Specification Rev-1 dated 24 September 2014
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_A0002.pdf | ||
| PAMLICO_Contractor_Questions.pdf | ||
| Amendment_A0001.pdf | ||
| PAMLICO_(WLIC_160A)_DS_FQ1_SER_15R0.pdf | ||
| SOLICITATION.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC PAMLICO (WLIC 800)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2015
Developed By: Spencer E Ross
(Rev-1, 24 September 2014)
USCGC PAMLICO (WLIC-160A) DOCKSIDE AVAILABILITY FY2015
TABLE OF CONTENTS
0BRevisions Record ...................................................................................................................................................... iii Consolidated List of References ............................................................................................................................... iv Consolidated List of Government-furnished Property ........................................................................................... viii Consolidated List of Critical Inspection Items ......................................................................................................... ix Principal Characteristics - Tender ............................................................................................................................. x 5BGeneral Requirements WORK ITEM 1: Main Diesel Engine (MDE) Exhaust Piping, Commercial Clean WORK ITEM 2: Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean WORK ITEM 3: Compressed Air Receivers and System Valves (All), Clean, Inspect, Hydro and Lift WORK ITEM 4: Crossdeck Winch, Inspect & Service WORK ITEM 5: Spuds, Overhaul WORK ITEM 6: Spud Wells, Inspect WORK ITEM 7: Sewage Vacuum Collection Tanks, Clean and Inspect WORK ITEM 8: Sewage Piping, Clean and Flush WORK ITEM 9: Tanks (Sewage Vacuum Collection), Preserve “100%” WORK ITEM 10: Decks - Exterior, Preserve (“Non-Skid Broadcast Grit” System) WORK ITEM 11: Lead-Based Paint and Asbestos-Containing Paint, Perform 100% Abatement, Aft
Steering WORK ITEM 12: Deck Covering, Wet/ Dry, Seal WORK ITEM 13: Lead-Based Paint, Perform Spot Abatement, Keel Cooler Valves & Grey Water Piping WORK ITEM 14: Pilot House Overhead, Renew WORK ITEM 15: SSDG Cooler Valves, Renew WORK ITEM 16: Deck Vent Pipe, Renew WORK ITEM 17: Single Point Davit, Inspect and Service WORK ITEM 18: Weather Deck Stuffing Tubes, Renew WORK ITEM 19: Lead-Based Paint, Perform Spot Abatement, Pilot House Overhead WORK ITEM 20: Lead-Based Paint, Perform Spot Abatement, Stuffing Tube WORK ITEM 21: Lead-Based Paint and Asbestos-Containing Paint, Perform 100% Abatement, Forward
Hold WORK ITEM 22: Lead-Based Paint and Asbestos-Containing Paint, Perform 100% Abatement, Storage
Hold WORK ITEM 23: Grey Water Drain Main Piping, Repair ii (Rev-1)
0BREVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-1) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
24SEP2014 1 13 Increased square footage of possible activation
24SEP2014 1 11 Updated Paragraph 3.1.1. Updated Table 2. Added Paragraph 3.4
24SEP2014 1 14 Added paragraph 3.4.3
24SEP2014 1 15 Updated Paragraph 1.1.1
24SEP2014 1 21 Updated Table 2. Added Paragraph 3.4
24DEP2014 1 22 Updated Table 2. Added Paragraph 3.4
24SEP2014 1 16 Inserted Paragraph 3.5.1
24SEP2014 1 23 Inserted Paragraph 3.4.1.1
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iii (Rev-1)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
• MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
• Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
• Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
• American Welding Society (AWS): http://www.awspubs.com/index.php
• ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
• NFPA: http://www.nfpa.org
• SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 160 WLIC 0103-2, Rev A, Booklet of General Plans Coast Guard Drawing 160 WLIC 1105-2, Rev C, Transv WT & OT Bulkheads Coast Guard Drawing 160 WLIC 1107-1, Rev L, Dk House Eng Casing & Stacks Coast Guard Drawing 160 WLIC 1205-1, Rev F, Spudwells and Spuds Coast Guard Drawing 160-WLIC 1900-1, Rev J, Painting Schedule Coast Guard Drawing 160-WLIC 3901-1, Rev C, Insulation & Sheathing Coast Guard Drawing 160-WLIC 3901-1, BM No. 48, Rev J, Insulation & Sheathing Coast Guard Drawing 160 WLIC 4105-3, Rev H, Arrgt Eng & Boiler Exhaust Coast Guard Drawing 160 WLIC 4808-1, Rev F, Pollution & Drainage Sys Coast Guard Drawing 160-WLIC 4808-1, BM No. 58, Rev G, Pollution Abatement & Drainage Sys Coast Guard Drawing 160 WLIC 4900-1, Rev B, Diagram Compressed Air System Coast Guard Drawing 160 WLIC 4900-2, Rev D, Arrangement Compressed Air System Coast Guard Drawing 160B-WLIC 4809-1, Rev D, Arrg Tank Vents & Sounding Tubes Coast Guard Drawing 160-WLIC 4105-1, Rev D, Diag FO & Eng Cooling Sys Coast Guard Drawing 160-WLIC 4105-2, Rev C, Arrgt Eng Cooling Piping Coast Guard Drawing 160-WLIC 8201-7, Rev -, Davit Assembly Coast Guard Drawing 160-WLIC 103-002, Rev -, Booklet of General Plans Coast Guard Drawing 160-WLIC 1107-02, Rev D, Pilot House Coast Guard Drawing 160-WLIC 3301-02, Rev B, Ceiling Plan Main and Upper Decks iv (Rev-1) http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace
Coast Guard Drawing 160-WLIC 451-3, Rev B, AN/SPS-50(V)1 Block Wiring Diagram & Details Coast Guard Fleet Drawing FL 2602-10, Rev J, Spud Arrangements and Details Coast Guard Fleet Drawing FL-1112-18, Rev -, HU40 Series Spud Winch Foundation
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST)_MI0360.3 (series) , Rev D, Jan 2014, Coatings and Color Manual Coast Guard Technical Publication (TP) 2056, Manufacturer's Instruction Book-SWBS Group(s) 313-665 Coast Guard Technical Publication (TP) 4958, Section A, Amendment 1; Mar 2011, Utility Air Winch
Model HU-40 Series Coast Guard Technical Publication E-451-032, AN/SPS-50(V) Marine Radar/Automatic Radar Potting
Aid – Installation Manual Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, 2012, General
Requirements Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0740, 2012, Welding and Allied
Processes Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0740, Jan 2012, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 3041, 2012, Shipboard
Electrical Cable Test Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 3042, 2012, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair, And Installation Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 6310, 2012, Requirements for
Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General
Requirements Surface Forces Logistics Center Standard Specification 0000(SFLC Std Spec 0000), 2012, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 0740(SFLC Std Spec 0740), 2012, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2012, Auxiliary
Machine Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2012, Temporary
Hull Accesses
OTHER REFERENCES
American Society for Testing and Materials (ASTM) B61-08, 2008, Standard Specification for Steam or
Valve Bronze Castings American Society for Testing and Materials (ASTM) F467-13, 2013, Standard Specification for
Nonferrous Nuts for General Use v (Rev-1)
American Society for Testing and Materials (ASTM) F468-12, 2012, Standard Specification for Nonferrous Bolts, Hex Cap Screws, Socket Head Cap Screws, and Studs for General Use
American Society of Mechanical Engineers (ASME) B16.24, 2007, Cast Copper Alloy Pipe Flanges and Flanged Fittings: Class 150, 300, 400, 600, 900, 1500 and 2500
American Society for Testing and Materials (ASTM) International F1508, 2010, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End
ASTM International (ASTM) 6966, 2008, Standard Practice for Collection of Settled Dust Samples Using Wipe Sampling Methods for Subsequent Determination of Metals
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component
Adhesives (An) ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates Code of Federal Regulations (CFR) Title 29, Part 1910, Jul 2008, Occupational Safety and Health
Standards Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health
Standards for Shipyard Employment Code of Federal Regulations (CFR) Title 33 CFR, Jul 2010, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth Insert Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe
Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Nonionic) MIL-D-3134, Sep 1989, Deck Covering Materials MIL-F-1183, May 1987, Fittings, Pipe, Cast Bronze, Silver-Brazing, General Specifications for MIL-I-3064, Mar 1991, Insulation, Electrical, Plastic-Sealer MIL-T-24107, Oct 1987, Tube, Copper (Seamless) (Copper Alloy Numbers C10100, C10200, C10300, C10800, C12000, C12200, And C14200) MIL-PRF-1149, Jun 1998, Gasket Materials, Synthetic Rubber, 50 and 65 Durometer Hardness MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric vi (Rev-1)
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant MIL-STD-2003-3, Sep 2009, Electric Plant Installation Standard Methods for Surface Ships &
Submarines (Penetrations) The Society for Protective Coatings (SSPC) Paint Application Specification No. 3 (SSPC-PA Guide 3), 1995, A Guide to Safety in Paint Application The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning vii (Rev-1)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
This section is not applicable to this package.
viii (Rev-1)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
15 SSDG Cooler Valves, Renew
17 Single Point Davit, Inspect and Service ix (Rev-1)
PC_160A_WLIC_1113
PRINCIPAL CHARACTERISTICS - TENDER
160' WLIC INLAND CONSTRUCTION TENDER
(A-CLASS)
PHYSICAL CHARACTERISTICS
Length Overall 160' 10"
Depth (main deck at side to baseline 10' 0"
Maximum Beam 30' 0"
Height of Highest Fixed Projection 40’ 0” (above keel)
Height of Highest Projection with Antenna Mast Extended
49’ 6” (above keel)
Frame Spacing 1' 0"
Full Load Draft 4' 8 1/4" LCF Draft
Full Load Displacement 484.22 Long tons (Fresh water)
Shore Tie Voltage Requirements N/A
MACHINERY CHARACTERISTICS
Number of Propellers 2
Number of Blades per Propeller 4
Diameter of Propeller 48"
Pitch 44" fixed
Revolutions per Minute (RPM) 475
Shaft Diameter N/A x (Rev-1)
00000_0414_FLT
REC_00000_FLT_ Commercial Project @ CG Facility (1212)
5BGENERAL REQUIREMENTS
1. SCOPE
1.1 UIntentU. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST)_MI0360.3 (series) , Rev D, Jan 2014, Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures
OTHER REFERENCES
ASTM International (ASTM) 6966, 2008, Standard Practice for Collection of Settled Dust Samples Using
Wipe Sampling Methods for Subsequent Determination of Metals Code of Federal Regulations (CFR) Title 29, Part 1910, Jul 2008, Occupational Safety and Health
Standards The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal Code of Federal Regulations (CFR) Title 33 CFR, Jul 2010, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
1 (Rev-1)
3. REQUIREMENTS
3.1 UGeneralU. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 UContractor-provided fire watch personnelU. The Contractor shall provide fire watch personnel and equipment.
3.3 UPreservation requirementsU. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 UBrand name approvalU. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 UCoating colors and system color schemes U. Ensure that all colors and color coat/paint schemes are in accordance with (COMDTINST)_MI0360.3C , Chapter 11 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 5 of COMDTINST MI0360.3) are strictly prohibited.
3.4 UWelding and brazing requirementsU. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 UHW disposalU. The Contractor shall be responsible for all hazardous wastes generated by work under this contract. Label and package all hazardous wastes in 49 CFR-approved containers, and in accordance with all other applicable Federal, state, and local laws and regulations. In addition, comply with applicable parts of 40 CFR 262, applicable to handling of hazardous wastes.
3.5.1 Along with the Government, the Contractor shall be contractually considered the co-generator of all hazardous wastes; be aware that the Government will make available its facility’s EPA Generator Identification (ID) Number for manifesting of hazardous wastes.
3.5.2 The Contractor shall identify, arrange, and be responsible for the turnover of all hazardous wastes, within the confines of the Coast Guard shore facility, to the facility’s HM/HW Coordinator. Notify the ship’s HW Coordinator prior to any transfers of HW from ship to shore.
3.5.3 The Contractor shall prepare a manifest of hazardous waste to be reviewed and signed by the HM/HW Coordinator. Contact the HM/HW Coordinator for turnover of any hazardous waste; in addition, notify the COR in writing 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.4 The Contractor shall be aware of the following:
3.5.4.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
2 (Rev-1)
Guard facility without COR or KO-approval.
3.5.4.2 Local environmental regulations at the Government facilities may be more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with local and state regulations.
3.5.4.3 Coast Guard facilities do not have Facilities Response Plans (see 33 CFR 154 Subpart F). It is the Contractor’s responsibility to furnish the Facility Response Plan (FRP) when required for over-the-water liquids transfers to and from vessels. This requirement is applicable to transfers to/from vessels with an oil/fuel capacity of 250 barrels or more.
3 (Rev-1)
3.6 USFLC standard specification approved changesU. The Contractor shall be aware that the following are approved changes to published SFLC 2012 Edition Standard Specifications and supersede published content:
3.6.1 SFLC Std Spec 8634, Drydocking, Appendix A, page A5, paragraph A2.7.1.3 Side Blocks: Remove formula value shown as g – Acceleration of gravity – 32.3 Ft/sec2, and replace with formula value g - Acceleration of gravity - 32.174 ft/sec2.
3.6.2 SFLC Std Spec 0740, Welding and Allied Processes. SFLC Std Spec 0740 added Appendix E, Stray Current Protection: New Appendix is posted with SFLC Standard Specifications as a separate document on internet and intranet webpage.
3.6.2.1 SFLC Std Spec 0740, page 1, paragraph 1.2 Appendices: Add ‘Stray Current Protection’ to ‘Process Standard column of appendices table. Add ‘E’ to ‘Appendix’ column of appendices table.
3.6.2.2 SFLC Std Spec 0740, page 4, paragraph 3.1.3 Stray current protection: Add “The Contractor shall meet all requirements for stray current protection as specified in Appendix E - Stray Current Protection.” directly after paragraph 3.1.3 title.
3.6.2.3 SFLC Std Spec 0740, page 4, paragraph 3.1.3 Stray current protection: Delete paragraphs 3.1.3.1 and 3.1.3.2.
3.6.3 SFLC Std Spec 0450, Electrical Power for Contractor’s Tools and Equipment, page 1, paragraph 1.1 Intent:
Add sentence, “Note that stray current protection for welding equipment is covered in SFLC Standard Specification 0740, Welding and Allied Processes, Appendix E.” to end of paragraph.
3.6.3.1 SFLC Std Spec 0450, page 5, paragraph 3.4 Equipment Grounding: Add sentence, “Stray current protection for welding equipment is covered in SFLC Standard Specification 0740, Welding and Allied Processes, Appendix E.” to end of paragraph.
3.6.3.2 SFLC Std Spec 0450, page 6, paragraph 3.4 Equipment Grounding: Delete paragraphs 3.4.1.4 and 3.4.1.5.
3.6.3.3 SFLC Std Spec 0450, page 6, paragraph 3.4 Equipment Grounding: Delete Figure 5.
3.6.4 SFLC Std Spec 0000, General Requirements, Appendix A Requirements for Environmental Protection:
Add paragraph A2.2.5.3.3, as follows:
“A2.2.5.3.3 UAdditional requirements during abatement of lead-based paint (LBP) and asbestos-containing coatings U. Abide by the following additional requirements, during work that involves disturbance or abatement LBP and asbestos-containing material (ACM)/vermiculite coatings:
A2.2.5.3.3.1 UCertification documentationU. At the Arrival Conference, submit documentation to the COR that all primary and sub contractors fulfilling abatement requirements related to the preceding disclosure paragraph possess all Local, State, and Federal certification licenses and applicable permits, for fulfilling those abatement requirements.
A2.2.5.3.3.2 UAdvance notificationU. Notify the COR 24 hours prior to any planned abatement actions.
Additionally, notify the Quarterdeck and COR, prior to starting any abatement task, to ensure a timely announcement to Coast Guard personnel to vacate the affected area.
4 (Rev-1)
NOTE
Be aware that Coast Guard personnel are not permitted to be in the location of abated spaces while abatement is being performed.
A2.2.5.3.3.3 UAdditional protective measuresU.
A2.2.5.3.3.3.1 Take the following additional safety precautions:
• Separate work area from other non-affected areas.
• Do not permit non-essential personnel in the work area.
• Work in one compartment/space at a time.
• Prevent dust from migrating to other areas, as follows:
• Seal doors, hatches, and all other openings between the work area and other areas with an airtight barrier, such as fire-rated polyethylene; seal both sides (inside the construction area, and inside the adjacent area) to provide a secondary dust barrier and prevent the doors and windows from being used (post alternative emergency exits, if applicable).
• Maintain work area under negative pressure in relation to adjacent areas.
• Take, at a minimum, the following measures, to protect de-contamination workers:
• Use a HEPA (high-efficiency particulate air) vacuum.
• Workers must wear a respirator which is approved by NIOSH and has N100, P100 or R100 filters
(the cartridges are usually purple); respirators must be fit-tested to insure proper seal, and employees must be medically screened and trained prior to wearing a respirator (see the OSHA Respirator Standard, 29 CFR 1910.134).
• Workers must wear full-body protective clothing, head covering and shoes (or shoe covers).
• Workers must not leave the work area without having gone through a proper decontamination process, to prevent spread of lead dust to un-affected areas.
• Eating, drinking and smoking are prohibited in work areas.
• Workers must wash hands and face before eating, drinking or smoking.
• Workers must remove work clothes and shoes before leaving the work area, and seal work clothes in plastic.
• Workers must shower and wash hair as soon as possible after leaving the work area.
• Non-disposable work clothes must be washed separately from other clothes.
NOTES
1. Negative pressure means that more air is exhausted from the area than is supplied so that lead dust and/or asbestos particles are contained within the work area, and do not contaminate adjacent non-affected compartments. Exhaust air must be filtered with a suitable HEPA filter.
2. A HEPA vacuum removes 99.97% of particles that are less than 0.3 microns in size.
3. Use of compressed air, conventional vacuum, and dry-sweeping is not permissible, during abatement.
A2.2.5.3.3.3.2 Remove and dispose of all protective covers, upon completion of work.
A2.2.5.3.3.4 UAbatement task particularsU.
5 (Rev-1)
A2.2.5.3.3.4.1 UCoating removal and surface preparationU.
A2.2.5.3.3.4.1.1 UACM U. Remove existing ACM by a suitable means such as chipping or scraping. Ensure all removed materials are carefully placed into bags that are specially designed for ACM removal, sealed and handed over to another worker to be sealed again.
A2.2.5.3.3.4.1.2 ULBPU. Remove LBP from identified areas, using one or a combination of the cleaning methods specified in Table A1 below, as applicable.
A2.2.5.3.3.4.2 UScope of spot abatementU. When spot or partial abatement is required due to interference with other ship repair work (including but not limited to: hotwork, equipment and component installations, structural inspections and repairs,), do the following:
• Perform inspections of all locations that have been slated for spot abatement, to identify paths of future hull cuts and weld seams and locations of weld repairs, as applicable.
• Ensure that abatement shall also include the following:
• The area itself, including but not limited to: attached framing, stiffeners, piping, equipment support – in addition to up to a three-inch boundary segment where removal is faired into surrounding intact coating.
• All areas of the heat affected zone (estimated to be at a minimum of 3-4 inches on each side of a weld repair), to permit welders sufficient room to safety make required repairs.
• Areas intended for tack welds used during fit up.
• Areas that asbestos material could be disturbed by personnel transiting the work site, setting up/moving equipment, setting up containment measures, or any activity by contractor personnel that could damage asbestos material adjacent to the site of any hotwork activity.
• Ensure that the presence of ACM and/or LBP adjacent to future weld repairs is readily apparent to welders through the use of signs on the compartment entry and local markings adjacent to repairs using a suitable means such grease pencils. Be aware that any accidental disturbance ACM and/or LBP by subsequent hot work or grinding associated with weld repairs shall require clean up in and clearance testing, at no cost to the Government.
TABLE A1 - SURFACE PREPARATION METHODS
MECHANICAL CLEANING CHEMICAL STRIPPING
STEEL SUBSTRATE ALUMINUM
SUBSTRATE
Use a suitable chemical stripper to safely remove all existing coatings
– and expose the bare substrate, in accordance with manufacturer’s instructions.
1. Waterjet to a SSPC-SP WJ- 2/NACE WJ-2 standard.
2. Abrasive-blast to SSPC- SP10/NACE No. 2, using grit conforming to MIL-A-22262 (1.5 to 2.5 mil anchor profile).
3. Power tool clean to a SSPC- SP 11 (1.0 mil anchor profile), with vacuum attachment, to capture lead dust and debris.
1. Waterjet to a SSPC-SP WJ-2/NACE WJ-2 standard.
2.Brush blasting with clean, fine aluminum oxide, garnet or equivalent inert material conforming CID A-A- 59316, Type I & IV, to remove all existing coatings and rust spots, down to bare metal (and produce a 1.0-1.5 mil anchor profile).
3. Mechanical cleaning, using power sanders and abrasive sandpaper with no metallic contents, to remove
6 (Rev-1) all existing coatings and rust spots, down to bare metal.
NOTES
1. Abrasive-blasting creates lead dust, which requires extensive post-surface preparation cleaning in affected compartments. Wet-abrasive blast cleaning (water introduced into the blast stream) may be used, to contain/eliminate dust.
2. Abrasive-blasting and waterjetting are not permissible inside machinery spaces or other outfitted spaces due to the difficulty of containing water spray and contamination of blasting dust particles. These methods are allowed to be performed in voids and tanks where full containment, negative ventilation, and isolation of the affected areas can be performed.
3. Known paint strippers meeting the requirements specified in Table 1 include, but are not limited to the following:
a. Franmar LeadOut
b. STRIP-TOX Paint Stripper
c. Aquastrip ACB
d. Smart Strip™ Advanced Paint Remover
WARNING
Paint stripper formulated with the following hazardous materials are strictly prohibited for use onboard CG vessels:
a. Methylene chloride
b. Chlorinated solvents
c. Phenols
d. Chromates
e. Ammonia
f. Amines
CAUTION
Any action that has the potential to generate dust (blasting, hand tooling) shall be rigorously monitored to ensure contamination of the ship does not occur.
Certifications are required for any personnel who engage in these practices.
A2.2.5.3.3.4.3 UPrecautionary measures when using chemical strippingU. Take the following precautionary measures, when chemical stripping is selected as one of coating removal methods:
A2.2.5.3.3.4.3.1 UVentilationU. In addition to all temporary ventilation requirements specified in SFLC Std 0000 and the “General Requirements” item, ensure the following:
• A flow rate ventilation (minimum 100 cfm) is installed in the affected compartment - and ventilation system inspected by COR, prior to commencement of work.
• Exhaust ducts from ventilation fans are run outside and away from the ship’s ventilation intakes and
7 (Rev-1) downwind from cutter location. This shall be monitored and adjusted as necessary if there are changes in wind location.
A2.2.5.3.3.4.3.2 UChemical residue removal U. After completion of coating removal, wash down all affected surfaces with suitable soap and water, required to ensure all solvents or solvent residues are removed.
A2.2.5.3.3.4.4 UTreatment of existing coating edges bordering abated areas. UIn lieu of abiding by the feathering guidance provided in SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs), build up new coating to overlap all existing adjacent coating edges.
WARNING
Feathering of edges will generate lead/asbestos dust.
A2.2.5.3.3.4.5 UPost-surface preparation cleaning, inspection, and clearanceU. Upon completion of coating removal procedures, do the following, as applicable:
A2.2.5.3.3.4.5.1 ULead dust clean-up U. Clean all lead dust from the worksite by suitable clean-up cleaning methods, or as follows:
• Step 1 - debris removal: Remove all gross debris, paint chips, etc. using either a vacuum with a HEPA filter or by spraying the materials with water in a spray bottle and picking up chips or large pieces of contaminated debris by hand.
• Step 2 – vacuum cleaning: Using a suitable HEPA vacuum, clean all affected surfaces, in accordance with the following guidelines:
• Begin cleaning with high areas first – with overhead surfaces and bulkheads working downward.
• Vacuum all surfaces in the compartment.
• Work in the direction furthest from the entry door toward it.
• Step 3 – wet cleaning: Following thorough HEPA vacuuming, wash all surfaces with any suitable cleaning detergent following the same cleaning pattern (high to low/ furthest from and toward entrance). Change the cleaning solution as it becomes dirty. Rinse all areas with a fresh cloth/mop.
Do not reuse contaminated mops and cloths. Use a three-bucket system for cleaning. (Detergent solution in first bucket/ rinse water for mop in second/ surface rinse on deck and/or bilge surfaces in third).
• Step 4 – vacuum cleaning: Perform a HEPA vacuum again as specified in “Step 2”.
• Step 5 – waste disposal: Properly dispose of contaminated materials, in accordance with all applicable Federal, state, and local regulations.
WARNING
1. Work Wet, Work Smart, and Work Clean. DO NOT GENERATE DUSTS. It is easier to effectively clean an area when dusts are not being generated to resettle on previously cleaned areas. Worker exposures may be high during wet sweeping.
2 A wet/dry HEPA unit is ideal for working with hazardous dust clean up.
3. Lead-contaminated objects that are porous or materials that may suffer damage from water may not be able to be sufficiently decontaminated by these methods and should be discarded.
A2.2.5.3.3.4.5.2 USubstrate inspectionU. Conduct a visual inspection, in the presence of the Coast Guard Inspector, to ensure that none of the following is present, and submit a CFR:
8 (Rev-1)
• Visible coatings on any part of the substrate, including pitted areas.
• Lead dust.
• Cleaning material haze.
A2.2.5.3.3.4.5.3 UPost- abatement clearanceU. Upon acceptance of the visual inspection results by the COR, do the following:
A2.2.5.3.3.4.5.3.1 ULead dust wipe samplingU.
A2.2.5.3.3.4.5.3.1.1 Conduct wipe sampling clearance testing, in accordance with ASTM 6966, in three locations in each affected compartment/space, as designated by the Coast Guard Inspector; to ensure that there exist no lead dust residues in excess of the below-listed concentrations, as specified below in TABLE A2. Submit a CFR with sample results. If a Change Request (CR) has been authorized and released, conduct additional wipe sampling and testing, as designated on the CR.
A2.2.5.3.3.4.5.3.1.2 Ensure that dust lead samples are analyzed by a laboratory certified by the National Lead Laboratory Accreditation Program (NLLAP) or the American Industrial Hygiene Association.
TABLE A2 - ACCEPTABLE LEAD CONCENTRATIONS
BERTHING AND/OR FOOD PREPARATION AREAS ALL OTHER AREAS
40 micrograms/square foot (mcg/ft 2) 200 micrograms/square foot (mcg/ft 2)
A2.2.5.3.3.4.5.4 UAdditional lead dust cleaning and samplingU. If laboratory analysis proves lead concentrations in excess of the thresholds specified in TABLE A2, then perform lead dust cleaning, and take subsequent wipe samples until the concentration of lead falls below the above standards.
NOTES
1. Be aware that the Coast Guard reserves the right to coordinate additional wipe clearance testing, at no cost to the contractor, to verify the sample results.
2. All additional wipe clearance testing conducted by the Coast Guard must be witnessed by the Contractor, to verify where and how samples were collected – and thus, prevent contract disputes.
A2.2.5.3.3.4.5.3.2 UAggressive sampling – asbestosU. After the completion of abatement, take at least five aggressive air samples in each affected compartment/space, using the Phase Contrast Microscopy (PCM) method to determine that the level of airborne fibers for each sample inside the work site is 0.01 or less fiber per cubic centimeter. Perform aggressive air sampling in accordance with EPA 600/4-85-049. Submit a CFR.
A2.2.5.3.3.5 USurface coatingU.
A2.2.5.3.3.1 UContaminant removal U. Prior to applying primer coat, and in accordance with SFLC Std Spec 6310, paragraphs 3.1.8.7 (Flash rusting/surface oxidation limitations) and 3.1.8.6 (Hydrocarbon substance removal), respectively,
• Remove all flash rusting, as applicable.
• Remove all grease and oil surface contaminants.
A2.2.5.3.3.2 UCoating applicationU. Coat all prepared surfaces, in accordance with Table A3.
9 (Rev-1)
TABLE A3 - COATING SYSTEM
SPOT ABATED AREAS FULLY-ABATED SURFACES AND
COMPARTMENT/SPACES
Prime and coat all abated surfaces, including adjacent structural members, in accordance with SFLC Std Spec 6310, to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, Appendix A and Appendix B, as applicable.
Prime and coat all abated surfaces, including adjacent structural members, as specified in applicable work item(s).
A2.2.5.3.4 UWaste DisposalU. Collect, test, dispose of all generated wastes, including waste water from cleaning of work spaces, in accordance with all applicable Federal, state, and local regulations.”
3.6.4.1 SFLC Std Spec 0000, page 22, paragraph 3.3.3.1 NOTE. Add "Flame-retardant polyethylene deck plate with a non-slip diamond pattern from 10 to 40mil thickness" to body of Note.
3.6.4.2 SFLC Std Spec 0000, page 3, bullet “ISC.” Delete “lead-contaminated materials.”
3.6.4.3 SFLC Std Spec 0000, page 27, after Note box under paragraph 3.3.13.1.2 add the following paragraphs:
“3.3.13.1.3 Dock and Sea trials. The Contractor shall conduct dock trials to test the work performed during the contract when required by individual work items (see 3.3.13 Tests and Inspections). This shall include operational tests or inspections, as appropriate, of all machinery, piping, wiring, insulation, preservation work, deck coverings, and any other article removed, moved, disturbed, or damaged by the Contractor in accomplishing the work outlined in the specification. Schedule for these specific dockside tests or inspections shall be included within the planning document (see 3.2.5 Planning document).
3.3.13.1.3.1 The Contractor shall provide a pier facility or allow the vessel to move to a Coast Guard pier to support dock trials. The Contractor shall not conduct trials that require the vessel to be waterborne while the vessel is floating inside a dock (e.g., graving dock, floating drydock).
3.3.13.1.3.2 Sea trials to conduct equipment operational tests are not required unless a Sea Trial Performance work item is specifically included within the specification.”
3.6.4.4 SFLC Std Spec 0000, page 11, paragraph 3.2.5, add the following bullets to the bulleted list:
• Identifies the “critical paths” for the project.
• Shows calculations for the “float” along the critical paths and labels the critical paths with the number of delay days the critical paths can absorb without affecting the final delivery date.
3.6.4.4.1 SFLC Std Spec 0000, page 11, Add the following Note between paragraphs 3.2.5 and 3.2.5.1:
NOTE
Float is the number of days that the critical paths can be delayed without affecting the final delivery date.
3.6.4.4.2 SFLC Std Spec 0000, page 12, add the following paragraphs and Note after Figure 1:
“3.2.5.4 When the critical path extends beyond or encroaches upon the final delivery date, provide a resource constraint and scheduling evaluation of the critical path before any request for extension will be entertained.
Submit the resource constraint and scheduling evaluation via a CFR.
10 (Rev-1)
The intent of the resource constraint and scheduling evaluation is to identify the resources necessary to ‘crash’ the critical path or make adjustments to the production schedule to meet the delivery date in lieu of a project extension.”
3.6.4.5 SFLC Std Spec 0000, General Requirements, Appendix A Requirements for Environmental Protection, page A-4, paragraph A2.2.5.3 remove lead content percent of 0.06 and replace with 0.009.
3.6.4.5.1 SFLC Std Spec 0000, General Requirements, Appendix A Requirements for Environmental Protection, page A-4, Warning Box, remove lead content percent of 0.06 and replace with 0.009.
3.6.4.5.2 Std Spec 0000, General Requirements, page 4, paragraph 1.3 Acronyms and term definitions, “Paint Containing Lead” remove lead content percent of “0.06 percent by weight (0.12 mg/cm2, or 600 ppm)” and replace with “0.009 percent by weight (0.018 mg/cm2, or 90 ppm)”
3.6.5 SFLC Std Spec 6310, Requirements For Preservation Of Ship Structures, page 10, add “3.1.6.5 Preconstruction Primers. Also known as shop primers, preconstruction primers are used as a temporary coating to protect steel from corrosion during welding, storage, and fabrication. Preconstruction primers shall be removed prior to applying the permanent coating system on all critical coated surfaces. Preconstruction primers may be left in place in other interior areas (such as machinery spaces, habitability spaces, etc.) if they are intact, uncontaminated, and compatible with the overcoating system.”
3.6.5.1 Std Spec 6310, Appendix B, page B12 , the formatting for of Notes 17-19 change and add as per the following:
• SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 17, delete sentence, “Persistent corrosion in a particular area of an aluminum bilge may dictate the need for a protective High Build Epoxy coating to be applied to that local area.”
• SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 18, replace entire note with “Persistent corrosion in a particular area of an aluminum bilge may dictate the need for a protective High Build Epoxy coating to be applied to that local area. “
• SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 19, replace entire note with “Painting plastic surfaces is highly discouraged, but after it is done once, it must be maintained.”
• SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Add Note “20. For aluminum surfaces, remove all oil, grease, dirt, metal oxides (corrosion products) and other foreign material by cleaning per SSPC-SP 1 prior to blast cleaning and following blast cleaning immediately prior to coating. The end result of abrasive blasting will be a surface cleanliness similar to that of SSPC-SP 10 for steel with all coating removed.
3.6.5.2 Std Spec 6310, Appendix E, pages E1, E3, and E4, QA Inspection Forms QA-1, QA-3a, and QA-3b respectively, reference The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No. 5 erroneously, and are corrected as per the following:
3.6.5.2.1 Std Spec 6310, Appendix E, pages E1, QA Inspection Form QA-1, Check point 5- Surface Preparation, check box description 2, replace “(i.e.: SSPC SP-12, SP-11, SP-10…).” with “(i.e.: SSPC SP-11, SP-10, SP WJ- 2…).”
11 (Rev-1)
3.6.5.2.2 Std Spec 6310, Appendix E, page E3, QA Inspection Form QA-3a, Surface Preparation Method column of the Profile Achieved table, 2nd record, replace “SSPC-SP-12/NACE No. 5” with “SSPC-SP WJ-1/NACE WJ- 1”.
3.6.5.2.2.1 Add record to table beneath “SSPC-SP WJ-1/NACE WJ-1” and label as “SSPC-SP WJ-2/NACE WJ- 2”
3.6.5.2.2.2 Add record to table beneath “SSPC-SP WJ-2/NACE WJ-2” and label as “SSPC-SP WJ-3/NACE WJ- 3”
3.6.5.2.2.3 Add record to table beneath “SSPC-SP WJ-3/NACE WJ-3” and label as “SSPC-SP WJ-4/NACE WJ- 4”
3.6.5.2.3 Std Spec 6310, Appendix E, page E4, QA Inspection Form QA-3b, Surface Preparation Method column of the Profile Achieved table, 2nd record, replace “SSPC-SP-12/NACE No. 5” with “SSPC-SP WJ-1/NACE WJ- 1”.
3.6.5.2.3.1 Add record to table beneath “SSPC-SP WJ-1/NACE WJ-1” and label as “SSPC-SP WJ-2/NACE WJ- 2”
3.6.5.2.3.2 Add record to table beneath “SSPC-SP WJ-2/NACE WJ-2” and label as “SSPC-SP WJ-3/NACE WJ- 3”
3.6.5.2.3.3 Add record to table beneath “SSPC-SP WJ-3/NACE WJ-3” and label as “SSPC-SP WJ-4/NACE WJ- 4”
3.6.6 SFLC Std Spec 8635, Temporary Services, page 2, delete paragraph 3.3.2.2.
3.6.7 SFLC Std Spec 5000, Auxiliary Machine Systems, Appendix C, page C9: Replace paragraph C2.8.1.3 and Table C-3, and add additional paragraphs C2.8.1.4, C2.8.1.5, and C2.8.1.6. as follows:
“C2.8.1.3 UFlushing fluid minimum flow rate requirementsU. Ensure the minimum flow rates provided in Table C- 3 are maintained for each circuit. If multiple loops are flushed concurrently, each loop shall be provided with a flow measuring device. Provide calibrated flow meters. Prior to flushing, submit the certification of calibration to the CG Inspector.
TABLE C-3 - MINIMUM FLOW RATE FOR FLUSHING WITH FLUID
PIPE SIZE INSIDE DIA
(INCH)
GAL/MIN
To 0.5 18
0.5 to 0.75 34
0.75 to 1.0 56
1.0 to 1.25 100
1.25 to 1.5 138
1.5 to 2.0 230
2.0 to 2.5 330
2.5 to 3.0 420
12 (Rev-1)
NOTES
1. Flow rates represent minimum flows needed to achieve a turbulent flow condition and maximize benefits of flushing effort.
2. Flow rate selected for flow velocity of 25 ft/sec in the schedule 80/160 pipe, as applicable. If there is a conflict between the pressure and flow rate requirements of this specification, the minimum flow rates shall be governing, unless the working pressure of the system is exceeded. The uses of by-pass (flow control) valves are not allowed downstream of the flow meters.
C2.8.1.4 Whenever a noticeable increase in the pressure drop across strainers is observed, the strainers should be cleaned and bag renewed. Be aware that this may occur as frequency as 15 min intervals.
C2.8.1.5 During flushing, constant monitoring of the flushing oil must be maintained in order to determine the contamination level. Filtering shall continue until the fluid entering the return flow filter meets the particle population ISO cleanliness code of 17/14, in accordance with ISO 4406. All flushing fluid shall pass through the return filter after passing through each system flushing circuit. All samples shall be taken at a point just prior to this filter
C2.8.1.6 Take a representative sample of oil from the hydraulic system of the hydraulic system. Send samples out for laboratory analysis. Analysis shall include viscosity, moisture, total acid number, particle size and population in sufficient detail to determine ISO cleanliness code of 17/14, in accordance with ISO 4406. Submit CFR.”
3.6.8 SFLC Std Spec 6341, Appendix A, Paragraph A2.1.1, replace with “A2.1.1 UCove vase U. Include a cove base, using the same epoxy resin deck covering system material, to a maximum height of four inches at all adjacent vertical bounding surfaces, where applicable."
4. NOTES
4.1 UQA inspection forms U. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
13 (Rev-1)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION