PAGE_2_A0002.doc
DOC document 29 KB Posted
- Solicitation number
- HSCG85-15-R-P45W51
About this file
Pages 2-3 of SF 30
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SHERMAN_FY15__MDE_REALIGNMENT_SADDLE_REV1.pdf | ||
| SF30-A002.pdf | ||
| PAGE_2_A0001.doc | DOC document | |
| SF30-A001.pdf | ||
| ATTACHMENT_2_-_SCHEDULE_OF_ITEMS_-_PRICES.doc | DOC document | |
| ATTACHMENT_3_CONTRACT_CLAUSES_AND_SUPPLEMENTAL_TERMS_AND_CONDITIONS.doc | DOC document | |
| SHERMAN_FY15__MDE_REALIGNMENT_SADDLE_Final_(2).pdf | ||
| Attachment_4_-_Solicitations_Provisions.doc | DOC document | |
| Request_for_Clarification_(SHERMAN).doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. HSCG85-15-R-P45W51
Unplanned Dockside Repairs of CGC SHERMAN (WHEC 720)
Amendment No. 0002
The purpose of this amendment is as follows:
a.
The following changes are made to the specification:
Work Item D-01, Main Engine Lifting & Realignment - Coast Guard personnel will be performing the task outlined on the following paragraphs for work item D-01:
3.4.2.1.2 – deck plate reinstallation;
3.4.2.3 - #1 Main Diesel Engine Upper Crankline
3.4.2.4 - Main Diesel Engine Quill Shaft Rotating Equipment Guard and Coupling Guard
3.91.1 – disconnect piping
3.11.1.1 – lifting checks
3.13 MDE reassembly
Work Item D-02, Main Diesel Engine, Thrust Bearing Repairs – No changes Sequencing:
Contractor must complete initial alignment ( work Item D-01 through paragraph 3.11.2.1) prior to proceeding to upper crankline repairs (work item #D-02). After completion of upper crankline repairs (work item D-02), Coast Guard will require 8 days (note: These 8 days are already included to total period of performance for this requirement.) to reassemble engine before contractor may proceed with final alignment (work item #d01, paragraph 3.11.3 to finish).
NOTE: Revision No. 1 of the specification is attached and made part of this amendment. All changes made during the solicitation process will be incorporated and will be made part of the contract.
b.
Due to changes stated above, the period of performance for this requirement is changed to read as follows:
FROM: 21 September 2015 through 06 October 2015
TO: Performance will commence at the award of the contract and must be completed within thirty-two (32) days. To reiterate the note above, the 32 days period of performance includes the 8 days required for Coast Guard personnel to complete reassembly.
c.
The due date to submit proposal in response to the solicitation is extended until 15 September 2015 at 10:00 A.M., Pacific Standard Time.
d.
All other terms and conditions cited on the solicitation remain unchanged.