Henderson Front Gate Replacement Scope of Work.docx
DOCX document 24 KB Posted
- Attached to
- Henderson - Front Gate Replacement
- Solicitation number
- 43ADG-S3923
- Issued by
- Nevada
About this file
This is a Scope of Work document from the State of Nevada, Office of the Military, for the Henderson Front Gate Replacement project at the Henderson Armory located at 151 E Horizon Ridge Parkway, Henderson, Nevada. The project seeks qualified contractors to upgrade current gate operations and swing arms, with additional chain link and barbed wire repairs required. The scope of work includes installing approximately 20 linear feet of 6-foot to 12-foot chain link fence on the south double gates, installing four steel pedestal stands on posts for new gate operators with black powder coating, removing four existing gate operator arms, supplying and installing four swing gate operators with battery backup (LiftMaster CSW24UL units), installing new loop detectors and connecting them with existing loop sensors, testing gates for proper operation, and fixing or replacing approximately 320 feet of barbed wire. The contractor is responsible for providing all materials, tools, hardware, and labor necessary to complete the project, as well as the proper disposal of all removed materials.
The document does not specify response dates, due dates, site visit requirements, bidders' meetings, award dates, contract terms, pricing terms, set-asides, incumbents, funding requirements, or amounts. Contractors are required to disclose the geographical location of services in their bid proposals and must include all work deemed necessary to complete the project as outlined in the scope of work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Henderson Front Gate Replacement Invitation to Bid.doc | DOC document | |
| Quote Instructions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment AA
State of Nevada, Office of the military Facilities Maintenance Scope of Work Summary
Date: July 8, 2026 Project: HENDERSON – Front Gate Replacement
General Intention: This scope of work is intended to include all the work required to complete the project described below. Contractors who submit bids are required to include and disclose in their bid all work deemed necessary to complete the project.
Task(s):
The State of Nevada, The Office of the Military, is seeking bids/proposals from qualified contractors to provide services for an upgrade to the current gate operations along with the swing arms. Some chain link and barb wire fix is also required. Please see scope of work below for detail breakdown. The Geographical location of service must be specified in the bid proposal.
Scope of Work:
The contractor shall provide services for an upgrade to the current gate operations with swing arms. The contractor is also responsible for all materials, tools, hardware, and labor to complete this project. Contractor is also responsible for properly disposing of all materials that have been removed from this project.
· Install approx. 20 lineal feet of 6’ to 12’ chain link fence on the south double gates to accommodate new gate operator for north gate leaf.
· Install (4) each steel pedestal stands on posts for new gate operators.
· Powder coat stands black prior to install.
· Remove (4) existing gate operator arms
· Supply and install (4) swing gate operators with battery backup LiftMaster CSW24UL
· Install new loop detectors and connect with existing loop sensors
· Test gates for proper operation
· Fix or replace approx. 320ft of barb wire.
Location:
HENDERSON ARMORY
151 E Horizon Ridge Pkwy Henderson, NV 89002