1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
Amendment 0002 January 15, 2016
6. ISSUED BY CODE 84 7. ADMINISTERED BY (If other than Item 6) CODE 84 Department of Homeland Security United States Coast Guard
SILC-COCO-BSS-COB4
300 East Main Street, Suite 965 Norfolk, VA 23510-9112
Same as Item 6 POC: Rebecca Brown (757) 628-4490 E-mail: Rebecca.A.Brown@uscg.mil
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
HSCG84-16-Q-BB8097
X 9B. DATED (SEE ITEM 11)
January 11, 2016
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for Receipt of Offers is extended / is not extended.
Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning one copy(s) of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required) N/A
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority).
E. IMPORTANT: Contractor is not / is required to sign this document and return _1_ copy(s) to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The subject solicitation is hereby amended as follows:
A. The following page(s) of QUESTIONS and ANSWERS is provided for informational purposes.
B. No additional or follow-up questions will be accepted.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Dawn J.Dabney 15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY:
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA, FAR (48 CFR) 53.24
Questions and Answers (Lease of Office Building, Shower/Bathroom Trailer)
Q1. We are having a difficult time finding 1 shower trailer that fulfills this requirement. Is it possible to bring 2 trailers out or is there just 1 water and sewer hookup for the shower/toilet hook up?
A1. There is one connection for sewage and one connection for water. Customer is open to use of multiple modular buildings as long as they meet the basic requirements set forth in the SOW and do not detract from the intended use. Each shower area shall have at minimum changing areas that are private to the gender as specified (8 male, 2 female) and directly connected to the shower area for the gender.
Q2. I know the lease starts on 2/1, but does this mean that the buildings have to be operable by the 1st or just delivered by the 1st? I’m asking because the set up will usually take 1-2 days for everything.
A2. Buildings must be operable by 1 February 2016.
Q3. If we are awarded this contract, we will need at least a 1 wk heads up to get all the facilities in place. Are you planning on making an award right away?
A3. The Government intends to award the contract as soon as possible.
| Amendment 0002 |
| January 15, 2016 |
| HSCG84-16-Q-BB8097 |
| January 11, 2016 |
| N/A |
Dawn J.Dabney
File details come from the government source that posted it. Updated .