This document contains frequently asked questions (FAQs) related to solicitation number HR001123S0047 from the Defense Advanced Research Projects Agency (DARPA) for the Advanced Sources for Single-event Effects Radiation Testing (ASSERT) program. The FAQs provide clarification on a range of topics including the types of technical approaches and award instruments that may be proposed, requirements for beam characteristics such as particle type, energy, and pulse width, guidelines for testing different device types and electronics, processes for submitting abstracts and full proposals, and recommendations for describing planned transition partnerships. Key details specified are that proposals can feature a single technical approach, award instruments will depend on the type of entity, analog transients of up to 2 GHz should be measurable, shielding volume is included, constant or peaked linear energy transfer of 5 MeV/mg are desired, and transition plans should be outlined in full proposals.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
[Type here] HR001123S0047 FAQs [Type here]
HR001123S0047
Advanced Sources for Single-event Effects Radiation Testing (ASSERT)
Frequently Asked Questions (FAQs) as of 07/21/2023
Q14: Can we include more than one technical approach in a proposal?
A14: Proposals should feature a single technical approach that is deemed by the proposer to be most responsive to the BAA. Technical approaches that are sufficiently distinct can be submitted as separate proposals.
Q13: Can you describe the effect of type of proposer (academic, small business, etc.) on the allowable award instruments?
A13: To a large extent, the appropriate award instrument is dictated by the type of entity the prime contractor is (i.e., traditional defense contractor, non-traditional defense contractor, university, etc.). Therefore, when pursuing teaming approaches, the team first needs to determine who the prime will be, as this will go a long way toward determining the award instrument type to request. Cooperative agreements would only be appropriate for a university serving as a prime. For traditional defense contractors, the appropriate award instrument typically is a procurement contract. Other Transactions were developed to target non-traditional defense contractors who might otherwise not be willing to do business with the Government, and therefore these are more commercial-like instruments and often are appropriate for non-traditional defense contractors.
Q12: Can you describe the magnitude and duration of analog transients that will be measured?
A12: Proposals should address a broad family of effects. ASSERT is not a program to develop novel diagnostics and there is currently no intent to characterize ultrafast phenomena. An oscilloscope with a 2 GHz sample speed should be adequate.
Q11: Does ASSERT seek to test deep nodes and quantum platforms?
A11: The intent is for ASSERT sources to be applicable to a wide range of device types. A tool with maximum utility for future DoD applications is desirable.
Q10: Is shielding included in the overall volume requirement?
A10: Yes, requisite shielding should be included in the system volume.
Q9: For the linear energy transfer (LET) requirement, is it constant LET of 5mm or a peak LET achieved at a range of depth?
A9: The metrics refer to LET achieved at range. Proposed approaches that use a highly peaked LET distribution to meet program metrics should justify how testing and validation can be realistically achieved using the proposed beam.
Q8: Is there a requirement on the duration of a single test?
[Type here] HR001123S0047 FAQs [Type here]
A8: There is no requirement for the duration of a single test. Test durations will vary by application. The intent is to produce a tool can be used to study single devices as well as rapidly test integrated electronics.
Q7: Should we constrain incidence to normal?
A7: The ability to vary the angle of incidence is desired.
Q6: Does the pulse width of 2 ps refer to the charged particles that strike the device?
A6: The pulse width requirement refers to the amount of time necessary to put charge into the material, per strike.
Q5: Can you provide a priority on particle beam type?
A5: No, this decision should be part of the proposed solution. All proposed approaches should be responsive to the program metrics and requirements and contain sufficient details to support technical feasibility.
Q4: Are there further details on what electronics will be tested and provided?
A4: Electronics for testing will be COTS; further details will be provided at program kickoff.
There is currently no plan to provide devices as Government Furnished Equipment.
Q3: What is the timeframe for receiving feedback on abstracts?
A3: Responses are expected to be provided within 15 days of the abstract submission deadline.
Q2: Can multiple abstracts be submitted for different ideas/paths?
A2: Yes.
Q1: If a team has a lead on transition partners, when, where, and how should this be discussed?
A1: Detail any existing or planned transition partner engagements in the proposal. See BAA, Part II, Sec. V, Subsection A: Evaluation Criteria: “The evaluation will consider the proposer’s plans and capabilities to transition proposed technologies to U.S. national security applications and to U.S. industry.”