Attach_1-SchedPrices_10-16.xls

XLS spreadsheet 186 KB Posted

Attached to
TANK & BILGE CLEANING AND POWER WASHING SERVICES
Solicitation number
HSCG40-14-R-60744
Issued by

About this file

Schedule of Supplies/Services

View the file

Other files

File Type Posted
QA.doc DOC document
SF1449-12a2.pdf PDF
Attach_3_Wage_Determination.pdf PDF
Attach_4_QASP.doc DOC document
Attach_2_PWS-Final_Revision_10-15.docx DOCX document
Solicitation_10-22.docx DOCX document
Attach_5_Past_Performance.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Year

ATTACHMENT 1 – SCHEDULE OF SUPPLIES/SERVICES AND PRICES
BASE YEAR
TANK/BILGE - CLEANING
STORAGE TANKS– LIQUID REMOVAL/DISPOSAL
OFFERORS ARE CAUTIONED TO CAREFULLY REVIEW THIS ENTIRE
SOLICITATION BEFORE SUBMITTING PRICES.
Services to be provided include the cleaning of tanks and bilges, removal and disposal
of liquids, Underwater Hull Cleaning, and certification of gas free conditions by a
Certified Marine Chemist (CMC). Certification by other than a CMC is not acceptable.
Services are to be provided for a period of one-year (365 days) from the date on which
the contract is awarded.
SPECIAL CONSIDERATIONS:
Normal working hours at the U.S. Coast Guard YARD are 7:00am through 3:30pm
E.S.T., Monday through Friday, excluding Federal holidays. It is expected that 40% of
the total work will require the successful bidder to provide services outside the normal
working hours, including Saturdays, Sundays, and Federal holidays.
In addition, the successful offeror may be required to provide the various services
listed within 48 hours after receiving notice from the Contracting Officer. It is expected
that half of the orders issued during the one-year performance period will require the
contractor to arrive at the U.S. Coast Guard YARD and commence work within 48 hours
from the time of contractor’s receipt of notice. In the majority of these cases, the notice
will be given to the contractor orally, and a written order will subsequently be provided.
The 48-hour response time will be computed from the time that the contractor receives
the oral notice.
OFFERORS MUST CONSIDER THESE REQUIREMENTS WHEN COMPUTING
AND SUBMITTING THEIR BID PRICES.
The estimated quantities shown are based on past experience and are approximations
only. They are not intended to limit the U.S. Coast Guard to either a minimum or
maximum quantity per order. They are also not intended to limit the U.S. Coast Guard to
either a minimum or maximum number of orders during the one-year period.
Offerors must complete each column. Prices must be submitted for the base year and
four option years. The proposal evaluation will include option year prices (see Section
IV). Failure to submit a unit price and a total price for each line item may result in the
rejection of your bid in its entirety.
Attachment 1 – Base Year
Item No.Description
0001.Tank Cleaning in accordance with Section 1.3, “Performance Work Statement"
Provide unit and total price for each item.
0001A.REMOVE and DISPOSE of the following from vessels either at berth
or dry docked. The estimated quantities shown are for a one-year period.
Tanks will normally be pumped to lowest level by vessels’ installed systems.
NOTE: REMOVALS WILL BE CONSIDERED INCOMPLETE WITHOUT
COPIES OF THE BILL OF LADING. (Reference Attachment 1. Performance Work Statement for
Tank Cleaning, Para. 1.3.1.1)
UnitUnit PriceEst. Qty/GalTotal Price
0001A1.Diesel Oil1 gal50,000$0
0001A2.Void1 gal10,000$0
0001A3.JP-5 Oil1 gal20,000$0
0001A4.Lubricating Oil1 gal7,000$0
0001A5.Sewage Effluent1 gal50,000$0
0001A6.Hydraulic Oil1 gal6000$0
0001A7.Used Oil1 gal30,000$0
0001A8.Ballast Water1 gal360,000$0
(NTE 2% of total tank capacity)
0001A9.Potable Water1 gal30,000$0
(NTE 2% of total tank capacity)
0001A10.50% Mixture Nalcool/Water
(Antifreeze)1 gal5,000$0
0001A11.Oily Water1 gal70,000$0
(Contents average 80% water)
SUB TOTAL ITEM 1A$0
Attachment 1 – Base Year
Item No.Description
0001B.CLEAN TANKS (Condition Code A) in accordance with the Performance Work Statement (1.3.1.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
0001B1.Diesel Oil1 gal90,000$0
0001B2.Voids1 gal1000$0
0001B3.JP-5 oil,1 gal25000$0
0001B4.Sewage1 gal10000$0
0001B5.Lubricating oil,1 gal1000$0
0001B6.Hydraulic oil,1 gal1000$0
0001B7.Used oil,1 gal1000$0
0001B8.Ballast water1 gal500,000$0
0001B9.Potable water1 gal1000$0
0001B10.Oily Water1 gal72000$0
.SUB TOTAL ITEM 1B$0
Attachment 1 – Base Year
Item No.Description
0001C.CLEAN TANKS (Condition Code B) in accordance with the Performance Work Statement (1.3.1.1) for tank cleaning
and removal of tank content below suction, including residual cleaning water. Wipe dry to
finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
0001C1.Diesel Oil,1 gal600,000$0
0001C2.Voids1 gal70,000$0
0001C3.JP-5 oil,1 gal80,000$0
0001C4.Sewage1 gal230,000$0
0001C5.Lubricating oil,1 gal15,000$0
0001C6.Hydraulic oil,1 gal5000$0
0001C7.Used oil,1 gal5,000$0
0001C8.Ballast water1 gal300,000$0
0001C9.Potable water1 gal80,000$0
0001C10.Oily Water1 gal25,000$0
0001C11.Hand scraping Diesel Oil Tank1 gal300,000$0
0001C12.Hand scraping Sewage1 gal115,000$0
SUB TOTAL ITEM 1C$0
Attachment 1 – Base Year
Item No.Description
0001D.CLEAN TANKS (Condition Code C) in accordance with the Performance Work Statement (1.3.1.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
0001D1.Diesel Oil,1 gal15000$0
0001D2.Voids1 gal5000$0
0001D3.JP-5 oil,1 gal1000$0
0001D4.Sewage1 gal20,000$0
0001D5.Lubricating oil,1 gal5000$0
0001D6.Hydraulic oil,1 gal1000$0
0001D7.Used oil,1 gal5000$0
0001D8.Ballast water1 gal20000$0
0001D9.Potable water1 gal1000$0
0001D10.Oily Water1 gal1000$0
SUB TOTAL ITEM 1D$0
Attachment 1 – Base Year
Item No.Description
0001E.REMOVE and DISPOSE OF FUEL and LUBE OIL SURPLUS when
directed by the Contracting Officer.
UnitFirm Fixed % of Commodity PriceEst. Qty/Gal
0001E1.Credit for diesel oil1 gal100,000
(98% pure)
0001E2.Credit for JP-51 gal10,000
(98% pure)
SUB TOTAL ITEM 1E
*For evaluations purposes only the discount proposed will be determined reasonable based on comparison between proposals received and the current rate found at Mundi index at the time of evaluation.
The fuel credit shall be based upon the current commodity price Fuel (energy) index, Heating Oil price. The current commodity price can be found at such websites such as Mundi. Ex: http://www.indexmundi.com/commodities/?commodity=heating-oil
NOTES:
(1) The total credits for item 1E will be deducted from the total amount of the task order.
(2) The minimum quantity for credit application is 1500 gallons of diesel oil per call.
0001F.REMOVE and DELIVER FUEL TO Yard facilities diesel storage tank when
directed by the Contracting Officer.
UnitUnit PriceEst. Qty/GalTotal Price
0001F.1Diesel Oil1 gal135,000$0
Attachment 1 – Base Year
Bilge Cleaning
Item No.Description
0002.Bilge areas CLEANED in accordance with Section 1.3.1.2, “Performance Work Statement for Bilge
Cleaning.”
0002a.REMOVE and DISPOSE of waste and/or contaminated sludge, oil, fuel, cleaning agent and
other contaminated liquid and all debris and rags from the designated bilge areas.
Contaminated liquids in these bilge areas average 95 percent water. Wipe dry to finished
surface removing all residue.
UnitUnit PriceEst. Qty/GalTotal Price
0002A1.Contaminated1 gal120,000$0
Liquids.
CLEAN (Condition Code A)
Bilge areas could be contaminated with heavy sludge as listed below:
0002A2.Bilge1 sq. ft.80,000$0
CLEAN (Condition Code B)
Bilge areas could be contaminated with heavy sludge as listed below:
0002A3Bilge1 sq. ft.80,000$0
CLEAN (Condition Code C)
Bilge areas could be contaminated with heavy sludge as listed below:
0002A4Bilge1 sq. ft.30,000$0
SUB TOTAL ITEM 2$0
Attachment 1 – Base Year
Contaminated Liquid Removal/Disposal
Yard Storage Tanks
Item No.Description
0003.Contaminated Liquid Disposal in accordance with Statement of Work Section 1.3.2,
“Contaminated Liquid Discharge.” Provide unit and total price.
0003a.PUMP-OUT, COLLECT & REMOVE waste liquids and sludge from each storage tanks
located at the U.S. Coast Guard YARD.
UnitUnit PriceEst. Qty/GalTotal Price
0003A1.Storage tanks1 gal400,000$0
Contents average
80% water.
SUB TOTAL ITEM 3$0
Attachment 1 – Base Year
MARINE CHEMIST CERTIFICATION
Item No.Description
0004.Provide written CERTIFICATION by a Marine Chemist that the specified areas worked are
gas free, safe for men and safe for hot work. Price to be per call, per vessel at the U.S. Coast
Guard YARD.
UnitUnit PriceEst. Qty/CallsTotal Price
0004A1. Call/Vessel1 call60$0
SUB TOTAL ITEM 4$0
Attachment 1 – Base Year
Underwater Hull Cleaning
Yard Storage Tanks
Item No.Description
0005.Underwater Hull Cleaning in accordance with Statement of Work Section 1.3.1.4,
“Underwater Hull Cleaning.” Provide unit and total price.
0005a.Power washing services for cleaning underwater hull and appendages of vessels
UnitUnit PriceEst. Qty/GalTotal Price
0005A1.Vessel/Vessels1 SQFT265,000$0
SUB TOTAL ITEM 5$0
Item No.Description
0006.Standby/delay charge for equipment and personnel due to unforeseen delays.
UnitUnit PriceEst. Qty/GalTotal Price
0006aFuel removal hourly standby rate fuel removal1 hour40$0.00
0006bTank cleaning hourly standby rate1 hour40$0.00
SUB TOTAL ITEM 6$0.00
SUMMARY
Item 1$0
Item 2$0
Item 3$0
Item 4$0
Item 5$0
Item 6$0
Total$0
Item 1e Credit$0
Grand Total$0

Option Year 1

ATTACHMENT 1 – SCHEDULE OF SUPPLIES/SERVICES AND PRICES
Option Year one (1)
TANK/BILGE - CLEANING
STORAGE TANKS– LIQUID REMOVAL/DISPOSAL
OFFERORS ARE CAUTIONED TO CAREFULLY REVIEW THIS ENTIRE
SOLICITATION BEFORE SUBMITTING PRICES.
Services to be provided include the cleaning of tanks and bilges, removal and disposal
of liquids, Underwater Hull Cleaning, and certification of gas free conditions by a
Certified Marine Chemist (CMC). Certification by other than a CMC is not acceptable.
Services are to be provided for a period of one-year (365 days) from the date on which
the contract is awarded.
SPECIAL CONSIDERATIONS:
Normal working hours at the U.S. Coast Guard YARD are 7:00am through 3:30pm
E.S.T., Monday through Friday, excluding Federal holidays. It is expected that 40% of
the total work will require the successful bidder to provide services outside the normal
working hours, including Saturdays, Sundays, and Federal holidays.
In addition, the successful offeror may be required to provide the various services
listed within 48 hours after receiving notice from the Contracting Officer. It is expected
that half of the orders issued during the one-year performance period will require the
contractor to arrive at the U.S. Coast Guard YARD and commence work within 48 hours
from the time of contractor’s receipt of notice. In the majority of these cases, the notice
will be given to the contractor orally, and a written order will subsequently be provided.
The 48-hour response time will be computed from the time that the contractor receives
the oral notice.
OFFERORS MUST CONSIDER THESE REQUIREMENTS WHEN COMPUTING
AND SUBMITTING THEIR BID PRICES.
The estimated quantities shown are based on past experience and are approximations
only. They are not intended to limit the U.S. Coast Guard to either a minimum or
maximum quantity per order. They are also not intended to limit the U.S. Coast Guard to
either a minimum or maximum number of orders during the one-year period.
Offerors must complete each column. Prices must be submitted for the base year and
four option years. The proposal evaluation will include option year prices (see Section
IV). Failure to submit a unit price and a total price for each line item may result in the
rejection of your bid in its entirety.
Attachment 1 – Option Year One (1)
Item No.Description
1001.Tank Cleaning in accordance with Section 1.3, “Performance Work Statement for Tank
Cleaning.” Provide unit and total price for each item.
1001A.REMOVE and DISPOSE of the following from vessels either at berth
or dry docked. The estimated quantities shown are for a one-year period.
Tanks will normally be pumped to lowest level by vessels’ installed systems.
NOTE: REMOVALS WILL BE CONSIDERED INCOMPLETE WITHOUT
COPIES OF THE BILL OF LADING. (Reference Attachment 1. Performance Work Statement for
Tank Cleaning, Para. 1.3.1.1)
UnitUnit PriceEst. Qty/GalTotal Price
1001A1.Diesel Oil1 gal50,000$0
1001A2.Void1 gal10,000$0
1001A3.JP-5 Oil1 gal20,000$0
1001A4.Lubricating Oil1 gal7,000$0
1001A5.Sewage Effluent1 gal50,000$0
1001A6.Hydraulic Oil1 gal6000$0
1001A7.Used Oil1 gal30,000$0
1001A8.Ballast Water1 gal360,000$0
(NTE 2% of total tank capacity)
1001A9.Potable Water1 gal30,000$0
(NTE 2% of total tank capacity)
1001A10.50% Mixture Nalcool/Water
(Antifreeze)1 gal5,000$0
1001A11.Oily Water1 gal70,000$0
(Contents average 80% water)
SUB TOTAL ITEM 1A$0
Attachment 1 – Option Year one (1)
Item No.Description
1001B.CLEAN TANKS (Condition Code A) in accordance with the Performance Work Statement (1.3.1.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
1001B1.Diesel Oil1 gal90,000$0
1001B2.Voids1 gal1000$0
1001B3.JP-5 oil,1 gal25000$0
1001B4.Sewage1 gal10,000$0
1001B5.Lubricating oil,1 gal1000$0
1001B6.Hydraulic oil,1 gal1000$0
1001B7.Used oil,1 gal1000$0
1001B8.Ballast water1 gal500,000$0
1001B9.Potable water1 gal1000$0
1001B10.Oily Water1 gal72000$0
.SUB TOTAL ITEM 1B$0
Attachment 1 – Option Year One (1)
Item No.Description
0001C.CLEAN TANKS (Condition Code B) in accordance with the Performance Work Statement (1.3.1.1) for tank cleaning
and removal of tank content below suction, including residual cleaning water. Wipe dry to
finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
1001C1.Diesel Oil,1 gal600,000$0
1001C2.Voids1 gal70,000$0
1001C3.JP-5 oil,1 gal80,000$0
1001C4.Sewage1 gal230,000$0
1001C5.Lubricating oil,1 gal15,000$0
1001C6.Hydraulic oil,1 gal5000$0
1001C7.Used oil,1 gal5,000$0
1001C8.Ballast water1 gal300,000$0
1001C9.Potable water1 gal80,000$0
1001C10.Oily Water1 gal25,000$0
1001C11.Hand scraping Diesel Oil Tank1 gal300,000$0
1001C12.Hand scraping Sewage1 gal115,000$0
SUB TOTAL ITEM 1C$0
Attachment 1 – Option Year one (1)
Item No.Description
1001D.CLEAN TANKS (Condition Code C) in accordance with the Performance Work Statement (1.3.1.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
1001D1.Diesel Oil,1 gal15000$0
1001D2.Voids1 gal5000$0
1001D3.JP-5 oil,1 gal1000$0
1001D4.Sewage1 gal20000$0
1001D5.Lubricating oil,1 gal5000$0
1001D6.Hydraulic oil,1 gal1000$0
1001D7.Used oil,1 gal5000$0
1001D8.Ballast water1 gal20000$0
1001D9.Potable water1 gal1000$0
1001D10.Oily Water1 gal1000$0
SUB TOTAL ITEM 1D$0
Attachment 1 – Option Year One (1)
Item No.Description
1001E.REMOVE and DISPOSE OF FUEL and LUBE OIL SURPLUS when
directed by the Contracting Officer.
UnitFirm Fixed % of Commodity PriceEst. Qty/Gal
1001E1.Credit for diesel oil1 gal100,000
(98% pure)
1001E2.Credit for JP-51 gal10,000
(98% pure)
SUB TOTAL ITEM 1E
*For evaluations purposes only the discount proposed will be determined reasonable based on comparison between proposals received and the current rate found at Mundi index at the time of evaluation.
The fuel credit shall be based upon the current commodity price Fuel (energy) index, Heating Oil price. The current commodity price can be found at such websites such as Mundi. Ex: http://www.indexmundi.com/commodities/?commodity=heating-oil
NOTES:
(1) The total credits for item 1E will be deducted from the total amount of the task order.
(2) The minimum quantity for credit application is 1500 gallons of diesel oil per call.
1001F.REMOVE and DELIVER FUEL TO Yard facilities diesel storage tank when
directed by the Contracting Officer.
UnitUnit PriceEst. Qty/GalTotal Price
1001F.1Diesel Oil1 gal135,000$0
Attachment 1 – Option Year One (1)
Bilge Cleaning
Item No.Description
1002.Bilge areas CLEANED in accordance with Section 1.3.1.2, “Performance Work Statement for Bilge
Cleaning.”
1002a.REMOVE and DISPOSE of waste and/or contaminated sludge, oil, fuel, cleaning agent and
other contaminated liquid and all debris and rags from the designated bilge areas.
Contaminated liquids in these bilge areas average 95 percent water. Wipe dry to finished
surface removing all residue.
UnitUnit PriceEst. Qty/GalTotal Price
1002A1.Contaminated1 gal120,000$0
Liquids.
CLEAN (Condition Code A)
Bilge areas could be contaminated with heavy sludge as listed below:
1002A2.Bilge1 sq. ft.80,000$0
CLEAN (Condition Code B)
Bilge areas could be contaminated with heavy sludge as listed below:
1002A3Bilge1 sq. ft.80,000$0
CLEAN (Condition Code C)
Bilge areas could be contaminated with heavy sludge as listed below:
1002A4Bilge1 sq. ft.30,000$0
SUB TOTAL ITEM 2$0
Attachment 1 – Option Year One (1)
Contaminated Liquid Removal/Disposal
Yard Storage Tanks
Item No.Description
1003.Contaminated Liquid Disposal in accordance with the Performance Work Statement Section 1.3.2,
“Contaminated Liquid Discharge.” Provide unit and total price.
1003A.PUMP-OUT, COLLECT & REMOVE waste liquids and sludge from each storage tanks
located at the U.S. Coast Guard YARD.
UnitUnit PriceEst. Qty/GalTotal Price
1003A1.Storage tanks1 gal400,000$0
Contents average
80% water.
SUB TOTAL ITEM 3$0
Attachment 1 – Option Year One (1)
MARINE CHEMIST CERTIFICATION
Item No.Description
1004.Provide written CERTIFICATION by a Marine Chemist that the specified areas worked are
gas free, safe for men and safe for hot work. Price to be per call, per vessel at the U.S. Coast
Guard YARD.
UnitUnit PriceEst. Qty/CallsTotal Price
1004A1. Call/Vessel1 call60$0
SUB TOTAL ITEM 4$0
Attachment 1 – Option Year One (1)
Underwater Hull Cleaning
Yard Storage Tanks
Item No.Description
1005.Underwater Hull Cleaning in accordance with the Performance Work Statement Section 1.3.1.4,
“Underwater Hull Cleaning.” Provide unit and total price.
1005a.Power washing services for cleaning underwater hull and appendages of vessels
UnitUnit PriceEst. Qty/GalTotal Price
1005A1.Vessel/Vessels1 SQFT285,000$0
SUB TOTAL ITEM 5$0
Item No.Description
1006.Standby/delay charge for equipment and personnel due to unforeseen delays.
UnitUnit PriceEst. Qty/GalTotal Price
1006aFuel removal hourly standby rate fuel removal1 hour40$0.00
1006bTank cleaning hourly standby rate1 hour40$0.00
SUB TOTAL ITEM 6$0.00
SUMMARY
Item 1$0
Item 2$0
Item 3$0
Item 4$0
Item 5$0
Item 6$0
Total$0
Item 1e Credit$0
Grand Total$0

Option Year 2

ATTACHMENT 1 – SCHEDULE OF SUPPLIES/SERVICES AND PRICES
Option Year Two (2)
TANK/BILGE - CLEANING
STORAGE TANKS– LIQUID REMOVAL/DISPOSAL
OFFERORS ARE CAUTIONED TO CAREFULLY REVIEW THIS ENTIRE
SOLICITATION BEFORE SUBMITTING PRICES.
Services to be provided include the cleaning of tanks and bilges, removal and disposal
of liquids, Underwater Hull Cleaning, and certification of gas free conditions by a
Certified Marine Chemist (CMC). Certification by other than a CMC is not acceptable.
Services are to be provided for a period of one-year (365 days) from the date on which
the contract is awarded.
SPECIAL CONSIDERATIONS:
Normal working hours at the U.S. Coast Guard YARD are 7:00am through 3:30pm
E.S.T., Monday through Friday, excluding Federal holidays. It is expected that 40% of
the total work will require the successful bidder to provide services outside the normal
working hours, including Saturdays, Sundays, and Federal holidays.
In addition, the successful offeror may be required to provide the various services
listed within 48 hours after receiving notice from the Contracting Officer. It is expected
that half of the orders issued during the one-year performance period will require the
contractor to arrive at the U.S. Coast Guard YARD and commence work within 48 hours
from the time of contractor’s receipt of notice. In the majority of these cases, the notice
will be given to the contractor orally, and a written order will subsequently be provided.
The 48-hour response time will be computed from the time that the contractor receives
the oral notice.
OFFERORS MUST CONSIDER THESE REQUIREMENTS WHEN COMPUTING
AND SUBMITTING THEIR BID PRICES.
The estimated quantities shown are based on past experience and are approximations
only. They are not intended to limit the U.S. Coast Guard to either a minimum or
maximum quantity per order. They are also not intended to limit the U.S. Coast Guard to
either a minimum or maximum number of orders during the one-year period.
Offerors must complete each column. Prices must be submitted for the base year and
four option years. The proposal evaluation will include option year prices (see Section
IV). Failure to submit a unit price and a total price for each line item may result in the
rejection of your bid in its entirety.
Attachment 1 – Option Year Two (2)
Item No.Description
2001.Tank Cleaning in accordance with Section 1.3, “Performance Work Statement for Tank
Cleaning.” Provide unit and total price for each item.
2001A.REMOVE and DISPOSE of the following from vessels either at berth
or dry docked. The estimated quantities shown are for a one-year period.
Tanks will normally be pumped to lowest level by vessels’ installed systems.
NOTE: REMOVALS WILL BE CONSIDERED INCOMPLETE WITHOUT
COPIES OF THE BILL OF LADING. (Reference Attachment 1. Performance Work Statement for
Tank Cleaning, Para. 1.3.1.1)
UnitUnit PriceEst. Qty/GalTotal Price
2001A1.Diesel Oil1 gal50,000$0
2001A2.Void1 gal10,000$0
2001A3.JP-5 Oil1 gal20,000$0
2001A4.Lubricating Oil1 gal7,000$0
2001A5.Sewage Effluent1 gal50,000$0
2001A6.Hydraulic Oil1 gal6000$0
2001A7.Used Oil1 gal30,000$0
2001A8.Ballast Water1 gal360,000$0
(NTE 2% of total tank capacity)
2001A9.Potable Water1 gal30,000$0
(NTE 2% of total tank capacity)
2001A10.50% Mixture Nalcool/Water
(Antifreeze)1 gal5,000$0
2001A11.Oily Water1 gal70,000$0
(Contents average 80% water)
SUB TOTAL ITEM 1A$0
Attachment 1 – Option Year Two (2)
Item No.Description
2001B.CLEAN TANKS (Condition Code A) in accordance with the Performance Work Statement (1.3.1.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
2001B1.Diesel Oil1 gal90,000$0
2001B2.Voids1 gal1000$0
2001B3.JP-5 oil,1 gal25000$0
2001B4.Sewage1 gal10000$0
2001B5.Lubricating oil,1 gal1000$0
2001B6.Hydraulic oil,1 gal1000$0
2001B7.Used oil,1 gal1000$0
2001B8.Ballast water1 gal500000$0
2001B9.Potable water1 gal1000$0
2001B10.Oily Water1 gal72000$0
.SUB TOTAL ITEM 1B$0
Attachment 1 – Option Year Two (2)
Item No.Description
2001C.CLEAN TANKS (Condition Code B) in accordance with the Performance Work Statement (1.3.1.1) for tank cleaning
and removal of tank content below suction, including residual cleaning water. Wipe dry to
finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
2001C1.Diesel Oil,1 gal600,000$0
2001C2.Voids1 gal70,000$0
2001C3.JP-5 oil,1 gal80,000$0
2001C4.Sewage1 gal230,000$0
2001C5.Lubricating oil,1 gal15,000$0
2001C6.Hydraulic oil,1 gal5000$0
2001C7.Used oil,1 gal5,000$0
2001C8.Ballast water1 gal300,000$0
2001C9.Potable water1 gal80,000$0
2001C10.Oily Water1 gal25,000$0
2001C11.Hand scraping Diesel Oil Tank1 gal300,000$0
2001C12.Hand scraping Sewage1 gal115,000$0
SUB TOTAL ITEM 1C$0
Attachment 1 – Option Year Two (2)
Item No.Description
2001D.CLEAN TANKS (Condition Code C) in accordance with the Performance Work Statement (1.31.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
2001D1.Diesel Oil,1 gal15000$0
2001D2.Voids1 gal5000$0
2001D3.JP-5 oil,1 gal1000$0
2001D4.Sewage1 gal20000$0
2001D5.Lubricating oil,1 gal5000$0
2001D6.Hydraulic oil,1 gal1000$0
2001D7.Used oil,1 gal5000$0
2001D8.Ballast water1 gal20000$0
2001D9.Potable water1 gal1000$0
2001D10.Oily Water1 gal1000$0
SUB TOTAL ITEM 1D$0
Attachment 1 – Option Year Two (2)
Item No.Description
2001E.REMOVE and DISPOSE OF FUEL and LUBE OIL SURPLUS when
directed by the Contracting Officer.
UnitFirm Fixed % of Commodity PriceEst. Qty/Gal
2001E1.Credit for diesel oil1 gal100,000
(98% pure)
2001E2.Credit for JP-51 gal10,000
(98% pure)
SUB TOTAL ITEM 1E
*For evaluations purposes only the discount proposed will be determined reasonable based on comparison between proposals received and the current rate found at Mundi index at the time of evaluation.
The fuel credit shall be based upon the current commodity price Fuel (energy) index, Heating Oil price. The current commodity price can be found at such websites such as Mundi. Ex: http://www.indexmundi.com/commodities/?commodity=heating-oil
NOTES:
(1) The total credits for item 1E will be deducted from the total amount of the task order.
(2) The minimum quantity for credit application is 1500 gallons of diesel oil per call.
2001F.REMOVE and DELIVER FUEL TO Yard facilities diesel storage tank when
directed by the Contracting Officer.
UnitUnit PriceEst. Qty/GalTotal Price
2001F.1Diesel Oil1 gal135,000$0
Attachment 1 – Option Year Two (2)
Bilge Cleaning
Item No.Description
2002.Bilge areas CLEANED in accordance with Section 1.3.1.2, “Performance Work Statement for Bilge
Cleaning.”
2002A.REMOVE and DISPOSE of waste and/or contaminated sludge, oil, fuel, cleaning agent and
other contaminated liquid and all debris and rags from the designated bilge areas.
Contaminated liquids in these bilge areas average 95 percent water. Wipe dry to finished
surface removing all residue.
UnitUnit PriceEst. Qty/GalTotal Price
2002A1.Contaminated1 gal120,000$0
Liquids.
CLEAN (Condition Code A)
Bilge areas could be contaminated with heavy sludge as listed below:
2002A2.Bilge1 sq. ft.80,000$0
CLEAN (Condition Code B)
Bilge areas could be contaminated with heavy sludge as listed below:
2002A3Bilge1 sq. ft.80,000$0
CLEAN (Condition Code C)
Bilge areas could be contaminated with heavy sludge as listed below:
2002A4Bilge1 sq. ft.30,000$0
SUB TOTAL ITEM 2$0
Attachment 1 – Option Year Two (2)
Contaminated Liquid Removal/Disposal
Yard Storage Tanks
Item No.Description
2003.Contaminated Liquid Disposal in accordance with the Performance Work Statement Section 1.3.2,
“Contaminated Liquid Discharge.” Provide unit and total price.
2003A.PUMP-OUT, COLLECT & REMOVE waste liquids and sludge from each storage tanks
located at the U.S. Coast Guard YARD.
UnitUnit PriceEst. Qty/GalTotal Price
2003A1.Storage tanks1 gal400,000$0
Contents average
80% water.
SUB TOTAL ITEM 3$0
Attachment 1 – Option Year Two (2)
MARINE CHEMIST CERTIFICATION
Item No.Description
2004.Provide written CERTIFICATION by a Marine Chemist that the specified areas worked are
gas free, safe for men and safe for hot work. Price to be per call, per vessel at the U.S. Coast
Guard YARD.
UnitUnit PriceEst. Qty/CallsTotal Price
2004A1. Call/Vessel1 call60$0
SUB TOTAL ITEM 4$0
Attachment 1 – Option Year Two (2)
Underwater Hull Cleaning
Yard Storage Tanks
Item No.Description
2005.Underwater Hull Cleaning in accordance with the Performance Work Statement Section 1.3.1.4,
“Underwater Hull Cleaning.” Provide unit and total price.
2005A.Power washing services for cleaning underwater hull and appendages of vessels
UnitUnit PriceEst. Qty/GalTotal Price
2005A1.Vessel/Vessels1 SQFT312,000$0
SUB TOTAL ITEM 5$0
Item No.Description
2006.Standby/delay charge for equipment and personnel due to unforeseen delays.
UnitUnit PriceEst. Qty/GalTotal Price
2006AFuel removal hourly standby rate fuel removal1 hour40$0.00
2006BTank cleaning hourly standby rate1 hour40$0.00
SUB TOTAL ITEM 6$0.00
SUMMARY
Item 1$0
Item 2$0
Item 3$0
Item 4$0
Item 5$0
Item 6$0
Total$0
Item 1e Credit$0
Grand Total$0

Option Year 3

ATTACHMENT 1 – SCHEDULE OF SUPPLIES/SERVICES AND PRICES
Option Year Three (3)
TANK/BILGE - CLEANING
STORAGE TANKS– LIQUID REMOVAL/DISPOSAL
OFFERORS ARE CAUTIONED TO CAREFULLY REVIEW THIS ENTIRE
SOLICITATION BEFORE SUBMITTING PRICES.
Services to be provided include the cleaning of tanks and bilges, removal and disposal
of liquids, Underwater Hull Cleaning, and certification of gas free conditions by a
Certified Marine Chemist (CMC). Certification by other than a CMC is not acceptable.
Services are to be provided for a period of one-year (365 days) from the date on which
the contract is awarded.
SPECIAL CONSIDERATIONS:
Normal working hours at the U.S. Coast Guard YARD are 7:00am through 3:30pm
E.S.T., Monday through Friday, excluding Federal holidays. It is expected that 40% of
the total work will require the successful bidder to provide services outside the normal
working hours, including Saturdays, Sundays, and Federal holidays.
In addition, the successful offeror may be required to provide the various services
listed within 48 hours after receiving notice from the Contracting Officer. It is expected
that half of the orders issued during the one-year performance period will require the
contractor to arrive at the U.S. Coast Guard YARD and commence work within 48 hours
from the time of contractor’s receipt of notice. In the majority of these cases, the notice
will be given to the contractor orally, and a written order will subsequently be provided.
The 48-hour response time will be computed from the time that the contractor receives
the oral notice.
OFFERORS MUST CONSIDER THESE REQUIREMENTS WHEN COMPUTING
AND SUBMITTING THEIR BID PRICES.
The estimated quantities shown are based on past experience and are approximations
only. They are not intended to limit the U.S. Coast Guard to either a minimum or
maximum quantity per order. They are also not intended to limit the U.S. Coast Guard to
either a minimum or maximum number of orders during the one-year period.
Offerors must complete each column. Prices must be submitted for the base year and
four option years. The proposal evaluation will include option year prices (see Section
IV). Failure to submit a unit price and a total price for each line item may result in the
rejection of your bid in its entirety.
Attachment 1 – Option Year Three (3)
Item No.Description
3001.Tank Cleaning in accordance with Section 1.3, “Performance Work Statementfor Tank
Cleaning.” Provide unit and total price for each item.
3001A.REMOVE and DISPOSE of the following from vessels either at berth
or dry docked. The estimated quantities shown are for a one-year period.
Tanks will normally be pumped to lowest level by vessels’ installed systems.
NOTE: REMOVALS WILL BE CONSIDERED INCOMPLETE WITHOUT
COPIES OF THE BILL OF LADING. (Reference Attachment 1. Performance Work Statement for
Tank Cleaning, Para. 1.3.1.1)
UnitUnit PriceEst. Qty/GalTotal Price
3001A1.Diesel Oil1 gal50,000$0
3001A2.Void1 gal10,000$0
3001A3.JP-5 Oil1 gal20,000$0
3001A4.Lubricating Oil1 gal7,000$0
3001A5.Sewage Effluent1 gal50,000$0
3001A6.Hydraulic Oil1 gal6000$0
3001A7.Used Oil1 gal30,000$0
3001A8.Ballast Water1 gal360,000$0
(NTE 2% of total tank capacity)
3001A9.Potable Water1 gal30,000$0
(NTE 2% of total tank capacity)
3001A10.50% Mixture Nalcool/Water
(Antifreeze)1 gal5,000$0
3001A11.Oily Water1 gal70,000$0
(Contents average 80% water)
SUB TOTAL ITEM 1A$0
Attachment 1 – Option Year Three (3)
Item No.Description
3001B.CLEAN TANKS (Condition Code A) in accordance with the Performance Work Statement (1.3.1.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
3001B1.Diesel Oil1 gal90,000$0
3001B2.Voids1 gal1000$0
3001B3.JP-5 oil,1 gal25000$0
3001B4.Sewage1 gal10000$0
3001B5.Lubricating oil,1 gal1000$0
3001B6.Hydraulic oil,1 gal1000$0
3001B7.Used oil,1 gal1000$0
3001B8.Ballast water1 gal500000$0
3001B9.Potable water1 gal1000$0
3001B10.Oily Water1 gal72000$0
.SUB TOTAL ITEM 1B$0
Attachment 1 – Option Year Three (3)
Item No.Description
3001C.CLEAN TANKS (Condition Code B) in accordance with the Performance Work Statement (1.3.1.1) for tank cleaning
and removal of tank content below suction, including residual cleaning water. Wipe dry to
finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
3001C1.Diesel Oil,1 gal600,000$0
3001C2.Voids1 gal70,000$0
3001C3.JP-5 oil,1 gal80,000$0
3001C4.Sewage1 gal230,000$0
3001C5.Lubricating oil,1 gal15,000$0
3001C6.Hydraulic oil,1 gal5000$0
3001C7.Used oil,1 gal5,000$0
3001C8.Ballast water1 gal300,000$0
3001C9.Potable water1 gal80,000$0
3001C10.Oily Water1 gal25,000$0
3001C11.Hand scraping Diesel Oil Tank1 gal300,000$0
3001C12.Hand scraping Sewage1 gal115,000$0
SUB TOTAL ITEM 1C$0
Attachment 1 – Option Year Three (3)
Item No.Description
3001D.CLEAN TANKS (Condition Code C) in accordance with the Performance Work Statement (1.3.1.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
3001D1.Diesel Oil,1 gal15000$0
3001D2.Voids1 gal5000$0
3001D3.JP-5 oil,1 gal1000$0
3001D4.Sewage1 gal20000$0
3001D5.Lubricating oil,1 gal5000$0
3001D6.Hydraulic oil,1 gal1000$0
3001D7.Used oil,1 gal5000$0
3001D8.Ballast water1 gal20000$0
3001D9.Potable water1 gal1000$0
3001D10.Oily Water1 gal1000$0
SUB TOTAL ITEM 1D$0
Attachment 1 – Option Year Three (3)
Item No.Description
3001E.REMOVE and DISPOSE OF FUEL and LUBE OIL SURPLUS when
directed by the Contracting Officer.
UnitFirm Fixed % of Commodity PriceEst. Qty/Gal
3001E1.Credit for diesel oil1 gal100,000
(98% pure)
3001E2.Credit for JP-51 gal10,000
(98% pure)
SUB TOTAL ITEM 1E
*For evaluations purposes only the discount proposed will be determined reasonable based on comparison between proposals received and the current rate found at Mundi index at the time of evaluation.
The fuel credit shall be based upon the current commodity price Fuel (energy) index, Heating Oil price. The current commodity price can be found at such websites such as Mundi. Ex: http://www.indexmundi.com/commodities/?commodity=heating-oil
NOTES:
(1) The total credits for item 1E will be deducted from the total amount of the task order.
(2) The minimum quantity for credit application is 1500 gallons of diesel oil per call.
3001F.REMOVE and DELIVER FUEL TO Yard facilities diesel storage tank when
directed by the Contracting Officer.
UnitUnit PriceEst. Qty/GalTotal Price
3001F.1Diesel Oil1 gal135,000$0
Attachment 1 – Option Year Three (3)
Bilge Cleaning
Item No.Description
3002.Bilge areas CLEANED in accordance with Section 1.3.2, “Performance Work Statement for Bilge
Cleaning.”
3002A.REMOVE and DISPOSE of waste and/or contaminated sludge, oil, fuel, cleaning agent and
other contaminated liquid and all debris and rags from the designated bilge areas.
Contaminated liquids in these bilge areas average 95 percent water. Wipe dry to finished
surface removing all residue.
UnitUnit PriceEst. Qty/GalTotal Price
3002A1.Contaminated1 gal120,000$0
Liquids.
CLEAN (Condition Code A)
Bilge areas could be contaminated with heavy sludge as listed below:
3002A2.Bilge1 sq. ft.80,000$0
CLEAN (Condition Code B)
Bilge areas could be contaminated with heavy sludge as listed below:
3002A3Bilge1 sq. ft.80,000$0
CLEAN (Condition Code C)
Bilge areas could be contaminated with heavy sludge as listed below:
3002A4Bilge1 sq. ft.30,000$0
SUB TOTAL ITEM 2$0
Attachment 1 – Option Year Three (3)
Contaminated Liquid Removal/Disposal
Yard Storage Tanks
Item No.Description
3003.Contaminated Liquid Disposal in accordance with the Performance Work StatementSection 1.3.2,
“Contaminated Liquid Discharge.” Provide unit and total price.
3003A.PUMP-OUT, COLLECT & REMOVE waste liquids and sludge from each storage tanks
located at the U.S. Coast Guard YARD.
UnitUnit PriceEst. Qty/GalTotal Price
3003A1.Storage tanks1 gal400,000$0
Contents average
80% water.
SUB TOTAL ITEM 3$0
Attachment 1 – Option Year Three (3)
MARINE CHEMIST CERTIFICATION
Item No.Description
3004.Provide written CERTIFICATION by a Marine Chemist that the specified areas worked are
gas free, safe for men and safe for hot work. Price to be per call, per vessel at the U.S. Coast
Guard YARD.
UnitUnit PriceEst. Qty/CallsTotal Price
3004A1. Call/Vessel1 call60$0
SUB TOTAL ITEM 4$0
Attachment 1 – Option Year Three (3)
Underwater Hull Cleaning
Yard Storage Tanks
Item No.Description
3005.Underwater Hull Cleaning in accordance with the Performance Work StatementSection 1.3.1.4,
“Underwater Hull Cleaning.” Provide unit and total price.
3005A.Power washing services for cleaning underwater hull and appendages of vessels
UnitUnit PriceEst. Qty/GalTotal Price
3005A1.Vessel/Vessels1 SQFT312,000$0
SUB TOTAL ITEM 5$0
Item No.Description
3006.Standby/delay charge for equipment and personnel due to unforeseen delays.
UnitUnit PriceEst. Qty/GalTotal Price
3006AFuel removal hourly standby rate fuel removal1 hour40$0.00
3006BTank cleaning hourly standby rate1 hour40$0.00
SUB TOTAL ITEM 6$0.00
SUMMARY
Item 1$0
Item 2$0
Item 3$0
Item 4$0
Item 5$0
Item 6$0
Total$0
Item 1e Credit$0
Grand Total$0

Option Year 4

ATTACHMENT 1 – SCHEDULE OF SUPPLIES/SERVICES AND PRICES
Option Year Four (4)
TANK/BILGE - CLEANING
STORAGE TANKS– LIQUID REMOVAL/DISPOSAL
OFFERORS ARE CAUTIONED TO CAREFULLY REVIEW THIS ENTIRE
SOLICITATION BEFORE SUBMITTING PRICES.
Services to be provided include the cleaning of tanks and bilges, removal and disposal
of liquids, Underwater Hull Cleaning, and certification of gas free conditions by a
Certified Marine Chemist (CMC). Certification by other than a CMC is not acceptable.
Services are to be provided for a period of one-year (365 days) from the date on which
the contract is awarded.
SPECIAL CONSIDERATIONS:
Normal working hours at the U.S. Coast Guard YARD are 7:00am through 3:30pm
E.S.T., Monday through Friday, excluding Federal holidays. It is expected that 40% of
the total work will require the successful bidder to provide services outside the normal
working hours, including Saturdays, Sundays, and Federal holidays.
In addition, the successful offeror may be required to provide the various services
listed within 48 hours after receiving notice from the Contracting Officer. It is expected
that half of the orders issued during the one-year performance period will require the
contractor to arrive at the U.S. Coast Guard YARD and commence work within 48 hours
from the time of contractor’s receipt of notice. In the majority of these cases, the notice
will be given to the contractor orally, and a written order will subsequently be provided.
The 48-hour response time will be computed from the time that the contractor receives
the oral notice.
OFFERORS MUST CONSIDER THESE REQUIREMENTS WHEN COMPUTING
AND SUBMITTING THEIR BID PRICES.
The estimated quantities shown are based on past experience and are approximations
only. They are not intended to limit the U.S. Coast Guard to either a minimum or
maximum quantity per order. They are also not intended to limit the U.S. Coast Guard to
either a minimum or maximum number of orders during the one-year period.
Offerors must complete each column. Prices must be submitted for the base year and
four option years. The proposal evaluation will include option year prices (see Section
IV). Failure to submit a unit price and a total price for each line item may result in the
rejection of your bid in its entirety.
Attachment 1 – Option Year Four (4)
Item No.Description
4001.Tank Cleaning in accordance with Section 1.3, “Performance Work Statementfor Tank
Cleaning.” Provide unit and total price for each item.
4001A.REMOVE and DISPOSE of the following from vessels either at berth
or dry docked. The estimated quantities shown are for a one-year period.
Tanks will normally be pumped to lowest level by vessels’ installed systems.
NOTE: REMOVALS WILL BE CONSIDERED INCOMPLETE WITHOUT
COPIES OF THE BILL OF LADING. (Reference Attachment 1. Performance Work Statementfor
Tank Cleaning, Para. 1.3.1.1)
UnitUnit PriceEst. Qty/GalTotal Price
4001A1.Diesel Oil1 gal50,000$0
4001A2.Void1 gal10,000$0
4001A3.JP-5 Oil1 gal20,000$0
4001A4.Lubricating Oil1 gal7,000$0
4001A5.Sewage Effluent1 gal50,000$0
4001A6.Hydraulic Oil1 gal6000$0
4001A7.Used Oil1 gal30,000$0
4001A8.Ballast Water1 gal360,000$0
(NTE 2% of total tank capacity)
4001A9.Potable Water1 gal30,000$0
(NTE 2% of total tank capacity)
4001A10.50% Mixture Nalcool/Water
(Antifreeze)1 gal5,000$0
4001A11.Oily Water1 gal70,000$0
(Contents average 80% water)
SUB TOTAL ITEM 1A$0
Attachment 1 – Option Year Four (4)
Item No.Description
4001b.CLEAN TANKS (Condition Code A) in accordance with the Performance Work Statement(1.3.1.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
4001B1.Diesel Oil1 gal90,000$0
4001B2.Voids1 gal1000$0
4001B3.JP-5 oil,1 gal25000$0
4001B4.Sewage1 gal10000$0
4001B5.Lubricating oil,1 gal1000$0
4001B6.Hydraulic oil,1 gal1000$0
4001B7.Used oil,1 gal1000$0
4001B8.Ballast water1 gal500000$0
4001B9.Potable water1 gal1000$0
4001B10.Oily Water1 gal72000$0
.SUB TOTAL ITEM 1B$0
Attachment 1 – Option Year Four (4)
Item No.Description
4001C.CLEAN TANKS (Condition Code B) in accordance with the Performance Work Statement(1.3.1.1) for tank cleaning
and removal of tank content below suction, including residual cleaning water. Wipe dry to
finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
4001C1.Diesel Oil,1 gal600,000$0
4001C2.Voids1 gal70,000$0
4001C3.JP-5 oil,1 gal80,000$0
4001C4.Sewage1 gal230,000$0
4001C5.Lubricating oil,1 gal15,000$0
4001C6.Hydraulic oil,1 gal5000$0
4001C7.Used oil,1 gal5,000$0
4001C8.Ballast water1 gal300,000$0
4001C9.Potable water1 gal80,000$0
4001C10.Oily Water1 gal25,000$0
4001C11.Hand scraping Diesel Oil Tank1 gal300,000$0
4001C12.Hand scraping Sewage1 gal115,000$0
SUB TOTAL ITEM 1C$0
Attachment 1 – Option Year Four (4)
Item No.Description
4001D.CLEAN TANKS (Condition Code C) in accordance with the Performance Work Statement(1.3.1.1) for tank
cleaning and removal of tank content below suction, including residual cleaning water.
Wipe dry to finished surface removing all residues.
UnitUnit PriceEst. Qty/GalTotal Price
4001D1.Diesel Oil,1 gal15000$0
4001D2.Voids1 gal5000$0
4001D3.JP-5 oil,1 gal1000$0
4001D4.Sewage1 gal20000$0
4001D5.Lubricating oil,1 gal5000$0
4001D6.Hydraulic oil,1 gal1000$0
4001D7.Used oil,1 gal5000$0
4001D8.Ballast water1 gal20000$0
4001D9.Potable water1 gal1000$0
4001D10.Oily Water1 gal1000$0
SUB TOTAL ITEM 1D$0
Attachment 1 – Option Year Four (4)
Item No.Description
4001E.REMOVE and DISPOSE OF FUEL and LUBE OIL SURPLUS when
directed by the Contracting Officer.
UnitFirm Fixed % of Commodity PriceEst. Qty/Gal
4001E1.Credit for diesel oil1 gal100,000
(98% pure)
4001E2.Credit for JP-51 gal10,000
(98% pure)
SUB TOTAL ITEM 1E
*For evaluations purposes only the discount proposed will be determined reasonable based on comparison between proposals received and the current rate found at Mundi index at the time of evaluation.
The fuel credit shall be based upon the current commodity price Fuel (energy) index, Heating Oil price. The current commodity price can be found at such websites such as Mundi. Ex: http://www.indexmundi.com/commodities/?commodity=heating-oil
NOTES:
(1) The total credits for item 1E will be deducted from the total amount of the task order.
(2) The minimum quantity for credit application is 1500 gallons of diesel oil per call.
4001F.REMOVE and DELIVER FUEL TO Yard facilities diesel storage tank when
directed by the Contracting Officer.
UnitUnit PriceEst. Qty/GalTotal Price
4001F.1Diesel Oil1 gal135,000$0
Attachment 1 – Option Year Four (4)
Bilge Cleaning
Item No.Description
4002.Bilge areas CLEANED in accordance with Section 1.3.1.2, “Performance Work Statementfor Bilge
Cleaning.”
4002A.REMOVE and DISPOSE of waste and/or contaminated sludge, oil, fuel, cleaning agent and
other contaminated liquid and all debris and rags from the designated bilge areas.
Contaminated liquids in these bilge areas average 95 percent water. Wipe dry to finished
surface removing all residue.
UnitUnit PriceEst. Qty/GalTotal Price
4002A1.Contaminated1 gal120,000$0
Liquids.
CLEAN (Condition Code A)
Bilge areas could be contaminated with heavy sludge as listed below:

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .