SPECIFICATIONS FOR DD REPAIRS REV-5
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 87346_DD_MWS_09ER5_BLANK 2 .pdf | ||
| SF300002FLYINGFISHDD.doc | DOC document | |
| SF300001FLYINGFISHDD.doc | DOC document | |
| 87346_DD_MWS_09ER3_BLANK 1 .pdf | ||
| RFQ FLYINGFISH 08 DD 06-30-08.doc | DOC document | |
| Copy of 87346_DD_MWS_09ER2_BLANK.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC FLYINGFISH (WPB-87346)
87 FOOT PATROL BOAT
SPECIFICATION FOR DRYDOCK REPAIRS
Developed By:
Alex Lin Mike Soost
Commander (v) Maintenance and Logistics Command, Atlantic 300 E. Main Street, Suite (600) Norfolk, VA 23510-9102
(15 July 2008 / Rev-5)
USCGC FLYINGFISH (WPB-87346) DRYDOCK AVAILABILITY 2009
TABLE OF CONTENTS
Work Item Title Page
List of Sketches iii
Revisions Record iv
List of Applicable References vii
List of Government-furnished Property xii
List of Critical Inspection Items xiv
Specification Feedback xv
Principal Characteristics xvi
General Requirements 1
1 Renew Hull Plating 9
2 Clean and Inspect Oil and Oily Waste Tanks 11
3 Clean and Inspect Fuel Tanks 14
4 Clean and Inspect Sewage Tank 17
5 Clean and Inspect Grey Water Tank 20
6 Realign Main Engine/Reduction Gear 23
7 Remove, Inspect, and Reinstall Propeller Shafts 26
8 Repair Shaft 37
9 Straighten Shaft 40
10 Renew Intermediate Water-Lubricated Shaft Bearing 42
11 Renew Aft Water-Lubricated Shaft Bearing 45
12 Renew Bearing Carrier 48
13 Remove, Inspect, and Reinstall Propellers 50
14 Perform Minor Repair and Recondition of Propeller 54
Page i (Rev-5)
15 Renew Depth Indicating Transducer 58
16 Preserve Transducer Hull Ring - Deleted 61
17 Overhaul Sea Valves 62
18 Renew Sea Valve 66
19 Clean and Inspect Sea Strainers 69
20 Remove, Inspect and Reinstall Rudder Assemblies 71
21 Renew Rudder Lower Bearing 75
22 Preserve Freeboard – 100% 77
23 Perform Ultrasonic Thickness Measurements – Freeboard Hull Plating 80
24 Preserve Forward Peak Compartment 82
25 Install RHIB Notch Skid Pad 85
26 Preserve Underwater Body – “Partial” 87
27 Preserve Underwater Body – “100%” 91
28 Ultrasonic Thickness Measurements – Underwater Body 94
29 Renew Cathodic Protection System 96
30 Routine Drydocking 99
31 Additional Fuel Removal and Disposal 103
32 Provide Temporary Logistics 105
33 Install New Deck Covering System 107
34 Clean Grey Water Piping System 110
35 Clean Sewage Piping System 114
36 Renew Hatch Coamings 118
37 Inspect Sea Chest Riser Piping and Flanges 121
38 Preserve Stern Tubes 123
Page ii (Rev-5)
List of Sketches
Work Item Sketch Number Page
This section is not applicable to this package.
Page iii (Rev-5)
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package.
Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK ITEM# CHANGES MADE
5/30/2008 1 2
Added paragraph 3.1.2 (Related work item), to link this item to the “Routine Drydocking” item.
Deleted “Excludes Fluid Offload and Disposal” from item title.
Added a “Notice” box, to indicate fluid offload and disposal is covered under “Routine Drydocking” item.
Deleted “Excludes Fluid Offload and Disposal” from item title.
Added a “Notice” box, to indicate fluid offload and disposal is covered under “Routine Drydocking” item.
Re-format and re-numbered paragraphs.
Added a “Notice” box, to indicate fluid offload and disposal is covered under “Routine Drydocking” item.
Modified paragraph 3.2.2 (Content removal).
Added a “Notice” box, to indicate fluid offload and disposal is covered under “Routine Drydocking” item.
Modified paragraph 3.2.2 (Content removal).
Revised entire item, as follows:
Deleted Tech Rep requirement.
Changed stern tube preservation to stern tube inspection (preservation will addressed in a separate optional item, as per the CMP).
15 Updated item.
16 Deleted “Preserve Transducer Hull Rings”
Page iv (Rev-5) in paragraph 3.1 (Related work item).
Deleted entire item. Transducer hull ring preservation is covered in the “Preserve Underwater Body” item.
Revised item, to include deletion of Tech Rep requirement, updating of phrases item format.
Changed “inspect” to “install” in paragraph 1.1 (Scope).
26 and 26
Revised items entirely, to also include sea chest riser pipes in u/w body definition.
Changed “30 linear feet” to “90 linear feet” in paragraph 3.1.
Changed “sewage” to “gray water” in paragraph 3.4.2.
Added new item “Inspect Sea Chest Riser Piping and Flanges”.
Added new “Preserve Stern Tubes” item, as an “OPT” item.
6/9/2008 2 List of Applicable References
Updated hyperlink.
Specification Feedback Updated hyperlinks.
General Requirements Updated hyperlink.
6/19/2008 3 All Changed “Flying Fish” to “Flyingfish” throughout.
Table of Contents Updated table.
Applicable Documents Updated drawing list.
List of Government-furnished Property
Updated table.
General Requirements Updated item.
1 Replaced “Weld Repair” work item with a new “Renew Hull Plating” work item.
7 Revised “Notice” format.
10 Revised “Notice” format.
11 Revised “Notice” format.
13 Edited paragraphs 3.7.1.1 and 3.7.1.2 for clarity.
15 Revised paragraph 3.2.1.
Page v (Rev-5)
Added “Related Work Items” as a new paragraph 3.1.1 and renumbered the former paragraph 3.1.1 to be 3.1.2.
Updated revision level to “Rev F” for drawing 87 WPB 163-001.
Updated revision level to “Rev T” for drawing 87 WPB 256-001.
Added “Related Work Items” as a new paragraph 3.1.1 and renumbered the former paragraph 3.1.1 to be 3.1.2.
Updated revision level to “Rev F” for drawing 87 WPB 163-001.
Updated revision level to “Rev T” for drawing 87 WPB 256-001.
19 Updated revision level to “Rev T” for drawing 87 WPB 256-001.
22 Updated item.
25 Added “Preserve Freeboard” to paragraph
3.1.2. Revised “Notice” format.
26 Added “Preserve Freeboard” to paragraph 3.1.1.
27 Added “Preserve Freeboard” to paragraph 3.1.1.
30 Updated item.
Added the following paragraph to the work item: “3.2 Additional temporary logistics. If the performance period of the contract is extended by the Contracting Officer, the contractor shall continue to provide all temporary logistics as specified herein for the extension period.”
33 Added “Armory Locker” to paragraph 3.1.
35 Revised “Notice” format.
37 Updated paragraph 3.1.2.
7/7/2008 4 All Updated drydock availability year.
7/15/2008 5 15 Revised paragraph 3.1.2.2.
16 Removed lined-through text and added note to indicate the item has been cancelled.
20 Removed all references to “tech rep”.
NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
Page vi (Rev-5)
List of Applicable References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution. Electronic copies of the latest Editions of MLCA Standard Specifications are available on the Internet and may be accessed at the following Internet Uniform Resource Locator (URL) address:
http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp.
Guidance for obtaining copies of all other documents referenced herein is provided in the solicitation.
Order of precedence. In the event of conflicts between text of this specification and the applicable references specified herein, order of precedence shall be in accordance with MLCA Standard Specification 0000_STD, paragraph 3.2 (Order of precedence), unless otherwise specified by the Contracting Officer (KO). The Contractor shall immediately notify the KO in writing of any perceived conflicts contained herein. Nothing in these documents, however, supersedes applicable laws and regulations, unless a specific exemption has been obtained.
FEDERAL AND MILITARY SPECIFICATIONS AND STANDARDS
DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust-Petrolatum
MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-PRF-24647, Feb 2005, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-STD-1623, Dec 1981, Fire Performance Requirements and Approved Specifications for Interior Finish Materials and Furnishings
MIL-STD-167-1, Nov 2005, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II - Internally Excited)
MIL-STD-1687A, Sep 1994, Thermal Spray Processes For Naval Ship Machinery Application
Page vii (Rev-5) http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp
MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main Propulsion Shafting
OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS
DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 1001_STD, 2004 Edition, Temporary Hull Accesses
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 6341_STD, 2004 Edition, Renew Deck Covering Systems
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8634_STD, 2004 Edition, Drydocking
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8635_STD, 2004 Edition, Provide Temporary Logistics
DRAWINGS
Coast Guard Drawing 87 WPB 085-003, Rev C, Docking Plan
Coast Guard Drawing 87 WPB 085-010, Rev C, Docking Plan
Coast Guard Drawing 87 WPB 085-011, Rev B, Lifting Slings
Coast Guard Drawing 87 WPB 085-012, Rev-, Lifting Cradle
Coast Guard Drawing 87 WPB 111-001, Rev C, Shell Expansion
Coast Guard Drawing 87 WPB 131-001, Rev H, Deck Construction Plan
Coast Guard Drawing 87 WPB 161-002, Rev-, Stern Tube Details Anode Access Ports
Coast Guard Drawing 87 WPB 163-001, Rev F, Sea Chest Details
Coast Guard Drawing 87 WPB 165-001, Rev D, Transducer Details
Page viii (Rev-5)
Coast Guard Drawing 87 WPB 167-001, Rev E, Schedule Of Doors, Manholes, Windows and Hatches
Coast Guard Drawing 87 WPB 182-001, Rev-, Main Engine and Generator Foundations
Coast Guard Drawing 87 WPB 243-001, Rev M, Propulsion Shaft Details
Coast Guard Drawing 87 WPB 245-002, Rev-, Propeller Details
Coast Guard Drawing 87 WPB 245-003, Rev A, Propeller Details
Coast Guard Drawing 87 WPB 256-001, Rev T, Sea Water Cooling Piping
Coast Guard Drawing 87 WPB 304-001, Rev B, Wireway Arrangement
Coast Guard Drawing 87 WPB 561-001, Rev F, Steering System Details
Coast Guard Drawing 87 WPB 562-001, Rev-, Rudder Details
Coast Guard Drawing 87 WPB 583-001, Rev K, RHIB Deployment Structure
Coast Guard Drawing 87 WPB 593-001, Rev H, Sewage Piping
Coast Guard Drawing 87 WPB 635-001, Rev C, Linings and Insulation Plan & Details
Coast Guard Drawing FL 6713-201, Rev B, Transducer adapter assembly
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series) Jun 2006, Coatings and Color Manual
Coast Guard Technical Publication (TP) 4529, Mar 2003, Compact Vacuum Toilet – 500 Series.
Coast Guard Technical Publication (TP) 4593, Mar 2003, SWBS 562, Rudderstock Seal-Type EJ
Coast Guard Technical Publication (TP) 4593C, Feb 2002, SWBS 243, Manufacturer's Instruction Book, 87' WPB Propulsion Shaft Seals, John Crane Type F.S.E.
Page ix (Rev-5)
Bollinger Shipyard, USCG CPB Project MTU-FA 771903, 07 Feb 2000, Engine/Gearbox Plant Alignment Instructions 8V396 TE94/Flange mounted BW 255
Deep Sea Seals Tech Pub (TP) TM-EL-68839, Issue A, Mar 2005, Rudderstock Seal Type EJ
International Organization for Standardization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive
INDUSTRY STANDARDS
American Bureau of Shipping (ABS), 2, Rule Requirements for Survey After Construction, 2006, Part 7, Appendix Section 10, Guide for Bronze and Stainless Steel Propeller Castings
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End
ASTM International (ASTM), D3951, Re-approved 2004, Standard Practice for Commercial Packaging
ASTM International (ASTM) A131, 2004, Standard Specification for Structural Steel for Ships
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Page x (Rev-5)
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 1998, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 7/NACE No.4, 2004, Brush-Off Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2004, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting
The Society for Protective Coatings (SSPC)/NACE International (NACE) 2004, Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, Near-White Blast Cleaning
Page xi (Rev-5)
List of Government-furnished Property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
7 N **Propeller shaft NSN: 2010-01-458-9175 2 ea. 9,566.14
N Type FSE Face (split)
PN: H75440-01-2-2
NSN: 5330-01-521-3559 2 ea. 1,995.07
N Type FSE Seal (split)
PN: H75440-01-1-1
NSN: 2040-01-521-2654 2 ea. 4,070.35
N Type FSE Seal Cup (split)
PN: H75440-01-1-3
NSN: 3120-01-521-2390 2 ea. 188.24
N Type FSE O-Cord PN: H75440-01-1-4 NSN: 3120-01-521-2268 2 ea. 252.84
N Type FSE Emergency Seal
PN: H75440-01-3-6
NSN: 5330-01-521-4855 2 ea. 260.92
N Splashguard 4”
FSE
PN: H75440-01-2-5 2 ea. 395.73
N
Clamp, Splashguard 4”
FSE
PN: H75440-01-2-6 2 ea. 37.84
N **Shaft Seal Bellow
PN: H75440-01-2-1
NSN: 5340-01-521-3573
2 ea. 270.45
N *Compression Tool Assembly
N/A 1 ea. 200.00
N *Alignment Kit N/A 1 set 3,000.00 10 N **Thordon bearing, Grade Orange (5.5" OD x 4" ID x 7.87" (200mm)
LG)
PN: F54615-02-8-1
NSN: 3120-21-914-2012
2 ea. 325.47
11 N **Thordon bearing, Grade Orange (5.5" OD x 4" ID x 11.41" (290mm)
LG)
PN: F54615-02-8-0
NSN: 3120-21-914-2011
2 ea. 399.50
13 Y **Starboard Propeller (RH)
PN: RH706-3350.00
NSN: 2010-01-457-0573
1 ea. 12,498.00
Y **Port Propeller
(LH)
PN: LH706-3350.00
NSN: 2010-01-459-0421
1 ea. 12,498.00
N *Propeller Nut Wrench N/A 1 ea 200.00
N **Propeller Nut NSN: 2010-01-458-9217 2 ea. 281.00 N **Propeller Nut, Locking NSN: 5310-01-458-9125 2 ea. 252.94
N Anode, Propeller Nut NSN: 5342-01-481-8403 2 ea. 97.34
Page xii (Rev-5)
N
***Airmar Depth Sounder Transducer
(SS555)
PN: M78733
NSN: 5845-01-465-9723 1 ea. 149.45
20 Y **Rudder Assembly, port
NSN: 2040-01-461-1944
1 ea. 2,000.00
Y **Rudder Assembly, starboard
NSN: 2040-01-461-1943 1 ea. 2,000.00
N Upper Roller Bearing
SKF21318 2 ea. 261.77
N Wartsila Lips EJ Seals Kit
P/N: H75492-01
NSN: 5330-01-491-7554
2 ea. 3,041.42
21 N **Thordon Bearing
P/N: TBFF113090
NSN: 2040-01-461-1943
2 ea. 290.56
25 N **Forward skid pad
N/A 1 ea. 300.00
30 N *Transducer cover plate
N/A 1 ea. 100.00
33 N Deck covering N/A 175 sq ft 13.00
N Molding N/A 1 set 200.00 N Flooring adhesive N/A 1 set 300.00
N Motif N/A 1 ea. 450.00
N 24” x 24” QA Raised Hatch Coaming
Fabricated by ISC Miami 3 ea. 1,300.00
N
24” x 24” QA Flush Hatch Coaming
Chand 1073536 1 ea. 1,300.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel, Electronic Systems Support Unit (ESU) or local Electronic Support Detachment (ESD).
Page xiii (Rev-5)
List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see Std Spec 0000_STD, paragraph 3.6.2 (Inspection report particulars)):
Work Item Title
7 Remove, Inspect, and Reinstall Propeller Shafts
20 Remove, Inspect and Reinstall Rudder Assemblies
21 Renew Rudder Lower Bearing
23 Perform Ultrasonic Thickness Measurements – Freeboard Hull Plating
25 Install RHIB Notch Skid Pad
37 Inspect Sea Chest Riser Piping and Flanges
38 Preserve Stern Tubes
Page xiv (Rev-5)
Specification Feedback
The intent of this section is to inform all users that a spec feedback mechanism is in place, and is located on the MLCA Naval Engineering Division’s website. Spec feedback is a very important part of our overall continuous improvement process, and is crucial to specification development. It will allow spec writers to capture all specification-related lessons learned, and avoid mistakes or ambiguities in follow-on availabilities. All feedback will be reviewed, evaluated, and responded to in a timely manner.
If you have access to the CGWeb (Intranet), please use the following link, which will connect you to the MLCA(v) Naval Engineering website, for submitting your feedbacks:
http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/default .cfm
If you do not have access to the CGWeb (Intranet), you may still submit your feedbacks, using the following web link:
http://www.uscg.mil/mlclant/vdiv/specfeedback.asp
Page xv (Rev-5) http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/default.cfm http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/default.cfm http://www.uscg.mil/mlclant/vdiv/specfeedback.asp
Page xvi (Rev-5)
PC_87_WPB
(21 Mar 2005)
Principal Characteristics
87' WPB Coastal Patrol Boat
Length Overall 87' 0"
Depth (main deck at frame 13 side to baseline) 10' 11"
Maximum Beam 19.4'
Height of Highest Projection (above DWL) 50.2'
Frame Spacing Various
Full Load Draft 5' 9"
Full Load Displacement 93.5 long tons
Shore Tie Voltage Requirements 450v
PROPELLERS / SHAFT
Number of Propellers 2
Number of Blades per Propeller 5
Diameter of Propeller 1040 mm
Pitch 1230 mm fixed
Revolutions per Minute (RPM) 828
Shaft Diameter 4"
Page 1 (Rev-5)
00000_PWB_FLT (08 Apr 2008)
General Requirements
1. SCOPE
1.1 Scope. This item describes the general requirements to be followed by the Contractor while conducting this availability.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements
Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in Std Spec 0000_STD and in this item, as applicable, during the performance of this availability.
NOTICE!
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor
shall provide fire watch personnel and equipment.
3.3 Welding and brazing requirements. The Contractor shall
perform all welding and allied processes, and nondestructive inspection (NDI), in accordance with Std Spec 0740_STD.
3.4 Term substitution – COTR for COR. The Contractor shall be aware that the term “COR” (Contracting Officer’s Representative) has been discontinued in favor of “COTR” (Contracting Officer’s Technical Representative); consequently, whenever “COR” is
Page 2 (Rev-5) encountered in this specification package, including referenced standard specifications and other referenced documents, it shall refer to “COTR”, explicitly.
3.5 Small boat storage particulars. When a small boat (Motor
Surf Boat (MSB)/Motor Cargo Boat (MCB)/Rigid Hull Inflatable (RHI) boat) is removed as interference to Contractor-work, the Contractor shall provide a suitable pierside storage cradle, for safely storing said boat.
3.5.1 Cradle design. Ensure that the cradle meets the following criteria:
• Be capable of safely supporting a boat weighing approximately 5100 pounds.
• Support the boat at the following locations:
o Along the full length of the flat portion of the keel.
o Forward and aft, in the locations similar to those provided by the shipboard davit cradle.
• Have the portions of the cradle directly contacting the hull or keel of the boat made from a homogeneous soft wood, such as Yellow Pine or Douglas Fir.
3.5.2 Boat protective cover. Provide a watertight cover with
raised wooden spreaders, to protect the small boat from nature, during the storage period.
3.5.3 Boat accessibility. Ensure the storage is located in the vicinity of the vessel, and is unrestricted, to allow for ship's force to complete maintenance, if required.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address:
http://www.uscg.mil/directives/cim.asp
5.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in Std Spec 0000_STD to be completed and submitted http://www.uscg.mil/directives/cim.asp
Page 3 (Rev-5) during preservation of “critical-coated surfaces”, are provided at the end of this item.
Page 4 (Rev-5)
QA-1: QUALITY ASSURANCE INSPECTION FORM - PRESERVATION CHECKLIST
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).
Verify surface anchor profile (1.5-3.5 mils for abrasive-blasted steel surfaces; 1.0 mil (minimum) for power-tool cleaned surfaces; 1.0-1.5 mils for abrasive-blasted aluminum surfaces); and 1.5 –2.5 for surfaces to be coated w/single coat of inorganic zinc).
Measure soluble salt conductivity (5 measurements per 1000 sqft) – maximum threshold: 70 microsiemens/cm for non-submerged surfaces and 30 microsiemens/cm for submerged surfaces.
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the Coating Manufacturer(s).
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness.
Verify system cure for service resumption - U/W Body surfaces: 5-8 hours @ 77 degrees F; Potable water tanks: 7 days @ 77 degrees F.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure (minimum 7 days @ 77 degrees F.), to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Signature of Inspector:______________________________________________________Date:____________
Page 5 (Rev-5)
QA-2. QUALITY ASSURANCE INSPECTION FORM
ENVIRONMENTAL READINGS
(Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat)
DATE TIME
ENTER ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION DEW
POINT
SURFACE
TEMP.
% REL.
HUMIDITY
SIGNATURE
OF
INSPECTOR
.Signature of Inspector:__________________________________________________Date:____________
Page 6 (Rev-5)
QA-3 QUALITY ASSURANCE INSPECTION FORM
SURFACE PROFILE LOG
Vessel Name And Hull Number:__________________________________________________
Work Item Title:_______________________________________________________________
Location Of Work (Including Frame Numbers):_____________________________________
Area (Square Feet):_____________
Surface Preparation Method:_____________________________________________________
Abrasive Manufacturer And Size:_________________________________________________
Degreasing Method Used:________________________________________________________
Number Of Hours Surfaces (Steel Only) Left Unpainted:______________________________
Sweep blasting performed to remove flash rusting (steel)? Yes/No:_____________________
Place Surface Profile Replica Tapes In The Spaces Provided Below, To Serve As Permanent QA record.
Maintain separate log for each area/location. When an Area Is Divided Into Separate Sections, Maintain A Separate Log for Each Section.
AVERAGE MILS
(IAW ASTM D4417,
METHOD C)
Place Surface Profile Replica Tape Here
Reading:__________ mils
• Place Surface Profile Replica Tape Here
Date and Time:__________________________________________________
Location of Surface Profile Measurements:___________________________________________________________
Signature of Inspector:____________________________________________________________________________
Page 7 (Rev-5)
QA-4. QUALITY ASSURANCE INSPECTION FORM
SURFACE SOLUBLE SALT CONDUCTIVITY LOG
Vessel Name and Hull Number:__________________________________________________
Work Item Title:_______________________________________________________________
Location of Work (including frame numbers):_______________________________________
Area (square feet):____________
DATE TEST LOCATIONS CONDUCTIVITY
(microsiemens/cm)
Date and Time:_________________________________________
Signature of Inspector:___________________________________
Page 8 (Rev-5)
QA-5. QUALITY ASSURANCE DATA FORM
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC PA-2
(Use one sheet for each sequence)
Vessel Name and Hull Number:__________________________________________________
Work Item Title:______________________________________________________________
Coating Manufacturer:_________________________________________________________
Product Name:________________________________________________________________
Batch Number:________________________________________________________________
Induction Time:_______________________________________________________________
Coating System Sequence (Indicate whether: primer, touch-up primer, barrier coat, 3rd coat…):__________________
DFT
MEASUREMENT
NUMBER
LOCATION OF READINGS MEASURED DFT
Application Method (Airless, Conventional Spray, Rolled):____________________
Average DFT: __________________________________________________________
Date and Time: _________________________________________________________
Signature of Inspector: ___________________________________
Page 9 (Rev-5)
S11000D_75404 (12 Nov 2004) 87346_MWS (25 Jun 2008)
WORK ITEM 1: Renew Hull Plating
1. SCOPE
1.1 Scope. The Contractor shall crop and renew a section of
hull plating on the forward portside.
2. APPLICABLE DOCUMENTS
Coast Guard Drawing 87 WPB 111-001, Rev C, Shell Expansion
Coast Guard Drawing 87 WPB 131-001, Rev H, Deck Construction Plan
Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Color Manual
3. REQUIREMENTS
3.1 General.
3.1.1 Related work items. The Contractor shall perform the work specified herein in conjunction with “Preserve Freeboard” and “Perform Ultrasonic Thickness Measurements – Freeboard Hull Plating”, which are separate parts of this specification package.
3.1.2 Interferences. The Contractor shall be aware that
interferences in way of work include, but are not limited to, the following:
• Crew bunks.
• Lockers.
• Bulkheads.
• Bulkhead insulation.
Page 10 (Rev-5)
NOTICE!
Be careful not to damage the removed insulation
3.2 Structural steel replacement. The hull structure (plates, shapes, and bars) for the 87WPB class cutters is made primarily with ABS AH36 steel. If the ABS steel cannot be obtained for the hull structure, the Contractor shall use ASTM A131 Grade AH36 as a substitute.
3.3 Renewal. The Contractor shall crop and renew up to 16
square feet of portside hull plating between transverse frames 4 and 5 and outboard longitudinals 16 and 20, adjacent to compartment 2-2-0-L, in accordance with Coast Guard Drawings 87 WPB 111-001 and 87 WPB 113-003 as applicable and Std Spec
0740_STD.
3.4 Touch-up preservation.
3.4.1 Exterior surfaces. The Contractor shall prepare and
touch-up coat all disturbed surfaces to match existing adjacent surfaces, in accordance with COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems). Abide by all touch-up requirements outlined in paragraph 3.11.9 (Touch-ups and minor coating repairs)) of Std Spec 0000_STD.
3.4.2 Interior surfaces. The Contractor shall prepare and
touch-up coat all disturbed surfaces to match existing adjacent surfaces in accordance with COMDTINST M10360.3, Appendix B (Cutter and Boat Interior Painting Systems). Abide by all touch-up requirements outlined in paragraph 3.11.9 (Touch-ups and minor coating repairs)) of Std Spec 0000_STD.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
This section is not applicable to this work item.
Page 11 (Rev-5)
12310_DLA_FLT (21 Mar 2008) 87 WPB (13 May 2008)
WORK ITEM 2: Clean and Inspect Oil and Oily Waste Tanks
1. SCOPE
1.1 Scope. This work item describes the requirements for the
Contractor to clean and inspect the following tanks:
TYPE OF TANK LOCATION CAPACITY
(GALLONS)
Dirty Oil Port Centerline
Oily Water Stbd Centerline
2. APPLICABLE DOCUMENTS
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General. The Contractor shall accomplish the following for the designated tanks:
3.1.1 Related work item. The Contractor shall accomplish this work item in conjunction with "Routine Drydocking," which is a separate work item in this specification package.
3.1.2 Operational test – initial. Prior to commencement of
work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.2 Cleaning requirements. The Contractor shall remove tank
covers and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall
Page 12 (Rev-5) dispose of tank residual contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
NOTICE!
Offloading and disposal of tank contents are covered under the “Routine Drydocking” item.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
• Tank level indicator (TLI) and/or float switch condition.
• Sounding tube and striker plate condition.
• Suction and discharge piping condition.
• Fastener material and condition (correct fastener material is stainless steel).
3.5 Tank closing. The Contractor shall ensure that the tanks
remain open for approximately 24 hours after completion of all authorized repair and preservation procedures. Notify the COTR at least 24 hours prior to closing the tanks. After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole covers with new gasket material conforming to AMS-C-6183.
4. QUALITY ASSURANCE
4.1 Operational test – final. In the presence of the Coast
Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit a CFR.
Page 13 (Rev-5)
5. NOTES
5.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
Page 14 (Rev-5)
12311A_FLT (09 Oct 2007) 87 WPB (13 May 2008)
WORK ITEM 3: Clean and Inspect Fuel Tanks
1. SCOPE
1.1 Scope. This work item describes the requirements for the
Contractor to clean the following tanks:
TYPE OF TANK LOCATION CAPACITY
(GALLONS)
Diesel fuel Stbd Centerline
1,450
Diesel fuel Port Centerline
1,450
2. APPLICABLE DOCUMENTS
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 1998, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General. The Contractor shall accomplish the following for the designated tanks:
3.1.1 Related work item. The Contractor shall accomplish this work item in conjunction with "Routine Drydocking," which is a separate work item in this specification package.
3.1.2 Operational test – initial. Prior to commencement of
work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.2 Cleaning requirements. The Contractor shall remove tank
covers and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall
Page 15 (Rev-5) dispose of tank residual contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
NOTICE!
Offloading and disposal of tank contents are covered under the “Routine Drydocking” item.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
• Tank level indicator (TLI).
• Sounding tube and striker plate condition.
• Suction and fill piping condition.
• Fastener material and condition (correct fastener material is stainless steel).
3.5 Tank closing. The Contractor shall ensure that the tanks
remain open for approximately 24 hours after completion of all authorized repair and preservation procedures. Notify the COTR at least 24 hours prior to closing the tanks. After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole covers with new gasket material conforming to AMS-C-6183.
4. QUALITY ASSURANCE
4.1 Operational test – final. In the presence of the Coast
Guard Inspector, the Contractor shall thoroughly test and prove the TLI’s to be in satisfactory operating condition (see 5.1 (Equipment operation)).
Page 16 (Rev-5)
5. NOTES
Page 17 (Rev-5)
12319A_FLT (09 Nov 2007) 87 WPB (13 May 2008)
WORK ITEM 4: Clean and Inspect Sewage Tank
1. SCOPE
1.1 Scope. This work item describes the requirements for the
Contractor to clean the below designated tanks:
TYPE OF TANK LOCATION CAPACITY
(GALLONS)
Sewage (stainless steel, uncoated)
Hold Deck between Frames 6 and 8, 3-7-0-W
2. APPLICABLE DOCUMENTS
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which is a separate work item in this specification package:
• “Routine Drydocking."
• “Clean Sewage Piping System.”
3.1.2 Interferences. The Contractor shall be aware that
interferences in way of work include, but are not limited to the following:
• Stateroom berthing locker.
• Tank level indicators.
• Access covers.
3.2 Cleaning requirements. The Contractor shall do the
following for the designated tanks listed in paragraph 1.1:
Page 18 (Rev-5)
3.2.1 Operational test - initial. Prior to commencement of
work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLI’s to demonstrate existing operational condition. Submit a CFR.
3.2.2 Content removal. Remove and dispose of all content
residual fluids in accordance with all applicable Federal, state, and local regulations.
NOTICE!
Offloading and disposal of tank contents are covered under the “Routine Drydocking” item.
3.2.3 Cleaning requirements. Remove manhole covers. Clean the designated structure's interior surfaces free of all foreign materials, sediment, and sludge. Remove cleaning media and residues continuously from the tanks during the washing process.
Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.2.4 Inspection. Visually inspect all interior surfaces;
including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Tank level indicator (TLI) condition.
• Suction and fill piping condition.
• Fastener material and condition (correct fastener material is stainless steel).
Page 19 (Rev-5)
3.3 Closing. The Contractor shall ensure that the tanks remain open for approximately 24 hours after completion of the tasks specified above. Notify the COTR at least 24 hours prior to closing the tank. After satisfactory inspection by the Coast Guard Inspector and after authorized repairs, if any, reinstall manhole covers with new gasket material conforming to ASTM D1330.
The Contractor shall clean and reseal all tank sight glasses, if applicable, prior to reinstallation.
4. QUALITY ASSURANCE
4.1 Operational test - final. In the presence of the Coast
Guard Inspector, the Contractor shall thoroughly test and prove the TLI’s to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit a CFR.
5. NOTES
Page 20 (Rev-5)
12319A_FLT (09 Nov 2007) 87 WPB (13 May 2008)
WORK ITEM 5: Clean and Inspect Grey Water Tank
1. SCOPE
1.1 Scope. This work item describes the requirements for the
Contractor to clean the below designated tanks:
TYPE OF TANK LOCATION CAPACITY
(GALLONS)
Grey Water (stainless steel, uncoated)
Below Hold Deck between Frames 8 and 9, 3-7-1-W
2. APPLICABLE DOCUMENTS
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which is a separate work item in this specification package:
• “Routine Drydocking."
• “Clean Grey Water Piping System.”
3.1.2 Interferences. The Contractor shall be aware that
interferences in way of work include, but are not limited to the following:
• Stateroom berthing locker.
• Tank level indicators.
• Access covers.
3.2 Cleaning requirements. The Contractor shall do the
following for the designated tanks listed in paragraph 1.1:
Page 21 (Rev-5)
3.2.1 Operational test - initial. Prior to commencement of
work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLI’s to demonstrate existing operational condition. Submit a CFR.
3.2.2 Content removal. Remove and dispose of all content
residual fluids in accordance with all applicable Federal, state, and local regulations.
NOTICE!
Offloading and disposal of tank contents are covered under the “Routine Drydocking” item.
3.2.3 Cleaning requirements. Remove manhole covers. Clean the designated structure's interior surfaces free of all foreign materials, sediment, and sludge. Remove cleaning media and residues continuously from the tanks during the washing process.
Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.2.4 Inspection. Visually inspect all interior surfaces;
including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Tank level indicator (TLI) condition.
• Suction and fill piping condition.
• Fastener material and condition (correct fastener material is stainless steel).
Page 22 (Rev-5)
3.3 Closing. The Contractor shall ensure that the tanks remain open for approximately 24 hours after completion of the tasks specified above. Notify the COTR at least 24 hours prior to closing the tank. After satisfactory inspection by the Coast Guard Inspector and after authorized repairs, if any, reinstall manhole covers with new gasket material conforming to ASTM D1330.
The Contractor shall clean and reseal all tank sight glasses, if applicable, prior to reinstallation.
4. QUALITY ASSURANCE
4.1 Operational test - final. In the presence of the Coast
Guard Inspector, the Contractor shall thoroughly test and prove the TLI’s to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit a CFR.
5. NOTES
Page 23 (Rev-5)
23320L_87 (21 Apr 2008)
WORK ITEM 6: Realign Main Engine/Reduction Gear
1. SCOPE
1.1 Scope. This work item describes the requirements for the
Contractor to realign a designated main diesel engine and its corresponding reduction gear assembly to the propeller shaft.
2. APPLICABLE DOCUMENTS
Coast Guard Drawing 87 WPB 182-001, Rev-, Main Engine and Generator Foundations
Coast Guard Drawing 87 WPB 243-001, Rev M, Propulsion Shaft Details
Bollinger Shipyard, USCG CPB Project MTU-FA 771903, 07 Feb 2000, Engine/Gearbox Plant Alignment Instructions 8V396 TE94/Flange mounted BW 255
3. REQUIREMENTS
3.1 General. The Contractor shall use USCG CPB Project MTU-FA 771903 as a guide.
3.1.1 Related work item. The Contractor shall accomplish this work in conjunction with "Remove, Inspect, and Reinstall Propeller Shafts", which is a separate work item in this specification package.
3.1.2 Personnel qualification. The Contractor shall ensure that the shaft alignment is performed under the direct supervision of personnel experienced in and regularly engaged in shaft and engine alignment. The qualified personnel shall meet the following requirements:
• Be familiar with manufacturer's installation techniques, able to assist with proper bearing and shaft alignment, analyze shaft and bearing clearances, and ensure compliance with engine/reduction gear manufacturer's standards during inspection and installation of the engine and shaft system.
Page 24 (Rev-5)
• Have a resume of previously demonstrated alignment experience as described within this work item.
• Be able to provide a list of references upon request to the COTR.
3.2 Alignment preparation. Prior to shaft realignment, the
Contractor shall ensure the following conditions are met for at least 24 hours before the alignment check:
• The vessel is waterborne with fuel, water, and temporary ballast tanks filled to normal operating levels, a minimum of three-quarters capacity.
• All major equipment and machinery weighing over 1,000 pounds (450 kilograms) are either installed or simulated by equivalent weights appropriately located.
3.3 Shaft realignment. The Contractor shall accomplish the
shaft realignment using Coast Guard Drawings 87 WPB 182-001, 87 WPB 243-001, and Engine/Gearbox Plant Alignment Instructions (USCG CPB Project MTU-FA 771903) as guidance.
3.3.1 Alignment adjustment. Correct any misalignment by
repositioning the propulsion engines and reduction gears. Shim the engine foundations in place as necessary.
3.3.2 Final readings. Recheck all alignment readings, insert
the bolts in the flanges, and tighten to the proper torque for the size and type.
NOTICE!
The tightening torque for the flange bolts shall be 430 Nm according to Engine/Gearbox Plant Alignment Instructions (USCG CPB Project MTU-FA 771903.
3.3.3 Report. After taking the alignment readings, submit to
the COTR a written report of all the final readings within 24 hours after alignment check.
4. QUALITY ASSURANCE
4.1 Operational test. The Contractor shall demonstrate proper operation of the propeller shaft without binding during sea trials. Inspect and correct any abnormal noise and vibration generated from the shaft or bearings.
Page 25 (Rev-5)
Page 26 (Rev-5)
24313_ANL_87 (14 May 2008)
WORK ITEM 7: Remove, Inspect, and Reinstall Propeller Shafts
1. SCOPE
1.1 Scope. This work item describes the requirements for the
Contractor to remove, inspect, and reinstall the port and starboard propeller shafts.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Coast Guard Drawing 87 WPB 243-001, Rev M, Propulsion Shaft Details
Coast Guard Technical Publication (TP) 4593C, Feb 2002, SWBS 243, Manufacturer's Instruction Book, 87' WPB Propulsion Shaft Seals, John Crane Type F.S.E.
3. REQUIREMENTS
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph(s):
• 3.3 (Shaft inspections).
• 3.4 (Bearing inspections).
• 3.5 (Establishing baseline bearing positions).
• 3.7.4 (Inspection).
3.1.2 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which are separate work items in this specification package:
• “Remove, Inspect, and Reinstall Propellers."
• “Remove, Inspect, and Reinstall Rudder Assemblies.”
Page 27 (Rev-5)
3.1.3 Interferences. The Contractor shall be aware that
interferences in way of work include, but are not limited to the following:
• Deck plates.
• Deck plate framing.
• Stern tube mid bearing access hatch.
• Stern tube aft bearing access hatch.
3.1.4 Weighing of shaft coupling. The Contractor shall weigh
the shaft coupling and its hardware, and clearly stamp the total weight into the body of the coupling (i.e. WT XX#).”
3.1.5 Standard forms. The Contractor shall complete and submit the measurement forms at the end of this work item as part of the required CFR/CIR's.
3.1.6 Initial shaft coupling alignment check. The Contractor
shall, prior to the vessel’s initial drydocking, perform the bore and…