C-130H FPS Industry Day Q&A June 2026
| Will the Government consider doing an OTA (Other Transaction Authority) rather than a FAR (Federal Acquisition Regulation) contract? |
| While the program office’s current acquisition & contracting approach is based on an RFO Part 6 activity, the Government may consider pursuing an OTA if deemed in the best interest of the Government to do so. Please submit any proposed alternative with rationale when responding to the request for feedback on the Draft RFP. |
| Is it possible to send the slides presented during the general session to participants? |
| Yes, all registered participants have been notified of the availability of the presentation by downloading from DoD SAFE. |
| Can the Government share who the awardee is for the C-130J FPS development? |
| Yes, the C-130J FPS EMD contract will be awarded to Lockheed Martin (Marietta, GA) later this month (June 2026). |
| Does the Government anticipate issuing this contract as a Cost-Plus type contract or Firm Fixed Price (FFP)? Will either type of offer be accepted? |
| While the program office’s current general contracting approach for this effort is primarily FFP, Cost type contracts may be considered/used for specific CLINs. |
| What’s the intent behind the Government’s question regarding contract incentives to ensure quality throughout the program’s life cycle? |
| While the timeline to fielding the system is a top priority and Fixed Price contract inherently motivates speed of completion, the USAF also needs the system to effectively meet operational needs. As such, the Government is seeking Industry input on how to not only field the system as swiftly as possible, but also how to ensure it actually works. |
| Is the absence of a probability of intercept requirement from the SRD intentional? |
| Yes, the current SKE system does not include LPI/LPD specifications so the Government is not levying any LPI/LPD-related requirements for the replacement system. That said, the MILACAS-FR does include LPI/LPD as optional features. |
Of particular note, however, are the FPS encryption requirements that align to the latest DoW standards.
| Has the Group B been determined, or will the H FPS prime integrator need to research and select a solution that is compatible with the C-130J FPS? |
| For a number of reasons, the program office is requiring use of the MILACAS-FR sensor for the H FPS technical solution. There is no need to conduct a market survey for the Group B kit design. |
| If the contract is FFP, why is Earned Value Management (EVM) required? |
| For this activity, executing to a well-crafted plan is integral to fielding the FPS capability as swiftly as possible. As such, the program office seeks to maintain oversight of progress and identify schedule variances as they arise. EVM allows the Government to effectively do that in a timely manner. That said, the program office is open to other alternative approaches & tools and requests Industry input on how to best ensure the program remains on track through development and fielding. |