagram
Coast Guard Drawing 175-WLM 551-5, Rev E, Compressed Air System A & D Hull Block 940, 950
Coast Guard Drawing 175-WLM 568-001, Rev B, Bow Thruster Arrangement & Detail
Coast Guard Drawing 175-WLM 180-7, Rev J, Foundations Hull Block 960 vii (Rev-0)
Coast Guard Drawing 175-WLM 256-001, Rev H, Seawater Cooling System Diagram
Coast Guard Drawing 175-WLM 256-003, Rev A, Seawater Cooling System, Fr 61 Fwd Blocks 910, 920, Coast Guard Drawing 175-WLM 256-004, Rev J, Seawater Cooling System A & D, Hull Blks 940-970
Coast Guard Drawing 175-WLM 330-7, Rev L, Lighting System 01 Level & Above Hull Block 960 / 970 Partial
Coast Guard Drawing 175-WLM 422-1, Rev G, Navigation, Signal & Searchlight Block, Isometric and Arrangements
Coast Guard Drawing 175-WLM 422-2, Rev F, Navigation, Signal & Searchlight Elementary Wiring Diagram
Coast Guard Drawing 175-WLM 423-1, Rev P, Electronic Navigation System Block & Isometric
Coast Guard Drawing 175-WLM 445-1, Rev H, Radio Communication Systems Block Diagram and Isometric
Coast Guard Drawing 175-WLM 573-001, Rev T, Buoy Deck Arrangement
Coast Guard Drawing 175-WLM 601-001, Rev P, General Arr Inboard and Outboard Profiles
Coast Guard Drawing 175-WLM 601-003, Rev L, Booklet of General Plans
Coast Guard Drawing 175-WLM 635-1, Rev F, Hull Thermal & Acoustic Insulation Schedule
Coast Guard Drawing 175-WLM 910-002, Rev H, Hull Block 910 Modules
Coast Guard Drawing 175-WLM 990-001, Rev J, Hull Block Erection Plan
Coast Guard Drawing 175-WLM-624-001, Rev F, Joiner Door Schedule
Coast Guard Drawing 175-WLM-635-001, Rev F, Hull Thermal and Acoustic Insulation Schedule
Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem
Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters
Coast Guard Fleet Drawing FL-2605-29, Rev H, Chain Stopper System – Rising Sheave Assembly
NAVSEA Drawing 2803-980209, Plates, Label
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation Details
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual
Coast Guard Technical Publication (TP) 3261, SWBS 422, Aug 1998, Searchlight
Coast Guard Technical Publication (TP) 3446, Jun 2009, Doppler Speed Log, Model SRD-500 Dual Axis
Coast Guard Technical Publication (TP) 3628, 1/1/1999; Vol 4 of 9, Instruction Manual, Bow Thruster
Coast Guard Technical Publication (TP) 3632, March 2014, Chapter 583, Section C, Technical Manual for Slewing Arm Davit Model D6000CT
Coast Guard Technical Publication (TP) 3653, Jul 2013; SWBS 245, Section A; Z-DRIVE - MODEL 1350-H
Coast Guard Technical Publication (TP) 3939, SWBS 573-A, Apr 2007, Rising Sheave Chain Stopper
Coast Guard Technical Publication (TP) 5458, SWBS 555, Oct 2012, Winch, Radial – Model 50.2PT (270 WMEC A-Class)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements viii (Rev-0)
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary Machine Systems Installation Details
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Preserve Ship Structures
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary Services
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2014, Temporary Hull Accesses
Time Compliance Technical Order 175-A-057, Sewage Tank Vent Piping, 2007
OTHER REFERENCES
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities
American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System Components - Health Effects
American National Standards Institute/NSF International (ANSI/NSF) 61, 2013, Drinking Water System Components - Health Effects
American Society for Testing and Materials (ASTM) International F1508, 2010, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End
American Society of Mechanical Engineers (ASME) B16.34, 2013, Valves-Flanged, Threaded, and Welding End
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D3359, 2009, Standard Test Methods for Measuring Adhesion by Tape Test
ASTM International (ASTM) D3359, 2010, Standard Test Methods for Measuring Adhesion by Tape Test
ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust- Petrolatum
Commercial Item Description (CID) A-A-59323, Rev A, Cloths, Cleaning, Low-Lint
Commercial Item Description (CID) A-A-59588, 2013, Rubber Silicone ix (Rev-0)
DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Federal Specification (Fed Spec) RR-C-271, Rev E, Dec 2010, Chain and Attachments, Welded and Weldless
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2011 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves
MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-C-24633, Apr 1998, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded
MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of Reliability Is Required
MIL-DTL-23549, Dec 2011, Grease, General Purpose
MIL-F-24402, May 1995, Filters (Hydraulic), Filter Elements (High Efficiency), and Filter Differential Pressure Indicators, General Specification
MIL-I-3064, Mar 1991, Insulation, Electrical, Plastic-Sealer
MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application
MIL-PRF-24647, 2013, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-S-19622/16, Dec 1992, Stuffing Tube, Nylon, Size 1: Packing Assemblies for
MIL-S-19622/17, Jun 1986, Stuffing Tube, Nylon, Size 2: Packing Assemblies for
MIL-S-19622/3, Dec 1992, Stuffing Tubes, Nylon, NPT
MIL-S-24235/10, Dec 1992, Stuffing Tubes, Metal, and Packing Assemblies for Electric Cables, Steel, for Decks and Bulkheads without Pipe Protection
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-STD-2003-3, Sep 2009, Electric Plant Installation Standard Methods for Surface Ships & Submarines (Penetrations)
Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA- PRO-160, Jan 2006, Chapter 16, Cofferdams x (Rev-0)
Naval Ship's Technical Manual (NSTM) Chapter 635, Jul 1998, Thermal, Fire and Acoustic Insulation
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 16 (SSPC-SP 16), 2010, Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steels, and Non-Ferrous Metals
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning
The Society for Protective Coatings (SSPC), May 2012, Paint Application Specification No. 2 (PA-2), Measurement of Dry Coating Thickness with Magnetic Gages
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 6/NACE No. 3, 2007, Commercial Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 7/NACE No.4, 2007, Brush-Off Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-4/NACE WJ-4, 2012, Waterjet Cleaning of Metals – Light Cleaning
The Society for Protective Coatings (SSPC)/NACE Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2004, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings SSPC-SP 10/NACE No.2, Jan 2007, Near-White Blast Cleaning
The Society for Protective Coatings SSPC-SP 11, Jul 2012, Power Tool Cleaning to Bare Metal xi (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM
DESCRIPTION
NSN/PN QTY ESTIMATED
COST
($/UNIT)
11 N Z drive seal Set PN: D8202363 2 ea. 25,493.00 11 N **Seal ring PN: B7807158 2 ea. 2,206.00 11 Y Clutch Overhaul kit 2010-01-551-1161 2 ea. 7,959.62 11 N **Seal ring B8106487 2 ea. 7,007 11 N **Lantern Ring B7802062 2 ea. 1,017 12 Y Starboard Z-Drive
(CCW rotation) Rolls Royce 1 ea. 500,250.00
12 Y Port Z-Drive (CW rotation)
Rolls Royce 1 ea. 500,250.00
12 Y Cover, Steering gear 2530-01-583-0164 2 ea. 1,200.00 12 Y Special Alignment
Pointer Set CG Tool 1 ea. 500
14 N ***Fathometer Transducer, Shallow Water, 50-200 kHz
NSN: 5845-01-470-2500
Airmar Technology SS505 {A-Team Note: Use NSN 5845-01-518-6920 for an assembly consisting of the
SQN-18 hull adapter plate & transducer ($2,682.90); turn in any old adapter plate for refurbishment to servicing
ESU/ESD}
1 ea. 148.92
22 N Seal kit, Bow thruster
NSN: 2010-01-555-9048 1 ea. 3,634.00
22 N Zinc Anode PN: A000SM44197 9 ea. 113.75 23 N Repair Kit Assembly NSN: 2040-01-496-9418 2 ea. 1,409.15 47 Y *Transducer Cover
Plate N/A 3 ea. 50.00
52 Y Cleat, Rope (15 in.
steel)
NSN: 2040-01-614-2587 6 ea.
52 Y Winch, Drum, Hand Operated
NSN: 3950-01-614-5150 4 ea.
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item
Title
2 Appendages (U/W), Leak Test
4 Tanks (MP Fuel Service), Clean and Inspect
11 Z-Drive Propulsion Units, Overhaul
17 Sea Strainers - Duplex (All Sizes), Overhaul
19 Sea Bay, Clean and Inspect
23 Hydraulic Chain Stoppers, Inspect and Test
24 Anchor Chain(s) and Ground Tackle, Inspect and Repair
53 Hull Plating (U/W Body), Ultrasonic Testing
54 Tanks (MP Fuel Stowage and Overflow), Clean and Inspect
65 U/W Body, Preserve (100%) xiii (Rev-0)
PRINCIPAL CHARACTERISTICS - TENDER
175' WLM, BUOY TENDER
PHYSICAL
Length overall 174' 8" Length between perpendiculars 155' 1" Depth 14' 8" Maximum beam 36' 0" Designed draft 8' 0" Mast height (above 8' waterline) 58' 8" Frame spacing 20" Full load displacement 855.15 Long Tons SW Light load displacement 719.78 Long Tons SW Minimum op condition displ 852.19 Long Tons SW
HULL
Hull material Steel
MACHINERY
Main propulsion Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM
Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM
Reduction gears Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio Shaft seal John Crane Type ND Shaft bearings Five pedestal mounted, Cooper split roller bearings Number of propellers 2 Number of blades 4 Diameter 57.1" Rudders None; Z-drive Ship's service generators Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800
RPM
Emergency diesel generator One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM
TANK CAPACITIES
Diesel oil capacity (100%) 16,385 gal Fresh water capacity (100%) 7,339 gal Lubricating oil (100%) 86 gal
1 (Rev-0)
00000_0315_FLT
REC_00000_FLT_ Commercial Project @ Contractor’ Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, 3 (Rev-0) and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to adequately accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
4 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down
(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
5 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL.
HUMID-
ITY DEW
PT.
SURFACE AMBIENT
ΔT
| DP -
Surface |
6 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
Location of Work (Frame References) Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
7 (Rev-0)
8 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):
_____ mils _____ mils _____ mils _____ mils _____ mils
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15
DATE TEST LOCATIONS
CONDUCTIVITY
(microsiemens/cm)
10 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
Coating Mfg Product Name Batch # Induction
Time Coating System Sequence
(Primer/Touchup/3rd Coat, etc.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL
READING (BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before Adjustments
After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before Adjustments
After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before Adjustments
After Adjustments
Avg.
Application Method (Airless, Conventional Spray, Rolled) Average DFT
11 (Rev-0)
11000_0814_FLT
REC_11000_UWHIB_FLT_175’ WLM (ALL) (1211)
WORK ITEM 1: Hull Plating (U/W Body), Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 114-001, Rev D, Shell Appendages
Coast Guard Drawing 175 WLM 801-006, Rev H, Docking Plan
Coast Guard Drawing 175 WLM 801-019, Rev C, Shell Expansion
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
The Society for Protective Coatings (SSPC), May 2012, Paint Application Specification No. 2 (PA-2), Measurement of Dry Coating Thickness with Magnetic Gages
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
12 (Rev-0)
Not applicable.
3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2 (References) as guidance. The Contractor shall provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:
A hull repair supervisor and a marker.
Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.
NOTES
1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.
3.2.1 Hull plating.
3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.
3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.
3.2.2 Sea chests and all other cooling system intake components. The Contractor shall inspect all sea chests, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.
3.2.3 Propeller and shaft associated components. The Contractor shall inspect the condition of propellers for propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade; inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.
13 (Rev-0)
3.2.4 Transducers. The Contractor shall check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.
3.2.5 Zinc anodes.
3.2.5.1 The Contractor shall remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.
3.1.5.2 The Contractor shall visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.
3.2.6 Coating system inspections. The Contractor shall accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB). Document the condition found as “Partial - Condition A”, “Partial - Condition B”, “Partial Condition C”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.
NOTE
The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector
– see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.2.6.1 Visual. Perform a visual inspection of the existing U/W body coating system.
3.2.6.2 Dry film thickness(DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.
3.2.6.3 Coating system thickness and scheme inspection. Perform a microscopic observation of precision angular cuts in the coating system film (“Tooke Paint Inspection”), in accordacne with ASTM D4138, and measure the of total coating thickness and thickness of each individual coat of paint, in addition to identifying/verifying the existing color scheme for each coat of paint comprising the coating system.
NOTE
The Tooke Paint Inspection Gage/Gauge (Plastic) is a precision tool for inspection and thickness measurement (ASTM D4138) of single or multiple coats on any substrate, and for microscopic observation and measurement of substrate and film defects. The gage uses an illuminated 50-power microscope with measuring reticle, and mounts tungsten carbide cutting tips for precise incision of the work surface.
Direct measurement of total coating thickness and thickness of individual coats of paint is a unique capability of the Tooke Paint Inspection Gage/Gauge. Thus, in addition to routine use, it often serves as a “referee” instrument to calibrate indirect or non-destructive thickness measuring instruments.
14 (Rev-0)
Other uses include assessment of substrate conditions and coating adhesion, and observation of microscopic cracking, tendency for brittleness, cratering, or other microscopic film symptoms.
3.2.6.3.1 Take a total of four readings in locations designated by the Coast Guard Inspector, and as follows: one each, port and starboard, in the boot-top area; and one each, port and starboard, below the boot-topping.
3.2.6.3.2 Ensure that the repair of all areas affected by the destructive Tooke Gauge inspection is included in the optional repair work item that is activated by the result of the inspection.
4. NOTES
4.1 Definitions.
4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.
4.1.2 "Partial - Condition B": The condition that exists where the anticorrosive (AC) undercoating system has incurred damage, but, the u/w body hull substrate is not exposed in any location.
4.1.3 "Partial - Condition C”: The condition that exists where damage is confined to the antifoulant (AF) topcoating; the epoxy undercoating system is not exposed in any location.
4.1.4 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.
4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
15 (Rev-0)
11400_0415_FLT
REC_11400_UWAppndgs_FLT_175’ WLM (ALL) (1111)
WORK ITEM 2: Appendages (U/W), Leak Test
1. SCOPE
1.1 Intent. This work item describes…