USCG 45622 (RB-M 45)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2015
Developed By: Edward A Wadley
(Rev-0, 14 November 2014)
USCG 45622 (RB-M-45) DRYDOCK AVAILABILITY FY2015
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ...................................................................................................................................................... iii Consolidated List of References ............................................................................................................................... iv Consolidated List of Government-furnished Property ........................................................................................... viii Consolidated List of Critical Inspection Items ........................................................................................................ xii Principal Characteristics ......................................................................................................................................... xiii General Requirements WORK ITEM 1: General Welding, Provide WORK ITEM 2: Ultrasonic Testing (UT) (100) Shots, Perform WORK ITEM 3: Hull Plating (U/W Body), Inspect WORK ITEM 4: Fendering System, Inspect WORK ITEM 5: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 6: Main Diesel Engine to Auragen Generator, Align WORK ITEM 7: Main Diesel Engine To Jet Drive, Align WORK ITEM 8: Water Jet-Inspect, Perform Service WORK ITEM 9: Jet Drive Anodes, Renew WORK ITEM 10: Sea Strainers, Inspect WORK ITEM 11: Engine Exhaust Piping, Inspect WORK ITEM 12: Electrical Isolation, Perform WORK ITEM 13: Sea Valves, Overhaul WORK ITEM 14: Sea Valves, Renew WORK ITEM 15: Diesel Tank, Refuel WORK ITEM 16: Water Jet Drive, Preserve WORK ITEM 17: U/W Body, Preserve (100%) WORK ITEM 18: Exterior and Interior Non-Skid Pads, Renew WORK ITEM 19: Interior Hull Insulation, Inspect WORK ITEM 20: Marine Chemist Services, Provide WORK ITEM 21: Drydocking WORK ITEM 22: Temporary Services, Provide WORK ITEM 23: Sea Trial Performance, Support, Provide WORK ITEM 24: Main Diesel Engine Mount Washers, Replace WORK ITEM 25: Low Level Lights FWD WORK ITEM 26: Air Intake Baffle, Mast Step, Handhold, Install WORK ITEM 27: Tow Reel, Anchor Reel - Preserve iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 45 RBM 201-001, Rev B, Main Engine Arrangement
Coast Guard Drawing 45 RBM 247-002, Rev C, Water Jet Propulsor Arrangement
Coast Guard Drawing 45 RBM 311-004, Rev C, APU Generator Drive System
Coast Guard Drawing 45 RBM 581-001, Rev E, Anchoring Handling and Stowage System
Coast Guard Drawing 45 RBM 582-002, Rev C, Mooring and Towing System
Coast Guard Drawing 45 RBM 631-001, Rev C, Painting Layout
Coast Guard Drawing 45RBM 150-009, Rev D, Pilothouse Structure Module C – Shell
Coast Guard Drawing 45RBM 150-010, Rev B, Pilothouse Structure Module C – Coach Top
Coast Guard Drawing 45RBM 256-002, Rev A, Cooling System Propulsion
Coast Guard Drawing 45RBM 259-002 Rev B, Exhaust System
Coast Guard Drawing 45RBM 321-200, Rev C, Wire Harness Arrangement
Coast Guard Drawing 45RBM 321-201, Rev B, Wire Way Arrangement
Coast Guard Drawing 45RBM 330-001, Rev -, Lighting System Arrangement
Coast Guard Drawing 45RBM 330-002, Rev C, Lighting System Schematic
Coast Guard Drawing 45RBM 634-002, Rev C, Deck Covering
Coast Guard Drawing 45RBM 635-002, Rev -, Insulation Details
Coast Guard Drawing 45RB-M_170_1 Rev A Folding Mast
Coast Guard Drawing 45-RB-M_261_1 Rev – Fuel Supply System Schematic
Coast Guard Drawing 45-RB-M_261_100 Rev – Fuel Fill and Vent Schematic http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-0)
Coast Guard Drawing 45-RB-M_261_101 Rev – Fuel Fill and Vent Arrangement
Coast Guard Drawing 45-RB-M_261_2 Rev A Fuel Supply System
Coast Guard Drawing 45-RB-M_261_4 Rev A Fuel Supply System Tubes
Coast Guard Drawing 45-RB-M_261_5 Rev – Fuel Supply System – pipe Assemblies
Coast Guard Drawing 45-RB-M_84_2 Rev – Docking Plan
Coast Guard Drawing 45RBM-084-002, Rev -, Docking Plan
Coast Guard Drawing 45RBM-110-001, Rev -, Hull Structure
Coast Guard Drawing 45RBM-110-002 Rev-, Hull Structure Module A
Coast Guard Drawing 45RBM-110-003 Rev -, Hull Structure Module B
Coast Guard Drawing 45RBM-114-001 Rev A, Fendering Arrangement
Coast Guard Drawing 45RBM-201-001 Rev-.Main Engine Arrangement
Coast Guard Drawing 45RBM-247-001 Rev-, Water Jet Propulsor Arrangement
Coast Guard Drawing 45RBM-247-002 Rev A, Water Jet Propulsor Arrangement
Coast Guard Drawing 45RBM-252-003 Rev-, Propulsion Control System
Coast Guard Drawing 45RBM-256-002 Rev -, Cooling System Propulsion
Coast Guard Drawing 45RBM-256-002 Rev A, Cooling System Propulsion
Coast Guard Drawing 45RBM-259-002 Rev A, Exhaust System
Coast Guard Drawing 45RBM-261-001 Rev -, Fuel Supply Schematic
Coast Guard Drawing 45RBM-261-002 Rev A, Fuel Supply System
Coast Guard Drawing 45RBM-261-002 Rev-, Fuel Supply System
Coast Guard Drawing 45RBM-261-100 Rev-, Fuel Fill and Vent Schematic
Coast Guard Drawing 45RBM-261-101 Rev-, Fuel Fill and Vent Arrangement
Coast Guard Drawing 45RBM-262-002 Rev-, Lube Oil FLOCS System
Coast Guard Drawing 45RBM-311-002 Rev A, APU System Arrangement
Coast Guard Drawing 45RBM-622-002 Rev-, Machinery Space Removable Deck Plate
Coast Guard Drawing 45RBM-631-001 Rev B, Painting Layout
Coast Guard Drawing 45RBM-631-001, Rev C, Painting Layout
Coast Guard Drawing 45-RBM-634-002 Rev B, Deck Covering
Coast Guard Drawing 45RBM-635-002 Rev A, Insulation Details
Coast Guard Drawing 45RBM-84-003 Rev N-A, Main Diesel Engine Mounting for 45 RB-M
COAST GUARD PUBLICATIONS
45 FT Response Boat Medium (RB-M) Operators Handbook COMDTINST M16114.41 March 2012
Coast Guard Commandant Instruction (COMDTINST) M16114.41, March 2012, 45 Ft Response Boat-
Medium (RB-M) Operators Handbook
Coast Guard Commandant Instruction (COMDTINST)_MI0360.3 (series), Coatings and Color Manual
Coast Guard Technical Publication (TP) 204412-R22 SEQ 1 Marine Trans Owners Manual, May 2009
Coast Guard Technical Publication (TP) 204413-R22 SEQ 3 176001, Rolls Royce Water Jet Maintenance
Manual, Jun 2009
Coast Guard Technical publication (TP) 4934 , Apr 2014, Small Boat Diagrams for Hotwork SWBS
Group 74, Section A
Coast Guard Technical Publication (TP) 4934, Small Boat Diagrams for Hotwork vi (Rev-0)
Coast Guard Technical Publication (TP) 4993, 3M Nonskid Pads, Peel and Stick Catalog
Coast Guard Technical Publication (TP) 5716, April 2014, Manufacture’s Information Book – SWBS
163, Section A, Seawater Cooling System Duplex Strainer - Model RBM-203976
Coast Guard Technical Publications 4934-074-A, Small Boat Diagrams for Hotwork March 2010
Commandant Instruction Manual COMDINST M9000.6 (series), Naval Engineering Manual, March 2011
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2012, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair and Installation
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2012, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2012, Temporary
Services
OTHER REFERENCES
270’s APM: Add the “NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), May 1997, Requirements for Fabrication, Welding, and Inspection of Submarine Structure” to below, if this package is for a 270 “B-Class” cutter.
45 RBM Water Jet Disassembly / Assembly Procedures
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and
Welding End
ASTM D1330-04(2010) Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) 6966, 2008, Standard Practice for Collection of Settled Dust Samples Using
Wipe Sampling Methods for Subsequent Determination of Metals
ASTM International (ASTM) D4138, 2007, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
Code of Federal Regulations (CFR) Title 29, Part 1910, Jul 2008, Occupational Safety and Health
Standards
Code of Federal Regulations (CFR) Title 33, Jul 2013, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency
Code of Federal Regulations (CFR) Title 40, Jul 2013, Protection of the Environment
Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
Code of Federal Regulations (CFR) Title 49, Oct 2013, Transportation
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service vii (Rev-0)
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves
MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of
Reliability Is Required
MIL-STD-2003A, Sep 2009, Electric Plant Installation Standard Methods for Surface Ships and
Submarines
Rolls-Royce Kamewa Water Jet Assembly Drawing 376 000 49
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and
Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC), June 1996, Paint Application Specification No. 2 (PA-2), Measurement of Dry Coating Thickness with Magnetic Gages
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-WJ-2/NACE WJ-2, 2012 Water Jet Cleaning of Metals-Very Thorough Cleaning viii (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
4 N Bow Fender NSN: 2040-01-612-5098 1 ea. $1450.00
4 N #4Stbd Side Fender NSN: 2040-01-612-5130 1 ea. $629.00
4 N Aft Stbd Fender NSN: 2040-01-612-5215 1 ea. $1122.00
6 Y *MDE/ TO GENERATOR
ALIGNMENT TOOL
PN: MMRBM0030 01
7 Y * MDE/ TO JET DRIVE
ALIGNMENT TOOL
PN: MMRBM0451 1 ea
8 N Stainless Steel Ball Joint NSN: 3040016152117
PN: 59915K483
10 EA $12.14
8 N Stainless Steel Threaded
Rod
NSN: 5306016152224
PN: 93250A140
1 EA $10.90
8 N Bearing Bushing NSN: 3120014555212
PN: 10106911
4 EA $6.88
8 N Bearing Bushing NSN: 3120580006242
PN: 36M05101
4 EA $68.55
8 N **Socket Head Screw NSN: 5305016171580
PN: 91210050
8 EA $1.98
8 N **Bolt Kit NSN: 2815016171688
PN: 93112085A
2 EA $10.25
8 N **Key NSN: 5315016166360
PN: 10100824
3 EA $21.21
8 N Seal NSN:5330580006238 PN:
10118902
2EA $4.00
8 N Bushing NSN: 3120580006239
PN: 10105511
2 EA $34.42
8 N Bearing Bushing NSN: 3120014555272
PN: 10105111
4 EA $24.42
8 N **Bolt Kit NSN: 2815016171974
PN: 93112080F
2 EA $4.81
8 N **Bolt Kit NSN: 5340016167191
PN: 93112065K
12 EA $8.00
8 N Bearing Unit NSN: 3110016166342
PN: 37506201
2 EA $403.50
8 N Bushing NSN: 3120580006240
PN: 10106011
4 EA $37.45
8 N **Set Screw NSN: 5305016020672
PN: 91608012
6EA $1.16
8 N **Bolt Kit NSN: 5305016173161
PN: 93112090K
10EA $9.19
ix (Rev-0)
8 N O-ring NSN: 5331580006241
PN: 10202606
6 EA $10.30
8 N **Mechanical Sealing NSN: 4320580006403
PN: 10203870
2 EA $767.45
8 N Bolt Kit NSN: 5306016164058
PN: 93310030E
6 EA $1.41
8 N O-ring NSN: 5331016020679
PN: 10202631
2 EA $5.15
8 N O-ring NSN: 5331016020680
PN: 10202625
4 EA $10.86
8 N Sealing NSN: 5365016233174
PN: 41018801
2 EA $7.31
8 N O-ring NSN: 5331016200368
PN: 10202611
2 EA $4.07
8 N Seal Lip NSN: 4730016204613
PN: 10202590
4 EA $77.25
8 N Sealing NSN: 5330016163186
PN: 45002010
2 EA $7.31
8 N **Lock Nut NSN: 5310016162982
PN: 10202908
2 EA $15.56
8 N Lock Washer NSN: 5310016232756
PN: 10203008
2 EA $4.79
8 N **Ring Nut NSN: 5310016164016
PN: 10202912
2 EA $30.00
8 N Bushing NSN: 3120580006240
PN: 10106011
4 EA $37.45
8 N Seal NSN: 5330016243735
PN: 10202540R
6 EA $13.56
8 N **Screw NSN: 5305016162955
PN: 93305025
8 EA $0.21
8 N **Washer NSN: 5310016162966
PN: 912505
8 EA $0.14
8 N SS Bond Seal NSN: 5330016212084
PN: 9900-04SS
4 EA $4.50
8 N 3/8” BSPP SS Seal NSN: 5330016212063
PN: 9900-06SS
6 EA $3.90
8 N Gasket NSN: 5330016232867
PN: 37527805
2 EA $49.52
8 N Bushing NSN: 5365016202680
PN: 10108416
8 EA $54.80
8 N **Bolt Kit NSN: 5305016242899
PN; 93110060A
4 EA $8.82
8 N **Bolt Kit NSN: 5305016242922
PN: 99110040G
14 EA $4.61
8 N Bushing NSN: 3120014555268
PN: 10106902
8 EA $5.51
8 N Gasket NSN: 5330016163014
PN: 10108901
2 EA $2.96
8 N **Bolt Kit NSN: 5305016231019
PN: 93110090A
4 EA $3.72
x (Rev-0)
8 N O-ring NSN: 5331016242120
PN: 10202603
2 EA $3.00
8 N Washer, Locking NSN: 5310016232699
PN: 10203012
2 EA $12.00
8 N Countersunk Screw PN: 99106016 4 EA $3.80
8 N Jet Interceptor Hydraulic
Actuator
NSN: 2010-01-590-4296 2 EA $840.54
9 N Anode, Corrosion
Preventive
NSN: 5342016020656
PN:10108228
2 EA $142.39
9 N Anode, Corrosion
Preventive
NSN: 5340015899440
PN:51125
2 EA $82.13
9 N Anode, Corrosion
Preventive
NSN: 5340015899425
PN:89287
2 EA $26.86
9 N Transom Anode NSN: 5342226078675
PN:10108230
4 EA $40.70
9 N Tunnel Anode NSN: 5342016020668
PN:10108220
4 EA $19.00
9 N Impeller
Housing/Bucket/Interceptor
Anode
NSN: 5342226078672
PN:10107701
10 EA $17.63
9 N Guide Vane Chamber
Anode
NSN: 5342016020669
PN:37517411
2 EA $205.28
9 N Anode, Anode Hatch NSN: 5342251465439
PN:10108210
2 EA $23.07
9 N Screw Connection PN:93310025H 4 EA $1.74
9 N Screw Connection NSN: 5305016275854
PN:93308025H
14 EA $0.92
9 N Screw Connection PN:016022105
PN:91206020E
8 EA $1.35
9 N Screw Connection NSN: 5340016243271
PN:93308025E
8 EA $0.71
9 N O-ring NSN: 5331251487667
PN:10202639
2 EA $4.95
9 N Screw Connection NSN: 5305016240905
PN:93310016E
8 EA $0.34
9 N Screw Connection PN:93312030E 2 EA $6.15
9 N Screw Connection NSN: 5305016204602
PN:91212025E
8 EA $1.41
9 N O-ring NSN: 5331226078691
PN:10202626
2 EA $6.79
9 N Tube Extension NSN: 4730016210708
PN:37610802
2 EA $120.10
9 N Tube Clamp NSN: 4730016200951
PN:10217881
2 EA $16.28
9 N Screw Connection NSN: 5305016022101
PN:93310030H
2 EA $1.60
9 N Connecting Cable NSN: 6145016203663
PN:10234301
4 EA $14.70
9 N Screw Connection NSN: 5305016176732
PN:93306016E
8 EA $0.34
xi (Rev-0)
10 N Victaulic (style 475)
Coupling Miller Leahman
Sea Strainers
PS00617 4 EA $140.00
10 Y Miller Leaman Strainer 3.0
Raw Water Duplex - Port
& Starboard
NSN: 4730-01-599-8545 2 EA $16,298.95
14 N Raw Water Sys De-Icing
Valve Valve, Ball, 1" NPT
316 SS
4820-01-600-0385 or PN:
V210FP-16
2 EA $109.00
14 N AC Supply/Discharge Ball
Valve Valve, Ball 3/4"
NPT 316 SS
4820-01-600-0389 or PN:
V210FP-12
3 EA $109.00
14 N AC Overboard Check
Valve High-Flow SS
Check Valve 3/4 NPT
Female
4820-01-599-7249 or PN:
46635K65
1 EA $59.40
18 N Non Skid 45 FT RBM
Box1
NSN: 2040-00-NIB-
0707B
1 1,459.29
18 N Non Skid 45 FT RBM
Box2
NSN: 2040-00-NIB-
0707C
1 1,204.69
18 N Non Skid 45 FT RBM
Box4
NSN: 2040-00-NIB-
0707E
1 574.42
18 N Non Skid 45 FT RBM
Box5
NSN: 2040-00-NIB-
0707F
1 422.55
18 N Non Skid 45 FT RBM
Box8
NSN: 2040-00-NIB-0707I 1 519.59
18 N Non Skid 45 FT RBM -
Round and Square Hatches
- (Not included in main kit)
NSN: 2040-00-NIB-0707J 1 94.82
24 N High Strength Steel Flat
Washer 5/8” Screw Size, 1-
5/16” OD, .21”-.23” Thick
PN: 98025A035 32 Ea $.79
24 N Black-Oxide Steel Thick
Flat Washer, 1” Screw
Size, 2” OD, .26”-.3” Thick
PN 98099A038 16 Ea $3.66
25 N ***TCTO Kit TD4000.0 NSN: 6220-01-HS2-6783 1 Kt.
26 N TCTO KIT TB1010.0 NSN: 2940-01-HS2-6782 1 ea UNK *Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
2 Ultrasonic Testing (UT) (100) Shots, Perform
4 Fendering System, Inspect
6 Main Diesel Engine to Auragen Generator, Align
7 Main Diesel Engine To Jet Drive, Align
8 Water Jet-Inspect, Perform Service
10 Sea Strainers, Inspect
16 Water Jet Drive, Preserve
17 U/W Body, Preserve (100%) xiii (Rev-0)
PRINCIPAL CHARACTERISTICS
45 FT RESPONSE BOAT MEDIUM
HULL MANUFACTURED BY MARINETTE MARINE CORP
5086 (GRADE) ALUMINUM
HIN- 2009
LENGTH OVERALL
44 FEET, 10.5 INCHES
UNFIXED HEIGHT
20 FEET 9 INCHES
BEAM, MAXIMUM
14 FEET, 7.75 INCHES
FULL LOAD DRAFT
3 FEET, 4 INCHES
FULL LOAD DISPLACEMENT
36,500 POUNDS
MAX SUSTAINED SPEED
42.5 KNOTS
RANGE
250 NAUTICAL MILES AT 30 KNOTS
MISSION LIMITS
8 FOOT SEAS / 30 KNOT WINDS
SURVIVABILITY LIMITS
12 FOOT SEAS / 50 KNOT WINDS
PROPULSION
TYPE 6 CYLINDER DIESEL ENGINE
NUMBER OF UNITS 2 MTU’S 60 SERIES 825 HP
WATER JETS
TYPE ROLLS-ROYCE WATER-JET
NUMBER OF UNITS
TWO
1 (Rev-0)
00000_0714_FLT
REC_00000_FLT_ Boats- 47 MLB @ Commercial Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting boat repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST)_MI0360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures
OTHER REFERENCES
ASTM International (ASTM) 6966, 2008, Standard Practice for Collection of Settled Dust Samples Using
Wipe Sampling Methods for Subsequent Determination of Metals
Code of Federal Regulations (CFR) Title 29, Part 1910, Jul 2008, Occupational Safety and Health
Standards
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal
Code of Federal Regulations (CFR) Title 33, Jul 2013, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Jul 2013, Protection of the Environment
Code of Federal Regulations (CFR) Title 49, Oct 2013, Transportation
3. REQUIREMENTS
2 (Rev-0)
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.2 Contractor-provided fire extinguishers. The Contractor shall provide portable fire extinguishers.
3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with (COMDTINST)_MI0360.3C , Chapter 11 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes
(provided in Chapter 5 of COMDTINST MI0360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3 (Rev-0)
3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC
Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable
Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is _________.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an
NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste
Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the
Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to adequately accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40
CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the
Environmental Records binder and required documentation, including environmental permits compliance and close-out.
4 (Rev-0)
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For
Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy.
3.6.1 Coast Guard turn-over preparation. The Contractor shall be aware that, upon arrival, after haulout, and prior to departing the Contractor’s facility, the Coast Guard crew shall be allowed to accomplish various tasks in preparation for the turn-over of the boat to the Contractor. The following conditions apply to this paragraph:
3.6.1.1 The Coast Guard requires a maximum of three days at the beginning of the contract, and three days at the end to accomplish various tasks.
3.6.1.2 The Contractor may commence/continue work during these time frames.
3.6.1.3 Coast Guard personnel will disconnect the Detroit Diesel Electronic Control (DDEC) System and any other electronic equipment, as required to avoid damage to systems arising from hotwork on the vessel during the availability.
3.6.1.4 Coast Guard personnel will remove the transducers after initial haul-out and reinstall prior to re-floating the vessel.
3.6.1.5 The Unit will contact the servicing ESD or ESU to setup removal/installation of the transducer if Unit personnel are unable to accomplish this task.
3.6.1.6 Any components removed by Coast Guard personnel at the beginning of the contract shall be reinstalled by Coast Guard personnel at the end of the contract.3.7 SFLC standard specification approved changes. The
Contractor shall be aware that the following are approved changes to published SFLC 2012 Edition Standard
Specifications and supersede published content:
3.7.1 SFLC Std Spec 8634, Drydocking, Appendix A, page A5, paragraph A2.7.1.3 Side Blocks: Remove formula value shown as g – Acceleration of gravity – 32.3 Ft/sec , and replace with formula value g -
Acceleration of gravity - 32.174 ft/sec
3.7.2 SFLC Std Spec 0740, Welding and Allied Processes. SFLC Std Spec 0740 added Appendix E, Stray
Current Protection: New Appendix is posted with SFLC Standard Specifications as a separate document on internet and intranet webpage.
3.7.2.1 SFLC Std Spec 0740, page 1, paragraph 1.2 Appendices: Add ‘Stray Current Protection’ to ‘Process
Standard column of appendices table. Add ‘E’ to ‘Appendix’ column of appendices table.
3.7.2.2 SFLC Std Spec 0740, page 4, paragraph 3.1.3 Stray current protection: Add “The Contractor shall meet all requirements for stray current protection as specified in Appendix E - Stray Current Protection.” directly after paragraph 3.1.3 title.
3.7.2.3 SFLC Std Spec 0740, page 4, paragraph 3.1.3 Stray current protection: Delete paragraphs 3.1.3.1 and
3.1.3.2.
3.7.3 SFLC Std Spec 0450, Electrical Power for Contractor’s Tools and Equipment, page 1, paragraph 1.1 Intent:
Add sentence, “Note that stray current protection for welding equipment is covered in SFLC Standard
Specification 0740, Welding and Allied Processes, Appendix E.” to end of paragraph.
5 (Rev-0)
3.7.3.1 SFLC Std Spec 0450, page 5, paragraph 3.4 Equipment Grounding: Add sentence, “Stray current protection for welding equipment is covered in SFLC Standard Specification 0740, Welding and Allied Processes, Appendix E.” to end of paragraph.
3.7.3.2 SFLC Std Spec 0450, page 6, paragraph 3.4 Equipment Grounding: Delete paragraphs 3.4.1.4 and
3.4.1.5.
3.7.3.3 SFLC Std Spec 0450, page 6, paragraph 3.4 Equipment Grounding: Delete Figure 5.
3.7.4 SFLC Std Spec 0000, General Requirements, Appendix A Requirements for Environmental Protection has been superseded by SFLC Std Spec 0000, General Requirements, Appendix A Requirements for Environmental
Protection at Contractor Operated (Non USCG) Facilities, with addition of SFLC Std Spec 0000 Appendix B
Requirements for Environmental Protection at USCG Facilities. The new Appendices are posted with SFLC
Standard Specifications as separate documents on SFLC Standard Specification webpage.
3.7.4.1 SFLC Std Spec 0000, page 22, paragraph 3.3.3.1 NOTE. Add "Flame-retardant polyethylene deck plate with a non-slip diamond pattern from 10 to 40mil thickness" to body of Note.
3.7.4.2 SFLC Std Spec 0000, page 3, bullet “ISC.” Delete “lead-contaminated materials.”
3.7.4.3 SFLC Std Spec 0000, page 27, after Note box under paragraph 3.3.13.1.2 add the following paragraphs:
“3.3.13.1.3 Dock and Sea trials. The Contractor shall conduct dock trials to test the work performed during the contract when required by individual work items (see 3.3.13 Tests and Inspections). This shall include operational tests or inspections, as appropriate, of all machinery, piping, wiring, insulation, preservation work, deck coverings, and any other article removed, moved, disturbed, or damaged by the Contractor in accomplishing the work outlined in the specification. Schedule for these specific dockside tests or inspections shall be included within the planning document (see 3.2.5 Planning document).
3.3.13.1.3.1 The Contractor shall provide a pier facility or allow the vessel to move to a Coast Guard pier to support dock trials. The Contractor shall not conduct trials that require the vessel to be waterborne while the vessel is floating inside a dock (e.g., graving dock, floating drydock).
3.3.13.1.3.2 Sea trials to conduct equipment operational tests are not required unless a Sea Trial Performance work item is specifically included within the specification.”
3.7.4.4 SFLC Std Spec 0000, page 11, paragraph 3.2.5, add the following bullets to the bulleted list:
Identifies the “critical paths” for the project.
Shows calculations for the “float” along the critical paths and labels the critical paths with the number of delay days the critical paths can absorb without affecting the final delivery date.
3.7.4.5 SFLC Std Spec 0000, page 11, Add the following Note between paragraphs 3.2.5 and 3.2.5.1:
NOTE
Float is the number of days that the critical paths can be delayed without affecting the final delivery date.
3.7.4.6 SFLC Std Spec 0000, page 12, add the following paragraphs and Note after Figure 1:
6 (Rev-0)
“3.2.5.4 When the critical path extends beyond or encroaches upon the final delivery date, provide a resource constraint and scheduling evaluation of the critical path before any request for extension will be entertained.
Submit the resource constraint and scheduling evaluation via a CFR.
NOTE
The intent of the resource constraint and scheduling evaluation is to identify the resources necessary to ‘crash’ the critical path or make adjustments to the production schedule to meet the delivery date in lieu of a project extension.”
3.7.4.7 Std Spec 0000, General Requirements, page 4, paragraph 1.3 Acronyms and term definitions, “Paint
Containing Lead” remove lead content percent of “0.06 percent by weight (0.12 mg/cm2, or 600 ppm)” and replace with “0.009 percent by weight (0.018 mg/cm2, or 90 ppm)”
3.7.5 SFLC Std Spec 6310, Requirements For Preservation Of Ship Structures, page 10, add “3.1.6.5
Preconstruction Primers. Also known as shop primers, preconstruction primers are used as a temporary coating to protect steel from corrosion during welding, storage, and fabrication. Preconstruction primers shall be removed prior to applying the permanent coating system on all critical coated surfaces. Preconstruction primers may be left in place in other interior areas (such as machinery spaces, habitability spaces, etc.) if they are intact, uncontaminated, and compatible with the overcoating system.”
3.7.5.1 Std Spec 6310, Appendix B, page B12 , the formatting for of Notes 17-19 change and add as per the following:
SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 17, delete sentence, “Persistent corrosion in a particular area of an aluminum bilge may dictate the need for a protective High Build Epoxy coating to be applied to that local area.”
SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 18, replace entire note with “Persistent corrosion in a particular area of an aluminum bilge may dictate the need for a protective High Build Epoxy coating to be applied to that local area. “
SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 19, replace entire note with “Painting plastic surfaces is highly discouraged, but after it is done once, it must be maintained.”
SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Add Note “20. For aluminum surfaces, remove all oil, grease, dirt, metal oxides (corrosion products) and other foreign material by cleaning per SSPC-SP 1 prior to blast cleaning and following blast cleaning immediately prior to coating. The end result of abrasive blasting will be a surface cleanliness similar to that of
SSPC-SP 10 for steel with all coating removed.
3.7.5.2 Std Spec 6310, Appendix E, pages E1, E3, and E4, QA Inspection Forms QA-1, QA-3a, and QA-3b respectively, reference The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface
Preparation Standard SSPC-SP 12/NACE No. 5 erroneously, and are corrected as per the following:
3.7.5.2.1 Std Spec 6310, Appendix E, pages E1, QA Inspection Form QA-1, Check point 5- Surface Preparation, check box description 2, replace “(i.e.: SSPC SP-12, SP-11, SP-10…).” with “(i.e.: SSPC SP-11, SP-10, SP WJ-
2…).”
3.7.5.2.2 Std Spec 6310, Appendix E, page E3, QA Inspection Form QA-3a, Surface Preparation Method column of the Profile Achieved table, 2 nd record, replace “SSPC-SP-12/NACE No. 5” with “SSPC-SP WJ-1/NACE WJ-
1”.
7 (Rev-0)
3.7.5.2.2.1 Add record to table beneath “SSPC-SP WJ-1/NACE WJ-1” and label as “SSPC-SP WJ-2/NACE WJ-
2”
3.7.5.2.2.2 Add record to table beneath “SSPC-SP WJ-2/NACE WJ-2” and label as “SSPC-SP WJ-3/NACE WJ-
3”
3.7.5.2.2.3 Add record to table beneath “SSPC-SP WJ-3/NACE WJ-3” and label as “SSPC-SP WJ-4/NACE WJ-
4”
3.7.5.2.3 Std Spec 6310, Appendix E, page E4, QA Inspection Form QA-3b, Surface Preparation Method column of the Profile Achieved table, 2 nd record, replace “SSPC-SP-12/NACE No. 5” with “SSPC-SP WJ-1/NACE WJ-
1”.
3.7.5.2.3.1 Add record to table beneath “SSPC-SP WJ-1/NACE WJ-1” and label as “SSPC-SP WJ-2/NACE WJ-
2”
3.7.5.2.3.2 Add record to table beneath “SSPC-SP WJ-2/NACE WJ-2” and label as “SSPC-SP WJ-3/NACE WJ-
3”
3.7.5.2.3.3 Add record to table beneath “SSPC-SP WJ-3/NACE WJ-3” and label as “SSPC-SP WJ-4/NACE WJ-
4”
3.7.6 SFLC Std Spec 8635, Temporary Services, page 2, delete paragraph 3.3.2.2.
3.7.7 SFLC Std Spec 5000, Auxiliary Machine Systems, Appendix C, page C9: Replace paragraph C2.8.1.3 and
Table C-3, and add additional paragraphs C2.8.1.4, C2.8.1.5, and C2.8.1.6. as follows:
“C2.8.1.3 Flushing fluid minimum flow rate requirements. Ensure the minimum flow rates provided in Table C-
3 are maintained for each circuit. If multiple loops are flushed concurrently, each loop shall be provided with a flow measuring device. Provide calibrated flow meters. Prior to flushing, submit the certification of calibration to the CG Inspector.
TABLE C-3 - MINIMUM FLOW RATE FOR FLUSHING WITH FLUID
PIPE SIZE INSIDE DIA
(INCH)
GAL/MIN
To 0.5 18
0.5 to 0.75 34
0.75 to 1.0 56
1.0 to 1.25 100
1.25 to 1.5 138
1.5 to 2.0 230
2.0 to 2.5 330
2.5 to 3.0 420
NOTES
1. Flow rates represent minimum flows needed to achieve a turbulent flow condition and maximize benefits of flushing effort.
8 (Rev-0)
2. Flow rate selected for flow velocity of 25 ft/sec in the schedule 80/160 pipe, as applicable. If there is a conflict between the pressure and flow rate requirements of this specification, the minimum flow rates shall be governing, unless the working pressure of the system is exceeded. The uses of by-pass (flow control) valves are not allowed downstream of the flow meters.
C2.8.1.4 Whenever a noticeable increase in the pressure drop across strainers is observed, the strainers should be cleaned and bag renewed. Be aware that this may occur as frequency as 15 min intervals.
C2.8.1.5 During flushing, constant monitoring of the flushing oil must be maintained in order to determine the contamination level. Filtering shall continue until the fluid entering the return flow filter meets the particle population ISO cleanliness code of 17/14, in accordance with ISO 4406. All flushing fluid shall pass through the return filter after passing through each system flushing circuit. All samples shall be taken at a point just prior to this filter
C2.8.1.6 Take a representative sample of oil from the hydraulic system of the hydraulic system. Send samples out for laboratory analysis. Analysis shall include viscosity, moisture, total acid number, particle size and population in sufficient detail to determine ISO cleanliness code of 17/14, in accordance with ISO 4406. Submit CFR.”
3.7.8 SFLC Std Spec 6341, Appendix A, Paragraph A2.1.1, replace with “A2.1.1 Cove vase. Include a cove base, using the same epoxy resin deck covering system material, to a maximum height of four inches at all adjacent vertical bounding surfaces, where applicable."
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down
(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
9 (Rev-0)
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
10 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL.
HUMID-
ITY DEW
PT.
SURFACE AMBIENT
ΔT
| DP -
Surface |
11 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
Location of Work (Frame References) Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
12 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):
_____ mils _____ mils _____ mils _____ mils _____ mils
13 (Rev-0)
QA-4 -…