Page2Amend.A0002.doc
DOC document 25 KB Posted
- Solicitation number
- HSCG85-08-B-625021
About this file
PG. 2 A0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1_SF30-AMEND.0005.doc | DOC document | |
| SF30-AMEND.0004.doc | DOC document | |
| Page2Amend.A0004.doc | DOC document | |
| SF30-AMEND.0002.doc | DOC document | |
| SF30-AMEND.0001.doc | DOC document | |
| SOLICITATIONPKG(WAREV).doc | DOC document | |
| ATTACHMENTS.doc | DOC document | |
| NOTICETOOFFERORS.doc | DOC document | |
| SF33(WA).doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. HSCG85-08-B-625021 FY08 Dry-dock and Repairs of CGC SWORDFISH (WPB 87358) & CGC BLUE SHARK (WPB 87360) Amendment No.: A0002
The purpose of this amendment is as follows:
a. The answers to the following Request for Clarifications are as follows:
QUESTION: Contractor has reviewed the Definite Work Items contained in the RFP for each craft and believes that the amount of work associated with the specifications would require an availability period of at least 45 days due to the limitations on Subcontracting as stated in Far Clause 52.219-14, which has been invoked for this Solicitation. Would the Coast Guard consider two 45 day periods of performance for each craft?
ANSWER: Due to operational scheduling, two 45 day periods of performance for each craft will not be possible.
b. All other terms and condition cited on the original solicitation remain unchanged.