RFI RESPONSES - 15-B-PMV251 AMENDMENT 0004

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI RECEIVED QUESTION ANSWER

1 11/2/2015

In Section 099600 – High Performance Coatings the specs call for an ESD urethane coating, the drawings for this section call for the flooring to be white. The particles from the additives and fillers in the ESD coating are grey and will over power any white coloring added. Will a grey ESD urethane coating be acceptable?

ESD is an Electro Static Dissipation and the hangar requires ESD floor. The specification is correct, and to get a white floor, the polyurethane top coats (Step 4

& 5) in System Installation shall be pigmented white so that the surface is pure white. Bid in accordance with the specifications

2 11/2/2015

1. The specifications calls for an ESD Urethane Coating. 2. The pictures that show the floor state that the color needs to be white. 3. The problem is that the additives and the fillers in the coatings that make it ESD are gray. So the lightest color for ESD coatings would be gray.

ESD is an Electro Static Dissipation and the hangar requires ESD floor. The specification is correct, and to get a white floor, the polyurethane top coats (Step 4

& 5) in System Installation shall be pigmented white so that the surface is pure white. Bid in accordance with the specifications

3 11/3/2015

1. Helicopter Tie Downs: Plan sheet G-03 shows the location for (8) helicopter tie downs and item (55) of the general requirements requires (10) more tie downs in the temp. hangar. What are the requirements for these tie downs?

Yes, The tide downs on G-03 are 8 existing to remain. Items 55 are new temporary tie downs inside the temporary hangar. Contractor to provide 10 Tie

Down including the removal after the temporary hangar is removed. Refer to detail provided on new sheet G-02.1.

2. Flat Bar: Item (56) of the general requirements requires a 25 inch thick aluminum flat bar. This looks like a typo? What width and thickness flat bar is required?

Provide alum flat bar and close cell foam gasket with concrete anchors as per manufacture specifications.

3. Paint Removal: Is the intent of the specifications to remove only the flaking paint inside the hangar and to encapsulate the remaining fully adhered paint, rather than to remove all lead containing paint?

Yes, the scope is to remove the loose material, you do not need to remove all paint as long as it is well adhered to the building component.

4. Electrical Drawings: Item (59) of the general requirements requires providing electrical drawings and specifications for the temporary hangar, but these are provided in drawings TE-1 thru TE-4 and specification section 26-05-05. What else is required?

Note #59 is revised for electrical submittals requirement of temporary structure

5. Candle Power Lighting: Item (60) in the general requirements requires a 30 candle power uniform distribution of lighting in the temporary hangar, but only (4) portable lights are shown on the drawings. Is the 30 candle power lighting to be designed and added by the contractor.

Min of 30ft candle uniform light distribution in the temporary hangar is required to be designed and added by the contractor. Portable LED light are additional light to be furnished under this contract. Contractor shall provide meter report at night.

6. NTP: Item 1.1.1.a of the general requirements Phase 1 allows 45 days from the

NTP to design, submit, fabricate, deliver, erect, and provide electrical requirements for the temporary hangar. We do not believe this is possible unless the NTP is held until the hangar structure is ready to install.

NTP will not be postponed. Please bid accordingly.

US AIRSTA NEW ORLEANS INTERIOR AND EXTERIOR REPAIRS

4 11/10/2015

Section 09 90 00 1.4 B 3 (page 4 of 9) states "Qualifications of Coating Contractor: All

Contractors and Subcontractors that perform surface preparation or coating application shall be certified to either ISO 9001 or SSPC QP-1 and SSPC QS 1 Prior to contract award. / Do you mean SSPC QP-1 and SSPC QP 2 Prior to contract award? / QS-1 certification. The timing required is a problem - "prior to award" may be problem, also maintaining the certification requires that you continue to perform work on QS 1 projects. Not sure we can meet that requirements as again this is the first one we have seen with this requirement.

This is a national standard. Bid in accordance with the specifications. (Prior to contract award removed)

5 11/10/2015

Section 09 90 00 1.4 B 3 (page 4 of 9) states "qualifications of Coating Contractor”: All

Contractors and Subcontractors that perform surface preparation or coating application shall be certified to either ISO 9001 or SSPC QP-1 and SSPC QS-1 prior to contract award. / Please note that there are no current "SSPC QS-1" qualified contractors in the state of LA. / QP-1 has to do with industrial coating applications on steel structures in the field, while QP-2 is for industrial hazardous paint removal in the field. Is this a typo and should it be SSPC QP-1 and SSPC QP-2?

This is a national standard. Bid in accordance with the specifications. (Prior to contract award removed)

6 11/13/2015

1) Will the Water for the Power Washing be Supplied by the Coast Guard. Yes, water will be supplied, but not the equipment. (tank, hoses, mobility, etc)

2) Can you clarify the area of the Power Wash – are you looking at all the Concrete

Ramp Area all 169,000 SF of it or less than that just under the New Fabric Temporary

Building

The area of Power Wash for the entire existing Concrete Ramp is approximately

206,000 SQ. FT. Attached revised Dwg. G-03.

3) Detail 4 on A-04 – how much of the Pretreated Blocking is required to be removed Roof warranty is held by unit and copy in our file. See Appendix "K"

4) Detail 4 & 5 on A-04 Should the Flashing be replaced as well as a new splice piece installed to tie back into the building at the replaced blocking and/or at the New

Panel areas?

Flashing is new, no blocking need to be replaced.

5) Detail 5 A-04 States to install New 6” x 2” x 3/8” angle – there is only a 6” x 3 ½” x

3/8” standard angle available in the market. Is that what you prefer to be installed?

Angle is not a standard due to the condition of the existing structure. 6” x 2” x 3/8” angle shall be specially made in order to allow clearance for panel screws into the existing steel channel behind. Provide shopdrawing.

6) Do the downspouts coming off the high roof of the hanger tie into another gutter system or continue onto the ground with another downspout from the lower roofs?

Contractor shall replace all existing gutters and downspouts (vertical and horizontal) in the entire building (upper and lower roof including the emergency stair). See revised dwg.

7) On Sheet G-03 talks about Helicopter Tie Downs – can you please specify which brand you are specifically looking for

Provide 10 helicopter Tie Downs inside the Temporary hangar, 2 per helicopter.

Attached drawing and detail. See new Sheet G-02.1.

8) Will there be any load testing or certification requirement for the Helicopter Tie

Downs

Contractor shall test new tie downs for 10,000 pounds.

7 11/13/2015

1) Sheet G-02 Sprung Building Detail references earth anchor typical details. Please provide the Tarmac Paving Section Thickness & Details of the construction for use in project application installation.

See new sheet G-02.1 and revised drawing G-02. Reference drawing included.

2) Sheet A-10, please provide the length of the Taxi Lines are to be extended from the face of the hanger doors.

See revised sheet A-10.

3) Sheet G-03 are the New Taxi Lines shown in addition to the 5,000 LF noted in

Note 4 (Re-paint approx. 5,000 LF of 18” line on Air Field)

Existing 18" taxi lines are approximately 5,000 LF. Re-paint over the existing taxi lines as per manufacture specifications.

4) Sheet A-01 Note 12 – How can we price this item if we are to evaluate & note the existing working condition of the fire alarm system during construction process.

Contractor to note the condition only. This job is not intended for the contractor to repair the alarm system. System only needs to be evaluated for what is or is not functioning.

5) Sheet A-06 – New Gutters & Downspouts – Do the downspouts that come across the lower roof extend to the ground vertically as a downspout or into a existing horizontal gutter. No downspouts are shown on the elevations but splash blocks are noted.

Contractor shall replace all existing gutters and downspouts (vertical and horizontal) in the entire building (upper and lower roof including the emergency stair). See revised dwg.

6) Sheet A-09 Note 7 states all piping to be painted - Fire Sprinkler, Gas, Heating

Supply & Returns etc, will you provide us with Existing As-Builts for each Mechanical

System for us to be able to quantify this scope?

Yes all piping to be painted: Fire Sprinkler to be red, Gas to be yellow.

Electrical : 1.) If it is existing as blue, the contractor should paint as blue (minimal work as indicted in the hangar interior photos).

2.) All other electrical conduits. Recommend to paint same color as wall finish.

3.) Exceptions: If an electrical small junction box cover (4" sq.) is painted or marked in red (indicative of fire alarm), than it should remain as red. If an electrical junction box has a circuit identification ID, that that ID should remain visible.

We do not have additional as-builts drawings. References drawing added at the end of the specs.

7) Sheet A-10 Note 10 – Since there is No Furniture or Equipment Layout Drawing, will you provide an Itemized List of the Furniture

Itemized List of the Furniture provided. Appendix "J".

8 11/13/2015

Attached you will find our substitution Request Form and enclosures regarding –

Specification 084523 Translucent Metal Panels – for the USCG Air Station Hangar

Repairs in New Orleans, LA (Job#6034068). I am trying to submit this request to the person in charge of approvals. If that is not you, could you please help me connect with them. There is only one manufacturer listed for this scope of the project. CPI meets the performance requirements and would like to be listed as an equal in the specification. I have attached supporting data comparing our product with that specified. We would appreciate your approval to bid as an equal on this project.

CEU does not exclude competition as alleged in the submitter's point by point analysis. CEU will accept any manufacturer of fiberglass reinforced translucent panel wall as equal. . See revised spec section.

9 11/13/2015 1.-SECTION 01 11 00 PG 2 OF 16 NOtE 15 T"SEAL EPOXY FLOOR" DO NOT SEE

ANY SPEC FOR EPOXY SEALER.

Note 15 deleted. Refer to SECTION 09 96 00

2.-NOTE 18 "CONTRACTOR TO EVALUATE FIRE ALARM SYSTEM" IF SYSTEM IS

NOT FUNCTIONING OR NOT TO CODE, HOW IS COST TO REMEDY TO BE

HANDLED.

Contractor to note the condition of the Alarm System only. This job is not intended for the contractor to repair the alarm system. System only needs to be evaluated for what is or is not functioning. Contractor to provide report.

3.-NOTE 24 "PROVIDE NEW COAST GUARD SIGNS" APPENDIX HAS MULTIPLE

SIGN OPTIONS WHICH ONES WILL BE REQUIRED

Size layout and shape are indicated on the drawing Sheet A-03. Additional information in the Appendix Comdtinst M5200 14A. Refer to pages 3-1 3-2.

4.-PAGE 3 OF 16 NOTE 32: "MAINTAIN EXISTING ROOF GUARANTEE" IS THERE

A ROOFER WHO CURRENTLY HOLD THE GUARANTEE? HOW LONG WILL WE

HAVE TO GUARANTEE ROOFING?

Roof is new. Roof warranties attached in Appendix "K"

5.-PAGE 5 OF 16 NOTE 55 "PROVIDE TWO (2) TIE DOWNS FOR HELICOPTERS"

NEED SPEC TO DETERMINE COST AND INSTALLATION / AND DECK REPAIR

COST

Items 55 are new temporary tie downs inside the temporary hangar. Contractor to provide 10 Tie Down including the removal after the temporary hangar is removed.

Refer to detail provided on sheet G-02.1.

6.-NOTE 57 "PROVIDE FANS AND HEATERS" NEED SPECS TO DETERMINE

ELECTRICAL LOAD REQUIRED. PRESENT TEMP. ELECTRICAL PANELS DO NOT

PROVIDE ANY INDICATION OF POWER TO ANY TEMP UNITS.

Two fixed infared heaters are required to be furnished and installed in the temporary hangar. See electrical TE drawing and spec.

10 11/13/2015

Can we bid on this project as an equal to the products specified under High

Performance Coatings, epoxy & urethane flooring?

No, Bid in accordance with the specifications.

11 11/13/2015

Sheet TE-01

1. Keyed note #2 – 3” conduit is too small for the size wire being installed and still maintain 40% fill. What size conduit do we use, 3 1/2” or 4”?

Revised conduit size to 3-1/2”C and shown on revised drawing

2. Keyed note #4 has disconnect fused at 350 Amp, on sheet TE-02Keyed Note #3 has it fused at 400 AMP. Which is correct?

Delete 400amp disconnect switch. Revise for wire gutter and three 200amp disconnect switches.

3. Under ”General Notes”, Note #6, is there a note #4? Revise notes order number.

4. Under ”General Notes”, Note #6, Note #5, Note #2, are there any dimensions you have in mind for the cart? Can you give a more specific type of metal to be used? And the size of the metal to be used? And the size wheel to be used? Detail #5 on TE-03 does not give any of this information.

The dimension of the cart is shown on revised drawing.

5. Under ”General Notes”, Note #6, Note #5, Note #4, what size wire and the number of conductors required for the 200lf of SOOW cord?

100LF of SOOW cord is furnished with the LED explosion proof light. Cord shall be sized per lighting load plus voltage drop. See revised drawings.

Sheet TE-02

1. Key note #3 mentions” termination lugs shall be rated for multiple lugs” and the one line diagram shows three feeders leaving the disconnect to distribute power to Panels

A, B & C. Should his be a panel with 3 branch breakers or a trough with 3 disconnects to feed the panels?

Revised for three 200amp disconnect switches to feed three panels.

2. Feeder “F2” – should this be in 3 ½” or 4” conduit? Revise for 3-1/2”C

In the General Requierments

1. Page 5 of 16 #61 – “Provide LED exit signs on all doors”. Where do we get power for these exit signs?

LED Exit lights and general lighting shall be designed and furnished with structure.

Electrical contractor shall connect power to nearby panel. See revised notes on drawings

2. Page 5 of 16 #62 – “Provide lightning protection for the structure”. Do we do a design build type lightning protection system for the temporary hanger or the pertinent hanger or both?

Contractor is require to design and built lightning protection to protect temporary hangar structure only.

3. Page 5 of 16 #63 – “Provide fire detection system for the temporary hanger”. Where do we mount the Fire Alarm Control Panel and where does it have to report to?

Connect FACP to nearby power panel in the temporary hangar. Coordinate with contracting officer for location of panel during construction. Provide local alarm only.

4. None of the above items are shown on the temporary Hanger drawings. See notes on revised drawings.

12 11/19/2015

1) The plans call for removal of all of the metal and translucent panels on the hangar.

Does acceptance or non-acceptance of Option Item 1 have any bearing on the amount of demolition work to be done?...i.e. more or less work whether the option is accepted or not?

Regardless of Option 1, demolition is the same. All the panels shall be removed and not to be reused.

2) It is noted in Unit Price #2 that there is a pricing request for “an additional 50 linear feet of taxi lines suggesting that the unit price is optional. Should we construe that Unit

Price #1 for the temporary hangar is optional also, or a necessity in carrying out this project? The purpose of the question is to understand whether the work to be carried out in the existing hangar will or will not be carried out with greater ease or greater difficulty depending on the response to this question.

Unit Price #2 is for additional 18" taxi lines after the temporary hangar has been removed. Unit price #1 is for additional monthly rent of the temporary hangar if needed.

3) Section H - Special Contract Requirements notes in H.4 that regular work hours are those hours the activity Command works on a day-to-day basis. General

Requirements Section 01 11 00, 1.10 Work Hours states that the work shall be done during the hours of 7am - 5pm, Monday thru Friday. On a project just completed we were forced to stop work at 3:30pm. Therefore, can you tell us with certainty the hours that we will be allowed to start and stop our work for bid purposes?

Work hours as as indicated in specification.

4) Referring to Section L - Instructions, Conditions, and Notices to Offerors, L.2,.....are the minority and female participation goals in 52.222-23 a mandatory requirement to be met, or suggestive target goals and not a mandatory requirement to be met

This is a mandatory requirement that mus be met.

5) Understanding pay rates prior to bidding is one of the most important parts of bidding. Since lead plays an important part in this project are we expected to apply the common laborer rate to for lead workers or is there a special rate for Davis - Bacon that we are to use?

There are no known special laborer rates for lead workers.

6) Under demolition, is the intent to remove only exterior light fixtures or interior ones also? Questions: Re: Hangar Interior/Exterior Repairs - Solicitation #HSCG82-15-B-

PMV251 Page -2-

YES, the note on this Hangar Exterior Elevations Demolition Work is correct.

Exterior and Interior light fixtures to be removed and to be provided. The removal of four (4) exterior MV apron area light fixtures is indicated on sheet E-01, 21/29, Plan

Note #4. Also the removal and replacement of the hangar interior lighting is as indicated on sheets, E-01, E-02, E-03, E-04, E-05, E-06, E-07, and Specification

Section 26 05 00, Article 2.10 Lighting, Interior & Exterior.

................................REFER TO ELECTRICAL DRAWINGS.

7) Under demolition it is called out for all of the exterior siding panels to be removed. I find one related sample (reading # 23 which reads “wall”, and it reads “negative”) in the LEAAF lead survey on 7/20/12, however, I am not sure whether that is a test for the hangar upper panel walls which we are to remove or a lower wall test elsewhere in the hangar. Also, in the LEAAF survey of 4/3/14 there was a Reading #9 wall test yielding negative results on gray metal on the NW side. However, not having visited the hangar yet, and being uncertain of the exact location tested questions loom.

Therefore, with this uncertainty, is the removal of these metal panels to be construed as lead component removal work or regular demolition work? Having a clear understanding of this is paramount to work methods to be employed and the resulting cost consequences.

This is regular demolition work, although the contractor is responsible for following the OHSA 29 CFR 1926.62 "Lead" Standards and provide for appropriate worker protection. As mentioned in the General Note on sheet 4 of 29 : "All existing coatings contain some level of lead content. OHSA Worker Protection shall be provided for disturbance of any painted surfaces. Painted coatings on existing building materials to be removed can be disposed of as normal construction waste provided they remain intact on the building material being removed" REMEMBER:

lead-based paint applies to target housing and child-occupied facilities. The OHSA

Worker Protection standards are what's applicable here.

8) What is the demarcation height between column lead work and regular work at the columns?

Or, would you prefer that we treat the lower column work as lead work in lieu of not knowing for certain? (See LEAAF letter dated 7/24/12, paragraph 4.

This is regular demolition work, although the contractor is responsible for following the OHSA 29 CFR 1926.62 "Lead" Standards and provide for appropriate worker protection. As mentioned in the General Note on sheet 4 of 29 : "All existing coatings contain some level of lead content. OHSA Worker Protection shall be provided for disturbance of any painted surfaces. Painted coatings on existing building materials to be removed can be disposed of as normal construction waste provided they remain intact on the building material being removed" REMEMBER:

lead-based paint applies to target housing and child-occupied facilities. The OHSA

Worker Protection standards are what's applicable here.

9) Have the hangar doors been changed out since the LEAAF report dated 7/24/12? I thought that I either heard that from my contractor or saw it elsewhere in the plans/specs information. Can you confirm?

Yes, Hangar doors are new.

10) Section B - Supplies or Services and Prices, Base Bid Item states ....”clean and eliminate rust and all loose material from all components of the metal structure including the emergency stairs”. Is this scope completely accurate as it reads or is it required that 100% of all paint, lead or nonlead, be removed?

Bid in accordance with the specifications. Remove the loose material, you do not need to remove all paint as long as it is well adhered to the building component.

Dust is present inside the main hangar cleaning is important before painting. Refer to the OSHA Lead standard for requirements associated with abrasive blasting.

Refer to spec for the coatings preparation requirements, ISO 9001, OR SSPC QP1

AND SSPC QS1. The USCG does not dictate the removal methods for the non-adhered coatings. Properly prepare accordingly to the manufacture recommendations.

11) Is it clear to the military that for the purposes of this work scope intent that there will be painted surfaces between roofing and top of structural flanges is sandwiched and cannot be addressed?

The contractor shall paint the existing metal deck on the underside that is facing the interior hangar space, including trusses, purlins, girts, columns, etc. It is clear to the military that all surfaces that you can reach without desmanteling the structure from the inside of the main hangar space shall be painted.

12) Is blasting acceptable for the intent of work scope to remove the loose rust and paint in the ceiling? If so, is there any form of blasting that is not acceptable?

Yes, refer to the OSHA Lead standard for requirements associated with abrasive blasting. The USCG does not dictate the removal methods for the non-adhered coatings.

13) Is chemical stripping acceptable for the intent of work scope to remove paint? Yes, but you are only required to remove non-adhered coatings from component surfaces. The USCG does not dictate the removal methods for the non-adhered coatings.

14) Lead paint may be on the outer surfaces (facing outward toward metal panels to be later removed of columns, girts, and other structural members trapped between metal panels and the structural component outer face. Access may only be attained after the panels are removed in the subsequent phase that follows abatement according to the phasing schedule in 01 11 00, 1.3.1. Is it the intent to perform additional outer lead preparation and painting work in the subsequent phase “c”, thereby requiring additional work consideration and cost consideration, or is exemption of further lead work and painting acceptable and also the intent to move the panel removal/replacement along swiftly to gain closure of the hangar? Questions: Re:

Hangar Interior/Exterior Repairs - Solicitation #HSCG82-15-B-PMV251 Page -3-

Yes, Lead paint shall be removed on the outter surfaces (facing outward toward metal panels to be later removed of columns, girts, and other structural members trapped between metal panels and the structural component outer face). Yes, additional work is required. Performing the interior first will allow the walls to contain the LBP inside the hangar. To combine phases for LBP removal shall be discussed with COR and CM.

15) There was no information regarding the paint content (lead or non-lead) on the floor of the hangar. Can you confirm whether this deck surface or any striping’s on it contains lead paint since it is to be removed?

Attached new LBP report in Appendix "G" G-5

16) A) Is flame retardant poly acceptable in satisfying “heavy dust proof flame retardant curtain walls” or tarps to cover the hangar doors on the inside? B) In the environmental business we know how to poly critical barriers for doors and windows, etc. Is individual polying of these openings at the adjacent “lean-to”buildings acceptable in lieu of a very difficult, more onerous method described in Specification

Section 01 11 00-1.3.2f? Our suggestion permits tighter, better controlled, and easier to monitor control of the openings during work progress.

Yes, use any dust proof barrier that's approved by OHSA. Main doors are new and require a heavy dust protection secured at the floor, the side walls and top of the doors, interior protection and exterior protection is needed for the two big doors.

During LBP removal and during painting of the support structure of the wall panels protection is needed. Opening must be protected at all times even while painting due to rain water infiltration.

17) What is the purpose of covering the exterior of the hangar doors? Is this a necessity?

The exterior of the hangar doors shall be covered as well during the exterior work.

Work will be done on top of the doors outside the façade.

18) The specification has some uncertain or conflicting information regarding asbestos abatement intent. Specification Section 01 11 00, 1.2.1-6 acknowledges asbestos presence from the LEAAF 6/12/15 environmental survey. That survey reports presence of asbestos (>1%) on piping and elbows as found in the Appendice.

Specification Section 01 11 00, 1.2.4.1 paragraph two conversely states that “no

ACBMs were present above the regulatory limit of 1% or greater”. Isit the intent to remove asbestos components during this renovation or not?

Section 01 1100, 1.2.4.1 paragraph two should state: "….and ACBMs were present above the regulatory limit…"

19) Regarding question #18 above, the drawing provided by LEAAF suggests that most of the positive ACM locations (samples 16, 18, 19, and 20) of the sampling is within the “lean to” offices and it is my understanding that no work is to be done there.

Is this correct that no asbestos work is to occur within the lean-to offices?

Yes, there will be not work on the "lean to" offices.

20) What I can’t discern is whether samples 21 and 22 are in the open hangar and therefore whether they suggest removal of this sample type throughout the open hangar. Can you confirm this please for our work scope purposes as it might or might not affect 01 11 00, 1.2.1-49 for the hot water circuit?

You must assume that all of the "Foam Glass Pipe Insulation" is an ACBM.

Samples 21 and 22 are in the main hangar.

21) The natural gas pipe was confirmed as having lead based paint on it. Should the removal of the two sections be considered as lead paint component removal work scope? It is listed under Mechanical scope #51 under 01 11 00, 1.2.1-51

The removal of the two sections of natural gas pipe should be considered as lead paint components.

22) Is an unexpired Safety Card for the named Competent Person acceptable in lieu of a Letter of Qualification for equipment operation?

All equipment operators must be licensed IAW OSHA and EMI-385

23) Specification Section 02 82 12, 1.3.1, Description of Work discusses removal of asbestos duct mastic. I do not see any relevancy to this work scope elsewhere in the specs and plans. Is the work scope for removal of asbestos duct mastic accurate or a mistake?....and does this paragraph need to be re-issued?

Questions:

Re: Hangar Interior/Exterior Repairs - Solicitation #HSCG82-15-B-PMV251 Page -4-

You must assume that all of the "Foam Glass Pipe Insulation" is an ACBM.

Samples 21 and 22 are in the main hangar. No duct mastic. Paragraph should read as: "1.3.1 Description of Work

The work covered by this section includes the handling and control of asbestos containing materials and describes some of the resultant procedures and equipment required to protect workers, the environment and occupants of the building or area, or both, from contact with airborne asbestos fibers. The work also includes the disposal of any asbestos containing materials generated by the work. More specific operational procedures shall be outlined in the Asbestos Hazard Abatement Plan called for elsewhere in this specification. All of the "Foam Glass Pipe Insulation" is an ACBM., and is governed by 40 CFR 763. Provide negative pressure enclosure techniques as outlined in this specification. Lead-Based Paint & ACBM Reports, are attached to these specification. Refer to appendix “G”. The Government will evacuate the work area during the asbestos abatement work. All asbestos removal work shall be supervised by a competent person as specified herein.

24) Should power outage be required, there is a conflict regarding the request for power outage causing a 13 day difference in the wait period. See Table at 1.12.5 which states 15 days wait versus Section 1.23 which states 2 working days, both in

Specification Section 01 11 00.

The power outage clarification. If it will affect unit only a 2-day notice is needed. If outage affects or could affect the units outside our fence line then the 15-day notice is required.

25) Referring to Specification Section 02 82 12, 1.5.1 Private Qualified Person

Documentation,if asbestos work is to be performed, is it correct that the requirement is such that the general contractor must hire the PQP?

Yes, but they can't be hired by the asbestos contractor; they need to be financially independent of the asbestos contractor.

26) In Specification Section 02 82 33, 1.3.1 Description of Work, there are statements that appear to be contrary to other information within the plans and specs. A) For instance, it says to “remove/control lead-based paint /paint with lead in good condition” where only the rusted, loose lead based paint was to be removed elsewhere throughout the specifications. Which is correct?

B) It also (awkwardly) states, for the first time I’ve seen throughout the plans and specifications, to remove/control lead paint at the “walls metal siding and underside of roof decking that that will be in direct contact and will result affected by construction activities”. Are the metal panels positive for lead paint? C) Hasn’t the roof deck already been changed out?

A) The scope is accurate remove the loose material, you do not need to remove all paint as long as it is well adhered to the building component. B)This is regular demolition work, although the contractor is responsible for following the OHSA 29

CFR 1926.62 "Lead" Standards and provide for appropriate worker protection. As mentioned in the General Note on sheet 4 of 29 : "All existing coatings contain some level of lead content. OHSA Worker Protection shall be provided for disturbance of any painted surfaces. Painted coatings on existing building materials to be removed can be disposed of as normal construction waste provided they remain intact on the building material being removed" REMEMBER: lead-based paint applies to target housing and child-occupied facilities. The OHSA Worker

Protection standards are what's applicable here. C) No, The roof deck has not been changed. All existing coatings contain some level of lead content.. The contractor shall paint the existing metal deck on the underside that is facing the interior hangar space, including trusses, purlins, girts, columns, etc.

27) In the same Specification Section it discusses “remove/control lead-based paint in exterior and/or interior paint of the EMERGENCY GENERATOR building”....and, “at contractor option,contractor may test for lead based paint and provide certification that no lead-based paint shall be disturbed.” Is this paragraph applicable to this project or a left over specification from a different project? If it’s related to this project then why wouldn’t the area be immediately tested to confirm whether to bid the abatement cost into the project (or not)?

Paragraph should read as:

1.3.1 Description of Work

Remove/control lead-based / paint with lead, located on areas of steel structural members including steel columns, beams and trusses and walls metal siding and underside of roof decking, including the emergency stair and during removal of panels and accessories that will be in direct contact and will result affected by construction activities. Refer to Leaaf reports Appendix "G".

28) Is it the intent to clean the rust and loose paint at the emergency stair under a lead removal protocol? I did not see sampling for the painted stair structures in either report and since the emergency stair has its own section separation at Specification Section

1.2.1-33 it appears not associated with the “Main Hangar” ceiling structures which have been identified for lead paint.

This is regular demolition work, although the contractor is responsible for following the OHSA 29 CFR 1926.62 "Lead" Standards and provide for appropriate worker protection. As mentioned in the General Note on sheet 4 of 29 : "All existing coatings contain some level of lead content. OHSA Worker Protection shall be provided for disturbance of any painted surfaces. Painted coatings on existing building materials to be removed can be disposed of as normal construction waste provided they remain intact on the building material being removed" REMEMBER:

lead-based paint applies to target housing and child-occupied facilities. The OHSA

Worker Protection standards are what's applicable here.

29) It was noted at the site visit that the crane permit for the airfield takes approximately 45 days to get processed and the first phase of the project requires construction of the temporary hangar to be performed in 45 days. In order to provide the construction in the amount of days in phase one for the temporary hangar, the NTP will need to be delayed until the crane permit has been approved. Is this a viable assumption for our scheduling of the work to be performed?

NTP will not be postponed.

30) Per the drawing M-01 we are to remove all the mechanical systems in the boiler room and piping that serves this equipment. Is it the intent of the RFP to not replace any of this equipment?

"Correct, none of the equipment will be replaced after removed"

13 11/19/2015

1. Will the existing taxiway markings on the airfield have to be removed and then replaced or will the contractor just repaint the existing markings? If contractor has to remove them, will hydro blasting of the lines be the preferred method of removal?

Contractor shall pressure clean the concrete taxi ramp and contractor to repaint the existing markings. No removal is needed for the existing taxi lines paint over. Follow manufacture's specifications.

2. Will the contractor that is awarded this project be required to perform a new hazardous material survey or will the government provided survey in the RFP documents be sufficient for the abatement SOW?

The contractor is responsible for documenting the RCRA waste classification, either through generator knowledge or analytical documentation.

3. Per the bid schedule, please provide a list or examples of the existing furniture and equipment that is to be removed, relocated, and reinstalled during the construction period of this project. Will the government provide an area for these items to be stored/protected or will the contractor be required to provide temporary storage containers?

Itemized List of the Furniture provided in Appendix "J" Contractor to provide storage containers, See Section 01 11 00.

4. Will the contractor be responsible for payment of temporary utilities to our job site trailer and the need of power during construction?

Government will provide "Reasonable" amounts of utilities at no cost to contractor as outlined in the general section of the specs.

5. Will a temporary construction fence be required to protect the construction site area during construction? If so, please provide the fencing requirements (height, fabric, etc…) and location for installation.

Up to KTR to prevent minimum access to site.

6. Per the bid schedule in regards to the monthly lease fee for the temporary hangar, will the government provide full payment of the 12 month cost for the temporary hangar once it is delivered to the site or will the contractor only be paid monthly for the cost shown in the bid schedule?

No. The Government will pay monthly progress payments.

14 11/19/2015

1. Will the airfield taxiway markings be priced only through the unit price or will the contractor need to include all the markings shown on drawing G-03 in the base bid and if additional markings are needed, the government can use the unit price to provide a mod for any additional work?

Yes, Contractor shall provide a price for the 5,000 LF specified on G-03. Contractor to provide unit price for additional taxilines if needed.

2. For bid option #2, survey and removal of inactive conduits and wire, will this require any lead abatement in order to remove these conduits?

Yes, This is regular demolition work, although the contractor is responsible for following the OHSA 29 CFR 1926.62 "Lead" Standards and provide for appropriate worker protection. As mentioned in the General Note on sheet 4 of 29 : "All existing coatings contain some level of lead content. OHSA Worker Protection shall be provided for disturbance of any painted surfaces. Painted coatings on existing building materials to be removed can be disposed of as normal construction waste provided they remain intact on the building material being removed" REMEMBER:

lead-based paint applies to target housing and child-occupied facilities. The OHSA

Worker Protection standards are what's applicable here.

3. Please provide Davis Bacon Wage rates that apply to this project if contractor has to adhere to this requirement for certified payrolls on our company and subcontractors.

Davis Bacon Wages are in the IFB

4. What onsite management will be required by the contractor for this project? Full time superintendent, QC manager, Site Safety Manager...etc or can one person carry all these qualifications?

KTR will need to provide site superintendent and QC Manager. Site Supper may act as safety manager provided that's how it is noted in the contractor's safety plan.

5. Per 2.1.3…Concrete Floor Slab Surface-High Impact and Chemical Resistant

Polyurethane Coating, several of my epoxy floor subcontractors are stating that the

“White High Gloss” finish is not a product that is readily available. Is another color acceptable for this application?

Another color is not acceptable. ESD is an Electro Static Dissipation and the hangar requires ESD floor. The specification is correct, and to get a white floor, the polyurethane top coats (Step 4 & 5) in System Installation shall be pigmented white so that the surface is pure white. Bid in accordance with the specifications

6. Per general hazardous note A on drawing A-01, it states that all existing paint coatings contain some level of lead. Will the work under note 1 on drawing A-08 be considered lead abatement? If so, will the lead have to be disposed of offsite?

All waste generated as a result of this project will be need to be classified and managed appropriately. If you are just removing rust with no coatings present this would be classified as nonhazardous solid waste. If is the contractors responsibility to properly classify the waste and insure proper disposal. See Section 01 1100

1.2.4.2 for additional instruction.

7. Per note 2 on drawing A-08, will these areas only receive a “wipe down” cleaning prior to painting or will this have to be pressure washed and or sand blasted first?

Pressure washing or sand blasting will strip the newly white painted areas and additional disposal and cleanup will be required if so.

Remove the loose material, you do not need to remove all paint as long as it is well adhered to the building component. Dust is present inside the main hangar cleaning is important before painting. Refer to the OSHA Lead standard for requirements associated with abrasive blasting. Refer to spec for the coatings preparation requirements, ISO 9001, OR SSPC QP1 AND SSPC QS1. and recommendations of the paint manufacturer The USCG does not dictate the removal methods for the non-adhered coatings.

8. Does the electrical equipment shown to be removed on drawing A-01 feed the existing fire alarm system that is to remain operational at all times during construction?

No, the electrical equipment noted on sheet A-01 is aircraft 400Hz power supply equipment, converters and cables reels. Work required is identified on Sheets E-

02 and E-08 and specification Section 26 05 00, Article 2.12.

9. Per drawing TE-01, has the government determined that the load needed at the temporary hangar can be supported by the existing 150KVA transformer that we are to connect to?

Existing 150KVA transformer is large enough to provide power to temporary hangar

10. Per the RFP, it states that the contractor is to provide sufficient lighting for the temporary hangar to meet 30fc. Will the government provide the light count and type that needs to be installed or is the contractor to provide the design and amount of lights needed?

Contractor provide the design and installation. Light shall be LED type.

15 11/19/2015

Zimmer-Eschette Service II, LLC 1) The following may be the most important question that you will get and the preface is important to understand the question. This project is more complicated for coatings due to the lead paint issue. In the coatings section, the surface preparation in Section

09 90 00, 3.2.C.a calls for simple hand tool cleaning, SSPC-SP2, “to remove (only) loose mill scale, loose rust, and other detrimental foreign matter”. This is basically equivalent to what the lead instructions read on most of the pertinent drawings, etc.

Section 09 90 00, 1.4.B.3 includes the coatings surface preparation to “be certified to either ISO 9001 OR SSPC QP1 AND SSPC QS1". It is apparent from discussions I’ve had that most lead abatement companies will not have the coatings certifications from the Society of Protective Coatings to do simple hand tool scraping work while most coatings companies will not have the lead abatement licenses (and environmental insurances) to do the lead abatement work. Since this conflict would narrow the field of pre-bid attendees (many of whom traveled long distances) and other competitive bidders significantly, will the Navy consider the lead abatement scrape as adequate

(by scraping the loose elements for prep WITHOUT the coatings preparation requirements, ISO 9001, OR SSPC QP1 AND SSPC QS1 noted above) for the coatings preparation? Due to the time allocation in bidding this project can you please issue the answer to this question sooner rather than later as it will govern our participation decision in the project.

Bid in accordance with the specifications. Remove the loose material, you do not need to remove all paint as long as it is well adhered to the building component.

Dust is present inside the main hangar cleaning is important before painting. Refer to the OSHA Lead standard for requirements associated with abrasive blasting.

Refer to spec for the coatings preparation requirements, ISO 9001, OR SSPC QP1

AND SSPC QS1. The USCG does not dictate the removal methods for the non-adhered coatings. Properly prepare accordingly to the manufacture recommendations.

16 11/19/2015

1. Standard Form 1442. Line item # 17. Does the base bid cost go in this line item or do we just write in “see attached section B”?

It can be filled out either way.

You may state "see attached section B".

2. Please confirm the Fedex address for sending our bid proposal. Please see SF 1442, #8

3. Section 01 11 00. 1.14. Please provide a list of equipment that we will have to store in a connex box as well as equipment that will need to be relocated in the temporary hanger.

Itemized List of the Furniture provided. Appendix "J"

4. Is the roof under warranty? If so by whom. See attached roof warranties.

5. Specification 02 82 16. 1.3.1 Decription of Work. Third sentence. “ The asbestos You must assume that all of the "Foam Glass Pipe Insulation" is an ACBM.

Samples 21 and 22 are in the main hangar. No duct mastic. Paragraph should read as: "1.3.1 Description of Work

The work covered by this section includes the handling and control of asbestos containing materials and describes some of the resultant procedures and equipment required to protect workers, the environment and occupants of the building or area, or both, from contact with airborne asbestos fibers. The work also includes the disposal of any asbestos containing materials generated by the work. More specific operational procedures shall be outlined in the Asbestos Hazard Abatement Plan called for elsewhere in this specification. All of the "Foam Glass Pipe Insulation" is an ACBM., and is governed by 40 CFR 763. Provide negative pressure enclosure techniques as outlined in this specification. Lead-Based Paint & ACBM Reports, are attached to these specification. Refer to appendix “G”. The Government will evacuate the work area during the asbestos abatement work. All asbestos removal work shall be supervised by a competent person as specified herein.

6. Specification 02 82 33. Is it the intent for all of the lead on the existing steel to be abated or just bad areas abated and all other areas incapsulated? Please clarity the specific scope of the lead abatement work.

No, Just abate the bad areas and encapsulate all other areas.

17 11/19/2015

1.- RFI-1-The site visit is scheduled for 11-12-15 and the deadline for submitting RFIs is 11-9-15. Would the Owner consider extending the deadline for questions until after the site visit?

Yes. Please see Amendment No. 0004.

2.- RFI-2-Please provide specification sections for the following trades:

- Mechanical

- Signage

- Roof Access Ladder

- Vinyl Flooring

- Pavement Markings

- Roofing and Sheet Metal Trim

- Gutters and Downspout

- Concrete

- Fire Alarm

No additional specification will be provided: Mechanical: Refer to drawings M-

01 & M-02 for mechanical scope of work and code compliance information.

Mechanical specs were not included because the mechanical work besides demolition of hot water piping is so minimal. All requirements are covered with notes in M-01 and M-02. Signage: Size layout and shape are indicated on the drawing

Sheet A-03. Additional information in the Appendix Comdtinst M5200 14A. Refer to pages 3-1 3-2. Roof Access Ladder: Answered in RFI-20. Vinyl Flooring:

Refer to RFI-23.Answer #16. Roofing and Sheet Metal Trim / Gutters and

Downspouts: specified on drawings and information of existing on reference drawings. Concrete: is specified in the attached drawings and reference drawing.

Fire Alarm: No work performed, only painting.

3.- RFI-3:

Orocon Construction has prior commitments scheduled for 11-12-15 (site visit). Would it be possible to re-schedule this visit? Possibly 11-11-15?

Please reach out to the Unit Point of Contact for site visits if still required.

18 11/19/2015

Section 1.3.1a of the specifications states that we have only 45 days from NTP to provide the temporary hangar. There is no design for the lighting , so design and submittals will take nearly all of the 45 days allotted. This will make it nearly impossible to meet the schedule. We respectfully request a minimum of 90 calendar days for this phase.

NTP will not be postponed. Please bid accordingly.

19 11/19/2015

1) According to an MBCI representative they can only do a non-concealed fastened panel to match the specifications. The specifications do not call for MBCI panels, but the current panels appear to MBCI. Can you please advise as to whether or not the panels are to be non-concealed fastened.

Provide concealed fastened panels as shown in the drawings and specs.

20 11/19/2015

Please verify if the ladder located on page A-03 in the Southwest elevation is to be removed and replaced.

Yes, The access roof ladder is to be removed and replaced.

PRODUCT MATERIALS NEW GALVANIZED METAL RAILING TO COMPLY WITH

ALL O.S.H.A REGULATION. / 1.- Metal Pipe Guardrails to comply with ASTM A53, Type S. Grade A. 2.- Anchors and Fasteners to comply with ASTM A325, stainless steel. Cage shall be provided in all ladders.

(SUBMIT SHOP DRAWINGS FOR APPROVAL.)

21 11/19/2015

1) In the RFP and Specs there are no instructions to offerors listed. Can you please elaborate on what items are required for bidding.

Please refer to the Solicitation. It contains all the information necessary. Note that a Bid Guarantee that must be submitted along with your bid.

2) The drawings on page A-01 reference additional drawings that were not provided. Drawings referenced but not provided are: G01, G02, G03, G04.

These are not drawings. Two (2) LBP and two (2) ACM Surveys were provided as

Appendix G in the specifications. Refer to Appendix "G"

22 11/19/2015

1. Per specification 09 90 00, paints and coatings, there is not a product or installation information for the painting of the existing CMU at the interior of the hangar.

Please provide the product requested for this application.

**Existing, previously painted Concrete masonry:

1. High Performance Architectural Latex.

MPI RIN 4.2K-G5 (Semigloss)

Spot Primer: Intermediate: Topcoat:

MPI 50 MPI 141 MPI 141

System DFT: 4.5 mils

2. We are requesting that the bid be moved to 1DEC15 since RFI’s have not been answered yet and will need time to distribute answers and get proper pricing in for the work.

Please see Amendment No. 0004

23 12/1/2015

1.- Pressure Wash: What are the limits of the pressure washing? The drawings states to pressure wash the entire concrete ramp. Can the government provide a clear drawing with limits at which this work is supposed to occur? Dwg. #G-03, General

Note #3.

The area of Power Wash for the entire existing Concrete Ramp is approximately

206,000 SQ. FT. See attached revised Dwg. Re-paint.

2.- Striping: Striping outlined on the drawing does not reflect what is in the field.

based on satellite imagery. Is the Contractor to repaint over the existing lines, or completely remove the existing lines and install new lines per the drawing? Or is the

Contractor to completely remove the existing lines and reinstall new lines per the current layout? Dwg.