HSCG40-16-Q-P30G21

Amendment Number A00003

14. (cont’d)

QUESTION: Looking at Std Spec 0000 para 3.2.1.1 KTR understands that actually there would not be a conflict as originally stated by the CG because the NOTE in the work item 4 spec would take precedence over the General Requirements Std Spec. as copied and pasted below for your reference.. Does the CG concur?

3.2.1.1 Order of precedence. In the event of a conflict between the text of the specifications and applicable references, hierarchy, priority, or order of precedence of requirements shall be as follows:

1. The text of the specification work items.

2. The text of the “General Requirements” specifications.

3. Coast Guard Drawings.

4. Coast Guard Technical Publications.

5. Commercial Drawings.

6. Commercial Technical Manuals.

7. Coast Guard Standards and Instructions.

8. Commercial or Industrial Standards.

9. Commercial Practices.

10. Federal and Military Specifications and Standards

ANSWER: CG concurs. The repair specification supersedes "General Requirements". REV-2

Specification attached

All other terms and conditions remain unchanged.

(END OF AMENDMENT NUMBER A00003)