Question_ _Answer_for_00003.docx
DOCX document 17 KB Posted
- Solicitation number
- HSCG85-14-Q-P45002
About this file
Questions and Answers to Amendment 00003 for FY14 CGC JOSHUA APPLEBY Dock-side Repairs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00003_SF30.docx | DOCX document | |
| 00002_SF30.docx | DOCX document | |
| Question_ _Answer_for_00002.docx | DOCX document | |
| 00001_SF30.docx | DOCX document | |
| Question_ _Answer_for_00001.docx | DOCX document | |
| Blank_JOSHUA_APPLEBY_FY14_DS.xlsx | XLSX spreadsheet | |
| R0_Specification_for_JOSHUA_APPLEBY_FY14_DS.docx | DOCX document | |
| GOVERNMENT_PROPERTY_REPORT.docx | DOCX document | |
| Request_for_Clarification_(Joshua_Appleby).docx | DOCX document | |
| Solicitation_For_USCGC_JOUSHA_APPLEBY_(WLM-556)_FY14__DS.docx | DOCX document | |
| JOSHUA_APPLEBY_(WLM_175)_DS_FQ1_RKW_14R0.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| Request for Quote | HSCG85-13-Q-P45002 | |
| DOCK-SIDE REPAIRS OF CGC JOSHUA APPLEBY (WLM-556) | Amendment 0003 |
A. Questions/Answers to Request for Clarification with regards to dock-side repairs of CGC JOSHUA APPLEBY (WLM-556)
0001 Question: WI-10, BUOY CRANE, INSPECT & SERVICE – TIER II: Requested quote from Subcontractor, however Sub is not sure work can be accomplished in one week period. How should the Prime Contractor bid this item without knowing the condition of the equipment in advance?
Answer: Please provide a quote for the work per the scope of work detailed in the specification.
B. The Solicitation is not extended.
NOTES: ACKNOWLEDGE RECEIPT OF ALL AMENDMENTS IN PROPOSALS.
A. THE SOLICITATION PERIOD IS NOT EXTENDED.
B. ALL OTHER TERMS AND CONDITIONS CITED IN THE ORIGINAL SOLICITATION REMAIN THE SAME.