Amend. A001.doc
DOC document 51 KB Posted
- Solicitation number
- HSCG85-09-R-66R995
About this file
Page 2 - Amendment A001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30 | — | |
| Attachment 1 | — | |
| USCGC SHERMAN Repair July 2009 Rev 1.doc | DOC document | |
| SF33 | — | |
| TECHNICAL EVALUATION CRITERIA.doc | DOC document | |
| NOTICE TO OFFERORS(SHERMAN).doc | DOC document | |
| Solicitation Pkg.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. HSCG85-09-R-66R995 Unplanned Dockside Repairs of CGC SHERMAN
Amendment No. A001
The purpose of the amendment is as follows:
a.
The following are the responses to the Request for Clarifications:
QUESTION NO. 1:
D-Item No. D-09, Temporary services, Dockside, Home Pier, paragraph no. 3.1.4; “NOTE:” under paragraph 3.1.4 states crane requirements for working at Naval Base San Diego. Do these same requirements exist for Coast Guard Island, Alameda, CA, and for this RFP?
ANSWER:
No this requirement does not apply under this requirement.
QUESTION NO. 2:
D-item No. D-09, Temporary Services, Dockside, Home Pier, paragraph no. 3.1.4 states requirements for garbage “dumpsters pierside for the cutter’s crew”. We know that this is a requirement while working at Naval Base San Diego. Is this a requirement for Coast Guard Island, Alameda, and this RFP, or was it included in error?
Delete paragraph 3.4.1. This requirement was included in error.
QUESTION NO. 3:
D-Item No. D-09, paragraph 3.2.1.1. How many amps will be made available to the Contractor at the pier, and at what voltage.
Power will be 440V, 200A. A special connector (which will not be furnished by the (which will not be furnished by the Government) may be required. See attached photo.
b.
All other terms and conditions cited on the solicitation remain unchanged.