HMA Resurfacing of North 36th St..pdf

PDF 5 MB Posted

Attached to
HMA Resurfacing of North 36th St.
Solicitation number
93848
Issued by
Adams County, Illinois

About this file

This is a Notice to Bidders and specifications document issued by the Illinois Department of Transportation (IDOT) for Adams County Highway Department regarding Contract No. 93848, a Hot-Mix Asphalt (HMA) resurfacing project on North 36th Street (County Highway 15). The project, identified as Section 23-00223-00-FP and Project VJXW-669 in District 6, consists of milling and resurfacing approximately 3,920 linear feet of roadway with 1 inch of HMA Binder Course and 1 inch of Polymerized HMA Surface Course. Additional work includes pavement patching, longitudinal joint sealant, pavement markings, inlet lid replacement, curb and gutter construction, utility adjustments, and traffic control. The work extends from Station 100+00 (84 feet south of Wavering Park Road) to Station 139+20 (78 feet south of Wisman Lane). Electronic bids must be submitted to the iCX-Integrated Contractors Exchange system prior to 12:00 p.m. on June 12, 2026, at which time bids will be publicly opened. The contract will be awarded to the lowest responsive and responsible bidder in accordance with state and federal requirements.

The project is funded through District 6 Construction Funds and is subject to both federal-aid and state construction contract requirements. Bidders must comply with standard specifications for road and bridge construction, supplemental specifications, recurring special provisions, and project-specific special provisions covering traffic control, utility coordination, quality assurance/quality management for HMA placement, prevailing wage requirements, and equal employment opportunity standards. The specifications include detailed requirements for HMA surface and binder course placement with polymerized materials, density verification testing, and strict traffic control measures including lane closure restrictions, mandatory flagger protection, and comprehensive signage requirements. Notable provisions include requirements for Illinois Registered Land Surveyors to preserve and reestablish property markers, 24-hour advance notice to affected businesses and residences, coordination with emergency services, and participation incentives for IDOT Training Program graduates at $15.00 per hour. All materials, including cement, aggregates, admixtures, and asphalt binders, must meet qualified product list requirements or departmental specifications.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting June 12, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 93848 ADAMS County Section 23-00223-00-FP Route FAU 7830 (North 36th Street) Project VJXW-669 () District 6 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

June 12, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 93848 ADAMS County Section 23-00223-00-FP Project VJXW-669 () Route FAU 7830 (North 36th Street) District 6 Construction Funds

HMA resurfacing of North 36th St. from Wavering Park Rd. to Wisman Ln.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

CONTRACT 93848

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)

3 EEO

4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS

Table of Contents

CHECK SHEET # PAGE NO.

LRS 1 Reserved LRS 2 Furnished Excavation LRS 3 Work Zone Traffic Control Surveillance LRS 4 Flaggers in Work Zones LRS 5 Contract Claims LRS 6 Bidding Requirements and Conditions for Contract Proposals LRS 7 Bidding Requirements and Conditions for Material Proposals LRS 8 Reserved LRS 9 Bituminous Surface Treatments LRS 10 Reserved LRS 11 Employment Practices LRS 12 Wages of Employees on Public Works LRS 13 Selection of Labor LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS 15 Partial Payments LRS 16 Protests on Local Lettings LRS 17 Substance Abuse Prevention Program LRS 18 Multigrade Cold Mix Asphalt LRS 19 Reflective Crack Control Treatment

Local Public Agency County Section Number

Adams County Highway Department Adams 23-00223-00-FP i

Index of Sheets Page

Contract Specifications 1

Description of Work 1

Preservation of Section or Sub-Section Stones and Other Markers 1

Public Convenience and Safety 1

Hot-Mix Asphalt Surface Removal – Butt Joint 2

Hot-Mix Asphalt Surface Removal, 2 ½” 2

Milling Restrictions 2

Saw Cuts 3 Hot-Mix Asphalt Binder Course 3 Polymerized Hot-Mix Asphalt Surface Course 3 Combination Concrete Curb and Gutter Removal 3 Combination Concrete Curb and Gutter, Type B-6.12 (AEP) 3 Valve Boxes to be Adjusted 4 Inlets to be Adjusted (Special) 4 Inlets to be Adjusted 4 Status of Utilities to be Adjusted 5 Traffic Control and Protection, (Special) 5 Insurance (LR 107-4) 8 Local Quality Assurance / Quality Management QC/QA (LR 1030-2) 9 IDOT Training Program Graduate On-The-Job Training 11

BDE SPECIAL PROVISIONS

The following special provisions indicated by an “X” are applicable to this contract. An * indicates a new or revised special provision for the letting.

File Name Pg. Special Provision Title Effective Revised 80099 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 _ 80274 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 13 Automated Flagger Assistance Device Jan. 1, 2008 April 1, 2023 80173 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017

* 80426 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 April 1, 2026 80475 Bridge Deck Concrete Overlays Jan. 1, 2026 80241 Bridge Demolition Debris July 1, 2009

5053I Building Removal Sept. 1, 1990 Aug. 1, 2022 5026I Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022

80460 14 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 31 Compensable Delay Costs June 2, 2017 April 1, 2019 80198 Completion Date (via calendar days) April 1, 2008 80199 Completion Date (via calendar days) Plus Working Days April 1, 2008 80461 Concrete Barrier Jan. 1, 2025 80453 Concrete Sealer Nov. 1, 2023 80261 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 Deck Slab Repair Jan. 1, 2026 80029 Disadvantaged Business Enterprise Participation Sept. 1, 2000 Jan. 2, 2025 80467 Erosion Control Blanket Aug. 1, 2025 80229 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 Guardrail Nov. 1, 2025 80472 High Friction Surface Treatment Nov. 1, 2025

* 80456 35 Hot-Mix Asphalt Jan. 1, 2024 April 1, 2026 80446 39 Hot-Mix Asphalt – Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024

* 80483 Inlet Filters April 1, 2026 80477 Longitudinal Tining Jan. 1, 2026 80450 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 41 Pavement Marking April 1, 2025 Nov. 1, 2025 80468 42 Pavement Patching Aug. 1, 2025

* 80441 43 Performance Graded Asphalt Binder Jan 1, 2023 April 1, 2026 80459 Preformed Plastic Pavement Marking June 2, 2024 3426I Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 Raised Reflective Pavement Markers Nov. 1, 2025

* 80455 49 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2026 80474 Residential Driveway Temporary Signal Nov. 1, 2025 80445 Seeding Nov. 1, 2022 80457 51 Short Term and Temporary Pavement Markings April 1, 2024 April 2, 2024 80462 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 Sinusoidal Rumble Strips Jan. 1, 2026 80469 Slope Wall Aug. 1, 2025 80448 55 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 Structural Repair of Concrete Jan. 1, 2026 80397 57 Subcontractor and DBE Payment Reporting April 2, 2018 80391 58 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019 80463 59 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025

File Name Pg. Special Provision Title Effective Revised

* 80482 60 Submission of Payroll Records – Federal Aid Contract April 1, 2026

* 80437 Submission of Payroll Records – State Contract April 1, 2021 April 1, 2026 80435 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 62 Surveying Services April 1, 2025 80481 Temporary Concrete Barrier Jan. 1, 2026 80466 Temporary Rumble Strips April 1, 2025 80470 Traffic Signal Backplate Aug. 1, 2025 20338 63 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022 80439 66 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2022 80458 Waterproofing Membrane System Aug. 1, 2024 80302 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 Wood Sign Support Nov. 1, 2023 80427 67 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026 80071 70 Working Days Jan. 1, 2002

SPECIAL PROVISIONS

The following Special Provisions supplement the “Standard Specifications for Road and Bridge Construction”, Adopted Adopted January 1, 2022, the latest edition of the “Manual on Uniform Traffic Control Devices for Streets and Highways”, and Highways”, the “Manual of Test Procedures for Materials” in effect on the date of invitation of bids, and the Supplemental Specification and Recurring Special Provisions indicated on the Check Sheet included here in which apply to and govern the construction of Adams County Section 23-00223-00-FP (FAU 7830 --- Co Hwy 15), Project No. VJXW (669) , and in case of conflict with any parts, or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.

DESCRIPTION OF WORK

The work on this section shall consists of milling and resurfacing North 36th Street (Co Hwy 15) with 1 ¼” HMA Binder Course and Polymerized 1 ½” HMA Surface Course.

Additional work includes pavement patching, longitudinal joint sealant, pavement markings, inlet lid replacement, and other ancillary work.

The work begins on North 36th Street at Sta. 100+00 (84 Ft South of Wavering Park Road) then proceeding northerly to Sta. 139+20 (78 Ft South of Wisman Lane).

PRESERVATION OF SECTION OR SUBSECTION STONES AND OTHER MARKERS

Unless otherwise noted or provided for, all stones, property pins and other markers encountered in the field should be cross-tied before any excavation or before the pavement is removed or resurfaced. A special plate or marker shall be secured from the Adams County Highway Department to be inserted in the (surfacing item specified) to re-reference the stone or marker. This work, including supplying a new monument record shall be done by an Illinois Registered Land Surveyor whose services shall be obtained by the Contractor. The Registered Land Surveyor will be paid in accordance with Article 109.04 of the Standard Specifications. The cost of any delay or inconvenience during the placing of these markers shall be incidental to the surfacing item specified. The new monument record shall be supplied to the Adams County Highway Department, County Engineer, P.O. Box 3797, 101 North 54th Street, Quincy, Illinois 62305 for filing.

PUBLIC CONVENIENCE AND SAFETY

In addition to requirements of Article 107.09 of the Standard Specifications, add the following:

The Contractor shall be required to notify the Engineer at least seven (7) days prior to the initiation of any work in this proposed improvement.

The Adams County Highway Department will provide notice to the general public of the proposed road improvement project, anticipated work time frame and a request to use alternate routes, if possible, due to lane closures. The general notification of the proposed project will be done through the news media.

The Adams County Highway Department will also be responsible for notifying the 9-1-1 Emergency Services Center of the proposed project work and timeframe. The Center, in turn, will notify the other community emergency services.

The Contractor shall be required to provide a minimum of 24 hour advance notice to any business or residence losing the short term use of their driveway entrance which has direct access to the proposed improvement due to construction activities. A card or mimeographed notification letter may be used for this purpose. At minimum, the card or letter should contain:

o Name of the Contractor and contact information for any questions or concerns.

o Estimated date, time, and duration of the loss of access.

o Notice that off street parking, if applicable, is prohibited during that time frame.

o Request that no deliveries be made during the time frame of the closure.

HOT-MIX ASPHALT SURFACE REMOVAL – BUTT JOINT

HOT-MIX ASPHALT SURFACE REMOVAL, 2 ½”

This work shall be done in accordance with all applicable portions of Section 440 of the Standard Specifications for Road and Bridge Construction and/or as follows:

For butt joints, the contractor shall saw the existing pavement to a depth equal to the proposed surface course with a concrete sawing machine to prevent the surface from spalling when the existing surface is being removed.

The surface to be removed shall be a wedge beginning at a depth equal to the proposed surface course and tapering to nothing in the length specified on Sheet 13 in the plans or as directed by the Engineer.

The depth of surface removal may vary slightly from 2-1/2” to fully remove the existing HMA surface and HMA Binder course as shown on the typical section sheet in the plans.

For mainline or traffic lane removal, the self-propelled milling machine shall be capable of milling an entire lane width in a single pass and have the capability of loading the millings into a truck.

Any existing HMA surface in the gutter flow line shall be removed during the milling operation but will not be included in the quantity measured for payment or paid for separately.

The cost of a labor, equipment, and materials to remove the existing surface as shown on the plans will be paid for at the contract unit price per square yard for HOT-MIX ASPHALT SURFACE REMOVAL – BUTT JOINT and HOT-MIX ASPHALT SURFACE REMOVAL, 2-1/2” and no additional compensation will be allowed.

MILLING RESTRICTIONS

This work shall be done in accordance with all applicable portions of Section 440 of the Standard Specifications for Road and Bridge Construction and/or as follows.

Vertical drop-offs occurring at centerline greater than 1 ½”, due to milling operations, shall be addressed by one of the following options:

• Option #1: Vertical drop-offs at centerline and lane lines shall be eliminated by milling both directions of traffic in a given workday.

• Option #2: Vertical drop-offs at centerline or lane line shall have a milled sloped edge treatment cut at a minimum of 1:3 to eliminate the vertical edge before being opened to traffic. Milled slope edge treatments at centerline shall be in place prior to re-opening the lane to traffic.

• Option #3: Any vertical drop-off greater than 1 ½” at centerline or lane line caused by milling operations shall have the level binder or binder lift placed prior to reopening the lane to traffic.

Vertical drop-offs occurring at the perpendicular edge of other mainline pavement or entrances greater than 1 ½”, due to milling operations, shall be addressed by constructing temporary ramps.

At no time shall traffic have to traverse a vertical drop-off greater than 1 ½” at centerline, perpendicular edge of other mainline pavement or entrances.

The Contractor will be required to reduce or eliminate the drop-off by one of the options mentioned above. This work shall be considered included in the HOT-MIX ASPHALT SURFACE REMOVAL pay items of the specified depth.

Temporary ramps shall be measured and paid for at the contract unit price per square yard for TEMPORARY

RAMP.

SAW CUTS

This work consists of performing the necessary full-depth or partial depth saw cuts as indicated in the plans and/or as directed by the Engineer prior to removal and replacement or patching of any existing material or surface.

Saw cutting, whether full-depth or partial depth will not be paid for separately but shall be considered as included in the contract unit price for the item being removed or in the contract unit price for the items being installed or constructed.

HOT-MIX ASPHALT BINDER COURSE

POLYMERIZED HOT-MIX ASPHALT SURFACE COURSE

Revise Article 406.06 (e) to include:

The operating width of the paver for mainline paving shall not exceed the width of the pavement lane shown on the typical sections and / or the longitudinal joint sealant detail sheet for the placement of the HMA Surface Course.

COMBINATION CURB AND GUTTER REMOVAL

This work consists of the removal of various types of curb, gutter, combination curb and gutter, with or without monolithic pavement, as shown on the plans and as directed by the Engineer in accordance with all applicable portions of Section 440 of the Standard Specifications for Road and Bridge Construction and the following.

A full depth saw cut is required in all locations before the removal process begins. These saw cuts are intended to sever existing tie bars or separate monolithically poured curb and gutter component from the PCC pavement or widening without causing damage to the pavement or widening. Any work performed in order to fix damage from the removal process will not be paid for separately.

The work will be paid for at the contract unit price per foot for COMBINATION CURB AND GUTTER REMOVAL regardless of the type of curb, gutter, or combination curb and gutter.

COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.12 (ABUTTING EXISTING PAVEMENT)

This work consists of constructing combination concrete curb and gutter adjacent to existing concrete pavement or hot-mix asphalt pavement with aggregate base course in accordance with all applicable portions of Section 606 of the Standard Specifications and the following.

Combination curb and gutter cast against existing concrete pavement or widening shall be attached to the pavement using drilled and grout-in-place tie bars of the size specified on Standard 606001.

Combination curb and gutter cast against existing hot-mix asphalt pavement shall be cast to the lines and grades as shown on the plans either prior to or following the hot-mix surface removal. The combination concrete curb and gutter shall be cast against a vertical saw cut edge of hot-mix asphalt pavement, or a form attached to the existing milled surface or concrete widening. The specific method used to construct the curb and gutter shall achieve the proposed location and profile without noticeable breaks or inconsistencies.

Any aggregate base course placed beneath the combination concrete curb and gutter will not be measured for payment.

This work shall be paid for at the contract unit price per foot for COMBINATION CONCRETE CURB AND GUTTER, (ABUTTING EXISTING PAVEMENT) of the type specified, including all excavation and backfilling.

VALVE BOXES TO BE ADJUSTED

This work shall consist of adjusting the valve stem casting and lid of existing utility structures in accordance with Section 603 of the Standard Specifications and the following.

If the structure houses a water utility, the existing valve box casting and lid may be reused unless damaged. The Quincy Water Department will inspect each casting and furnish at no cost a new one for either a damaged or a non-standard box and lid.

If the adjustment is on gas structure, the existing valve casting and lid may be reused unless damaged. The gas facility owner will furnish at no cost a new one for either a damaged or a non-standard valve casting and lid.

Damage to the casting during adjustment shall be reason for replacement of the box at the Contractor's expense.

In the case that the utility has been previously adjusted, the contractor will be required to remove and replace all the surrounding area to the limits of the previous adjustment.

Revise Article 603.05 Replacement of Existing Flexible Pavement to read: After the castings have been adjusted, the surrounding space shall be filled with Class SI concrete to the elevation of the surface of the base course or the binder course. Class SI concrete shall be cured for a period of not less than 72 hours.

Basis of Payment: This work shall be paid for at the contract unit price per each for VALVE BOXES TO BE ADJUSTED which price shall include any necessary pavement removal, backfilling, concrete and excavation, except excavation in rock.

INLETS TO BE ADJUSTED (SPECIAL)

This work shall consist of removing the existing inlet lid, grout bed and other deleterious materials and installing a new concrete lnlet, Type E lid at the location(s) indicated in the plans in accordance with all applicable portions of Section 602 of the Standard Specifications, special detail sheets and the following.

A precast lid may be used at the Contractor’s option. No additional compensation shall be allowed for any required alteration or modification of the precast inlet lid due to unforeseen conditions or changes in the field.

This work will be paid for at the contract unit price each for INLET TO BE ADJUSTED (SPECIAL) which price shall include the necessary labor, materials, equipment and all excavation and backfill, except excavation in rock

INLETS TO BE ADJUSTED

This work shall consist of removing the existing inlet frame, grout bed and other deleterious materials and resetting the existing inlet frame with the new curb at the location(s) indicated in the plans in accordance with all applicable portions of Section 602 of the Standard Specifications, special detail sheets and the following.

This work will be paid for at the contract unit price each for INLETS TO BE ADJUSTED which price shall include the necessary labor, materials, equipment and all excavation and backfill, except excavation in rock.

STATUS OF UTILITES TO BE ADJUSTED

Estimated Date

Name and Address of Utility Type Location Relocation Completed

J.U.L.I.E. 1-800-892-0123

Adams Telesystems Phone & Fiber Entire Job None Anticipated

Ameren Illinois Gas Entire Job None Anticipated

AT & T Phone Entire Job None Anticipated

Comcast Phone Entire Job None Anticipated

City of Quincy Water Entire Job None Anticipated

The above represents the best information of the Department and is only included for the convenience of the bidder. The applicable provisions of Articles 105.07 ,107.20, and 107.39 of the Standard Specifications for Road and Bridge Construction shall apply.

If any utility adjustment or removal has not been completed when required by the Contractor’s operations, the Contractor should notify the Engineer in writing. A request for an extension of time will be considered to the extent the Contractor’s operations were affected.

TRAFFIC CONTROL AND PROTECTION, (SPECIAL)

Traffic control shall be in accordance with the applicable sections of the Standard Specification for Road and Bridge Construction, the applicable guidelines contained in the Illinois Manual on Uniform Control Devices for Streets and Highways, these special provisions, and any special details and Highway Standards contained herein and in the plans.

Special attention is called to Section 107 and Section 701 thru Section 703, as applicable, of the Standard Specifications for Road and Bridge Construction, and as amended by the Supplemental Specifications, Recurring Special Provisions, the Special Provisions contained herein, and the following Highway Standards relating to traffic control.

701301 701306 701311 701502

A minimal traffic control plan is included in these Special Provisions.

Limitations of Construction:

1. The Contractor will be responsible for the traffic control devices at all times during construction activities and shall coordinate the items of work in order to keep traffic hazards to a minimum.

2. The Contractor shall be required to submit form BSPE 725 prior to the start of the project.

3. There will be no lanes closures without flagger protection. Flagmen for this project shall be equipped with two-way radios for effective communication when required by the Engineer. Additional flaggers will be required at locations which have major intersections at each end or side-roads where two-way traffic is maintained on a single open lane of pavement.

4. There will be no overnight lane closures.

5. The Contractor is to furnish, install and maintain all required signs, posts, lights drums and barricades. The

Contractor will be responsible for the traffic control devices at all times during construction and throughout winter shutdown periods.

6. The Engineer shall determine the location for all advanced warning signs, information signs and barricades.

The Engineer reserves the right to modify the traffic control plan or standards, as construction proceeds to accommodate local traffic.

7. Construction signs referring to daytime lane closures during working hours shall be removed or covered during nonworking hours.

8. All Type III barricades used on this project shall be in new or like new condition at the start of the project. If the barricade is damaged during the project, the Type III barricade shall be replaced by a new or like new Type III barricade. All Type III barricades shall be reflectorized on both sides. Two (2) Type A flashing lights will be required on all Type III barricades. Sandbags will be required for all Type III barricades. The additional Type III barricades shall be considered incidental to the contract unit price for traffic control and protection at that location.

9. All advance-warning signs shall be in new or like new condition at the start of the project. All warning signs shall be 48 inches by 48 inches and have a black legend on an orange reflectorized background. If an advanced warning sign is damaged or becomes unreadable, the sign shall be replaced by a new or like new sign.

10. Signposts must be a 4-inch x 4-inch wood post per Article 1007.05, or metal posts if being used with temporary “skid-type” bases. A flashing yellow light shall be placed above each post mounted sign.

11. "Road Construction Ahead" signs (W20-I103) shall be furnished and erected at both ends of the project and at all side roads within the project limits. The "Road Construction Ahead" signs shall be post mounted if the work to be performed exceeds 96 hrs. If the duration of work within the project does not exceed 96 hours, a collapsing stand-mounted sign shall be acceptable. Collapsing stand mounted signs may be used in residential subdivisions, at the discretion of the Engineer.

12. A Shoulder Drop-Off sign (W21-I103) shall be utilized as warranted if there is a drop-off greater than 3 inches at the edge of pavement. See Article 701.07 of the Standard Specifications.

13. Where construction operations require the construction of a temporary ramp, a “Bump” sign(s) (W8-1(0)48) shall be used. The Contractor shall place the sign(s) adjacent to the temporary ramp or as directed by the Engineer. The signs shall be placed immediately prior to the work that will result in the temporary ramp and shall remain in place until the temporary ramp is eliminated.

14. The Contractor shall post the roadway with “LOOSE GRAVEL” (W8-7) and “SPEED LIMIT 35” signs in accordance with applicable articles of Division 700 of the Standard Specifications. These signs shall be placed at the start of the work, near intersection roadways and then at an average spacing of 0.5 miles. The signs may be removed as soon as the sweeping operation has been completed.

15. The Contractor shall post the roadway with “FRESH OIL” (W21-2) sign(s) when prime and fine aggregate, bituminous materials for the A-1 surface and the micro-surfacing emulsion are applied to pavement that is open to traffic. The signs shall remain until tracking of the bituminous material ceases or as directed by the Engineer. The signs shall be erected a minimum of 500 ft preceding the start of the application area.

16. When construction operations on two–lane roads open to traffic result in the removal or covering of any pavement striping indicating passing restrictions, “NO PASSING ZONES NOT STRIPED NEXT _____ MILES” (G20-I100) signs shall be used. The Contractor shall place the signs at the beginning of the unstriped area, and at such other locations as the Engineer may direct to ensure a minimum spacing of five miles.

17. Barricades or drums shall be placed at 50 feet centers at all locations where a drop- off of 3 inches or more occurs during the construction of the project. The Engineer reserves the right to adjust this spacing to adequately protect the public.

All labor, materials and equipment required to satisfy the conditions stated herein shall be paid for at the contract unit price per lump sum for TRAFFIC CONTROL AND PROTECTION, (SPECIAL) and no additional compensation shall be allowed. Traffic control and protection provided under individual Standards will not be paid for separately but shall be considered incidental to TRAFFIC CONTROL AND PROTECTION, (SPECIAL).

LR107-4

State of Illinois Department of Transportation

Bureau of Local Roads and Streets

SPECIAL PROVISION

FOR

INSURANCE

Effective: February 1, 2007 Revised: August 1, 2007

All references to Sections or Articles in this specification shall be construed to mean specific Section or Article of the Standard Specifications for Road and Bridge Construction, adopted by the Department of Transportation.

The Contractor shall name the following entities as additional insured under the Contractor’s general liability insurance policy in accordance with Article 107.27:

The entities listed above and their officers, employees, and agents shall be indemnified and held harmless in accordance with Article 107.26.

LR1030 2

State of Illinois

DEPARTMENT OF TRANSPORTATION

Bureau of Local Roads & Streets

SPECIAL PROVISION

FOR

LOCAL QUALITY ASSURANCE/ QUALITY MANAGEMENT QC/QA

Effective: January 1, 2022

Replace the first five paragraphs of Article 1030.06 of the Standard Specifications with the following:

� 1030.06 Quality Management Program. The Quality Management Program (QMP) will be Quality Control / Quality Assurance (QC/QA) according to the following.�

Delete Article 1030.06(d)(1) of the Standard Specifications.

Revise Article 1030.09(g)(3) of the Standard Specifications to read:

� (3) If core testing is the density verification method, the Contractor shall provide personnel and equipment to collect density verification cores for the Engineer. Core locations will be determined by the Engineer following the document �Hot-Mix Asphalt QC/QA Procedure for Determining Random Density Locations� at density verification intervals defined in Article 1030.09(b). After the Engineer identifies a density verification location and prior to opening to traffic, the Contractor shall cut a 4 in. (100 mm) diameter core. With the approval of the Engineer, the cores may be cut at a later time.�

Revise Article 1030.09(h)(2) of the Standard Specifications to read:

� (2) After final rolling and prior to paving subsequent lifts, the Engineer will identify the random density verification test locations. Cores or nuclear density gauge testing will be used for density verification. The method used for density verification will be as selected below.

Density Verification Method Cores Nuclear Density Gauge (Correlated when paving 3,000 tons per mixture)

Density verification test locations will be determined according to the document �Hot- Mix Asphalt QC/QA Procedure for Determining Random Density Locations�. The density testing interval for paving wider than or equal to 3 ft (1 m) will be 0.5 miles (800

m) for lift thicknesses of 3 in. (75 mm) or less and 0.2 miles (320 m) for lift thicknesses greater than 3 in. (75 mm). The density testing interval for paving less than 3 ft (1 m) wide will be 1 mile (1,600 m). If a day�s paving will be less than the prescribed density testing interval, the length of the day�s paving will be the interval for that day. The density testing interval for mixtures used for patching will be 50 patches with a minimum of one test per mixture per project.

If core testing is the density verification method, the Engineer will witness the Contractor coring, and secure and take possession of all density samples at the

LR1030 2

density verification locations. The Engineer will test the cores collected by the Contractor for density according to Illinois Modified AASHTO T 166 or AASHTO T 275.

If nuclear density gauge testing is the density verification method, the Engineer will conduct nuclear density gauge tests. The Engineer will follow the density testing procedure detailed in the document �Illinois Modified ASTM D 2950, Standard Test Method for Density of Bituminous Concrete In-Place by Nuclear Method�.

A density verification test will be the result of a single core or the average of the nuclear density tests at one location. The results of each density test must be within acceptable limits. The Engineer will promptly notify the Contractor of observed deficiencies.�

Revise the seventh paragraph and all subsequent paragraphs in Section D. of the document �Hot-Mix Asphalt QC/QA Initial Daily Plant and Random Samples� to read:

�Mixtures shall be sampled from the truck at the plant by the Contractor following the same procedure used to collect QC mixture samples (Section A). This process will be witnessed by the Engineer who will take custody of the verification sample. Each sample bag with a verification mixture sample will be secured by the Engineer using a locking ID tag. Sample boxes containing the verification mixture sample will be sealed/taped by the Engineer using a security ID label.�

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING SPECIAL PROVISION

Effective: August 1, 2012 Revised: February 2, 2017

In addition to the Contractor’s equal employment opportunity (EEO) affirmative action efforts undertaken as required by this Contract, the Contractor is encouraged to participate in the incentive program described below to provide additional on-the-job training to certified graduates of the IDOT pre-apprenticeship training program, as outlined in this Special Provision.

IDOT funds, and various Illinois community colleges operate, pre-apprenticeship training programs throughout the State to provide training and skill-improvement opportunities to promote the increased employment of minority groups, disadvantaged persons and women in all aspects of the highway construction industry. The intent of this IDOT Pre-Apprenticeship Training Program Graduate (TPG) special provision (Special Provision) is to place these certified program graduates on the project site for this Contract in order to provide the graduates with meaningful on-the-job training. Pursuant to this Special Provision, the Contractor must make every reasonable effort to recruit and employ certified TPG trainees to the extent such individuals are available within a practicable distance of the project site.

Specifically, participation of the Contractor or its subcontractor in the Program entitles the participant to reimbursement for graduates’ hourly wages at $15.00 per hour per utilized TPG trainee, subject to the terms of this Special Provision. Reimbursement payment will be made even though the Contractor or subcontractor may also receive additional training program funds from other non-IDOT sources for other non-TPG trainees on the Contract, provided such other source does not specifically prohibit the Contractor or subcontractor from receiving reimbursement from another entity through another program, such as IDOT through the TPG program. With regard to any IDOT funded construction training program other than TPG, however, additional reimbursement for other IDOT programs will not be made beyond the TPG Program described in this Special Provision when the TPG Program is utilized.

No payment will be made to the Contractor if the Contractor or subcontractor fails to provide the required on-site training to TPG trainees, as solely determined by IDOT. A TPG trainee must begin training on the project as soon as the start of work that utilizes the relevant trade skill and the TPG trainee must remain on the project site through completion of the Contract, so long as training opportunities continue to exist in the relevant work classification. Should a TPG trainee’s employment end in advance of the completion of the Contract, the Contractor must promptly notify the IDOT District EEO Officer for the Contract that the TPG’s involvement in the Contract has ended. The Contractor must supply a written report for the reason the TPG trainee involvement terminated, the hours completed by the TPG trainee on the Contract, and the number of hours for which the incentive payment provided under this Special Provision will be, or has been claimed for the separated TPG trainee.

Finally, the Contractor must maintain all records it creates as a result of participation in the Program on the Contract, and furnish periodic written reports to the IDOT District EEO Officer that document its contractual performance under and compliance with this Special Provision.

Finally, through participation in the Program and reimbursement of wages, the Contractor is not relieved of, and IDOT has not waived, the requirements of any federal or state labor or employment law applicable to TPG workers, including compliance with the Illinois Prevailing Wage Act.

METHOD OF MEASUREMENT: The unit of measurement is in hours.

BASIS OF PAYMENT: This work will be paid for at the contract unit price of $15.00 per hour for each utilized certified TPG Program trainee (TRAINEES TRAINING PROGRAM GRADUATE).

The estimated total number of hours, unit price, and total price must be included in the schedule of prices for the Contract submitted by Contractor prior to beginning work. The initial number of TPG trainees for which the incentive is available for this contract is 1.

The Department has contracted with several educational institutions to provide screening, tutoring and pre-training to individuals interested in working as a TPG trainee in various areas of common construction trade work. Only individuals who have successfully completed a Pre- Apprenticeship Training Program at these IDOT approved institutions are eligible to be TPG trainees. To obtain a list of institutions that can connect the Contractor with eligible TPG trainees, the Contractor may contact: HCCTP TPG Program Coordinator, Office of Business and Workforce Diversity (IDOT OBWD), Room 319, Illinois Department of Transportation, 2300 S. Dirksen Parkway, Springfield, Illinois 62764. Prior to commencing construction with the utilization of a TPG trainee, the Contractor must submit documentation to the IDOT District EEO Officer for the Contract that provides the names and contact information of the TPG trainee(s) to be trained in each selected work classification, proof that that the TPG trainee(s) has successfully completed a Pre-Apprenticeship Training Program, proof that the TPG is in an Apprenticeship Training Program approved by the U.S. Department of Labor Bureau of Apprenticeship Training, and the start date for training in each of the applicable work classifications.

To receive payment, the Contractor must provide training opportunities aimed at developing a full journeyworker in the type of trade or job classification involved. During the course of performance of the Contract, the Contractor may seek approval from the IDOT District EEO Officer to employ additional eligible TPG trainees. In the event the Contractor subcontracts a portion of the contracted work, it must determine how many, if any, of the TPGs will be trained by the subcontractor. Though a subcontractor may conduct training, the Contractor retains the responsibility for meeting all requirements imposed by this Special Provision. The Contractor must also include this Special Provision in any subcontract where payment for contracted work performed by a TPG trainee will be passed on to a subcontractor.

Training through the Program is intended to move TPGs toward journeyman status, which is the primary objective of this Special Provision. Accordingly, the Contractor must make every effort to enroll TPG trainees by recruitment through the Program participant educational institutions to the extent eligible TPGs are available within a reasonable geographic area of the project. The Contractor is responsible for demonstrating, through documentation, the recruitment efforts it has undertaken prior to the determination by IDOT whether the Contractor is in compliance with this Special Provision, and therefore, entitled to the Training Program Graduate reimbursement of $15.00 per hour.

Notwithstanding the on-the-job training requirement of this TPG Special Provision, some minimal off-site training is permissible as long as the offsite training is an integral part of the work of the contract, and does not compromise or conflict with the required on-site training that is central to the purpose of the Program. No individual may be employed as a TPG trainee in any work classification in which he/she has previously successfully completed a training program leading to journeyman status in any trade, or in which he/she has worked at a journeyman level or higher.

AUTOMATED FLAGGER ASSISTANCE DEVICES (BDE)

Effective: January 1, 2008 Revised: April 1, 2023

Description. This work shall consist of furnishing and operating automated flagger assistance devices (AFADs) as part of the work zone traffic control and protection for two-lane highways where two-way traffic is maintained over one lane of pavement in segments where no sideroads or entrances require deployment of additional flaggers. Use of these devices shall be at the option of the Contractor.

Equipment. AFADs shall be the STOP/SLOW or Red/Yellow Lens type mounted on a trailer or moveable cart meeting the requirements of the MUTCD and NCHRP 350 or MASH 2016, Category 4.

General. AFADs shall be placed at each end of the traffic control, where a flagger is shown on the plans. The AFAD shall be setup within five degrees of vertical.

Flagger symbol signs as shown on the plans shall be replaced with “BE PREPARED TO STOP” signs when the AFAD is in operation.

Personal communication devices shall not be used to operate the AFAD.

Flagging Requirements. Flaggers and flagging requirements shall be according to Article 701.13 of the Standard Specifications and the following.

Each AFAD shall be operated by a flagger trained to operate the specific AFAD to be deployed.

A minimum of two flaggers shall be on site at all times during operation. Each flagger shall be positioned outside the lane of traffic and near each AFAD’s location.

Flagging equipment required for traditional flagging shall be available near each AFAD location in the event of AFAD equipment malfunction/failure.

For nighttime flagging, the AFAD and flagger shall be illuminated according to Article 701.13 of the Standard Specifications.

When not in use, AFADs will be considered non-operating equipment and shall be stored according to Article 701.11 of the Standard Specifications.

Basis of Payment. This work will not be paid for separately but shall be considered as included in the cost of the various traffic control items included in the contract.

80192

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

Effective: January 1, 2025 Revised: January 1, 2026

Revise the first paragraph of Article 285.05 of the Standard Specifications to read:

“ 285.05 Fabric Formed Concrete Revetment Mat. The grout shall consist of a mixture of cement, fine aggregate, and water so proportioned and mixed as to provide a pumpable slurry.

Fly ash or ground granulated blast furnace (GGBF) slag, and concrete admixtures may be used at the option of the Contractor. The grout shall have an air content of not less than 6.0 percent nor more than 9.0 percent of the volume of the grout. The mix shall obtain a compressive strength of 2500 psi (17,000 kPa) at 28 days according to Article 1020.09.”

Revise Article 302.02 of the Standard Specifications to read:

“ 302.02 Materials. Materials shall be according to the following.

Item Article/Section

(a) Cement

(b) Water

(c) Hydrated Lime .................................................................................................... 1012.01

(d) By-Product, Hydrated Lime ................................................................................ 1012.02

(e) By-Product, Non-Hydrated Lime ........................................................................ 1012.03

(f) Lime Slurry ......................................................................................................... 1012.04

(g) Fly Ash

(h) Soil for Soil Modification (Note 1) ....................................................................... 1009.01

(i) Bituminous Materials (Note 2)

Note 1. This soil requirement only applies when modifying with lime (slurry or dry).

Note 2. The bituminous materials used for curing shall be emulsified asphalt RS-2, CRS- 2, HFE 90, or HFE 150; rapid curing liquid asphalt RC-70; or medium curing liquid asphalt MC-70 or MC-250.”

Revise Article 312.07(c) of the Standard Specifications to read:

“ (c) Cement .................................................................................................................... 1001”

Add Article 312.07(i) of the Standard Specifications to read:

“ (i) Ground Granulated Blast Furnace (GGBF) Slag ...................................................... 1010”

Revise the first paragraph of Article 312.09 of the Standard Specifications to read:

“ 312.09 Proportioning and Mix Design. At least 60 days prior to start of placing CAM II, the Contractor shall submit samples of materials to be used in the work for proportioning and testing.

The mixture shall contain a minimum of 200 lb (120 kg) of cement per cubic yard (cubic meter).

Cement may be replaced with fly ash or ground granulated blast furnace (GGBF) slag according to Article 1020.05(c)(1) or 1020.05(c)(2), respectively, however the minimum cement content in the mixture shall be 170 lbs/cu yd (101 kg/cu m). Blends of coarse and fine aggregates will be permitted, provided the volume of fine aggregate does not exceed the volume of coarse aggregate. The Engineer will determine the proportions of materials for the mixture according to the “Portland Cement Concrete Level III Technician Course” manual. However, the Contractor may substitute their own mix design. Article 1020.05(a) shall apply, and a Level III PCC Technician shall develop the mix design.”

Revise Article 352.02 of the Standard Specifications to read:

“ 352.02 Materials. Materials shall be according to the following.

(a) Cement (Note 1)

(b) Soil for Soil-Cement Base Course ....................................................................... 1009.03

(c) Water

(d) Bituminous Materials (Note 2)

Note 1. Bulk cement may be used for the traveling mixing plant method if the equipment for handling, weighing, and spreading the cement is approved by the Engineer.

Note 2. The bituminous materials used for curing shall be emulsified asphalt RS-2, CRS-2, HFE 90, or HFE 150; rapid curing liquid asphalt RC-70; or medium curing liquid asphalt MC-70 or MC-250.”

Revise Article 404.02 of the Standard Specifications to read:

“ 404.02 Materials. Materials shall be according to the following.

(a) Cement

(b) Water

(c) Fine Aggregate .................................................................................................... 1003.08

(d) Bituminous Material (Tack Coat) .......................................................................... 1032.06

(e) Emulsified Asphalts (Note 1) (Note 2) .........................................................