Spec P-420-0335 (J)

View the file

Other files

File Type Posted
Aton_61127_120998f.pdf PDF
Ombudsman.doc DOC document
Required_Information.doc DOC document
Aton_61127_P-420-0334_RevJ_Buoy_Bell_and_Gong_Tappers.docx DOCX document
COMBO-FebBiz-Q_ _A_to_HSCG40-14-Q-61127.doc DOC document
FAR_52.246-1 _QA_inspection.pdf PDF
Aton_61127_121159d.pdf PDF
ASTM-D-3951-shipping_instructions.doc DOC document
Required_Information.doc DOC document
Aton_61127_121159d.pdf PDF
Ombudsman.doc DOC document
Aton_61127_P-420-0335_RevJ_Buoy_Bell_and_Gong_Stands.docx DOCX document
Aton_61127_120998f.pdf PDF
FAR_52.246-1 _QA_inspection.pdf PDF
ASTM-D-3951-shipping_instructions.doc DOC document
Aton_61127_P-420-0334_RevJ_Buoy_Bell_and_Gong_Tappers.docx DOCX document
ASTM-D-3951-shipping_instructions.doc DOC document
Aton_61127_120998f.pdf PDF
Required_Information.doc DOC document
Aton_61127_121159d.pdf PDF
Aton_61127_P-420-0334_RevJ_Buoy_Bell_and_Gong_Tappers.docx DOCX document
FAR_52.246-1 _QA_inspection.pdf PDF
Aton_61127_P-420-0335_RevJ_Buoy_Bell_and_Gong_Stands.docx DOCX document
ASTM-D-3951-shipping_instructions.doc DOC document
Aton_61127_P-420-0334_RevJ_Buoy_Bell_and_Gong_Tappers.docx DOCX document
FAR_52.246-1 _QA_inspection.pdf PDF
Required_Information.doc DOC document
Aton_61127_120998f.pdf PDF
Aton_61127_121159d.pdf PDF
Aton_61127_P-420-0335_RevJ_Buoy_Bell_and_Gong_Stands.docx DOCX document
Aton_Purchase_Description_61127.pdf PDF
Aton_61127_P-420-0335_RevJ_Buoy_Bell_and_Gong_Stands.docx DOCX document
Required_Information.doc DOC document
Aton_61127_P-420-0334_RevJ_Buoy_Bell_and_Gong_Tappers.docx DOCX document
Aton_61127_120998f.pdf PDF
Ombudsman.doc DOC document
Aton_61127_121159d.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P-420-0335 Rev J May 2012

REVISION __J____ REV DATE May 2012

SPECIFICATION OR

STATEMENT OF WORK

COVER SHEET

TITLE

SPECIFICATION FOR FABRICATION OF BUOY BELL AND GONG STANDS

SPECIFICATION NUMBER

P-420-0335

(FORMERLY HQ SPECIFICATION NO. 362G)

ORIGINATED BY: David W. White DATE: May 2012

ORIGINATOR’S COMMAND: Surface Forces Logistics Center (SFLC)

DEPARTMENT/DIVISION: ALD/Compliance/Aton-General Stores

INTERNAL REVIEWER: DATE: _______

SOWRB APPROVAL: DATE: _______

Specification P-420-0335 Rev J May 2012

1. SCOPE

1.1 Scope. This specification defines the requirements for the fabrication of buoy bell and gong stands for use on aids to navigation buoys. The items covered by this specification are as follows:

85 lb. Bell Stand
2050-00-856-4618
225 lb. Bell Stand
2050-00-856-4614
20 inch Gong Stand
2050-00-301-4074

2. APPLICABLE DOCUMENTS

2.1 General. The documents listed in this section are referenced in sections 3 and 4 of this specification. This section does not include documents cited in other sections of this specification which are recommended for additional information or used as examples. While every effort has been made to ensure the completeness of this list, document users are cautioned that they must meet all specified requirements cited in sections 3 and 4 of this specification, whether or not the referenced documents are listed here.

2.2 Government Documents. The following documents form a part of this specification to the extent referenced herein. Suffixes denoting the specific issue of each document are omitted from future references to the documents in this specification.

SPECIFICATIONS

MIL-PRF-24647D

Jun 12 2006

Paint System, Anticorrosive and Antifouling, Ship Hull

QPL-24647-QPD

Apr 25 2012 Qualified Products List of Products Qualified Under Military Specification MIL-P-24647, Paint System, Anticorrosive and Antifouling, Ship Hull

MIL-PRF-24176C

Oct 14 2004

Military Specification, Cement, Epoxy, Metal Repair and Hull Smoothing

MIL-STD-129P Chg4 Sep 19 2007

Standard Practice for Military Marking

MIL-R-900F(1)

Mar 27 1991 Rubber Gasket Material, 45 Durometer Hardness

2.3 Industry Publications. The following documents of the issues specified form a part of this specification to the extent referenced herein. Suffixes denoting the specific issue of each document will be omitted from future references to the document in this specification.

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

A36/A36M May 15 2008

Standard Specification for Structural Steel

D 3951 Aug 15 2010

Standard Practice for Commercial Packaging

A108 Sep 01 2007

Standard Specification for Steel Bars, Carbon, Cold Finished, Standard Quality

A276 May 01 2010 Standard Specification for Austenitic Stainless Sheet, Strip, Plate, and Flat Bar Pressure Vessels

AMERICAN WELDING SOCIETY (AWS)

AWS D1.1/D1.1M

Jan 01 2010 Structural Welding Code - Steel

STEEL STRUCTURES PAINTING COUNCIL (SSPC)

SSPC-SP-10/NACE No. 2 Jan 01 2007 Joint Surface Prep Std, Near White Blast Cleaning Item 21066

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

AIM BC 1

Aug 16 1995 Uniform Symbology Specification, Code 39

AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)

ASNT-TC-1A

01 Jan 2011 Recommended Practice for Personal Qualification and Certification in Nondestructive Testing – Item 2071; Includes CP-105

AMERICAN SOCIETY FOR QUALITY (ASQ)

ASQ Q9001

Jan 01 2008 Quality Systems - Model for Quality Assurance in Production, Inspection, and Servicing

2.4 Drawings. The latest revision of the following United States Coast Guard Ocean Engineering drawing forms a part of this specification to the extent referenced herein, and shall be referred to as "the drawing" throughout this specification:

Drawing Number

Title

120998

Buoy Bell and Gong Stands

2.5 Source of Documents. The documents may be obtained from the following sources:

Government Documents.

Standardization Documents Order Desk
Building 4, Section D
700 Robbins Avenue
Philadelphia, PA 19111-5094

Industry Publications.

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
1916 Race Street
Philadelphia, PA 19103-1187
AMERICAN WELDING SOCIETY (AWS)
550 NW LeJeune Road
PO Box 351040
Miami, Florida 33135
AIM USA
634 Alpha Drive
Pittsburgh, PA 15238-2802
STEEL STRUCTURES PAINTING COUNCIL (SSPC)
4400 Fifth Avenue
Pittsburgh, PA 15213

AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)

1711 Arlingate Lane
Columbus, OH 43228-0518
AMERICAN SOCIETY FOR QUALITY (ASQ)
310 West Wisconsin Avenue
Milwaukee, Wisconsin 53203

2.6 Precedence. In the event of a conflict between the text of this document and the references cited herein, the text of this document takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained.

3. REQUIREMENTS

3.1 Materials.

3.1.1 Steel.

3.1.1.1 Steel Bars, Shapes, and Plates. All steel bars, shapes, and plates shall meet the requirements of ASTM A36/A36M, unless otherwise specified.

3.1.1.2 Gong Posts. The gong post shall be fabricated from AISI 1018 grade cold drawn steel meeting the requirements of ASTM A108.

3.1.2 Stainless Steel.

3.1.2.1 Stainless Steel Hardware. All stainless steel hardware (nuts, bolts, pins, washers, etc.) shall meet the requirements of ASTM A276, type 316 or 316L.

3.1.3 Gasket Material. Rubber gasket material shall meet the requirements of MIL-R-900F.

3.2 Design and Construction.

3.2.1 Design, Dimensions, and Dimensional Tolerances. All items shall conform to the design, dimensions, and tolerances shown in the drawing.

3.2.2 Threads. The threads on all nuts and bolts shall be Unified Course Thread Series (UNC).

3.3 Welding. The plates, bars, rods and other shapes forming the various components of the items shall be fitted and faired prior to being welded in place. All welds shall be performed as indicated on the drawing. Shielded Metal Arc Welding (SMAW), Flux-Cored Arc Welding (FCAW), Gas Metal Arc Welding (GMAW), or Submerged Arc Welding (SAW) shall be used to weld all steel parts. All welding procedures and weld quality shall meet the requirements of AWS D1.1/D1.1M. All welders employed for welding under this specification shall be qualified by the Contractor using procedures which meet the requirements of AWS D1.1/D1.1M.

3.4 Marking.

3.4.1 Identification Marking. For tracking purposes, each item shall be identified by an identification marking. The marking shall be stamped, engraved, or otherwise permanently affixed to each item. The marking shall consist of ½-inch tall block alphanumeric characters and be clearly visible after the items have been painted. The marking shall be of the form 00-XX. The first two digits are the last two digits of the calendar year built and the last two letters are the Contractor’s designation, which will be furnished by the Contracting Officer after contract award.

3.4.2 Serial Number. For inspection purposes, the Contractor shall assign each item a unique serial number. The serial number shall be stamped, engraved, or otherwise permanently affixed to each item. The serial number shall consist of ½-inch tall block alphanumeric characters and be clearly visible after the items have been painted.

3.5 Surface Preparation. Prior to surface preparation, all stainless steel parts shall be protected (i.e. taped, masked, etc). All exterior steel surfaces shall be blast cleaned to near-white metal in accordance with NACE Number 2, SSPC-SP-10. Prior to painting, all surfaces shall be free of contaminants such as oil, water, grease, dirt, blasting residue, weld spatter, slag, and flash rust.

3.5.1 Epoxy Repair Compound. After all surfaces have been blasted clean, any weld containing porosity shall be filled with an epoxy repair compound meeting the requirements of MIL-PRF-24176. The epoxy repair compound shall only be used to fill porosity discontinuities that are within the allowable maximums stated in table 6.1 of AWS D1.1/D1.1M.

3.6 Painting. Prior to painting, all stainless steel parts shall be protected (i.e. taped, masked, etc). The items shall be painted with the coating system outlined below. All painting shall be performed after the items have been cleaned in accordance with paragraph 3.5. All welding, machining, cutting, drilling, forming, or any other operation which would damage the coating system shall be performed prior to painting. The Contractor shall follow the manufacturer’s instructions for correct application of the coating system. In addition, the Contractor shall be responsible for implementing appropriate worker safety procedures for the application of the coating system, and for ensuring that the procedures are strictly followed by the paint applicators.

3.6.1 Epoxy primer. All exterior surfaces shall be coated with an epoxy primer. The epoxy primer shall meet the requirements of MIL-PRF-24647, Type I, Class 1A, Grade A or B, Application 1 or 2, and shall be listed in QPL-24647. The color shall be either haze gray or off-white (manufacturers' standard colors are acceptable). Apply by spraying two coats, 5 mils minimum dry film thickness each. Sharp corners, edges, and other hard-to-coat areas shall be striped before each full coat is applied.

3.7 Documentation.

3.7.1 Quality Assurance Inspection Form. The Contractor shall develop and provide a Quality Assurance Inspection Form (QAIF). The QAIF shall be used to document the inspections and tests performed on every item throughout its fabrication process. The form shall be typewritten on standard (i.e., 8½x11 inch) white paper. Inspection results may be handwritten on the form. The form shall be prepared in the Contractor's format and shall be legible, in English, and suitable for reproduction. The form shall be made available to the Contracting Officer’s Technical Representative (COTR) for review.

3.7.1.1 QAIF Content. At a minimum the QAIF shall include:

a) Item serial number.

b) Date of test or inspection.

c) Test or inspection to be performed (list every test and inspection required by section 4.0).

d) Result of test or inspection.

e) Accept/Reject criteria for each test or inspection.

f) Corrective action taken (if any).

g) Notes.

h) Initials or signatures of Contractor’s test personnel.

3.7.2 Material Certifications. When requested by the COTR, the Contractor shall furnish material certifications, either from the material manufacturers or an independent testing laboratory, to the effect that all of the material described in paragraphs 3.1.1 through 3.1.3 have been tested and found to meet the requirements of the applicable sections of this specification. The material certifications shall be stored by the Contractor for the life of the contract.

3.7.3 Material Inspection and Receiving Report (DHS Form 700). A form DHS-700 shall be used as a certification of product quality assurance, as a packing list, and as a certification of acceptance. The Contractor shall prepare a separate DHS-700 for each shipping lot. Prior to shipment, the DHS-700 must be signed by the COTR.

4. VERIFICATION

4.1 General. The Contractor's quality assurance program shall meet the requirements of ASQ Q9001. However, the Contractor does not have to be Q9001 certified.

4.2 Classification of Inspections. The inspection requirements specified herein are classified as follows:

a. First article inspection (paragraph 4.3)
b. Contractor production inspection (paragraph 4.4)
c. Coast Guard production inspection (paragraph 4.5)

4.3. First Article Inspection. When first article samples are required, a first article inspection shall be performed by the Contractor and at the Contractor’s facility. The first articles shall meet the requirements of this specification and shall pass all the tests and inspections listed in paragraph 4.6.

4.3.1 First Article Tests and Inspections Notification. The Contractor shall notify the Contracting Officer in writing at least 7 calendar days prior to the scheduled commencement of any inspections and tests required by this specification.

4.3.2 Waiver of First Article Requirements. The Contracting Officer reserves the right to waive all or part of the first article requirements specified herein.

4.3.3 Rejection Criteria. The results of the first article inspection will be reviewed by the Contracting Officer to determine compliance with the requirements of this specification. Failure of any of the tests or inspections described herein will be cause for rejection of the first article. If the first article is rejected, the Contractor will be notified in writing by the Contracting Officer and allowed 14 calendar days to fix or resubmit a new first article. Repair or replacement of the first article shall be by the Contractor at the Contractor's expense.

4.3.4 Authorization to Proceed. Upon successful completion of the first article inspection, the Contracting Officer will provide the Contractor with written authorization to begin fabricating production quantities.

4.3.5 Standardization. Materials, parts, design, and fabrication methods used in the production quantities shall be identical to those used in the first articles, unless otherwise authorized in writing by the Contracting Officer.

4.4 Contractor Production Inspection. The tests and inspections required by this specification are not intended to supplant any controls, examinations, inspections, or tests normally employed by the Contractor to assure product quality. The Contractor shall perform the tests and inspections specified in paragraph 4.6 to ensure conformance to this specification. The Contractor shall provide space, personnel, and test equipment to conduct all inspection and test requirements.

4.5 Coast Guard Production Inspection. The Coast Guard reserves the right to observe, verify, or perform the tests and inspections outlined in paragraph 4.6.

4.6 Tests and Inspections. The following tests and inspections shall be conducted for each first article unit and subsequent production units:

a. Visual inspection
b. Weld inspection
c. Paint inspection
c. Documentation review

4.6.1 Visual Inspection. Each item shall be visually inspected for quality of workmanship and conformance to this specification and the drawing. The inspection shall include checks of dimensional conformance, mechanical fit, alignment of parts, and marking.

4.6.2 Weld Inspection. All welds shall be visually inspected for quality in accordance with section 6 of AWS D1.1/D1.1M.

4.6.3 Paint Inspection. The Contractor shall provide written proof that each item was cleaned and painted in accordance with paragraphs 3.6 and 3.7. The Contractor shall check the millage at a minimum of six different locations.

4.6.4 Documentation Review. The documentation required by paragraph 3.8 shall be reviewed for conformance with this specification and provided to the COTR upon request.

4.7 Rejection for Defects. The Coast Guard will reject all items which do not conform to the requirements of this specification. Repair or replacement of the rejected items shall be by the Contractor at the Contractor's expense. All rejected items shall be resubmitted for inspection only when they conform to the requirements of this specification. Resubmitted items shall be identified as such, and shall be kept separate from new items. If defective items are found, no further items will be accepted by the Coast Guard until the Contractor has demonstrated that the defects have been corrected and that the cause of the defects has been eliminated from the production process.

5. PACKAGING.

5.1 Each item is to be packaged in accordance with ASTM D 3951. Associated hardware (items 17 and 18 of drawing 52100-120998 page 1, or 29 and 30 of drawing 52100-120998 page 2) are to be packaged in a sealed plastic bag and inserted into the shipping container.

5.2 Each item is to be individually marked in accordance with MIL-STD-129.

5.3 Bar coding in accordance with AIM BC 1 is required.

Specification P-420-0335 October 2011

SPECIFICATION NO. 362G - FABRICATION OF BUOY BELL AND GONG STANDS

MARCH 2000

Prepared by Reviewed by:

SIGNATURE ON FILESIGNATURE ON FILE
_____________________________________________________________
Mr. Sean McEvoyMr. Wayne Danzik
Buoy & Structures TeamBuoy & Structures Team Leader, Acting

Approved: Date:

SIGNATURE ON FILE3/6/00
___________________________________________________

Mr. Harley Cleveland Chief, Ocean Engineering Division, Acting

File details come from the government source that posted it. Updated .