12NOV2011 REV 0 GOVERNMENT ESTIMATE FOR:

USCGC SITKINAK (WPB-1329) DRYDOCK AVAILABILITY 2012

ITEM DESCRIPTION UNIT PRICE UNIT QTY EXTENDED PRICE

D-001 Hull Plating, U/W Body, Inspect JOB 1

O-002 Hull Plating (U/W Body), Ultrasonic Testing

SHOTS 10

O-003 Aluminum Hull and Structural Repairs - 1/4" Plate 4 SQFT 50

O-004 Aluminum Hull and Structural Repairs - 3/16" Plate 4 SQFT 25

O-005 Aluminum Hull and Structural Repairs - 5/16" Plate 4 SQFT 25

O-006 Hull and Structural Plating Repairs -Crack (Aluminum) 1 LF 50

O-007 Hull and Structural Plating Repairs - Crack (Steel) 1 LF 50

O-008 Hull and Structural Plating Repairs - Eroded Weld (Aluminum) 1 LF 50

O-009 Steel Hull and Structural Plating Repairs (5-Pound) 4 SQFT 50

O-010 Steel Hull and Structural Plating Repairs (7.0 Pound, 7.5-Pound or 7.65- Pound) 4 SQFT 50

O-011 Steel Hull and Structural Plating Repairs , Corrugated Plate (4.0-Pound) 4 SQFT 10

O-012 Hull and Structural Plating Repairs (6.0-Pound or 5.63-Pound) 4 SQFT 10

O-013 Perform Steel Hull and Structural Plating Repairs (10-Pound or 10.2-Pound) 4 SQFT 10

D-014 Appendages (U/W), Leak Test JOB 1

D-015 Appendages (U/W) - Internal, Preserve JOB 1

D-016 Tanks (Fuel Service), Clean and Inspect JOB 1

D-017 Voids (Non-Accessible), Leak Test JOB 1

D-018 Tanks (Fuel Stowage and Overflow), Clean and Inspect JOB 1

D-019 Voids (Non-Accessible), Preserve Internal Surfaces JOB 1

D-020 Tanks, Air Test JOB 1

D-021 Tanks (Dirty Oil and Waste), Clean and Inspect JOB 1

D-022 Propulsion Shafting, Remove, Inspect, and Reinstall JOB 1

D-023 Mechanical Shaft Seal Assemblies, Overhaul JOB 1

O-024 Propulsion Shaft Bearings (External) , Renew JOB 1

O-025 Propulsion Shaft Stern Tube Bearings , Renew JOB 1

D-026 Propellers ; Remove, Inspect, and Reinstall JOB 1

D-027 Exhaust System , MDE, Inspect JOB 1

D-028 Fathometer Transducer, Renew JOB 1

D-029 Speed Doppler, Renew, Doppler Valve, Overhaul JOB 1

D-030 Sea Strainers - Duplex (All Sizes), Overhaul JOB 1

D-031 Fin Stabilizers (General), Overhaul JOB 1

D-032 Tanks, (Grey Water) Clean and Inspect JOB 1

D-033 Forward Void, Preserve JOB 1

O-034 Tanks (Aft Grey Water) , Preserve “ 100% ” JOB 1

O-035 Tanks (Aft Grey Water) , Preserve “ Partial” JOB 1

O-036 Tanks (Dirty Oil), Preserve “ 100% ” JOB 1

O-037 Tanks (Dirty Oil) , Preserve “ Partial ” JOB 1

O-038 Tank ( Oily Water ), Preserve “ 100% ” JOB 1

(11/10/2011)

12NOV2011 REV 0 GOVERNMENT ESTIMATE FOR:

USCGC SITKINAK (WPB-1329) DRYDOCK AVAILABILITY 2012

ITEM DESCRIPTION UNIT PRICE UNIT QTY EXTENDED PRICE

O-039 Tank ( Oily Water ), Preserve “ Partial ” JOB 1

O-040 U/W Body, Preserve “100%” JOB 1

O-041 U/W Body, Preserve “Partial – Condition A ” JOB 1

O-042 U/W Body, Preserve “Partial - Condition B” JOB 1

O-043 U/W Body, Preserve “Partial - Condition C ” JOB 1

D-044 Cathodic Protection System (Bilge and Sea Chest), Renew JOB 1

D-045 Drydocking JOB 1

D-046 Temporary Services, Provide JOB 1

D-047 Data Service , Provide JOB 1

D-048 Sea Trial Performance, Provide Support JOB 1

D-049 CCTV Security System, Install (EC-110-C-111) JOB 1

D-050 Sea Valves and Waster Pieces , Overhaul or Renew JOB 1

D-051 Firemain Valves, Overhaul or Renew JOB 1

D-052 Bilge and Ballast Valves, Overhaul or Renew JOB 1

D-053 Tanks (Potable Water), Clean and Inspect JOB 1

O-054 Propulsion System, Alignment Check JOB 1

D-055 SW Heat Exchangers , Clean, Inspect and Hydro JOB 1

D-056 Rudder Assembly, Remove, Inspect and Reinstall JOB 1

D-057 Tanks (Sewage Holding) Clean and Inspect JOB 1

D-058 Grey Water Piping , Clean and Flush JOB 1

D-059 Sewage Piping , Clean and Flush JOB 1

D-060 Forward Peak Compartment, Preserve JOB 1

061 T k ( S H ldi ) P “ 100% ” JOB 1O-061 Tanks ( Sewage Holding ) , Preserve “ 100% ” JOB 1

O-062 Tanks ( Sewage Holding ) , Preserve “ Partial ” JOB 1

O-063 Tanks (Potable Water), Preserve “ 100% ” JOB 1

O-064 Tanks ( Potable Water ), Preserve “ Partial ” JOB 1

D-065 Bilge Surfaces, Preserve JOB 1

D-066 Cathodic Protection System, Inspect and Maintain JOB 1

D-067 Cofferdam, Drain Line, Repair JOB 1

D-068 Deck Covering (Galley), Renew JOB 1

D-069 Deck Covering (Shower Stall), Renew JOB 1

D-070 Hull, Structural, (Magazine Locker), Preserve and Insulate JOB 1

D-071 Piping, Fuel Oil System, Stripping Line, Renew JOB 1

D-072 Structural, (Aluminum), Deck Plating, Repairs JOB 1

D-073 Steering Gear (General) , Overhaul JOB 1

O-074 Tanks, Potable Water, Structural Repairs JOB 1

O-A Composite Labor Rate Hour 130

D-B GFP Report EA 1

O-Z Laydays Day 5

Total Price of Definite Items

Total Price of Option Items

Total Price of Definite and Optional Items

(11/10/2011)

Blank SOS&S