HSCG85-15-Q-P45174
USCGC SEQUOIA (WLB-215),
SCHEDULED DOCKSIDE REPAIRS
REVISED PAGES
PRICE TOTALS
Insert individual prices in Schedule of Supplies/Services above and insert totals of extended prices as indicated below:
Total Definitive Item CLINs: $_________________
Total Optional Item CLINs: $_________________ Excluding Composite Labor
Composite Labor: $_________________
TOTAL: $_________________
PRICING SCHEDULE FOR: REVISED SCHEDULE
USCGC SEQUOIA (WLB-225B) DOCKSIDE AVAILABILITY FY2015
| ITEM |
| DESCRIPTION |
| UNIT PRICE |
| UNIT |
| QTY |
| EXTENDED PRICE |
| D-001 |
| Tanks (Potable Water), Clean and Inspect |
| D-002 |
| Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean |
| D-003 |
| Vent Ducts (Galley and Pantry Room All), Commercial Cleaning |
| D-004 |
| Potable Water Pneumatic Tanks, Clean and Inspect |
| D-005 |
| Compressed Air Receivers and System Valves (All), Clean, Inspect, Hydro and Lift |
| D-006 |
| Single Point Davit - Slewing Arm, Level 2 Inspect and Repair |
| D-007 |
| Grey Water Holding Tank(s), Clean and Inspect |
| D-008 |
| Sewage Holding Tank(s), Clean and Inspect |
| D-009 |
| Grey Water Piping, Clean and Flush |
| O-010 |
| Tanks (Grey Water Holding), Preserve “100%” |
| O-011 |
| Tanks (Sewage Holding), Preserve “100%” |
| O-012 |
| Tanks (Potable Water), Preserve “100%” |
| D-013 |
| Port and Starboard Air castle, Preserve “100%” |
| D-014 |
| Gooseneck Vents, Renew |
| D-015 |
| Handrails and Stanchions, Renew |
| O-016 |
| Deck Covering (Interior Wet/Dry), Renew- Grey |
| D-017 |
| Piping Insulation, Renew |
| D-018 |
| Main Diesel Engine, Mount Upgrade |
| D-019 |
| Boat Boom, Level 2 Inspect and Repair |
| O-020 |
| Deck Covering (Interior Wet/Dry), Renew |
| O-021 |
| Deck Covering (Inorganic Zinc), Renew |
| D-022 |
| Temporary Services, Provide - Cutter |
| D-023 |
| Sea Trial Performance, Support, Provide |
| O-024 |
| Bilges (Machinery Space/Non-Machinery Space), Preserve |
| O-025 |
| Deck Covering, Carpeting, Renew |
| D-026 |
| Air Castle Foam Insulation, Renew |
| D-028 |
| Propulsion Reduction Gear Lube Oil Piping, Repair |
| D-029 |
| Vent Duct Systems, Repair |
| D-030 |
| Main Diesel Engines Lube Oil Piping, Repair |
| D-031 |
| HVAC Fan Coil Unit, Renew |
| D-032 |
| MDE Jacket Water Coolers, Inspect and Clean |
| D-033 |
| Decks - Exterior, Preserve (“Non-Skid Broadcast Grit” System) |
| D-034 |
| Ventilation System, Renewals |
| D-035 |
| Interior Spaces, Preserve |
| D-036 |
| Compartment Insulation (General), Renew |
| D-037 |
| Potable Water Pump Room Deck, Preserve |
| O-00A |
| Composite Labor Rate |
NSP
| D-00C |
| Travel and Per-diem |
JOB
Total Price of Definite Items
Total Price of Option Items
Total Price of Definite and Optional Items
$0.00
The place of performance is the Cutter’s Home Port.
The Coast Guard intends to conduct the procurement in accordance with Federal Acquisition Regulation (FAR) Part 12, Acquisition of Commercial Items and FAR Subpart 13.5 Test Program for Certain Commercial Items.
Refer questions to Jack Rodman, Contract Specialist (510) 637-5988. Quotes must arrive no later than 10 a.m. PDT, Dec 12, 2014. Quotations may be sent via electronic mail (e-mail) to Jack.E.Rodman@uscg.mil. No Hard copies of the solicitation will be issued Inspection and Acceptance is at destination.
FAR 52.212-4 Contract Terms and Conditions -- Commercial Items (May 2014) (ADDENDUM)
FAR 52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights (APR 2014)
(a) This contract and employees working on this contract will be subject to the whistleblower rights and remedies in the pilot program on Contractor employee whistleblower protections established at 41 U.S.C. 4712 by section 828 of the National Defense Authorization Act for Fiscal Year 2013 (Pub. L. 112-239) and FAR 3.908