FAA AC 150/5370-2F Operational Safety on Airports During Construction
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BID_RESULTS_-_15-PCR009.pdf | ||
| Wage_Rates_-_Highway_NC.doc | DOC document | |
| Amendment_A00002_15-PCR009.pdf | ||
| TT-1952_Reference_Specifications.pdf | ||
| Amendment_00001_15-PCR009.pdf | ||
| c8264x.docx | DOCX document | |
| C8264C08.pdf | ||
| C8264C07.pdf | ||
| IFB_15-PCR009_250K-500K.doc | DOC document | |
| C8264C01.pdf | ||
| C8264C03.pdf | ||
| C8264C06.pdf | ||
| C8264G01.pdf | ||
| C8264C04.pdf | ||
| C8264C05.pdf | ||
| FAA_150_5340_1k.pdf | ||
| C8264C02.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Presented to:
By:
Date:
Federal Aviation Administration Construction Safety
& Phasing Plan Requirements per AC 150/5370-2F
New England Sponsors & Consultants
John Merck, FAA Airports Division
29 March 2012
2 Federal Aviation Administration
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Objective Review of AC 150-5370-2F requirements to facilitate better Construction Safety & Phasing Plan (CSPP) planning, development, and execution.
3 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Operational Safety on Airports During Construction
Common Themes:
Airport Operations
Construction on Airports
4 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
AC 150/5370-2F Highlights
AC 150/5370-2F
includes:
A Consolidated List of 18 CSPP Subjects.
Rules and Best
Practices Organized by Subject.
Detailed CSPP Checklist w/ Subject Cross References.
5 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
AC 150/5370-2F Highlights
AC 150/5370-2F
introduces:
Safety Risk Management
(SRM) Coordination.
Safety Plan Compliance
Documents (SPCDs).
Guidelines to Writing
CSPPs.
6 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
AC 150/5370-2F Highlights
AC 150/5370-2F:
Emphasizes Planning.
Emphasizes Airport
Operations.
Requires CSPPs for all tenants including FAA Airway Facilities.
Determined RSA dimensions & RSA requirements apply for construction and maintenance.
7 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
(CSPP)
The CSPP is the primary tool used to ensure operational safety on the airport during construction.
The CSPP is a PLAN not a specification.
The CSPP describes how everyone will support operational safety on the airport during construction, not just the construction contractor.
8 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
Eighteen (18) CSPP Subjects Coordination Phasing
Areas & Operations Affected by Construction
Navigational Aid (NAVAID) Protection Contractor Access Wildlife Management
FOD Management HAZMAT Management
Notification of Construction Activities
Inspection Requirements
Underground Utilities Penalties
Special Conditions Runway & Taxiway Visual Aids
Marking and Signs for Access Routes
Hazard Marking, Lighting & Signing
Protection of Runway & Taxiway
Areas, Zones, & Surfaces
Other Limitations on Construction
9 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
1. Coordination
Requirements:
Predesign, Prebid, & Preconstruction meetings (i.e. HIT).
Contractor progress meetings.
Scope or schedule changes.
FAA ATO & airport user coordination as required.
10 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
1. Coordination
CSPP Contents:
Description of past coordination efforts.
Description of proposed future coordination.
11 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
2. Phasing
Requirements:
Establish phases by balancing aircraft operations with construction activities.
Identify phase elements (impacts, closures, etc.)
12 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
2. Phasing
CSPP Contents:
Scope of Work by phase.
Construction
Safety Drawings (CSDs): usually at least one drawing per phase.
JoAnn Napolitano Typewritten Text
13 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
3. Areas & Operations
Affected by the Construction Activity Requirements:
Identify affected areas by phase.
Determine operational impacts by phase.
Establish mitigation of effects by phase.
Project Runway 15-33 Reconstruction
Phase Phase II: Reconstruct Runway 15 End
Scope of Work Reconstruct 1,000 feet of north end of Runway 15-33 with Portland Cement Concrete (PCC).
Operational Requirements Normal Phase II
Runway 15-33 ARC: C-IV C-IV
Runway 15 Approach Visibility Minimums ¾ mile 1 mile
Runway 33 Approach Visibility Minimums ¾ mile 1 mile
Runway 15 Declared Distances
TORA: 7,820 TORA: 6,420
TODA: 7,820 TODA: 6,420
ASDA: 7,820 ASDA: 6,420
LDA: 7,820 LDA: 6,420
Runway 33 Declared Distances
TORA: 8,320 TORA: 6,920
TODA: 8,320 TODA: 6,920
ASDA: 8,320 ASDA: 6,920
LDA: 7,820 LDA: 6,420
Runway 15 Approach Procedures
ILS LOC only
RNAV
VOR
Runway 33 Approach Procedures
ILS Visual only
RNAV
VOR
Taxiway G ADG IV
IV (N/A between T/W H and R/W
15 end) Taxiway E ADG IV IV
ATCT (hours open) 06:00 – 24:00 local
06:00 – 24:00 local
ARFF Index D D
Special Conditions Airline XYZ requires VGSI
Airline XYZ requires VGSI
14 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
3. Areas & Operations
Affected by the Construction Activity CSPP Contents:
Affected areas in each phase shown on CSDs.
Tables with NORMAL vs.
AFFECTED operations for each phase.
Project Runway 15-33 Reconstruction
Phase Phase II: Reconstruct Runway 15 End
Scope of Work Reconstruct 1,000 feet of north end of Runway 15-33 with Portland Cement Concrete (PCC).
Operational Requirements Normal Phase II
Runway 15-33 ARC: C-IV C-IV
Runway 15 Approach Visibility Minimums ¾ mile 1 mile
Runway 33 Approach Visibility Minimums ¾ mile 1 mile
Runway 15 Declared Distances
TORA: 7,820 TORA: 6,420
TODA: 7,820 TODA: 6,420
ASDA: 7,820 ASDA: 6,420
LDA: 7,820 LDA: 6,420
Runway 33 Declared Distances
TORA: 8,320 TORA: 6,920
TODA: 8,320 TODA: 6,920
ASDA: 8,320 ASDA: 6,920
LDA: 7,820 LDA: 6,420
Runway 15 Approach Procedures
ILS LOC only
RNAV
VOR
Runway 33 Approach Procedures
ILS Visual only
RNAV
VOR
Taxiway G ADG IV
IV (N/A between T/W H and R/W
15 end) Taxiway E ADG IV IV
ATCT (hours open) 06:00 – 24:00 local
06:00 – 24:00 local
ARFF Index D D
Special Conditions Airline XYZ requires VGSI
Airline XYZ requires VGSI
15 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
4. Navigational Aid
(NAVAID) Protection Requirements:
Identify affected
NAVAID facilities.
Protect NAVAID
Critical Areas.
Prevent visual
NAVAID obstructions.
Coordinate NAVAID shutdowns & startups.
16 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
4. Navigational Aid
(NAVAID) Protection CSPP Contents:
List of affected
NAVAID facilities.
NAVAID Critical Areas identified on the CSDs.
NAVAID shutdown & start-up procedures.
17 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
5. Contractor Access
Requirements:
Establish vehicle & pedestrian requirements (training, site escorts, communications, vehicle marking & lighting, security, etc.)
Determine storage & stockpile locations.
18 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
5. Contractor Access
CSPP Contents:
Site access, haul routes
& stockpile locations indicated on the CSDs.
Vehicle requirements.
Procedures for driver
& pedestrian training & communications.
Security badging as required.
19 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
6. Wildlife Management
Requirements:
Identify construction related wildlife attractants:
Trash.
Standing water.
Tall grass & seed.
Maintain fence & gates.
Address potential disruption of habitats.
Abide by airport’s WHMP.
20 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
6. Wildlife Management
CSPP Contents:
Procedures to prevent wildlife attractants.
Permanent & temporary wildlife fences & gates indicated on CSDs.
Procedures to address disrupted wildlife entering into active AOA’s.
Any special WHMP procedures.
21 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
7. Foreign Object Debris
(FOD) Management Requirements:
Identify construction related FOD sources.
Determine FOD control methods.
22 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
7. Foreign Object Debris
(FOD) Management CSPP Contents:
Description of FOD control methods:
Worksite housekeeping.
Vehicle tire inspections.
Pavement sweeps.
Procedures to address FOD entering into active AOAs.
23 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
8. Hazardous Material
(HAZMAT) Management Requirements:
Identify potential HAZMAT
& HAZMAT sources.
Determine procedures for transport and handling of HAZMAT & spill control.
Comply with AC 150/5320-15, Management of Airport Industrial Waste.
24 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
8. Hazardous Material
(HAZMAT) Management CSPP Contents:
Description of HAZMAT management methods (fuel delivery, spill recovery, MSDS availability, etc.)
Specific HAZMAT transport and handling procedures.
HAZMAT restrictions.
25 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
9. Notification of
Construction Activities Requirements:
Notify airport users.
Issue NOTAMs.
Develop list of responsible reps. & points of contacts.
Establish emergency notification procedures.
Notify ARFF & FAA as required.
26 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
9. Notification of
Construction Activities CSPP Contents:
NOTAM procedures.
List of OE/AAA 7460
& 7480 submissions.
FAA NAVAID shutdown/restart forms (copies).
Emergency notification procedures.
List of responsible representatives & points of contacts (completed via the SPCD).
27 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
10. Inspection Requirements
Requirements:
Identify construction safety elements requiring daily inspections.
Establish final inspection procedures such as prior to reopening areas to air operations.
28 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
10. Inspection Requirements
CSPP Contents:
List of construction safety elements requiring inspection & maintenance.
Schedule of inspections.
Role of certificated airport self-inspections regarding construction.
Remedial actions to correct deficiencies.
Safety Officer (identified in the SPCD)
29 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
11. Underground Utilities
Requirements:
Establish procedures for locating & identifying underground utilities.
Establish procedures for protecting underground utilities.
Establish procedures for repairing damaged utilities.
30 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
11. Underground Utilities
CSPP Contents:
Methods of locating & protecting utilities on-site.
List of utility owners & emergency contacts.
Procedures for reporting & repairing damaged utilities.
Utility drawings, if requested.
31 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
12. Penalties
Requirements:
Determine enforcement procedures for non-compliance with airport regs. & CSPP.
Penalties listed in ACM apply at certificated airports.
32 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
12. Penalties
CSPP Contents:
List penalties for specific non-compliance:
VP/Ds SIDA Violations Security breach.
Reference applicable ACM sections regarding penalties at certificated airports.
33 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
13. Special Conditions
Requirements:
Determine applicable special conditions:
Low visibility operations.
Severe weather.
Aircraft in distress / accident.
Security breach.
Restricted access (i.e. dignitary visits).
V/PDs.
Establish Corresponding Procedures
34 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
13. Special Conditions
CSPP Contents:
List of applicable special conditions.
Corresponding procedures including suspension & resumption of construction activities as applicable.
35 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
14. Runway & Taxiway Visual Aids
Requirements:
Determine areas restricted from aircraft operations (by phase).
Determine most effective visual aids to guide pilots away from such areas:
Temporary or altered pavement markings.
Temporary or altered airfield lighting.
Temporary or altered airfield signs.
Temporary or altered visual NAVAIDs & lighted X’s.
36 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
14. Runway & Taxiway Visual Aids
CSPP Contents:
Description of temporary visual aids including graphic diagrams.
Visual aid locations indicated on CSDs.
Existing visual aids temporarily altered, removed, or disconnected indicated on CSDs.
Visual aid maintenance procedures.
Responsible individuals (identified in SPCD).
37 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
15. Marking and Signs for Access Routes Requirements:
Determine roadway markings & signs to indicate access routes to construction vehicle drivers.
Markings must meet AC 150/5340-1.
Signs must meet AC 150/5340-18
& should comply with MUTCD.
38 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
15. Marking and Signs for Access Routes CSPP Contents:
Sign schedule (separate sheet or included on CSDs).
Temporary markings indicated on CSDs.
Signs locations indicated on CSDs.
JoAnn Napolitano Typewritten Text
39 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
16. Hazard Marking and Lighting Requirements:
Identify potential construction hazards to aircraft.
Determine most effective means to isolate & identify such hazards:
Barriers - highly visible/reflective & preferably interlocking.
Red lights - steady burning or flashing.
Signs.
40 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
16. Hazard Marking and Lighting CSPP Contents:
Description of hazard marking & lighting equipment to be used including graphic diagrams.
Equipment locations indicated on CSDs.
Equipment maintenance procedures.
Responsible individuals (identified in SPCD).
41 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
17. Protection of Runway & Taxiway
Areas, Zones, & Surfaces Requirements:
Determine affected areas:
Safety Areas.
Object Free Areas.
Obstacle Free Zones.
Approach / Departure Surfaces.
Determine requirements:
Construction activity restrictions during aircraft operations.
Open excavation restrictions & erosion control.
42 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
17. Protection of Runway & Taxiway
Areas, Zones, & Surfaces CSPP Contents:
Areas, zones, & surfaces depicted on CSDs.
Methods of demarcation.
Construction activity restrictions during aircraft operations.
Open excavation restrictions.
Erosion control methods.
43 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
18. Other Limitations on Construction
Requirements:
Determine prohibitions:
Tall equipment (w/o 7460).
Open flame welding.
Electrical blasting caps.
Determine restrictions:
Construction suspension during certain airport operations.
Areas that cannot be worked on simultaneously.
Day or night construction restrictions.
Seasonal construction restrictions.
44 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Requirements & Contents by Subject
18. Other Limitations on Construction
CSPP Contents:
List of applicable prohibitions.
Description of applicable restrictions (other than those indicated in other sections) including where & when they apply.
45 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Key Points
PLAN
Start the CSPP development at the Project Scoping Meeting.
Develop the CSPP in concert with the design effort.
46 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
COORDINATE
Key Coordination:
Sponsor & Consultant.
Involve FAA ATO & users.
Conduct design review independent of the CSPP.
Sponsor a SRM panel per
AC 150/5200-37 if required.
47 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
CREATE
Organize CSPP by subject.
Use headings with section
(subject) numbers and titles.
Choose the most appropriate section for subject matter and cross reference other sections to it.
Include CSDs! Keep them clear and concise.
48 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
SUBMIT
Submit an optional draft CSPP directly to the FAA Project Manager at 30% +/-design.
Submit final CSPP though OE/AAA (7460) at 90% +/-design. Include optional CSPP checklist.
49 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
EXECUTE
Request a SPCD from the awarded contractor.
Require routine Safety Meetings for contractor employees.
Submit revisions to the CSPP as required.
50 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Key Points
KEEP IN MIND
The only way to reduce RSA dimensions is to temporarily change the runway ARC.
Taxiway Safety Areas protect wheels.
Taxiway Object Free Areas protect wings.
Forty-five (45) days is required for FAA review after OE/AAA (7460) submission.
CSPP Determination Letter must be issued prior to Notice to Proceed.
51 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Key Points
REMEMBER
The CSPP is designed to enforce aircraft operational safety during construction.
If a subject matter does not involve both aircraft operational safety and construction, it should not be included in the CSPP.
52 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
INTERACTIVE GROUP
EXERCISE
In the PLAN or
NOT in the PLAN
53 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
In the PLAN or NOT in the PLAN
1. Coordination:
The airport sponsored a coordination meeting with airport tenants and operators on 15 May 2011.
If the airport requires input from affected tenants and users, users meetings are a highly effective coordination tool. Note that an informative user meeting would be included in Section 9, Notification of Construction Activities, instead.
54 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
12. Penalties:
The Contractor must agree to pay the Owner liquidated damages for each and every calendar day the work remains incomplete beyond the specified time.
Liquidated damages are not a penalty.
55 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
6. Wildlife Management:
Grass in the construction area will be mowed routinely to reduce deer tick exposure.
Deer ticks do not pose a danger to aircraft.
This is an OSHA concern, not an operational safety concern.
56 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
4. Navigational Aid (NAVAID) Protection:
Reference Section 11, Underground Utilities, for FAA ILS cable identification and protection methods.
The identification and protection of underground cables is best described in Section 11, not Section 4.
But because they are NAVAID related, a cross reference to Section 11 in Section 4 is appropriate.
57 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
17. Protection of Runway and Taxiway Areas, Zones, & Surfaces:
The new EMAS will protect aircraft from overrunning the Runway Safety Area (RSA). EMAS may be part of the scope of work, but the statement does not describe how the RSA will be protected during the construction.
58 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
14. Runway and Taxiway Visual Aids:
The Runway 6 VASI will remain in service during the full 60 day Runway 6 shutdown.
Though written correctly in the correct section, an operational visual aid serving a closed runway is misleading to pilots. This is a poor practice!
59 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
1. Coordination:
FAA Technical Operations will be notified 30 days prior to the shutdown of the Runway 35 ILS.
This is a notification, not a coordination activity. It should be included in Section 9, Notification of Construction Activities, instead.
60 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
EXERCISE
In the PLAN or NOT in the PLAN
6. Wildlife Management:
Disrupted wildlife observed moving toward the Air Operations Area (AOA) will be immediately reported to Air Traffic Control and Airport Operations by the full time Resident Engineer.
Wildlife disrupted by construction near an AOA is a hazard to aircraft. An action plan is required.
61 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
EXERCISE
In the PLAN or NOT in the PLAN
9. Notification of Construction
Activities:
The following OE/AAA cases were filed on 29 March 2012:
2012-ANE-25-NRA (crane) 2012-ANE-26-NRA (const. vehicles) Listing other related OE/AAA cases in the CSPP is a best practice and is highly recommended.
62 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
EXERCISE
In the PLAN or NOT in the PLAN
14. Runway and Taxiway Visual Aids:
The direction signs for T/W A and the outbound destination sign for R/W 6 at T/W A will be disconnected and covered by Airport Maintenance prior to the T/W A closure. This statement describes removing information that would otherwise be misleading to pilots. What will be done, when it will be done, and who is responsible is indicated.
63 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
12. Penalties:
Non-compliance with airport rules and regulations by contractor personnel will result in suspension or revocation of their vehicle operating privileges and may subject the contractor to fines as described in the ACM. Well, yes.
64 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
5. Contractor Access:
Temporary personnel shall be escorted at all times.
The responsible party for escorting temporary personnel is not indicated. This also reads like a specification rather than a plan (“shall” versus “will”).
65 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
7. Foreign Object Debris (FOD) Management:
Mud, dirt, sand, loose aggregate, debris, rubber deposits, and other contaminants shall be removed as soon as practical.
The source of the FOD is not identified as construction related, the responsible party is not identified, and the statement reads like a specification not a plan.
66 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
13. Special Conditions:
Snow is removed off movement area surfaces so that all air carrier aircraft propellers, engine pods, and wingtips may clear any snowdrift.
Clearing snow from movement areas usually has little or nothing to do with construction.
67 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
14. Runway and Taxiway Visual Aids:
Runway markings will meet AC 150/5340-1K.
It is not clear whether the markings are temporary or permanent; only temporary markings should be mentioned in the CSPP. The statement also points out the obvious (all markings meet AC 150/5340-1K).
68 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
Badges?
We don’t need no stinking badges!
69 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
EXERCISE
In the PLAN or NOT in the PLAN
17. Protection of Runway and Taxiway
Areas, Zones, & Surfaces:
Trenching operations between 200 and 250 feet of the runway centerline will immediately stop and all contractor personnel will vacate the RSA when instructed by ATC.
Aircraft cannot operate on a runway with open trenches in the Runway Safety Area (RSA).
70 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
EXERCISE
In the PLAN or NOT in the PLAN
3. Areas and Operations Affected by the Construction Activity:
Operational
Requirements Normal Phase I
Runway 15-33 ARC: C-IV B-II
This partial example clearly shows a construction related aircraft restriction during Phase I.
71 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
16. Hazard Marking and Lighting:
Interlocking barriers will be as indicated on Drawing CS 1.2.
This statement is fine as long as Drawing CS 1.2 is a CSD included in the CSPP.
72 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
All construction activity will be immediately suspended after any construction related Vehicle/Pedestrian Deviation (V/PD) until an FAA investigation is concluded.
You can count on this!
73 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
Drawing Title: Facility Site Utility Layout
11. Underground Utilities:
Maybe, maybe not:
a utility drawing should not be included in the CSPP, unless requested.
74 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
18. Other Limitations on Construction:
No construction will take place during the months of June, July, and August, as this is the airport’s “high season” for activity.
This is often a restriction at summer resort airports (Cape and Islands airports, for example).
75 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
8. Hazardous Materials (HAZMAT) Management:
At least one emergency fuel shutoff control station shall be conveniently accessible to each fueling position.
The location of emergency fuel shutoff stations has nothing to do with construction Hazmat management.
76 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
The Contractor shall enter and exit the airport only at designated points established at the Preconstruction Conference.
The designated entry and exit points need to be established in the CSPP, not during the Precon.
77 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
The project includes three hazard beacon replacements.
The hazard beacons will not protect aircraft from construction related hazards.
78 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
9. Notification of Construction Activities:
Phone numbers (partial list):
Airfield operations: (111) 123-4567 ATCT cab: (111) 987-6543 ← a best practice!
ARFF: (111) 345-6789
79 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
Contractor personnel responsible for the maintenance of the lighted barriers will be as indicated in the SPCD. Because the CSPP will be finalized prior to the award of the contract, the name(s) of the responsible contract individual(s) cannot be identified until the SPCD submission by the contractor.
80 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
10. Inspection Requirements:
Unless otherwise directed, all materials used in the work area shall be inspected, tested, and approved by the Engineer before incorporation in the work. Construction material inspection has nothing to do with airport operations.
81 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
2. Phasing:
Phases 1 through 6 are indicated on drawing CS1.1, which will be included in the bid drawing package.
Incorporating six (6) phases on one CSD will be nearly impossible to decipher. Also, all CSDs must be included with the CSPP.
82 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
4. NAVAID Protection:
See Section 9 for NAVAID NOTAM requirements.
9. Notification of Construction Activities:
See Section 4 for NAVAID NOTAM requirements. Beware of circular references!
83 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
All construction personnel will be required to wear hard hats and other personal protection at all times at the worksite.
Personal protection equipment is usually an OSHA requirement, not an operational safety requirement.
84 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
15. Marking and Signs for Access Routes:
All signs will be as indicated in the airport’s ACM sign and marking plan.
Only permanent signs are included in the ACM sign and marking plan. Signs for access routes are temporary and must be indicated in the CSPP.
85 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
10. Inspection Requirements:
Airport Operations personnel will use a supplemental inspection checklist, listing all construction phase elements requiring inspection, during each airport self-inspection. An inspection checklist is a best practice, especially at certificated airports. Include the checklist(s) in the CSPP if possible.
86 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
All construction will be suspended during periods when Air Force One is operating or parked at the airport.
If unique or special events are expected to interrupt the construction, mention them in the
CSPP.
87 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
EXERCISE
In the PLAN or NOT in the PLAN Appendix A: Temporary Sign Schedule
TEMPORARY SIGN SCHEDULE
SIGN C1 SIGN C3
SIGN C2
WAIT FOR
ESCORT
VEHICLE
CONSTRUCTION
ENTRANCE
Good!
88 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan
EXERCISE
In the PLAN or NOT in the PLAN Appendix C: Contract Specifications
INSTALLATION OF AN END-FIRE GLIDE SLOPE (EFGS)
FACILITY SERVING RUNWAY 34 AT THE T. F. GREEN
AIRPORT, WARWICK, RI.
REQUEST FOR OFFERS NO: RFO NO. NE110:01
PROPOSAL CLOSE DATE: June 5, 2007
2:00 PM EASTERN TIME
Prepared by:
Parsons Infrastructure and Technology Group Inc.
Parsons TSSC-III
C/o Federal Aviation Administration 12 New England Executive Park
Burlington, MA 01803
For:
Federal Aviation Administration – New England Region
MAGNITUDE OF CONSTRUCTION: Between $250,000 and $500,000
Specifications do not normally discuss airport operations (except where CSPP compliance is specified).
Please do not include contract specs with the
CSPP.
89 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Acronym Glossary
AC – Advisory Circular ACM – Airport Certification Manual AOA – Air Operations Area ARC – Airport Reference Code ARFF – Aircraft Rescue and Firefighting ATO – Air Traffic Organization (FAA) CSD – Construction Safety Drawing CSPP – Construction Safety & Phasing Plan FOD – Foreign Object Debris HAZMAT – Hazardous Material HIT – Horizontal Integration Team MSDS – Material Safety Data Sheet MUTCD – Manual of Uniform Traffic Control Devices NAVAID – Navigational Aid NOTAM – Notice to Airmen OE/AAA – Obstruction Evaluation / Airport Airspace Analysis RSA – Runway Safety Area SIDA – Security Identification Display Area SPCD – Safety Plan Compliance Document SRM – Safety Risk Management V/PD – Vehicle / Pedestrian Deviation WHMP – Wildlife Hazard Management Plan
90 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan References
AC 150/5200-28, Notice to Airmen (NOTAMs) for Airport Operators AC 150/5200-30, Airport Winter Safety Options AC 150/5200-33, Hazardous Wildlife Attractants On or Near Airports AC 150/5200-37, Introduction to Safety Management Systems (SMS) for Airport Operators AC 150/5210-5, Painting, Marking, and Lighting of Vehicles Used on an Airport AC 150/5210-20, Ground Vehicle Operations on Airports AC 150/5300-13, Airport Design AC 150/5310-24, Airport Foreign Object Debris Management AC 150/5320-15, Management of Airport Industrial Waste AC 150/5340-1, Standards for Airport Markings AC 150/5340-18, Standards for Airport Sign Systems AC 150/5340-30, Design and Installation Details for Airport Visual Aids AC 150/5370-2, Operational Safety on Airports During Construction AC 150-5370-10, Standards for Specifying Construction of Airports Form 7460-1, Notice of Proposed Construction or Alteration Form 7480-1, Notice of Landing Area Proposal Manual of Uniform Traffic Control Devices (Federal Highway Administration) Title 14 CFR Part 77, Safe, Efficient Use, and Preservation of the Navigable Airspace Title 14 CFR Part 139, Certification of Airports Title 49 CFR Part 1542, Airport Security
91 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Summary
Tell the story
- through words and illustrations -about how you will protect Aviation from the dangers of Construction on your Airport.
This is your Construction Safety & Phasing Plan.
92 Federal Aviation
Construction Safety & Phasing Plan Requirements per AC 150/5370-2F 29 March 2012
Construction Safety and Phasing Plan Acknowledgements
Special thanks to:
Craig Bailey, Ruben Cabalbag, Laurie J. Dragonas, Barry Hammer, Peter Hasslinger, Michael Meyers, Bryon Rakoff, Bob Siris & Cliff Vacirca FAA Airports Division
Bob Enos, FAA ATO
Ned London, Parsons / TSSC
Gale Associates, Inc.
Nashua Municipal Airport