c8264x.docx
DOCX document 114 KB Posted
- Solicitation number
- HSCG83-15-B-PCR009
About this file
Specification
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BID_RESULTS_-_15-PCR009.pdf | ||
| Wage_Rates_-_Highway_NC.doc | DOC document | |
| Amendment_A00002_15-PCR009.pdf | ||
| TT-1952_Reference_Specifications.pdf | ||
| Amendment_00001_15-PCR009.pdf | ||
| C8264C08.pdf | ||
| construction_safety_ac_150_5370_2f.pdf | ||
| C8264C07.pdf | ||
| IFB_15-PCR009_250K-500K.doc | DOC document | |
| C8264C01.pdf | ||
| C8264C03.pdf | ||
| C8264C06.pdf | ||
| C8264G01.pdf | ||
| C8264C04.pdf | ||
| C8264C05.pdf | ||
| FAA_150_5340_1k.pdf | ||
| C8264C02.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
ENGINEERING SERVICES DIVISION
SPECIFICATIONS
FOR
REMOVE RUBBER AND PAINT R/W 1028
U.S. COAST GUARD BASE
ELIZABETH CITY
ELIZABETH CITY, NORTH CAROLINA
September 2014
COMMANDING OFFICER
UNITED STATES COAST GUARD
CIVIL ENGINEERING UNIT, RM 2179
1240 EAST NINTH STREET
CLEVELAND, OHIO 44199-2060
| AUTHOR: |
| D. G. Ward |
| DIV 1 |
| Final |
TABLE OF CONTENTS
Division Section Title Page
1 GENERAL REQUIREMENTS
| 01 11 00 | Scope of Work | 4 | |||||
| 01 14 00 | Contractor Work Hours | 5 | |||||
| 01 14 13 | Pre-Bid Site Visits | 7 | |||||
| 01 14 14 | Pre-Construction Site Conditions | 8 | |||||
| 01 14 16 | Coordination | 8 | |||||
| 01 14 19 | Field Adjustments | 13 | |||||
| 01 18 14 | Building Permits | 13 | |||||
| 01 18 17 | Environmental Permits | 13 | |||||
| 01 26 13 | Request for Information | 13 | |||||
| 01 31 19 | Project Meetings | 15 | |||||
| 01 32 16 | Construction Schedule, Schedule of Values | 16 | |||||
| and Progress Schedule | 16 | ||||||
| 01 32 26 | Construction Daily Reports | 17 | |||||
| 01 33 00 | Submittal Procedures | 17 | |||||
| 01 35 29 | Safety Program | 18 | |||||
| 01 51 00 | Temporary Utilities | 19 | |||||
| 01 51 16 | Temporary Fire Protection | 19 | |||||
| 01 55 00 | Access Roads and Parking | 20 | |||||
| 01 55 29 | Staging Areas and Access | 20 | |||||
| 01 56 00 | Lights, Signs and Barricades | 20 | |||||
| 01 57 23 | Pollution Control | 21 | |||||
| 01 65 00 | Recovered Materials Notice | 22 | |||||
| 01 66 13 | Hazardous Waste | 22 | |||||
| 01 66 16 | Safety Data Sheets and Material Handling Procedures | 23 | |||||
| 01 74 00 | General Cleanup and Site Restoration of Work Areas | 23 | |||||
| 01 78 00 | As-Built Drawings | 24 | |||||
| List of Submittals | 25 | ||||||
| Contract Item Acceptance Request | 26 |
3 CONCRETE
| 03 20 00 | Concrete Reinforcement | 27 | |
| 03 30 00 | Cast-in-Place Concrete | 29 | |
| 03 63 00 | Epoxy Grouting | 32 |
7 THERMAL AND MOISTURE PROTECTION
| 07 91 23 | Backer Rods | 35 | |
| 07 92 13 | Joint Sealing Filler | 37 |
9 FINISHES
09 97 27 Runway and Taxiway Painting 40
32 EXTERIOR IMPROVEMENTS
| 32 01 11 | Runway Rubber Removal | 48 | |
| 32 12 18 | Asphalt Crack Filling | 52 |
DIVISION 1
GENERAL REQUIREMENTS
(January 2012 Version)
SECTION 01 11 00
SCOPE OF WORK
Scope of Work
1. WORK INCLUDED: Major items of work shall include the following:
1.1 Rubber Removal: Remove rubber from the grayed out portions of the runway shown on sheet C-01 of the drawings. Rubber shall be removed by abrasive methods. All debris and cleaning water shall be vacuumed cleaned during removal operations by using specially designed runway cleaning equipment. All rubber removal operations shall be conducted at night to allow the airfield to remain in operation.
1.2 Joint Repair: Scrape and remove damaged joint sealant and underlying backer rod material from the runway joints located within the areas shown on sheet C-02 of the drawings. Base work shall include the repair of 2,000 lineal feet of joints.
1.3 Spalled Joint Edge Repairs: Areas along joints with spalling shall be cleaned and patched using epoxy-concrete. Spalled areas shall be abrasively cleaned and water blasted prior to patching. Patch areas shall be formed to maintain straight and uniform joints. Base work shall include the repair of 500 lineal feet of spalled joint edges.
1.4 Asphalt Crack Filling: Clean and remove debris from cracks in the asphalt throughout the areas of the taxiways and fill with new crack filler indicated on the drawing C-06. The crack filler will be cold-applied, flush filled with a three-inch wide over-band. Cracks range from ¼” wide to ½” wide. Base work shall include crack filling of 9,580 lineal feet of cracks for the taxiways shown on sheet C-07.
1.5 Runway and Taxiway Marking Removal: Remove all markings from the runway and taxiways that service Runway 10-28. Markings shall be removed using abrasives means and all debris shall vacuumed and contained. Areas shall be wetted to minimize dust and debris.
1.6 Runway and Taxiway Markings: Repaint Runway 10-28 and servicing taxiways markings in their entirety. Use the coating system as specified in Section 09 97 27. Verify exact layout of markings with the Elizabeth City facilities maintenance department. All markings shall be lay out and conform with FAA Advisory Circular 150/5340-1K.
1.7 Work Item 1: Provide a unit work item for each additional 50 lineal feet of joint repair at $_____ per lineal foot for a total of $________.
1.8 Work Item 2: Provide a unit work item for each additional 10 lineal feet of joint repair at $_____ per lineal foot for a total of $________.
1.9 Work Item 3: Provide a unit work item for each additional 100 lineal feet of crack filler at $______ per lineal foot for a total of $__________.
2. Work associated with these items is described in the following specification sections and/or is shown on the contract drawings. Incidental work items not listed above and necessary for completing the project shall be included.
2. DRAWINGS: Drawings and the accompanying specifications are the property of the Government and comprise legal documentation that pertains exclusively to this project. Drawings will be made available in a format determined by the solicitation method. CEU Cleveland will not provide hard copies of drawings.
| 2.1 Construction Drawings: |
| 8264-D, Sheets 1 of 6 through 6 of 6 |
| 2.2 Reference Documents: |
| FAA AC 150/5340-1K, Standards for Airport Markings |
FAA AC 150/5370-2F, Operational Safety on Airports During Construction
SECTION 01 14 00
CONTRACTOR WORK HOURS
Contractor Work Hours
| 1. | WORK HOURS: Accomplish work during the hours of 6:30 a.m. to 6:30 p.m., Monday through Friday and 7:30 a.m. to 4:30 p.m. Saturdays unless otherwise approved by the Coast Guard. All work hours will be restricted by the Air Station Commander. Note any departures from these work hours on the Daily Reports. |
| 2. | SATURDAY, SUNDAY AND HOLIDAYS: The contractor shall provide the Contracting Officer's Representative (COR) at least forty-eight hours advance notice prior to working on weekends or Federal holidays. The Government may reject any such request without impacting the completion time of the contract. |
| 3. | CONTRACT COMPLETION: The contractor shall complete work within the time frame indicated upon issuance of the Notice to Proceed. Limitations imposed by these work hours will not entitle the Contractor additional time to complete the project. Refer to FAR Clause 52.211-10 "Commencement, Prosecution and Completion of Work". |
| 4. | RAPIDGATE PROGRAM: US Coast Guard Base Elizabeth City has implemented the RAPIDGate Program for their security protocol. The contractor shall register with RAPIDGate and obtain security passes in accordance with the instructions below prior to commencing any on site work. |
RAPIDGate Program Enrollment Information
1. Enroll your company by calling 1-877-RAPIDGate (1-877-727-4342)
To enroll your company in the RAPIDGate Program, please go to the following web address to fill out the enrolment forms, https://eform.rapidgate.com/ . On the enrollment forms you will need to provide your USCG Base Elizabeth City Sponsor Contracting Officer Representative (COR) point of contact, including a name, phone number, and e-mail address [Mr. Garry Manning, 252-335-6476, garry.w.manning@uscg.mil]. USCG Base Elizabeth City must authorize your request to participate in the RAPIDGate Program. The minimum elapsed time from company enrollment to an employee receiving his or her RAPIDGate Credential is approximately two weeks. If you would like additional information please call Eid Passport at 1877- RAPIDGate (1877-727-4341). A customer service representative will give you all the necessary information regarding the RAPIDGate Program.
If your company is already enrolled in the RAPIDGate Program at another installation, it may request access for its employees at this installation by calling 1877-RAPIDGate (1877-727-4341). Once your company is approved by USCG Base Elizabeth City, your employee who already holds a RAPIDGate Credential may be able to use the same credentials at the additional installation.
2. Employees register at onsite registration stations.
Once your company has been approved for the enrollment and paid the enrollment fee your company will receive an email with you company’s RAPIDGate Company Code. Instruct your employees who need access to USCG Base Elizabeth City to register at the self-service registration station located at USCG Base Elizabeth City. Each employee should be ready to provide your company’s RAPIDGate company code, his or her address, phone number, date of birth, and Social Security Number. The registration station will capture the employee’s photograph for credentialing and fingerprints for identity verification.
Assisted registration at your company’s location may be available if you have 50 or more employees to register. Call 1877-RAPIDGate (1877-727-4341) for details.
3. The RAPIDGate Program performs background screening and credentialing.
Once your company has approved each employee for participation and paid the registration fee, the RAPIDGate Program performs identity authorization and background screening. Your company will be notified when qualified employees may pick up their personalized RAPIDGate Credentials at the USCG Base Elizabeth City Pass and ID. Each employee must show proof of identity by presenting one form of identification from List A, or two forms of identification from list B (next page) to retrieve their credentials.
After activating their RAPIDGate Credentials, employees present their credentials to request entry to USCG Base Elizabeth City, and must wear and display the credentials at all times while on the installation. Questions about the USCG Base Elizabeth City RAPIDGate Program should be addressed to info@rapidgate.com with the subject line RE: RAPIDGate Program.
Forms of acceptable identification for picking up your credentials:
List A – one needed
· U.S. Passport (unexpired)
· Permanent Resident Card or Alien Registration Receipt Card (Form I-551)
· Unexpired foreign passport, with I551 stamp or attached form I-94 indicating unexpired employment authorization
· Unexpired employment authorization document that contains a photograph (Form I-766, I-688, I-688A, or I668B)
List B – two needed
· Driver’s License or ID card issued by a state
· ID card issued by federal, state, or local government agencies or entities
· School ID card with a photograph
· Voter’s registration card
· U.S. Military or draft record
· Military dependent’s ID card
· U.S. Coast Guard Merchant Mariner Card
· Native American Tribal Document
· Drivers License issued by a Canadian government authority
· U.S. Social Security card issued by the Social Security Administration
· Certificate of Birth Abroad issued by the Department of State (Form FS-545 or DS 1350)
· Original or certified copy of a birth certificate issued by a state, country, municipal authority or outlying possession of the Unites States bearing an official seal.
· U.S. Citizen ID Card (Form I-197)
· ID Card for use of resident citizen in the United States (Form I-179)
· Unexpired employment authorization document issued by DHS (other than those listed in list A)
SECTION 01 14 13
PRE-BID SITE VISITS
Pre-Bid Site Visits
| 1. | GENERAL: Bidders are responsible for visiting the site to field verify existing conditions and determine actual dimensions and the nature of the work required. Failure to visit the site does not relinquish the bidder from determining the extent and scope of the work required and estimating the difficulty and cost to complete the project. Requests for equitable adjustments, in either time or money, arising from failing to field verify site conditions may be denied. Provisions regarding the site visit requirements are outlined in FAR Clause 52.236-3 “Site Investigation and Conditions Affecting the Work” |
| 2. | SITE VISIT: Arrange pre-bid site visits to Base Elizabeth City to verify existing conditions with Mr. Garry Manning, CEU Cleveland, Detached, at (252) 335-6476. |
SECTION 01 14 14
PRE-CONSTRUCTION SITE CONDITIONS
Pre-Construction Site Conditions
| 1. | SITE CONDITION VERIFICATION: The Contractor shall verify the conditions of the existing site, equipment and facilities potentially affected by the work under this contract and photograph and/or videotape the conditions in order to document their pre-construction condition. Copies of the photos and videos shall be submitted to the Contracting Officer prior to starting work. |
| 2. | UTILITIES: The contractor shall use proactive measures such as digging, metering, testing, underground utility location devices, and utility company location services to locate all underground utilities identified in the area of work at no additional expense to the Government. Additional cost of unplanned outages and repair of damaged utilities, including emergency repairs by others, not properly identified by the Contractor shall be the Contractor’s responsibility. |
SECTION 01 14 16
COORDINATION
Coordination
| 1. | INTERFERENCE WITH COAST GUARD OPERATIONS: Accomplish work in a manner that causes minimal impact on normal operations. The Contractor shall notify the Contracting Officer’s Representative at least five working days in advance of any planned outages of water, electrical, telephone, or sanitary facilities. Notify the Contracting Officer’s Representative at least one week prior to beginning construction. |
| 2. | MILITARY STATION REGULATIONS: |
| 2.1 | The Contractor, his employees, and subcontractors shall become familiar with and obey all station regulations. All personnel employed on the project shall keep within the limits of the work and avenues of ingress and egress, and shall not enter any other areas outside of the site of the work unless required to do so in the performance of their duties. The Contractor's equipment shall be conspicuously marked for identification. |
| 2.2 | There shall be NO SMOKING in any Coast Guard building. |
| 2.3 | Storage Areas: Storage Areas: The Contracting Officer’s Representative will determine exact location and boundaries of staging areas. Under no circumstances shall materials be stored in areas that will interfere with aircraft operations. |
| 2.4 | Storm Protection: If a gale force wind warning or higher is issued, take precautions to minimize any danger to persons and protect the work and nearby Government property. Precautions shall include, but not be limited to, closings, removing loose materials, tools and equipment, from exposed locations. Remove and secure scaffolding and temporary work. Close openings in the work area if storms of less intensity are imminent. |
| 3. | INTERFERENCE WITH AIRFIELD OPERATIONS: |
| 3.1 | Operational Safety during Construction: Adhere to the procedures and requirements outlined in FAA Advisory Circular No. 150/5370-2F, Operational and Safety on Airports during Construction. Submit a Construction Safety Phasing Plan (CSPP) outlining the planning effort to assure airfield safety throughout the duration of the project. Factors as outlined in AC 150/5370-2F include identification of affected areas, description of current operations, allowances for temporary changes to operations adhere with the required measures to revised operations. The plan shall be submitted to the Contracting Officer and will be reviewed by Air Station personnel for approval. The plan will only be accepted after it is approved by the Air Station. The plan shall comply with the requirements of AC 150/5370-2F for construction operations, material stockpiling, equipment operation and related construction activities. |
| 3.2 | Scheduling: Schedule work to accommodate aircraft operations. The Government will make every effort to schedule aircraft operations so as to permit the maximum amount of time for contractor activities. However, in the event of an emergency, intense operational demand, adverse wind conditions, and other such unforeseen difficulties, the contractor shall discontinue operations at the specified locations in the aircraft operation area for the safety of the contractor and military personnel and the protection of Government property. Submit a schedule to the Contracting Officer describing work to be accomplished, work locations relative to distances from buildings, runways, etc., and dates and times work is scheduled. Keep the Contracting Officer and the Contracting Officer’s Representative apprised of any changes to this schedule. |
| 3.3 | Hazards to Airfield and Heliport Operations: Follow strict precautions regarding aircraft operations for all construction work within proximity of runways, taxiways, parking aprons, runway end zones and within 75 feet on either side of runways and taxiways. Park equipment in an area designated by the Contracting Officer’s Representative and under no circumstances shall equipment be parked overnight or for any extended period of time in proximity to runways or taxiways. Do not store materials in aircraft operation areas. |
| 3.4 | Airfield Operations: The contractor shall coordinate work that impacts airfield operations with the Air Station and have the flexibility to adjust the schedule as required to accommodate Air Station operations. The contractor will be allotted a 14 day duration to perform runway and 7 days for apron work as specified. The contractor shall provide sufficient crews and equipment necessary to accomplish work in the time period specified. All rubber removal operations shall be conducted between the hours of 10 p.m. and 6 a.m. The airfield shall remain operational during non-working hours for rubber removal. |
| 3.5 | Daytime Markings: Daytime Markings: During daylight hours, mark stationary and mobile equipment with international orange and white checkered flags; mark the material and work site with yellow flags. |
| 3.6 | Nighttime Markings: During nighttime, which begins two hours before sundown and ends two hours after sunrise, mark stationary and mobile equipment, material and the work site with red lanterns. Should the Contracting Officer’s Representative determine that red lanterns could confuse pilots, the red lenses shall be replaced with lenses of the color designated. |
| 3.7 | Excavation: Excavate only trenches for which back-fill material is on site and ready for placement. Immediately back-fill and compact trenches as specified |
3.8 CONSTRUCTION SAFETY AND SECURITY
| A. | General. The following sections are in accordance with AC 150 5370‐2F “Operational Safety on Airports during Construction.” Contractors working at the Elizabeth City Regional Airport shall adhere to the standards and requirements contained herein. The AFM’s safety and security objective is to achieve incident‐free and secure construction project | |
| B. | Airfield Security. Maintenance of the secured area is subject to US Coast Guard security requirements, and must meet those standards for access control, movement of ground vehicles, and identification of construction contractor and tenant personnel. The Contractor and its personnel shall be aware of the increased security, and familiar with the security policies of the of the US Coast Guard as directed by the COR, Airfield Manager (AFM), and Coast Guard Police Department. | |
| C. | Emergency Notification. | In the event of any situation or condition that may adversely affect the operational safety of the Airfield, the Contractor shall immediately notify the Airfield Manager. If the condition has an immediate impact on aircraft operations or an emergency situation exists, immediately notify the Air Traffic Control Tower followed by the Airfield Manager. |
| D. | Airfield Coordination. The Contractor shall coordinate with the AFM through the COR early to schedule runway or taxiway shutdowns and facility shutdowns and restarts so the AFM can coordinate with FAA Air Taxi Commercial Operator (ATCO). Relocation or adjustments to NAVAIDs, or changes to grades in critical areas, may require an FAA flight inspection before restarting the facility. Flight inspections must be coordinated and scheduled well in advance of the intended facility restart. | |
| E. | FAA Form 7460-1 Notice of Proposed Construction. 14 CFR Part 77.9 states that any person or organization who intends to sponsor construction or alterations must notify the FAA if construction or alteration if proposed construction or alteration is within 20,000 feet of a public use or military airport which exceeds a 100:1 surface from any point on the runway. | Any changes to the pavement on an airfield, i.e., construction/modification/resurfacing of runways, taxiways, aprons, etc. require an FAA aeronautical hazard determination. |
| F. | NAVAIDS Shutdown. For emergency (short‐notice) notification impact on NAVAIDs, contact the AFM (OPS-1) at 252-334-5388. If construction operations require a shutdown of a NAVAID for more than 24 hours or more than 4 hours daily on consecutive days, Contractor shall provide a 50‐day minimum notice to the Airport prior to facility shutdown. The AFM must notify the appropriate FAA ATO Service Area Planning and Requirements (P&R) Group | a minimum of 45 days prior to implementing an event that causes impacts to NAVAIDs. The AFM will coordinate work for a NAVAID shutdown with the FAA, including any necessary reimbursable agreements and flight checks. The Contractor shall provide procedures in the project that will address utility outages and cable cuts that could impact NAVAIDs. |
| G. | Hazardous Material. Contractors operating construction vehicles and equipment on the Airfield must be prepared to expeditiously contain and clean‐up spills resulting from fuel, hydraulic fluid, or other chemical fluid leaks. Transport and handling of other hazardous materials on the Airfield also requires special procedures. The contractor is required to develop and implement spill prevention and response procedures for vehicle operations. This includes maintenance of appropriate MSDS data and appropriate prevention/response equipment onsite. The contractor shall notify the Airfield Manager, COR and Contracting Officer immediately when a spill occurs. | |
| H. | Vehicle Operations. |
1. Vehicle and pedestrian access routes for Airfield construction projects must becontrolled to prevent inadvertent or unauthorized entry of persons, vehicles, or animals onto the AOA. The AFM will coordinate requirements for vehicle operations with airport tenants, the Air Traffic Manager and contractors.
2. All personnel operating a motor vehicle on Airport property shall have a valid state driver’s license. North Carolina State Motor Vehicle Laws will be observed when operating a vehicle on the Airport.
3. Aircraft will continue to use existing runways, aprons, and taxiways during the time that work under a contract is being performed. The Contractor shall, at all time, conduct the work as to create no hindrance, hazard, or obstacle to aircraft using the Airport.
I. Construction Site Parking. The CSPP will show parking areas for contractor employees to prevent any unauthorized entry of persons or vehicles onto the AOA, and penetration of protected airspace by parked vehicles. These areas will allow reasonable contractor employee access to the job site. The project area(s) shall be bounded by approved barricades identifying contractor personnel and vehicle area operation limits.
J. Construction Equipment Parking. Contractor employees must park and service construction vehicles in an area designated by the AFM outside the Runway Object Free Area (ROFA) and never in the safety area of an active runway or taxiway. Contractor parking and equipment staging areas will be identified as the Contractor Staging Area in the drawing set in the project’s CSPP. Inactive equipment shall not be parked on a closed taxiway or runway, unless a complex setup makes movement of specialized equipment infeasible. Construction vehicles shall be parked outside the OFA when not in use by construction personnel (for example, overnight, on weekends, or during other periods when construction is not active.
K. Marking and Lighting of Vehicles. The Contractor shall abide by the requirements established under AC 150/5210‐5, Painting, Marking, and Lighting of Vehicles Used on an Airport. All vehicles and equipment operating in the Angle of Attack (AOA) and in the general vicinity of the safety area or in aircraft movement areas must be marked with flashing yellow/amber beacons or orange and white flags during daylight hours. In addition the vehicles and equipment will have identifying symbols at a minimum of 2‐inch block‐type characters of contrasting color that are easily legible. During hours of darkness or low visibility they shall be marked with at least flashing yellow/amber beacons. Beacons and flags must be maintained to standards in good working and operational condition. Beacons must be located on the uppermost part of the vehicle structure, visible from any direction, peak intensity within the range of 40 to 400 candelas, and flash 75 +/‐ 15 flashes per minute. Flags shall be 3’ by 3’ with alternating 1’ by 1’international orange and white squares, and shall be replaced by the contractor if they become faded, discolored, or ragged or as determined by the Airfield Manager and COR.
L. Required escorts. At no time will vehicles or personnel enter portions of the Airfield outside the contract area unless permitted and accompanied by an Airfield approved escort. All construction related activity taking place within any active area of the Configuration Management Automation (CMA) requires the presence of an En route Communications Gateway (ECG) licensed Airfield Driver escort having radio communication with the Control Tower unless prior approval is obtained from the AFM (OPS-1). Spotters and/or flaggers having radio or telephone contact with the Control Tower may be used with the approval of the AFM and the Control Tower
M. Driver Training. To ensure compliance with ECG’s Airfield Driving rules and regulations, all personnel who drive a vehicle or operate equipment in the AOA shall take the “Airfield Driver Training before operating on the Airfield, unless properly escorted. The training includes proper vehicle operations on various areas under normal, lost communications, and emergency conditions.
O. Wildlife management. The CSPP must be in accordance with AC 150/5200‐33, Hazardous Wildlife Attractants on or near Airports, and Certalert 98‐05, Grasses Attractive to Hazardous Wildlife. Construction contractors must carefully control and continuously remove waste or loose materials that might attract wildlife. Contractor personnel must be aware of and avoid construction activities that can create wildlife hazards on airports, such as:
P. Foreign Object Debris (FOD) Management. Special care and measures shall be taken to prevent Foreign Object Debris / Damage (FOD) when working in an airport environment. The Contractor shall be held responsible for implementing an approved FOD Plan that will be incorporated into the CSPP. The FOD Management Plan will have procedures for prevention, regular cleanup, and containment of construction material and debris.
Q. Miscellaneous
1. Concrete mixer chutes, Must be retracted to a single chute while traveling on the AOA.
2. Forklift forks. Must be raised no less than 6 inches and no more than 12 inches, and covered or protected by an approved pallet, when proceeding from one point to another.
3. Radio Contact. Construction vehicles operating in the CMA must have radio contact with the Control Tower or must be escorted by a vehicle that has radio contact with the Tower.
4. Runway Crossing. No person will operate vehicle or construction equipment belonging to or under the supervision of a contractor on or across a runway or taxiway, unless they have met the requirements in Chapter 3-H, or are escorted by Airfield Operations.
5. Open-flame welding or torch cutting is prohibited unless adequate fire and safety precautions are provided and have been approved by COR. NOTE: Under no circumstances are flare pots allowed on the Airfield at any time.
SECTION 01 14 19
FIELD ADJUSTMENTS
Field Adjustments
1. The Contracting Officer’s Representative may authorize field adjustments. Field adjustments are those alterations that do not affect time, price, or intent of the contract documents. All field adjustments shall be documented in the Daily Reports and on the As-Built Drawings.
SECTION 01 18 14
BUILDING PERMITS
Building Permits
1. NO BUILDING PERMITS from state or local governments are required for work performed on federal property. Courtesy permits may be obtained at the Contractor's option. No payment will be made to the Contractor for any permit cost. Design changes to obtain courtesy permits, even at no cost, will not be allowed without written approval of the Contracting Officer.
SECTION 01 18 17
ENVIRONMENTAL PERMITS
Environmental Permits
1. Unless directed by other sections of this specification, the Contractor will not be responsible for obtaining environmental permits.
SECTION 01 26 13
REQUESTS FOR INFORMATION
Request for Information
| 1. | SUMMARY: | ||
| A. Section Includes: Administrative requirements for requests for information. | |||
| 2. | DEFINITIONS: | ||
| A. Request for Information: A document submitted by the Contractor requesting clarification of a portion of the contract documents, hereinafter referred to as RFI (Request for Information). | |||
| B. Proper RFI’s: A properly prepared request for information shall include a detailed written statement that indicates the specific Drawings or Specification in need of clarification and the nature of the clarification requested. | |||
| 1. RFI’s shall be sequentially numbered. | |||
| 2. Drawings shall be identified by drawing number and location on the drawing | sheet. | ||
| 3. Specifications shall be identified by Section number, page and paragraph. | |||
| C. Improper RFI’s: RFI’s that are not properly prepared. |
1. Improperly prepared RFIs will not be processed by the Contracting Officer, but will be returned unprocessed.
| D. Frivolous RFI’s: RFI’s that request information that is clearly shown on the Contract Documents. | |
| 1. Frivolous RFI’s may be returned unprocessed. |
| 3. | CONTRACTOR’S REQUESTS FOR INFORMATION: | |
| A. When the Contractor is unable to determine from the Contract Documents, the material, process or system to be installed, the Contracting Officer shall be requested to make a clarification of the indeterminate item. | ||
| 1. Wherever possible after contract award, such clarification shall be requested at the next site visit by the Contracting Officer’s Representative (COR), with the response entered on the daily reports. When clarification at the COR’s site visit is not possible either because of the urgency of the need, or the complexity of the item, Contractor shall prepare and submit an RFI to the Contracting Officer. | ||
| B. Contractor shall endeavor to minimize the number of RFIs. In the event that the process becomes unwieldy, in the opinion of the Contracting Officer because of the number and frequency of the RFIs submitted, the Contracting Officer may require the Contractor to abandon the process and submit future requests as either submittals, substitutions or requests for change. | ||
| C. RFIs shall be submitted on the form provided by the Contracting Officer. Forms completely filled in, and if prepared by hand, shall be fully legible after photocopying or fax transmission. Each page of the attachments to RFIs shall bear the RFI number in the upper right corner. | ||
| D. RFIs shall be originated by the Prime Contractor. |
1. RFIs from subcontractors or material suppliers shall be submitted through, reviewed by, and signed by the Prime Contractor prior to submitting to the Contracting Officer.
2. The Contracting Officer will neither act on nor respond to RFIs received directly from subcontractors or suppliers.
| E. Contractor shall carefully study the Contract Documents to assure that the requested information is not available therein. RFIs which request information available in the Contract Documents will be deemed either Improper or Frivolous as defined above. | |
| F. In cases where RFIs are issued to request clarification of coordination issues, for example, pipe and duct routing, clearances, specific locations of work shown diagrammatically, and similar items when feasible, Contractor shall fully lay out a suggested solution using drawings or sketches drawn to scale, and submit with the RFI. | |
| G. RFIs shall not be used for the following purposes: | |
| 1. To request approval of submittals. | |
| 2. To request approval of substitutions. | |
| 3. To request changes which entail additional cost or credit. |
4. To request different methods of performing work than those drawn and specified.
| H. In the event the Contractor believes that a clarification by the Contracting Officer results in additional cost or time, the Contractor shall not proceed with the work indicated by the RFI until a modification is prepared and approved. RFIs do not automatically justify a cost increase in the work or a change in the project schedule. | |
| 1. Answered RFIs shall not be construed as approval to perform extra work. | |
| I. Contractor shall prepare and maintain a log of RFIs, and at any time requested by the Contracting Officer, Contractor shall furnish copies of the log showing outstanding RFIs. Contractor shall note unanswered RFIs in the log. | |
| J. Contractor shall allow up to 14 days review and response time for RFIs, however, the Contracting Officer will endeavor to respond in a timely fashion to RFIs. | |
| K. The Government reserves the right to issue a change order to expedite the work per FAR Clause 52.243-4, Changes. |
4. CONTRACTING OFFICER’S RESPONSE TO RFIs:
| A. Contracting Officer will respond to RFIs on one of the following forms: | |
| 1. Proper RFIs: | |
| a. Change Order | |
| b. Request for Proposal | |
| 2. Improper or Frivolous RFIs: |
a. Unprocessed RFIs will be returned with a stamp or notation: Not Reviewed.
3. Answers to properly prepared RFIs may be made directly upon the RFI form with supplementary instructions as necessary.
SECTION 01 31 19
PROJECT MEETINGS
Project Meetings
| 1. | LOCATION: Project meetings will be conducted either on-site or with a conference call. The following meetings may be held: |
| 1.1 | Pre-Construction Conference: After award of a contract, the Coast Guard will arrange a conference with the contractor, and necessary Coast Guard personnel. The purpose of this conference is to orient the Contractor to Government procedures for wage rates, contractual and administrative matters, and to discuss specific issues regarding actual construction. |
| 1.2 | Progress and Technical Review Meetings: These meetings generally take place at the project site. Either party may request a meeting to review the progress of the project and/or review or clarify the technical requirements of the specifications. |
SECTION 01 32 16
CONSTRUCTION SCHEDULE, SCHEDULE OF VALUES,
AND PROGRESS SCHEDULE
Construction Schedule, Schedule of Values and Progress Schedule
| 1. | In accordance with the Notice to Proceed letter, the Contractor shall submit the following: |
| a. Construction Schedule-This schedule shall be prepared using a horizontal bar graph with time scale. It shall be in an industry accepted Project Management format and shall accurately display: |
1. All major categories of work to be performed within the required contract completion date broken out in sufficient detail to track progress throughout the life of the contract. Major work categories should include but are not limited to mobilization, carpentry, plumbing, mechanical, electrical, roofing, concrete, site work, and demobilization. In addition to construction activities, procurement times for critical items, submittal turnaround time, mobilization, final inspection, punchlist work, and demobilization shall be shown on the schedule.
2. The duration of each work category.
3. Any concurrent work categories.
b. Schedule of Values-This schedule shall be prepared as a detailed cost breakdown of the contract price and be submitted with the Construction Schedule. This schedule shall include but not be limited to costs of materials, equipment, and labor for all major work categories shown on the Construction Schedule. The Contractor shall adhere to the following guidelines when developing the Schedule of Values.
1. Format - The line items in the Schedule of Values shall be the same as that of the Construction Schedule.
2. Bonds - Bonding costs will only be paid in a lump sum if they are broken out separately and included with the schedule of values. The Contractor shall provide evidence that he has furnished full payment to the surety.
3. Materials - To request progress payments for materials delivered to the construction or fabrication site, the particular category of work associated with the materials must be broken down into separate material and labor costs.
2. UPDATES: Each month and /or with each progress payment request, the Contractor shall submit the following:
a. Progress Schedule-This schedule shall be an update of the Construction Schedule. It shall show the current schedule of all work.
1. Modifications - If modifications are made to the contract, the work added shall be tracked separately from the original Construction Schedule and shall maintain its individuality on the Progress Schedule throughout the life of the contract. Progress Payment requests shall not lump modification costs into the original contract price.
SECTION 01 32 26
CONSTRUCTION DAILY REPORTS
Construction Daily Reports
| 1. | GENERAL: The Contractor shall complete a Daily Report for each and every day after mobilization. The importance of an accurate, fully detailed Daily Report, promptly delivered to the designated On-Site Representative cannot be overemphasized. The report shall provide an accurate cumulative summary of the history and performance of the work. The Daily Report shall document weather; work hours; work in-place; inspections and tests conducted, and their results; dimensional checks; equipment and material checks; data on workers by classification; the mobilization and demobilization of construction equipment; materials delivered to the site; and any other pertinent noteworthy event; e.g., personnel injury, site visit by Coast Guard personnel, etc. |
| 2. | RESPONSIBILITY: The Daily Reports play an important role in settling disputes and claims for both parties. For this reason the On-Site Representative and the Contractor's Superintendent, together, should review the report to ensure its completeness and accuracy. Each day's report shall be submitted to the On-Site Representative no later than 10:00 a.m. the following morning. The maximum allowable retainage will be enforced for late, sporadic or non-submission of Daily Reports. In the absence of an On-Site Representative the Contractor shall mail the Daily Reports directly to the Contracting Officer every Friday. Should the Daily Report indicate an accident, environmental issue, OSHA violation or any crisis the On-Site Representative deems important, the Report should be faxed immediately to the Contracting Officer at (216) 902-6278. |
| 3. | DESIGNATED ON-SITE REPRESENTATIVE RESPONSIBILITY: After a Notice to Proceed for site work has been issued the On-Site Representative shall complete a Daily Report for each day until the Contractor mobilizes. After the Contractor is at the site, the On-Site Representative shall ensure that the Contractor completes the Daily Report in accordance with Paragraphs 1 and 2 above. Any items of dispute or other notes the On-Site Representative feels appropriate shall be added to the Daily Report. The On-Site Representative is also responsible for informing the COR when the contractor fails to submit daily reports. |
SECTION 01 33 00
SUBMITTAL PROCEDURES
Submittal Procedures
| 1. | GENERAL: The Contractor shall submit to the Contracting Officer (4) copies of submittals required by this specification and/or itemized on the "List of Submittals" found at the end of this division. |
| 2. | REQUEST: A "CONTRACT ITEM ACCEPTANCE REQUEST" shall accompany all submittals. All items shall be individually listed and clearly identified, referencing the applicable Section and Paragraph. A copy of this form is located at the end of this division and may be reproduced as needed. |
| 2.1 | Up to eight (8) items may be listed on an individual acceptance request. Number each Contract Item Acceptance Request consecutively (Submittals # 1, 2, etc.) and re-submittals with letters (Submittal #1A is the first re-submittal of Submittal #1). |
| 2.2 | Submittals shall be forwarded to the Contracting Officer. The contractor shall allow 14 calendar days, excluding mailing time, for the review process in the Construction Schedule and all project planning. In instances where submittal review must be expedited, the Contractor may annotate the Contract Item Acceptance Request as "Urgent" and provide a FAX number for prompt return. The Coast Guard will make every effort to accelerate the review of each urgent submittal; however, the Contractor should not anticipate a reduced time schedule and shall plan project progress accordingly. |
| 3. | ACCEPTANCE: Submittals will be stamped "Accepted," "Accepted with Comments," or "Resubmit". Acceptance, Acceptance with comments or Resubmit for each item will be indicated on the Contract Item Acceptance Request form and one copy returned to the Contractor. |
| 3.1 | Prompt re-submittal of items is required. The Contractor shall furnish a new Contract Item Acceptance Request numbered in accordance with the requirements of paragraph 2.1. |
| 4. | DEFECTIVE WORK: Acceptance of Submittals does not restrict the Government's right to reject departures from contract requirements, use of damaged or improperly installed items/materials, or latent defects, nor does it prejudice the Government's rights of rejecting any work found defective at Final Inspection and Acceptance. |
| 4.1 | Work started or completed prior to submittal acceptance is solely at Contractor's risk and may jeopardize contract performance. |
SECTION 01 35 29
SAFETY PROGRAM
Safety Program
| 1. | GENERAL: The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. The Contractor shall provide appropriate safety barricades, signs, signal lights, etc. (see Section 01 56 00, “Lights, Signs & Barricades”) as well as complying with the requirements of all applicable Federal, State and Local safety laws, rules and regulations. |
| 2. | COMPLIANCE: The Contractor is specifically required to comply with the requirements of the U. S. Army Corps of Engineers "Safety and Health Requirements Manual" (EM 385-1-1, latest version available) and the “Accident Prevention” clause (FAR 52.236-13). Once accepted, this safety plan shall become part of the contract requirements. Note: This review/acceptance does not in any way relinquish the Contractor from responsibility for work site safety nor the obligation to comply with the OSHA regulations found in 29 CFR 1910 & 1926 or any other State or Local safety law, rule or regulation applicable to the contract work. The Coast Guard will cooperate fully with the Department of Labor (Occupational Safety and Health Administration) in their enforcement of OSHA regulations. |
| 3. | SAFETY PLAN: The Contractor shall submit a written safety plan. At a minimum, this plan shall describe the Contractor's general safety program and identify specific safety provisions for hazards incidental to the contract work; e.g., elevated working surfaces, working over water, working from floating work platforms, overhead crane operations, etc. |
SECTION 01 51 00
TEMPORARY UTILITIES
Temporary Utilities
| 1. | GENERAL: All temporary utility connections shall be compatible with existing materials and equipment to provide safe and efficient installation, operation and removal. |
| 2. | ELECTRICITY AND WATER: Electrical power and water are available on the site. The Contractor will be permitted to utilize these utilities in performing the work, provided that the existing systems are not overloaded. The Contractor is responsible for installing and removing all connections to existing systems and shall ensure work and materials are in accordance with local codes. The use of the electricity shall be limited to tools that can be operated on 60 Hertz, single phase, 20 ampere, 120 volt circuits. |
| 3. | TELEPHONE: Telephone services will not be available for use by the Contractor. |
| 4. | WATER HOOKUP: All connections to the water system shall be equipped with back flow protection. Temporary potable water pipes and hoses shall be sterilized before being placed in operation and every time the system is opened to the atmosphere for repair or relocation. |
| 5. | SANITARY FACILITIES: It shall be the Contractor's responsibility to furnish and maintain approved portable toilet facilities for all Contractor personnel. The On-Site Representative will designate the physical location for the facility and the Contractor shall maintain the toilet facility to the satisfaction of the Government. Contractor personnel are forbidden to use toilet facilities within existing buildings. |
SECTION 01 51 16
TEMPORARY FIRE PROTECTION
Temporary Fire Protection
| 1. | Temporary Fire Protection: Install and maintain temporary fire-protection facilities to protect against predictable and controllable fire loss. Comply with NFPA 10 "Standard for Portable Fire Extinguishers" and NFPA 241 "Standard for Safeguarding Construction, Alterations and Demolition Operations". |
| 1.1 | Maintain unobstructed access to fire extinguishers, fire hydrants, temporary fire-protection facilities, stairways and other access routes for fighting fires. |
| 1.2 | Provide training for all personnel on-site in the proper operation of each type of fire extinguisher provided. Provide all personnel with the proper notification procedure to summon the local fire department or emergency medical service. |
| 1.3 | There shall be NO SMOKING or unsupervised open flame inside any structure, temporary or permanent; nor within 25 feet of combustible material or within 50 feet of flammable liquids or compressed gasses. |
SECTION 01 55 00
ACCESS ROADS AND PARKING
Access Roads and Parking
| 1. | ACCESS: Access to the site is available from public roads. Any damage to these roads by the Contractor's vehicles shall be repaired without cost to the Government.//The site is remote and the contractor shall comply with all rules imposed by the owner of the site.// |
| 2. | PARKING: Vehicular operations and parking shall comply with all applicable government orders and regulations. All driveways and entrances serving the Government shall be kept clear and available to emergency vehicles at all times. |
| 3. | VEHICLE AND VEHICLE OPERATION: All vehicles, owned by the Contractor or employees of the Contractor, and operators of these vehicles, shall meet all state regulations for safety, noise, loading and minimum liability insurance. All vehicle operators demonstrating reckless or careless operation in the opinion of the Government shall not be allowed to operate vehicles on government property for the duration of the contract. |
| 4. | VISITORS: No visiting vehicles will be permitted on government property unless the operator is employed by a subcontractor or supplier. |
SECTION 01 55 29
STAGING AREAS AND ACCESS
Staging Areas and Access
| 1. | LOCATION: The Contractor shall store materials and operate equipment within the confines of the staging area identified by the Government. Storage of materials outside of the staging area will not be permitted. |
| 2. | COORDINATION: Two weeks prior to construction, the Contractor shall contact Mr. Garry Manning at U.S. Coast Guard Air Station Elizabeth City to verify the condition of the staging area. |
| 3. | ADJACENT AREAS: The Contractor shall ensure that all land and vegetation adjacent to the staging area and access drive remain undisturbed and undamaged; all damages shall be repaired at no cost to the Government. |
SECTION 01 56 00
LIGHTS, SIGNS AND BARRICADES
Lights, Signs and Barricades
| 1. | GENERAL: The contractor shall provide and maintain all warning lights, sign, and barriers to insure the safety of pedestrians or vehicles traveling near or through any hazardous area caused by the execution of the Contract work. |
| 2. | LIGHTING: All lighting requirements shall meet table 7-1 in the US Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1). |
| 3. | BARRICADES: Hard barricades or flexible barriers shall completely encompass all exterior work areas. Flexible barriers shall consist of 1/2 inch steel bars or 2" X 2" wood stakes driven 12 inches minimum into hard packed soil. Space stakes on a maximum 10 feet interval and with two rows of yellow or orange 1/4 inch diameter rope (wire and plastic tape are not acceptable) at 24 inches and 36 inches each above ground. |
| 4. | HAZARD FENCING: Special fencing 4 foot high shall be installed to prevent small children or pets from entering the work area when within 300 feet of family housing or for special hazards as shown on the drawings. |
SECTION 01 57 23
POLLUTION CONTROL
Pollution Control
| 1. | Volatile Organic Compound (VOC) Regulations: Contractors are required to comply with local, state and federal VOC compliance laws and regulations in the foregoing order of precedence. In order to comply with the provisions of the Clean Air Act, each state must have a State Implementation Plan. Some contractors may be required to abide by the provisions of a Title V Permit. Some contractors may be required by state or local law to operate under the terms of a Compliance Plan to reduce VOC Emissions. |
| 1.1 | In accordance with the Notice to Proceed Letter, the contractor will submit copies of any local, state or federal implementation plans, permits or compliance plans required/applicable to the use/application of VOCs at contractor's facility or offsite work places. |
| 1.2 | If no local, state or federal implementation plans, permits or compliance plans are required/applicable to the use/application of VOCs, then the contractor shall submit to the designated Contracting Officer a letter, notarized under oath, that such documents are not required. |
| 1.3 | If the use of paint is required the contractor shall submit to the Contracting Officer and in accordance with the Notice to Proceed Letter, certificates, specifications or manufacturing data verifying the VOC rating. |