HPSD DB RFP FINAL.pdf
PDF 14 MB Posted
- Attached to
- Design Build Services State and local contract opportunity
- Solicitation number
- RFP HEML 260000002235 5
- Issued by
- Saginaw County, Michigan
About this file
Summary of Design-Build RFP for Hemlock Public School District
This Request for Proposals (RFP) from Hemlock Public School District in Michigan solicits comprehensive Design-Build services for the expansion and potential renovation of Hemlock Elementary School/Early Childhood Center. The District is seeking a qualified Design-Builder to provide complete design and construction services from conceptual design through project close-out, with work anticipated to commence the week of August 24, 2026. Phase I of the project involves approximately 3,000 square feet of new construction, funded by a $1 million USDA grant, including a secure main corridor connection, office and student support spaces, two to three new early childhood classrooms with attached restrooms, student restrooms, and a redesigned parent drop-off and pick-up loop. Phase II, contingent upon voter approval of a November 2026 non-qualified bond of approximately $14 million, would add an additional 9,000 square feet with additional classrooms, staff facilities, office and intervention spaces, and flexible learning environments. The mandatory pre-proposal meeting is scheduled for June 30, 2026 at 10:30 AM EST at the PW Fieldhouse, with optional site walk-throughs immediately following. Proposals are due electronically by July 15, 2026 at 12:00 PM EST to Denise Dowdell, Director of Business Operations and Human Resources. Interviews are anticipated for July 28, 2026, with final Board approval for Design-Builder selection scheduled for the August 12 regular Board meeting. Construction is expected to begin in Spring 2027, with substantial completion targeted for Summer 2028 and opening for the 2028-2029 school year.
The Design-Builder will be compensated based on a Guaranteed Maximum Price (GMP) to be established during the design and bidding phases, with proposers required to submit fee percentages for design services, general conditions, contractor overhead and profit, and change order markups for both Phase I and Phase II work. The District anticipates allocating most of the $1 million USDA grant to construction costs with soft costs from a separate funding source, and upon successful bond passage, $2 million to $3 million in additional funds will support expanded scope. All work must comply with Michigan prevailing wage requirements, and the Design-Builder must competitively bid all trade categories to satisfy public bidding requirements under MCL 380.1267 and MCL 380.1274. The contract will utilize a modified AIA A141-2014 Standard Form of Agreement. Proposers must provide sworn and notarized familial relationship disclosure statements and Iran Economic Sanctions Act compliance certifications. Required insurance includes Commercial General Liability ($3 million aggregate/$1 million per occurrence), Professional Liability ($1 million), Workers' Compensation ($100,000), and Automobile Liability ($1 million). Background checks and fingerprinting are mandatory for Design-Builder personnel who will regularly work on school property.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| HDPS DB RFP ADDM #1 corrected.pdf | ||
| Design Build Services RFP Addendum #3.pdf | ||
| HDPS DB RFP ADDM #2_FINAL.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Issue Date: June 17, 2026
Proposal Due Date: July 15, 2026
HEMLOCK, MICHIGAN 48626
HEMLOCK PUBLIC SCHOOL DISTRICT
cv
Hemlock Public School District
Request for Proposals for
Design-Build Services
ADVERTISEMENT FOR PROPOSAL
PROJECT: Hemlock Public School District
Hemlock Elementary School/Early Childhood Center Expansion and Renovation
OWNER: Hemlock Public School District
1095 N Hemlock Rd
PO Box 260
Hemlock, MI 48626
SCOPE OF WORK:
Hemlock Public School District (the “District” or “Owner”) is soliciting proposals from firms to provide comprehensive Design-Build services for the expansion and potential renovation of Hemlock Elementary
School/Early Childhood Center. This work will be completed utilizing approximately $1M in United States
Department of Agriculture (USDA) funding. Services will include complete design and construction, from conceptual design through close-out. It is anticipated that as much of the $1M grant will be allocated to the cost of work, with soft costs coming out of a separate funding source.
In addition, the District will be pursuing a non-qualified bond in November 2026 for approximately $14M. Upon voter approval, between $2M and $3M in additional funding will be put towards extended work scope at
Hemlock Elementary School. Upon successful passage of the bond, it is the District’s intent to continue with the chosen Design-Build team for the full implementation of the bond program, from pre-design through construction, Owner move-in and close-out.
DUE DATE:
Proposals shall be submitted electronically to Denise Dowdell, Director of Business Operations and Human
Resources, at dowdell@hemlockps.com no later than July 15 at 12:00 pm EST with the e-mail subject line “HPSD
Design-Build RFP Response”. The District will not consider or accept proposals received after the specified date and time.
REQUIRED DISCLOSURE STATEMENT:
The bid shall be accompanied by a sworn and notarized statement disclosing any familial relationship that exists between the owner or any employee of the bidder and any member of Hemlock Public School District Board of
Education or Hemlock Public School District Superintendent. The bid shall also be accompanied by a sworn and notarized statement disclosing whether the bidder is an Iran Linked Business in compliance with PA 517 of 2012.
The Board shall not accept a bid that does not include these sworn and notarized disclosure items.
RIGHTS RESERVED BY THE OWNER:
Contract award will be with the Design-Builder whose proposal Hemlock Public School District determines to be in their best interest. The District reserves the right to waive any irregularities, reject any or all bids, or accept any bid when in the opinion of the Board such action will best serve the District’s interest. The District reserves the right to waive any irregularity in the RFP process or any proposal. The District reserves the right to request additional information from any or all proposers, including an oral interview to discuss, clarify, and answer any questions regarding the proposal.
HEMLOCK, MICHIGAN 48626
HEMLOCK PUBLIC SCHOOL DISTRICT
cv
SECTION I: PROJECT OVERVIEW
PURPOSE:
The District desires to utilize recent Michigan Design-Build legislation to reimagine school construction delivery and is seeking a qualified Design-Build partner to support this innovative turnkey approach from concept through completion.
BACKGROUND INFORMATION/PROJECT SCOPE:
Hemlock Public School District is a general powers public school district located in Saginaw County, Michigan serving approximately 1,200 K-12 students. The District is governed by an elected seven-member Board of
Education.
The District has secured a $1M grant from the USDA to fund improvements to Hemlock Elementary School/Early
Childhood Center, located at 200 Wilson Street in Hemlock, Michigan. Work would include the expansion and possible renovation of the southeast wing of the school, adding approximately 3,000 s.f. of building space, and would encompass the following programmatic elements:
• Secure main corridor connection
• Office and student support space
• Two to three new ECC classrooms with attached toilet rooms
• Student toilet rooms
• Re-worked parent drop-off and pick-up loop
This work scope is being thought of as Phase I, with a potential second phase if voters approve the bond in the
November election. Phase II would utilize $2M to $3M of the allocated bond dollars to expand the elementary school building by another 9,000 s.f., to include:
• Additional classrooms
• Staff toilet rooms
• Office and intervention spaces
• Flexible learning environments
The overall goal of this expansion is to relocate the early childhood programming to the new wing, to make space to bring 1st grade back to this building. 1st grade classrooms would be relocated to those left by the ECC.
A very conceptual plan showing the work scope is included as Appendix ‘A’—the Design-Build team will be charged with working through plan concepts with the District to align their Phase I and II wish list(s) with the allocated budget(s). Because work for Phase I will begin prior to knowing the outcome of the bond vote, the team will need to anticipate the Phase II future growth as part of the initial conceptual layout for the school.
The District has engaged Veridus Advisors to serve as its Owner’s Representative. Rounding out the current project team are PFM and Thrun as financial advisor and legal counsel, respectively. The chosen Design-Build firm will work closely with this team throughout the course of the project (and into Phase II).
DELIVERY MODEL:
The District intends to utilize a Design-Build delivery method for implementation of the bond program.
PROJECT BUDGET:
The initial project budget is approximately $1M, funded through a grant provided by the USDA. Upon successful passage of the November bond, another $2M to $3M will be allocated to expand the work scope, which will be balanced with the desired work outlined in the larger bond program.
DESIGN-BUILD GMP:
While the District is not requesting a GMP from potential proposers at this time, contracts will eventually be based on same. For purposes of the proposal responses, the District would like to better understand each proposer’s fee structure. To this end, the following is being requested:
• For phase I scope of work:
o A fee range for design services (expressed as a % of the cost of work). Include all disciplines that will be required to complete the work.
o A fee range for general conditions along with a list of what is included in same (expressed as a % of the cost of work) o A fee range for contractor overhead and profit (OHP) (expressed as a % of the cost of work) o A % fee for contractor mark-up for changes to the work
• For phase II scope of work (including Hemlock Elementary/ECC addition/improvements as well as all approved bond scope):
o A fee range for design services (expressed as a % of the cost of work). Include all disciplines that will be required to complete the work.
o A fee range for general conditions along with a list of what is included in same (expressed as a % of the cost of work) o A fee range for contractor overhead and profit (OHP) (expressed as a % of the cost of work) o A % fee for contractor mark-up for changes to the work
As the chosen Design-Build team develops project costs and finalizes the project’s fixed-fee GMP, it is expected that they will reflect fees in the percentage ranges noted above or as negotiated with the District.
NOTE that a GMP for phase I will be established first. Upon successful passage of the bond, the chosen Design-
Build team will establish a second GMP for the additional scope of the Hemlock Elementary/Early Childhood
Center work. One or more GMPs will be established for the full bond scope as well and may be delivered in multiple bid packages/phases. This will be determined by the team upon voter approval in November.
It is also required that the chosen Design-Builder will competitively bid all trade categories for all work that will be completed on campus in order to meet public bidding requirements and assure that the District is getting the best pricing for each.
The District intends to enter into a contract with the chosen Design-Builder immediately upon the start of work. A fee for design and pre-construction services will be negotiated at the outset and reflected in the initial
Agreement. Once the GMP is established after the design and bidding phases, the Agreement will be amended to reflect the final scope and agreed-upon GMP.
SECTION II: PRELIMINARY SCHEDULE
ANTICIPATED PROPOSAL TIMELINE:
• RFP Issued: June 17
• Mandatory Pre-Proposal Meeting: June 30 at 10:30 am EST
• Optional on-site walk-through of phase I work scope: June 30, following the pre-proposal meeting
• Deadline to submit clarifying questions: July 6 at 12:00 pm EST o Send questions to Denise Dowdell, Director of Business Operations and Human Resources, dowdell@hemlockps.com
• Responses to questions to be posted: July 7 by end of day
• Proposal Due Date: July 15 at 12:00 pm EST
• Notification of Interviews: July 20
• Interviews: July 28 between 8:00 am and 5:00 pm EST
• Final Decision by Selection Committee: July 31
• Board Meeting for Design-Builder Selection Approval: August 12
The District plans to make a recommendation to the Board of Education at the August regular meeting and will engage the chosen Design-Build team by the end of that week.
MANDATORY PRE-PROPOSAL MEETING / OPTIONAL SITE WALK-THROUGH:
A mandatory pre-proposal meeting will be held on Tuesday, June 30 at 10:30 am EST in the PW Fieldhouse, located at 1029 N Hemlock Rd., Hemlock, MI 48626. This meeting will be both virtual and in person. Any proposer wishing to bid on the project must be in attendance, either online or in person. There will be a brief presentation by the Ownership team, and an opportunity for questions during this time.
An optional site walk-through will be conducted directly after the pre-proposal meeting for those teams that wish to see the elementary school in person and review the scope with the Ownership team. Parking will be available in the parking lot east of Hemlock Elementary School/Early Childhood Center. Photos will be allowed.
Responses to questions received at the pre-proposal meeting and walk-through will be formally answered via addendum and will be issued to all firms that participate in the former by the date noted in the timeline above.
INTERVIEW:
The District may invite one or more firms for an interview. Interviews will take place between 8:00 am and 5:00 pm EST on the date indicated in the timeline above. Please plan to include all team members that will be assigned to the project.
ANTICIPATED PROJECT TIMELINE:
Work on Phase I is expected to begin immediately upon Board approval. The following target dates have been established:
• Kick off meeting with entire team: week of August 24, 2026
• Design and Bidding Phases: August 2026 to Spring 2027
• Construction Begins: Spring 2027
• Substantial Completion: Summer 2028
• Open Fall 2028 for 2028-2029 school year
SECTION III: SCOPE OF SERVICES
Hemlock Public School District is looking to contract with a qualified firm to provide Design-Build services throughout all phases of planning, design, construction and closeout services of the project.
While not all services will be required for Phase I, proposers should be able to develop a full team to address all potential aspects of the design work for Phase II, including architecture, interior design, structural, M/E/P/FP, civil and landscape services, technology, security and furniture. A preliminary scoping document is included herein as Appendix ‘B’. Please address your ability to provide these services in-house or with trusted consultants, for a full-service approach to the potential work scope.
It is anticipated that a modified version of the AIA A141-2024 Standard Form of Agreement Between Owner and
Design-Builder will be utilized for both phases of the project. The 2014 version of this contract has been approved by the District’s legal counsel as well as the USDA for use on previous projects on campus. A copy of this draft document is included as Appendix ‘C’. The District’s attorney is currently working with the USDA on the newer version of the contract, which will go into effect on August 1, 2026. This will be shared with proposers if the review process is completed ahead of the last addendum date.
PHASE 1 – HEMLOCK ELEMENTARY/EARLY CHILDHOOD CENTER:
It is expected that the selected Design-Builder will provide a single point of responsibility for both the design and construction of the project through all of the typical phases of both. Work scope will include, but is not limited to the following:
Design
Work with the Ownership team to establish project goals, beginning with programming and conceptual design, preparation of drawings and specifications, coordination with consultants, regulatory agencies, and stakeholders. Provide continued monitoring of the design process to assure alignment with scope, schedule and budget objectives.
Schedule & Budget Planning
Collaborate with the District, Owner’s Representative, legal counsel and financial advisors to develop and confirm the project schedule, assist in the development of a total project budget inclusive of construction and non-construction (soft) costs, provide cost estimates at each phase of design to assure continued alignment with same and ultimately, establish a construction GMP.
Bidding & Construction
Lead the bidding process, procure and manage subcontractors; obtain appropriate permits and approvals; provide construction oversight and coordinate field activities; manage project close out.
Project Oversight & Advisory Support
Lead and document design and construction meetings; provide regular updates to the District’s Building
Committee and Board; work with the District to coordinate any Owner-provided vendors during the design and construction process.
PHASE 2 – POST-BOND IMPLEMENTATION SERVICES:
Contingent upon successful bond passage, the District intends to continue engagement with the selected
Design-Builder for full implementation services of the bond scope. Services will be similar to those outlined above for Phase I and will be contracted separately.
SECTION IV: PROPOSAL REQUIREMENTS
Please provide the following information, keeping simplicity top of mind as you prepare your response:
1. Cover letter – 1 page limit
a. Please include name and address of submitting firm, along with phone and e-mail address for primary contact person.
b. Proposals should be signed by an official authorized to bind the Professional to its provisions.
2. Firm Background – 1 page limit
3. Project Understanding – 1 page limit
a. A summary of your understanding of the full scope of the project and how your team plans to address the main issues outlined.
4. Similar Project Experience (no more than 5 project examples) – 5 page limit
a. Demonstrate relevant experience and qualifications for the proposed scope of work, including the Design-Build delivery model and K-12 experience.
b. Include references for each project.
c. Indicate whether any of the proposed team members were involved and if so, their role.
5. Brief List of Services – 2 page limit
a. As part of this list, as noted in Section III above, address your team’s ability to provide all of the anticipated consultant services for both Phase I and II.
6. Describe Project Approach – 1 page limit
a. Provide a proposed work plan and timeline showing how your team will meet the target dates outlined above, based on a start date the week of August 24.
7. Team Organization Chart – 1 page limit
8. Resumes of Key Personnel – 1 page maximum per person
9. Fee Proposal – no page limit
a. Provide fee percentages as outlined in the Design-Build GMP paragraph in Section I above.
10. Acknowledgements – 1 page limit
a. Please acknowledge any addenda in your response.
11. Please provide sample Certificate of Insurance showing current insurance coverages – no page limit
12. Required forms as outlined in Section VIII below.
SECTION V: SELECTION PROCESS
SELECTION CRITERIA:
Proposals will be evaluated based on experience and qualifications of the firm and personnel, cost-effectiveness of the proposal, project approach/work plan and understanding of the project and scope of work.
SECTION VI: INSTRUCTIONS
1. RFP CLARIFICATIONS
Any and all clarification questions pertaining to this RFP must be submitted in writing via dowdell@hemlockps.com and will be answered and posted so all bidders are notified. Bidders who do not comply may be disqualified from the proposing process. It is the bidder’s responsibility to check for any changes, posted questions and answers, and/or addenda to this solicitation. Bidders are responsible for checking this website prior to proposal submission. Failure to acknowledge all addenda may result in rejection of your proposal as being non-responsive.
2. BUILDING CLOSURE
In the event the submittal of additional paper documentation is required to be delivered to Hemlock
Public School District Administration Building, and the District, and/or district building, is closed due to unforeseen circumstances on the day proposals are due, proposals will be due at the same time on the next day that the District and/or district building is open.
3. COMMUNICATION WITH HEMLOCK PUBLIC SCHOOL DISTRICT STAFF
Any and all communication shall go through the Director of Business Operations and Human Resources. If a bidder works with Hemlock Public School District on other projects and must communicate with an individual that is involved with this RFP, the bidder must contact the Director of Business Operations and
Human Resources for approval. Failure to comply with this may be grounds for disqualification.
4. EXCEPTIONS
Proposals must meet or exceed all requested services detailed herein. Any and all deviations must be clearly detailed otherwise, it will be considered that items offered are in strict compliance with the RFP, and the successful Design-Builder will be held responsible thereof.
5. WITHDRAWAL OF PROPOSALS
Any bidder may withdraw their proposal at any time prior to the opening of proposals. All proposals shall remain firm for acceptance for a period of 180 (one hundred eighty) days beyond the proposal opening.
The awarded Design-Builder shall honor the proposal pricing for a period of one hundred eighty (180) days.
6. BIDDER QUESTIONS
Each bidder is required to respond to the questions where specified. If you would like to attach documentation to support your other answers, please do so. Responses should be concise and stand on their own. The quality of the response to the RFP will be viewed as an example of the bidder’s capabilities.
7. PROPOSAL COSTS
All costs incurred in preparing the proposal, providing reasonably requested or required presentations, or in negotiating applicable contracts shall be the sole responsibility of the proposer. Hemlock Public School
District shall not be responsible for any cost or expense the bidder incurs during the preparation or award of the proposal.
8. PROPOSAL ACCEPTANCE/REJECTION
The Board of Education reserves the right to accept any item in the proposal; to accept or reject any or all proposals; to waive any informality; or for reasons of establishing uniformity, to award the contract to other than the lowest bidder in the sole discretion of the district.
9. INTEREST
No member of Hemlock Public School District Board of Education, Hemlock, MI or any officer, employee or person whose salary is payable in whole or in part from the treasury of said Board of Education is directly or indirectly interested in this proposal or in the supplies, materials, equipment, work, services or any portion of the profits thereof to which it relates.
10. GIFTS, GRATUITIES OR KICKBACKS
Acceptance and the offering of gifts, gratuities or kickbacks from bidders or the Design-Builder to District employees and their family members or the members of the Board of Education are prohibited.
11. VERBAL REPRESENTATIONS
Proposals must contain in writing all the terms and conditions of the offer being made. Verbal representations made before or after proposals are submitted will not be considered unless they are made in answer to questions asked by the District or its representatives and are followed up in writing.
12. SOLE BIDDER
If only one proposal is received in response to the RFP, a detailed cost proposal, if requested by Hemlock
Public School District, will be required of the single bidder. A cost/price analysis and evaluation and/or audit shall be performed of the cost proposal in order to determine if the price is fair and reasonable.
13. BIDDER INTERVIEWS AND DEMONSTRATIONS
Hemlock Public School District may, at its option, elect to conduct interviews and/or demonstrations with selected bidders, or request to visit the bidder’s site for bidders that are under active consideration.
Hemlock Public School District is not required to hold such presentations and is not obligated to provide all bidders with such an opportunity.
14. MISREPRESENTATIONS
If it is discovered, prior to an award, that a proposal contains false, misleading, or otherwise inaccurate information, the proposal will immediately be disqualified. If it is discovered, after a contract has been executed, that the Design-Builder had provided false, misleading, or otherwise inaccurate information, the contract may be terminated.
15. PROPRIETARY OR CONFIDENTIAL INFORMATION
Any proprietary or confidential material (financial statements, etc.) that was submitted by a bidder and is clearly marked as such will be returned upon request. Marking the entire proposal as confidential will not be accepted or honored. Remaining non-confidential material in the proposal, including proposed costs and compensation, will be maintained for the official files and will be subject to the Freedom of
Information Act, MCL 15.231 et. seq.
16. NOTIFICATION OF AWARD
Upon approval by the Board of Education, Hemlock Public School District will notify awarded bidder.
17. RELEASE
Each proposer submitting its proposal releases the District from any and all claims arising out of, and related to, the RFP process and selection of the Design-Builder.
SECTION VII: GENERAL TERMS & CONDITIONS
1. CONTRACT
The contract will be in the form attached as Attachment B (the “Contract”), except that the District may elect in its sole discretion to further negotiate the terms of same with bidder. The bidder shall be deemed to agree with the attached document in its entirety, except and to the extent the bidder specifically objects in writing to any provision therein and attaches the objection(s) as a separate document to its response to this RFP, along with a proposed alternative. The absence of any such written objection shall constitute an agreement to all proposed Contract terms. Notwithstanding anything herein to the contrary, the District shall have the ability, in its sole discretion, to negotiate any term of the Contract. The award of the Contract shall be contingent upon the successful negotiation of any such issues identified by the
District.
2. GRANT/BOND PROGRAM
All proposers are placed on notice that the scope of the USDA grant project and 2026 bond and may be revised, expanded or reduced based on voter-approval, market conditions, received bids, value engineering, schedule changes, and other similar variables. In the event that the 2026 bond program is not approved by voters, the District may no longer have a need for Design-Builder services. Accordingly, the District reserves the right to rescind this RFP, cancel any award, and terminate any Contract entered into with a proposer in the event this occurs.
3. CONFIDENTIALITY
The proposers must ensure that suitable measures will be taken to assure the confidentiality of Hemlock
Public School District and its member schools’ data.
4. FREEDOM OF INFORMATION ACT
The proposals and supporting materials become the property of Hemlock Public School District and are subject to public access according to the Freedom of Information Act, MCL 15.231 et. Seq.
5. NEWS RELEASES
Proposers will at no time make any news or advertising releases pertaining to the proposal document for any purpose without the prior approval of, and in coordination with, Hemlock Public School District.
6. SMOKING/ALCOHOL ON SCHOOL PREMISES
Smoking, the use of tobacco products or alcohol shall not be permitted on the school property at any time.
7. INSURANCE REQUIREMENTS TO BE MET BY THE SUCCESSFUL DESIGN-BUILDER
Design-Builder agrees, at its sole cost and expense, to purchase, prior to the commencement of services, and maintain the following insurance coverages in the minimum amounts indicated for the entire duration of the contract. All coverage shall be with insurance carriers licensed and admitted to do business in
Michigan and acceptable to Hemlock Public School District.
a. Commercial General Liability Insurance with limits of three million dollars ($3,000,000) aggregate and not less than one million dollars ($1,000,000) per occurrence for bodily injury, death, and property damage, including personal injury, contractual liability, independent contractors, broad-form property damage, and products and completed operations coverage;
b. Professional Liability Insurance (Errors & Omissions) of one million dollars ($1,000,000) each occurrence;
c. Workers’ Compensation including Employer’s Liability Coverage of one hundred thousand dollars
($100,000) per occurrence for all employees engaged in services or operations under the Contract in accordance with state law;
d. Automobile Liability with limits of one million dollars ($1,000,000) each occurrence combined single limit of liability for bodily injury, death, and property damage, including owned and non-owned automobile coverages, as applicable.
The required coverage as described above shall include an endorsement stating the following: “It is understood and agreed that thirty (30) days advance Notice of Cancellation, Non-Renewal, Reduction and/or Material change shall be sent to: Director of Business Operations and Human
Resources, Hemlock Public School District, PO Box 260, 1095 N Hemlock Rd., Hemlock, MI 48626. If such insurance is not in force, Hemlock Public School District may, at its option, terminate and cancel the contract.
8. BACKGROUND CHECKS
The Design-Builder, and any team members who will regularly and continuously work at the District, must present themselves for fingerprinting upon award of the Contract so that Hemlock Public School District is able to request from the Criminal Records Division of the Department of State Police (1) a criminal history check and (2) a criminal records check through the Federal Bureau of Investigation and receive from the
Department of State Police reports concerning the same. Neither the Design-Builder nor sub-contractor thereof of any degree shall assign any individual, and Hemlock Public School District shall not allow any individual, to regularly and continuously work under contract in any of its schools or in the schools of a constituent district that is being served by the Design-Builder pursuant to this Agreement if the reports on an individual's criminal history or criminal records check have not been received or if those checks would disclose or do disclose that individual has been convicted of a "listed offense" as that term is defined in
Section 2 of the Sex Offenders Registration Act, 1994 PA 295, as amended, or which disclose that individual has been convicted of a felony other than a "listed offense" unless the Superintendent and the Board of
Hemlock Public School District each specifically approve of the work assignment in writing.
Any personnel of the Design-Builder or of the sub-contractors thereof of any degree that have been charged with any of the referenced crimes referenced in 2006 PA 680 shall immediately report that circumstance to Hemlock Public School District Superintendent and shall not be permitted to work in any of the District’s schools or schools of the constituent districts served pursuant to the Contract during the pendency of the prosecution associated with such charge(s). Hemlock Public School District reserves the right to refuse the Design-Builder ‘s assignment of any individual, agent or employee of the Design-Builder or subcontracted personnel of any degree to render services under the Contract where the criminal history of that individual (including any pending charges) indicate, in Hemlock Public School District’ judgment, unfitness to perform services under the Contract. Violation of the above by the Design-Builder or a sub-contractor thereof shall be a basis for immediate termination of the Contract. The Design-Builder shall require language similar to the above in all of its agreements and/or contracts with its consultants, sub-contractors, suppliers and materialmen of any degree.
9. IRAN ECONOMIC SANCTIONS ACT
Public Act 517 of 2012, commonly known as the "Iran Economic Sanctions Act" (the "Act"). The Act provides that beginning April 1, 2013; an "Iran Linked Business" is not eligible to submit a proposal on a request for proposal with a "public entity" (Hemlock Public School District). The Act also requires that a person that submits a proposal in response to Hemlock Public School District’ request for proposal must certify to the public entity that it is not an Iran Linked Business. This requirement applies to all requests for proposals issued by Hemlock Public School District, and not just to construction projects.
The Act defines an Iran Linked Business as:
a. A person engaging in investment activities in the energy sector of Iran, including a person that provides oil or liquefied natural gas tankers or products used to construct or maintain pipelines used to transport oil or liquefied natural gas for the energy sector of Iran;
b. A financial institution that extends credit to another person, if that person will use the credit to engage in investment activities in the energy sector of Iran.
If Hemlock Public School District determines, using credible information available to the public, that a person or entity has submitted a false certification, Hemlock Public School District must provide written notice to the person or entity of its determination and of its intent not to enter into or renew the contract.
The notice must include information on how to contest the determination. The notice must also specify that the individual or entity may become eligible for future contracts with the public entity if the activities that caused it to be an Iran Linked Business are ceased.
SECTION VIII: REQUIRED FORMS
Proposing firms shall complete the forms on the following pages:
Notarized Familial Disclosure Statement
Iran Economic Sanctions
NOTARIZED FAMILIAL DISCLOSURE STATEMENT
(Return completed and notarized form with bid)
Pursuant to MCL 380.1267, a sworn and notarized statement disclosing any familial relationship that exists between the owner or any employee of the bidder and any member of Hemlock Public School District Board or Hemlock Public School District Superintendent shall be accompanied with the bid. Bids without this disclosure statement will not be accepted. The members of Hemlock Public School District Board are: Katherine
Ellison, Matt Wesener, Jamie Rivette, David Messing, Lindsay Kerry, Kaleigh Berent and Kimberly Hoeppner.
Hemlock Public School District Superintendent is Don Killingbeck.
The following are the familial relationship(s):
Owner/Employee Name Related to: Relationship
1.
2.
3.
4.
Attach additional pages if necessary to disclose all familial relationships.
□ There is no familial relationship that exists between the owner or any employee of the bidder and any member of Hemlock Public School District Board, or Hemlock Public School District
Superintendent.
The undersigned, the owner or authorized representative of bidder (insert name) does hereby represent and warrant that the disclosure statements herein contained are true.
Print Name Signature of Bidder
Representative Title
STATE OF MICHIGAN
COUNTY OF
The foregoing instrument was acknowledged before me on the day of , 20 , by
Notary Public-Signature
Notary Public-Printed Name
My commission expires: / / Acting in the
County of:
IRAN ECONOMIC SANCTIONS
The undersigned, the owner or authorized officer of the below-named Design-Builder (the
“Design-Builder”), pursuant to the compliance certification requirement provided in the
Hemlock Public School District (the “School District”) Invitation For Proposal, hereby certifies, represents and warrants that the Design-Builder (including its officers, directors and employees) is not an “Iran linked business” within the meaning of the Iran Economic
Sanctions Act, Michigan Public Act No. 517 of 2012 (the “Act”), and that in the event the
Design-Builder is awarded a contract as a result of the aforementioned RFP, the Design-
Builder will not become an “Iran linked business” at any time during the course of performing any services under the contract.
The Design-Builder further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or 2 times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the School District’s investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to proposal on an Invitation for Proposal for three (3) years from the date it is determined that the person has submitted the false certification.
Name of Company
Signature of Authorized Representative
Name of Authorized Representative
Title of Authorized Representative
Date
CERTIFICATION OF COMPLIANCE - IRAN ECONOMIC SANCTIONS ACT
Michigan Public Act No. 517 of 2012
SECTION IX: APPENDICES
Appendix A: Conceptual Hemlock Elementary School/ECC Work Scope
Appendix B: Bond Scoping Summary
Appendix C: Draft AIA A141-2014
Appendix D: Hemlock Elementary School/ECC Floor Plan and Site Survey kjacobs Rectangle kjacobs Image kjacobs Rectangle kjacobs Text Box North Hemlock Rd.
kjacobs Rectangle kjacobs Text Box kjacobs Line kjacobs Text Box North Maple Rd.
kjacobs Text Box North Pine Rd.
kjacobs Text Box North Maple Rd.
kjacobs Text Box North Elm Rd.
kjacobs Text Box Wilson St.
kjacobs Text Box
OVERALL CAMPUS PLAN
kjacobs Ellipse kjacobs Text Box Approximate area designated for relocated Fordney Road School (Phase II) kjacobs Arrow kjacobs Text Box
APPENDIX A
kjacobs Image kjacobs Rectangle kjacobs Highlight kjacobs Arrow kjacobs Arrow kjacobs Arrow kjacobs Arrow kjacobs Arrow kjacobs Arrow kjacobs Arrow kjacobs Arrow kjacobs Arrow kjacobs Text Box New parent drop-off/pick-up loop kjacobs Polygon kjacobs Text Box Phase II (future) addition kjacobs Ellipse kjacobs Ellipse kjacobs Text Box Phase I addition kjacobs Arrow kjacobs Text Box hallway connector kjacobs Ellipse kjacobs Ellipse kjacobs Ellipse kjacobs Ellipse kjacobs Cloud kjacobs Text Box Phase II (future) parking expansion and relocation of Fordney Road School kjacobs Text Box Phase I (USDA grant):
~3,000 s.f. addition to southeast side of Hemlock Elementary School/Early Childhood Center + site work to augment the existing entry drive to create new parent pick-up and drop-off loop.
Phase II (future bond allocation):
Further addition (anticipated 9,000 s.f.) to southeast side of Hemlock Elementary School/Early Childhood Center + site work to replace parking spaces lost with addition. To maximize the available space for parking, RELOCATE the Fordney Road School to a site south of the administration building.
kjacobs Arrow kjacobs Text Box
HEMLOCK ELEMENTARY SCHOOL / EARLY CHILDHOOD CENTER
CONCEPTUAL SITE PLAN
kjacobs Text Box North Elm Rd.
kjacobs Text Box Wilson St.
kjacobs
North Hemlock Rd.
Proposed Future Capital Priorities
Hemlock Public School District
Building on progress. Planning for what is next.
A. Hemlock Elementary Expansion | Phase I Expand and renovate the southeast wing of Hemlock Elementary to the east as Phase I, utilizing approximately $1 million in United States Department of Agriculture (USDA) funding. The project would add approximately 3,000 square feet and include:
● Secure main corridor connection
● Parent drop-off and pick-up loop with bus/car turnaround
● Office and student support space
● Two to three classrooms with attached restrooms
A+ Alternative | Pending Tax-Neutral Bond Initiative Pending community support through a future tax-neutral bond initiative, expand an additional 9,000 square feet to include:
● Additional classrooms
● Student and staff restrooms
● Office and intervention spaces
● Flexible learning environments
This alternative would also include relocating the historic Fordney Road School to the area adjacent to the soccer parking lot across from the administration office, adding a basement, outdoor learning space, sidewalks, and site improvements.
B. K.C. Ling Elementary Expansion Expand the east side of K.C. Ling Elementary, turning south and architecturally aligning with the recent gymnasium addition. Potential components include:
● Student and public restrooms
● Four or more office/support spaces
● Open, flexible multipurpose learning area for lunch space for approximately 65 students
● Six or more additional classrooms
An alternative would evaluate reconfiguring the current cafeteria and other spaces to maximize efficiency.
C. Campus Outdoor Learning and Recreation Corridor Reimagine the shared outdoor space between K.C. Ling and the middle school to create a connected, student-centered activity corridor, including:
● Enhanced outdoor gathering and learning spaces
● New basketball and pickleball courts
● Improved soccer field amenities
● Renovated kickball/Little League field
● Safe pedestrian walkways connecting both campuses kjacobs Text Box
APPENDIX B
kjacobs
(including but not limited to the following)
D. Parking, Traffic Flow, and Site Infrastructure Continue improving district-wide infrastructure through:
● Expanded parking near soccer, baseball, and softball facilities
● Creative infill parking opportunities across campus
● Internal and external sidewalk improvements
● Enhanced traffic flow, lighting, and accessibility upgrades
E. Safety and Security | Priority One Continue investing in district-wide safety and security improvements, including:
● Secure entries and access control
● Camera and monitoring systems
● Emergency communication systems
● Site visibility and traffic safety enhancements
F. Technology, Transportation, and Furnishings Continue district investment in:
● Classroom and instructional technology
● Fleet modernization, including buses and service vehicles
● Student and staff furnishings
● Flexible learning environments
AIA
Document A141
– 2014
Standard Form of Agreement Between Owner and Design-Builder
AIA Document A141
– 2014. Copyright © 2004 and 2014 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 13:44:42 ET on 11/01/2022 under Order No.2114378925 which expires on 10/31/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.
User Notes: (1500802385)
ADDITIONS AND DELETIONS:
The author of this document has added information needed for its completion.
The author may also have revised the text of the original AIA standard form.
An Additions and Deletions
Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.
This document has important legal consequences.
Consultation with an attorney is encouraged with respect to its completion or modification.
Consultation with an attorney is also encouraged with respect to professional licensing requirements in the jurisdiction where the
Project is located.
ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.
AGREEMENT made as of the « » day of « » in the year « » (In words, indicate day, month and year.)
BETWEEN the Owner:
(Name, legal status, address and other information)
« Hemlock Public School District » « 733 N. Hemlock Road, Suite 100 » « Hemlock, Michigan 48626 » and the Design-Builder:
(Name, legal status, address and other information) for the following Project:
(Name, location and detailed description)
« Hemlock Childcare Facility Project as described in Exhibit C in accordance with the Owner’s fixed budget, the approved plans and specifications, and as otherwise approved by the Owner. »
The Owner and Design-Builder agree as follows.
– 2014. Copyright © 2004 and 2014 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 13:44:42 ET on 11/01/2022 under Order No.2114378925 which expires on 10/31/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report
TABLE OF ARTICLES
1 GENERAL PROVISIONS
2 COMPENSATION AND PROGRESS PAYMENTS
3 GENERAL REQUIREMENTS OF THE WORK OF THE DESIGN-BUILD CONTRACT
4 WORK PRIOR TO EXECUTION OF THE DESIGN-BUILD AMENDMENT
5 WORK FOLLOWING EXECUTION OF THE DESIGN-BUILD AMENDMENT
6 CHANGES IN THE WORK
7 OWNER’S RESPONSIBILITIES
8 TIME
9 PAYMENT APPLICATIONS AND PROJECT COMPLETION
10 PROTECTION OF PERSONS AND PROPERTY
11 UNCOVERING AND CORRECTION OF WORK
12 COPYRIGHTS AND LICENSES
13 TERMINATION OR SUSPENSION
14 CLAIMS AND DISPUTE RESOLUTION
15 MISCELLANEOUS PROVISIONS
16 SCOPE OF THE AGREEMENT
TABLE OF EXHIBITS
A DESIGN-BUILD AMENDMENT
B INSURANCE AND BONDS
C SUSTAINABLE PROJECTS
ARTICLE 1 GENERAL PROVISIONS
§ 1.1 Owner’s Criteria This Agreement is based on the Owner’s Criteria set forth in this Section 1.1.
(Note the disposition for the following items by inserting the requested information or a statement such as “not applicable” or “unknown at time of execution.” If the Owner intends to provide a set of design documents, and the requested information is contained in the design documents, identify the design documents and insert “see Owner’s design documents” where appropriate.)
§ 1.1.1 The Owner’s program for the Project:
(Set forth the program, identify documentation in which the program is set forth, or state the manner in which the program will be developed.)
« See the Design Builder’s Proposal dated _____________ (Exhibit C). »
§ 1.1.2 The Owner’s design requirements for the Project and related documentation:
– 2014. Copyright © 2004 and 2014 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 13:44:42 ET on 11/01/2022 under Order No.2114378925 which expires on 10/31/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report
(Identify below, or in an attached exhibit, the documentation that contains the Owner’s design requirements, including any performance specifications for the Project.)
« See Exhibit C. »
§ 1.1.3 The Project’s physical characteristics:
(Identify or describe, if appropriate, size, location, dimensions, or other pertinent information, such as geotechnical reports; site, boundary and topographic surveys; traffic and utility studies; availability of public and private utilities and services; legal description of the site; etc.)
§ 1.1.4 The Owner’s anticipated Sustainable Objective for the Project, if any:
(Identify the Owner’s Sustainable Objective for the Project such as Sustainability Certification, benefit to the environment, enhancement to the health and well-being of building occupants, or improvement of energy efficiency.
If the Owner identifies a Sustainable Objective, incorporate AIA Document A141™–2014, Exhibit C, Sustainable
Projects, into this Agreement to define the terms, conditions and Work related to the Owner’s Sustainable
Objective.)
« To be determined »
§ 1.1.5 Incentive programs the Owner intends to pursue for the Project, including those related to the Sustainable Objective, and any deadlines for receiving the incentives that are dependent on, or related to, the Design-Builder’s services, are as follows:
(Identify incentive programs the Owner intends to pursue for the Project and deadlines for submitting or applying for the incentive programs.)
§ 1.1.6 The Owner’s budget for the Work to be provided by the Design-Builder is set forth below:
(Provide total for Owner’s budget, and if known, a line item breakdown of costs.)
§ 1.1.7 The Owner’s design and construction milestone dates:
.1 Design phase milestone dates:
.2 Submission of Design-Builder Proposal:
.3 Phased completion datesConstruction Start date:
« To be determined. »
.4 Substantial Completion date:
« To be determined. »
.5 Other milestone dates:
§ 1.1.8 The Owner requires the Design-Builder to retain the following Architect, Consultants and Contractors at the Design-Builder’s cost:
– 2014. Copyright © 2004 and 2014 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 13:44:42 ET on 11/01/2022 under Order No.2114378925 which expires on 10/31/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report
(List name, legal status, address and other information.)
.1 Architect
« To be provided by Design-Builder »
.2 Consultants
.23 Contractors
« To be selected in accordance with applicable laws, including competitive bidding required by MCL
380.1267 and MCL 380.1274. For all Contractors and every category of Work, the Design-Builder will implement, coordinate, and manage a competitive bidding process in accordance with MCL
380.1267 and MCL 380.1274 on behalf of the Owner. The Owner will award competitively bid contracts in accordance with applicable law and, immediately after award, assign such contracts to the Design-Builder. »
§ 1.1.9 Additional Owner’s Criteria upon which the Agreement is based:
(Identify special characteristics or needs of the Project not identified elsewhere, such as historic preservation requirements.)
§ 1.1.10 The Design-Builder shall confirm that the information included in the Owner’s Criteria complies with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities.
§ 1.1.10.1 If the Owner’s Criteria conflicts with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, the Design-Builder shall notify the Owner of the conflict in writing.
§ 1.1.11 If there is a substantial change in the Owner’s Criteria, the Owner and the Design-Builder may shall execute a Modification in accordance with Article 6.
§ 1.1.12 If the Owner and Design-Builder intend to transmit Instruments of Service or any other information or documentation in digital form, they may shall endeavor to establish necessary protocols governing such transmissions. Unless otherwise agreed, the parties will use AIA Document E203™–2013 to establish the protocols for the development, use, transmission, and exchange of digital data and building information modeling.
§ 1.2 Project Team § 1.2.1 The Owner identifies the following representative in accordance with Section 7.1.1:
(List name, address and other information.)
« Superintendent » « Hemlock Public School District » « 733 N. Hemlock Road, Suite 100 » « Hemlock, Michigan 48626 »
§ 1.2.2 The persons or entities, in addition to the Owner’s representative, who are required to review the Design- Builder’s Submittals are as follows:
« State of Michigan, any others deemed advisable by the Owner’s Board of Education, and any others required by law. »
§ 1.2.3 The Owner Design-Builder will retain any necessary the following consultants and separate contractors to timely and satisfactorily complete the Project, including:
– 2014. Copyright © 2004 and 2014 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This draft was produced by AIA software at 13:44:42 ET on 11/01/2022 under Order No.2114378925 which expires on 10/31/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report
(List discipline, scope of work, and, if known, identify by name and address.)
§ 1.2.4 The Design-Builder identifies the following representative in accordance with Section 3.1.2:
§ 1.2.5 Neither the Owner’s nor theThe Design-Builder shall not change its’s representative shall be changed without ten days’the Owner’s prior written consentnotice to the other party unless the Design-Builder’s representative is unavailable due to death, illness, injury, retirement, or termination. In the event the Design-Builder’s representative is unavailable for the aforementioned reasons, the Design-Builder shall propose an alternative representative, subject to the Owner’s ability to reject the proposed representative.
§ 1.3 Binding Dispute Resolution For any Claim subject to, but not resolved by, mediation pursuant to Section 14.3, the method of binding dispute resolution shall be the following:
(Check the appropriate box. If the Owner and Design-Builder…