CSCII RFP Solicitation Package. Please note all referenced attachments/exhibits are embedded within the main RFP PDF document and should appear on the left pane when opening the file (ensure you use Adobe Acrobat).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 09:00 AM local time 01 Sep 2016

X

A X B

C D

EX

X G F 27 - 33

34 - 48 X H 49 - 56 miguel.a.colungahuerta.civ@mail.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

1 56

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

HC1028 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

(via WWW-see Section L.2.9) conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

MIGUEL A. COLUNGA-HUERTA 618-229-9571

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 5

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 8 - 11 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 12 - 17 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

18 - 25

PART II - CONTRACT CLAUSES

DISA/DITCO-SCOTT-PL83

2300 EAST DRIVE

SCOTT AFB IL 62225-5406

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

02 Aug 2016

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

HC1028-16-R-0012

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0001 5 Years CSCII - Base Period

FFP

Communications Capacity Services Contract 5-Year Base Ordering Period (will be from date of award through 60 months) FOB: Destination

MAX

NET AMT

UNIT UNIT PRICE MAX AMOUNT

1001 1 Years OPTION CSCII - Option Period 1

FFP

Communications Capacity Services Contract

UNIT UNIT PRICE MAX AMOUNT

2001 1 Years OPTION CSCII - Option Period 2

FFP

UNIT UNIT PRICE MAX AMOUNT

3001 1 Years OPTION CSCII - Option Period 3

FFP

UNIT UNIT PRICE MAX AMOUNT

4001 1 Years OPTION CSCII - Option Period 4

FFP

UNIT UNIT PRICE MAX AMOUNT

5001 1 Years OPTION CSCII - Option Period 5

FFP

CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

$15,000,000.00 $902,000,000.00

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 1001 Destination Government Destination Government 2001 Destination Government Destination Government 3001 Destination Government Destination Government 4001 Destination Government Destination Government 5001 Destination Government Destination Government

CLAUSES INCORPORATED BY REFERENCE

52.246-4 Inspection Of Services--Fixed Price AUG 1996 52.246-16 Responsibility For Supplies APR 1984

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC

0001 N/A N/A N/A N/A

1001 N/A N/A N/A N/A

2001 N/A N/A N/A N/A

3001 N/A N/A N/A N/A

4001 N/A N/A N/A N/A

5001 N/A N/A N/A N/A

52.242-15 Stop-Work Order AUG 1989 52.242-17 Government Delay Of Work APR 1984

Section G - Contract Administration Data

252.204-7002 Payment For Subline Items Not Separately Priced DEC 1991 252.245-7002 Reporting Loss of Government Property APR 2012 252.245-7003 Contractor Property Management System Administration APR 2012

CLAUSES INCORPORATED BY FULL TEXT

52.204-9000 POINTS OF CONTACT (AUG 2005)

Contracting Officer Name: Lisa A. O’Donnell Organization/Office Symbol: DISA/DITCO/PL8322 Phone No.: 618-229-9721 E-Mail Address: lisa.a.odonnell.civ@mail.mil

Contract Specialist Name: Miguel A. Colunga-Huerta Organization/Office Symbol: DISA/DITCO/PL8322 Phone No.: 618-229-9571 E-Mail Address: miguel.a.colungahuerta.civ@mail.mil

COR/Mission Partner Point of Contact (Note: To be filled in upon contract award)

Name:

Organization/Office Symbol:

Phone No.:

E-Mail Address:

Alternate COR/Mission Partner Point of Contact (Note: To be filled in upon contract award)

Name:

Phone No.:

E-Mail Address:

Contractor Point of Contact (Note: To be filled in upon contract award)

Contractor Legal Business Name:

DUNS:

CAGE CODE:

Contractor POC:

E-Mail Address:

Phone Number:

(End of clause)

52.204-9001 CONTRACT/ORDER CLOSEOUT—FIXED-PRICE, TIME-AND-MATERIALS, OR LABOR-

HOURS (JAN 2007)

Timely contract closeout is a priority under this contract/order. The Contractor shall submit a final invoice within ninety (90) calendar days after the expiration of this contract/order, unless the Contractor requests and is granted an extension by the Contracting Officer, in writing. In addition, and concurrent with the submission of the final invoice, the Contractor shall notify the Contracting Officer of the amount of excess funds that can be deobligated from this contract/order so the closeout process can begin as soon as possible upon expiration of this contract/order.

A bilateral contract/order closeout modification will be forwarded to the Contractor by the Contracting Officer and must be signed by the Contractor and returned to the Contracting Officer within thirty (30) calendar days of issuance of the modification. A Contractor’s failure to respond and/or sign the bilateral closeout modification within thirty

(30) calendar days of receipt will constitute approval of the terms of the modification and the modification will subsequently be processed unilaterally by the Contracting Officer to deobligate excess funds and close this contract/order.

If this contract/order contains option periods, the Contractor is required to submit an invoice within ninety (90) calendar days after expiration of the base period of performance and the expiration of each exercised option period of performance to allow for deobligation of excess funds that were obligated in those respective periods of performance.

52.237-9001 ENTERPRISE-WIDE CONTRACTOR MANPOWER REPORTING APPLICATION (eCMRA)

REPORTING (JAN 2015)

The contractor shall ensure ALL contractor labor hours including subcontractor, at all levels/tiers, labor hours required for the performance of services provided under this contract are reported via a secure data collection site.

The contractor and all subcontractors, at all levels/tiers, providing direct labor under this contract shall report complete and accurate data for the labor executed during the period of performance during each Government fiscal year (FY), which runs from October 1 to September 30. The Contractor shall input the data into the appropriate eCMRA reporting tool, which can be accessed via a secure web site at http://www.ecmra.mil/. There are four separate eCMRA tools: Army, Air Force, Navy and All Other Defense Components. The appropriate eCMRA reporting tool to use is determined by the requiring activity being supported (e.g., if DISA awards a contract for an Air Force requiring activity, the contractor shall load the required reporting data in the “Department of Air Force CMRA” tool). While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. The contractor shall completely fill in all required data fields. The contractor shall enter initial data into the appropriate eCMRA tool to establish the basic contract record no later than 15 working days after receipt of contract award or contract modification incorporating this clause. The contractor shall notify the COR when the basic contract record has been established in the appropriate eCMRA tool.

eCMRA User Manuals and Frequently Asked Questions (FAQs) are available at http://www.ecmra.mil/

Contractors may direct technical questions to the eCMRA help desk at usaf.pentagon.saf-aq.mbx.cmra-help-desk-dod@mail.mil

DFARS 252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)

(a) Definitions. As used in this clause— “Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:

(1) Document type. The Contractor shall use the following document type(s).

Invoice and Receiving Report (Combo)

Note: If a “Combo” document type is identified but not supportable by the Contractor’s business systems, an “Invoice” (stand-alone) and “Receiving Report” (stand-alone) document type may be used instead.)

(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.

Not Applicable

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC HQ0131

Issue By DoDAAC HC1028

Admin DoDAAC HC1028

Inspect By DoDAAC (Will be provided on award document)

Service Approver (DoDAAC) (Will be provided on award document)

Service Acceptor (DoDAAC) (Will be provided on award document)

Accept at Other DoDAAC N/A

Ship To Code N/A

Ship From Code N/A

Mark For Code N/A

LPO DoDAAC N/A

DCAA Auditor DoDAAC N/A

Other DoDAAC(s) N/A

(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.

(5) WAWF email notifications. The Contractor shall enter the e-mail address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system:

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

Payment Processing Questions: Contact the following DFAS office as specified in the contract/order:

Columbus Center: 1-800-756-4571 HQ0131 – Option 2 – Then Option 2

Additional DISA WAWF guidance and information for both contractor and government personnel is available at:

http://www.ditco.disa.mil/hq/WAWF

(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.

Section H - Special Contract Requirements

252.232-7007 LIMITATION OF GOVERNMENT'S OBLIGATION (APR 2014)

(a) Contract line item(s) (clause to be included and filled in on individual task orders) is/are incrementally funded. For this/these item(s), the sum of of the total price is presently available for payment and allotted to this contract. An allotment schedule is set forth in paragraph (j) of this clause.

(b) For items(s) identified in paragraph (a) of this clause, the Contractor agrees to perform up to the point at which the total amount payable by the Government, including reimbursement in the event of termination of those item(s) for the Government's convenience, approximates the total amount currently allotted to the contract. The Contractor is not authorized to continue work on those item(s) beyond that point. The Government will not be obligated in any event to reimburse the Contractor in excess of the amount allotted to the contract for those item(s) regardless of anything to the contrary in the clause entitled "TERMINATION FOR THE CONVENIENCE OF THE GOVERNMENT." As used in this clause, the total amount payable by the Government in the event of termination of applicable contract line item(s) for convenience includes costs, profit and estimated termination settlement costs for those item(s).

(c) Notwithstanding the dates specified in the allotment schedule in paragraph (j) of this clause, the Contractor will notify the Contracting Officer in writing at least ninety days prior to the date when, in the Contractor's best judgment, the work will reach the point at which the total amount payable by the Government, including any cost for termination for convenience, will approximate 85 percent of the total amount then allotted to the contract for performance of the applicable item(s). The notification will state (1) the estimated date when that point will be reached and (2) an estimate of additional funding, if any, needed to continue performance of applicable line items up to the next scheduled date for allotment of funds identified in paragraph (j) of this clause, or to a mutually agreed upon substitute date. The notification will also advise the Contracting Officer of the estimated amount of additional funds that will be required for the timely performance of the item(s) funded pursuant to this clause, for subsequent period as may be specified in the allotment schedule in paragraph (j) of this clause, or otherwise agreed to by the parties. If after such notification additional funds are not allotted by the date identified in the Contractor's notification, or by an agreed substitute date, the Contracting Officer will terminate any item(s) for which additional funds have not been allotted, pursuant to the clause of this contract entitled "TERMINATION FOR THE

CONVENIENCE OF THE GOVERNMENT".

(d) When additional funds are allotted for continued performance of the contract line item(s) identified in paragraph

(a) of this clause, the parties will agree as to the period of contract performance which will be covered by the funds.

The provisions of paragraph (b) through (d) of this clause will apply in like manner to the additional allotted funds and agreed substitute date, and the contract will be modified accordingly.

(e) If, solely by reason of failure of the Government to allot additional funds, by the dates indicated below, in amounts sufficient for timely performance of the contract line item(s) identified in paragraph (a) of this clause, the Contractor incurs additional costs or is delayed in the performance of the work under this contract and if additional funds are allotted, an equitable adjustment will be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of the item(s), or in the time of delivery, or both. Failure to agree to any such equitable adjustment hereunder will be a dispute concerning a question of fact within the meaning of the clause entitled "disputes."

(f) The Government may at any time prior to termination allot additional funds for the performance of the contract line item(s) identified in paragraph (a) of this clause.

(g) The termination provisions of this clause do not limit the rights of the Government under the clause entitled "DEFAULT." The provisions of this clause are limited to work and allotment of funds for the contract line item(s) set forth in paragraph (a) of this clause. This clause no longer applies once the contract if fully funded except with regard to the rights or obligations of the parties concerning equitable adjustments negotiated under paragraphs (d) or

(e) of this clause.

(h) Nothing in this clause affects the right of the Government to this contract pursuant to the clause of this contract entitled "TERMINATION FOR CONVENIENCE OF THE GOVERNMENT."

(i) Nothing in this clause shall be construed as authorization of voluntary services whose acceptance is otherwise prohibited under 31 U.S.C. 1342.

(j) The parties contemplate that the Government will allot funds to this contract in accordance with the following schedule:

On execution of contract $--

(month) (day), (year) $----

(month) (day), (year) $----

(month) (day), (year) $---- (clause to be included and filled in on individual task orders)

ENVIRONMENTAL CONDITIONS

H.1 Environmental Conditions

This special section is intended to be used for all contracts at the Federal Center, 4300 Goodfellow, St. Louis, MO (DECC St. Louis).

Summary of Goodfellow Federal Complex Environmental Conditions

This effort may require work at DECC St. Louis at the Goodfellow Federal Complex. Many of the facilities and grounds on the Goodfellow Federal Complex, St. Louis, Missouri have been reported to have environmental concerns with varying concentrations of hazardous chemicals/materials. Contractors are required to include the costs of working around and in these known conditions at the Goodfellow complex in the proposal.

The following is a list of reported environmental contaminants that have the potential to affect worker safety and health. This list has been extracted from the 2013 Tetra Tech Occupational Exposure Evaluation Report.

ASBESTOS

Amosite – trace amounts up to 6% Chrysotile – trace amounts up to 10% Crocidolite – trace amounts Total Asbestos – trace amounts up to 15%

TOXIC METALS

Antimony Arsenic Barium Beryllium Cadmium Chromium Copper Lead Mercury

Selenium Silver

Polychlorinated Biphenyls (PCBs) Decachlorobiphenyls Dichlorobiphenyls Heptachlorobiphenyls Hexachlorobiphenyls Monochlorobiphenyls Nonachlorobiphenyls Octachlorobiphenyls Pentachlorobiphenyls Tetrachlorobiphenyls Trichlorobiphenyls Total PCBs

Total Petroleum Hydrocarbons (TPHs) Diesel Range Organics Gasoline Range Organics Oil Range Organics

Volatile Organic Compounds (VOCs) Acetone Carbon disulfide Dichloroethylene, 1,2-cis- Methyl Ethyl Ketone Trichloroethene Xylenes, m Xylenes, p Total Xylenes

Semi-Volatile Organic Compounds (SVOCs) Acenaphthene Acenaphthylene Acetophenone Anthracene Benzaldehyde Benz(a)Anthracene Benzo(a)Pyrene Benzo(b)Flouranthene Benzo(g,h,i)Perylene Benzo(k)Fluoranthene Bis(2-Ethyl Hexyl) Phthalate Biphenyl, 1,1´- Butyl Benzyl Phthalate Caprolactam Carbazole Carbon disulfide Chlorophenyl Phenyl Ether, 4- Chrysene Dibenzo(a,h)Anthracene Dibenzofuran Dichlorophenol, 2,4- Diethyl Phthalate

Dimethylphenol, 2,4- Di-n-Butyl Phthalate Di-n-Octylphthalate Fluoranthene Fluorene Hexachlorocyclohexane, beta Indeno(1,2,3-cd)Pyrene Methylnaphthalene, 2- Methylphenol, 2-, 3-, 4- (Cresols) Naphthalene Nitroaniline, 3- Nitrophenol, 4- Nitrosodiphenylamine, n- Pentachlorophenols Phenanthrene Phenol Pyrene

POISON

Cyanide

EXPLOSIVE COMPOUNDS AND PHOSPHORUS

2,4-Dinitrotoluene 2,6-Dinitrotoluene 2-Amino-4, 6-Dinitrotoluene 4-Nitrotoluene Nitrobenzene Phosphorus

Approximately 82 total contaminants that have the potential to affect worker safety and health were reported by Tetra Tech on site (Cyanide was reported by SCS Engineers 2008 Combined Preliminary Assessment/Site Inspection Report (starting on page 4-19) and is provided as part of this list of contaminants). The added totals of each variation of the asbestos contaminants, the xylene contaminants, and the polychlorinated biphenyls contaminates may make them a potential safety and health hazard as well. A list of contaminants and their locations can be found in Appendix B, Tables 1 through 14 of the 2013 Tetra Tech Occupational Exposure Evaluation Report. The 2013 Tetra Tech report does not constitute a complete list of potential contaminants.

Twenty-one additional reports assessing various aspects of the environmental contamination on the Goodfellow Federal Complex are available upon request. Safety Fact Sheets are provided for each contaminant. All these reports were compiled to assess the contamination from an environmental perspective. Environmental action thresholds do not necessarily correlate into OSHA permissible exposure limits (PELs) because they were the result of testing/sampling in a static environment. OSHA requirements involve sampling/testing using an 8-hour time weighted average/30-minute excursion limit while each job specific activity is in progress.

Contractors whose employees are engaged in work that could potentially put them into contact with, or disturb any and/or all of the environmental contaminants present in such a manner as to make them airborne, shall perform the appropriate hazard assessment and testing to protect their employees according to OSHA 29 CFR 1910 and 1926 regulations. The hazard assessment shall include industrial hygiene sampling/testing as necessary. Contractors shall take the appropriate protective measures to ensure their actions do not place other federal complex personnel at risk (i.e. post warning signs, install engineering controls, create barriers, erect containment, control access to work areas, etc.). Contractors will also ensure their employees decontaminate as required prior to leaving work areas and/or the job site so they do not cross contaminate non-contaminated areas/spaces.

Multiple building interiors (first and second floors) are reported to contain varying amounts of lead based-paint and/or particulate lead and mercury that could affect worker safety and health. These areas include, but are not limited to, the space above the ceiling tiles and some mechanical rooms. Asbestos containing materials are also present in some of these spaces and are currently being managed in place. Work in areas that has the potential to disturb asbestos containing materials requires an asbestos work permit to be issued from the GSA Building Manager prior to the start of work. This permit should be worked directly with GSA with the knowledge of the COR Efforts that may affect asbestos containing materials require a pre-assessment to be accomplished and coordination through the GSA Region 6 Asbestos Program Manager prior to the start of work. The asbestos pre-assessment for construction projects is typically performed by GSA.

Multiple building interiors (basement/basement crawl spaces/utility tunnels) are reported to contain a variety of environmental contaminants that could affect worker safety and health. Contamination includes friable asbestos in the soil, different toxic metals on building surfaces and in the soil, different explosive compounds and phosphorus in the sump water and soil, and different organic compounds in the sump water and soil. Asbestos containing materials are also present in some of these spaces and are currently being managed in place. Work in areas that has the potential to disturb asbestos containing materials requires an asbestos work permit to be issued from the GSA Building Manager prior to the start of work. This permit should be worked directly with GSA with the knowledge of the COR Efforts that may affect asbestos containing materials require a pre-assessment to be accomplished and coordination through the GSA Region 6 Asbestos Program Manager with the knowledge of the COR prior to the start of work. The asbestos pre-assessment for construction projects is typically performed by GSA.

Multiple building interiors (building electrical spaces and interior/exterior ground soil and groundwater) are reported to contain a variety of polychlorinated biphenyl (PCB) contamination. Building interior contamination includes PCBs in the concrete where PCB oil filled transformers used to be. The crawlspace soil of Building 108B is also reported to have PCB contamination. Exterior building ground soil and groundwater is also contaminated with PCB contamination that could affect worker safety and health. Maintenance and construction projects that could disturb PCB laden concrete, interior/exterior ground soil or groundwater must be coordinated through the GSA Region 6 Environmental Program Manager prior to the start of work.

Multiple federal complex exterior areas are reported to be contaminated with a variety of environmental contaminants in the ground soil and groundwater that could affect worker safety and health. Maintenance and construction projects that could disturb federal complex grounds/ground water must be coordinated through the GSA Region 6 Environmental Program Manager with the knowledge of the COR prior to the start of work.

The 2013 Tetra Tech Occupational Exposure Evaluation Report and the SCS Engineers 2008 Combined Preliminary Assessment/Site Inspection Report with Addendum 1(Interim Lead Wipe Sampling and Assessment Report) can be reviewed. GSA Region 6 Public Building Services has made these reports and the twenty-one additional reports available in a reading library located at the Goodfellow Federal Office Complex, GSA St. Louis West Field Office, 4300 Goodfellow Boulevard, St. Louis Missouri.

Reports incorporated by reference – 2008 SCS Engineers Combined Preliminary Assessment/Site Inspection Report with Addendum 1(Interim Lead Wipe Sampling and Assessment Report, 2013 Tetra Tech Occupational Exposure Evaluation Report, and 2016 OCCU-TECH Asbestos Air, Lead Air, and Lead Dust Investigation report. These reports can be reviewed at the reading room located at the Federal Center in Building 107.

If new information or updates become available concerning the environmental conditions at the Goodfellow complex they will be made available via the GSA website at:

www.gsa.gov/goodfellow.

If your organization would like to receive updates from GSA’s Environmental Team, please add your email address to the GSA distribution list by visiting the following website and registering:

https://docs.google.com/forms/d/1Y4UMAMcYYu2Co_TM7ERpuuNq3mWJGlSkA9b5GXcOsE/viewform?c=0& w=1

SUBMITTALS

Prior to beginning any work (after contract award and prior to Notice to Proceed), the contractor shall prepare and submit to the GSA Region 6 Environmental Program Manager with knowledge of the COR for review, a site specific work/safety plan describing the protective measures they will use. Contractors shall provide any sampling/testing results as part of the safety plan. The site specific work/safety plan shall include but not be limited to the following (cover the who, what, when, where, why, and how):

a. Introduction

b. Location and Description

c. Hazard Assessment

Assessment Personal Protective Equipment Required

d. Responsibilities

e. Operating Procedures

Must include disposal procedures for contaminated materials/PPE

f. Emergency Procedures

Emergency Contacts Emergency Procedures Accident/Incident Reporting

Section I - Contract Clauses

52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or

Improper Activity

MAY 2014

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal

Transactions

OCT 2010

52.203-13 Contractor Code of Business Ethics and Conduct OCT 2015 52.203-17 Contractor Employee Whistleblower Rights and Requirement

To Inform Employees of Whistleblower Rights

APR 2014

52.204-2 Security Requirements AUG 1996 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber

Content Paper

MAY 2011

52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

OCT 2015

52.204-13 System for Award Management Maintenance JUL 2013 52.207-3 Right of First Refusal of Employment MAY 2006 52.209-6 Protecting the Government's Interest When Subcontracting

With Contractors Debarred, Suspended, or Proposed for Debarment

OCT 2015

52.209-7 Information Regarding Responsibility Matters JUL 2013 52.209-9 Updates of Publicly Available Information Regarding

Responsibility Matters

JUL 2013

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.219-4 Notice of Price Evaluation Preference for HUBZone Small

Business Concerns

OCT 2014

52.219-8 Utilization of Small Business Concerns OCT 2014

52.219-9 ALT II

(Dev)

Small Business Subcontracting Plan (Deviation 2013-O0014)

- Alternate II

OCT 2015

52.219-16 Liquidated Damages-Subcontracting Plan JAN 1999 52.222-3 Convict Labor JUN 2003 52.222-19 Child Labor -- Cooperation with Authorities and Remedies FEB 2016 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity APR 2015 52.222-29 Notification Of Visa Denial APR 2015 52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans FEB 2016 52.222-40 Notification of Employee Rights Under the National Labor

Relations Act

DEC 2010

52.222-50 Combating Trafficking in Persons MAR 2015 52.222-54 Employment Eligibility Verification OCT 2015 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011

52.223-6 Drug-Free Workplace MAY 2001 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

AUG 2011

52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.227-14 Rights in Data--General MAY 2014 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.229-3 Federal, State And Local Taxes FEB 2013 52.229-6 Taxes--Foreign Fixed-Price Contracts FEB 2013 52.232-1 Payments APR 1984 52.232-8 Discounts For Prompt Payment FEB 2002 52.232-17 Interest MAY 2014 52.232-18 Availability Of Funds APR 1984 52.232-23 Assignment Of Claims MAY 2014 52.232-25 Prompt Payment JUL 2013 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

JUL 2013

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

52.233-1 Alt I Disputes (May 2014) - Alternate I DEC 1991 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.237-2 Protection Of Government Buildings, Equipment, And

Vegetation

APR 1984

52.237-3 Continuity Of Services JAN 1991 52.239-1 Privacy or Security Safeguards AUG 1996 52.242-13 Bankruptcy JUL 1995 52.243-1 Alt II Changes--Fixed-Price (Aug 1987) - Alternate II APR 1984 52.244-6 Subcontracts for Commercial Items JUN 2016 52.245-1 Government Property APR 2012 52.245-9 Use And Charges APR 2012 52.246-25 Limitation Of Liability--Services FEB 1997 52.248-1 Value Engineering OCT 2010 52.249-2 Termination For Convenience Of The Government (Fixed-

Price)

APR 2012

52.249-8 Default (Fixed-Price Supply & Service) APR 1984 52.252-6 Authorized Deviations In Clauses APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies

DEC 2008

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General DEC 2012 252.204-7000 Disclosure Of Information AUG 2013 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A FEB 2014 252.204-7005 Oral Attestation of Security Responsibilities NOV 2001 252.204-7008 Compliance With Safeguarding Covered Defense Information

Controls

DEC 2015

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting.

DEC 2015

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By

The Government of a Country that is a State Sponsor of Terrorism

OCT 2015

252.215-7008 Only One Offer OCT 2013 252.219-7003 Small Business Subcontracting Plan (DOD Contracts)--Basic MAR 2016 252.222-7002 Compliance With Local Labor Laws (Overseas) JUN 1997 252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or

Hazardous Materials

SEP 2014

252.225-7048 Export-Controlled Items JUN 2013 252.226-7001 Utilization of Indian Organizations and Indian-Owned

Economic Enterprises, and Native Hawaiian Small Business Concerns

SEP 2004

252.227-7013 Rights in Technical Data--Noncommercial Items FEB 2014 252.227-7014 Rights in Noncommercial Computer Software and

Noncommercial Computer Software Documentation

FEB 2014

252.227-7015 Technical Data--Commercial Items FEB 2014 252.227-7016 Rights in Bid or Proposal Information JAN 2011 252.227-7017 Identification and Assertion of Use, Release, or Disclosure

Restrictions

JAN 2011

252.227-7030 Technical Data--Withholding Of Payment MAR 2000 252.227-7037 Validation of Restrictive Markings on Technical Data JUN 2013 252.229-7002 Customs Exemptions (Germany) JUN 1997 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

JUN 2012

252.232-7008 Assignment of Claims (Overseas) JUN 1997 252.232-7010 Levies on Contract Payments DEC 2006 252.233-7001 Choice of Law (Overseas) JUN 1997 252.237-7023 Continuation of Essential Contractor Services OCT 2010 252.239-7001 Information Assurance Contractor Training and Certification JAN 2008 252.239-7010 Cloud Computing Services AUG 2015 252.239-7018 Supply Chain Risk OCT 2015 252.239-7999 (Dev) Cloud Computing Services. (DEVIATION 2015-O0011) FEB 2015 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.245-7004 Reporting, Reutilization, and Disposal MAR 2015 252.246-7007 Contractor Counterfeit Electronic Part Detection and

Avoidance System

MAY 2014

252.247-7023 Transportation of Supplies by Sea APR 2014 252.247-7024 Notification Of Transportation Of Supplies By Sea MAR 2000

52.209-9000 ORGANIZATIONAL AND CONSULTANT CONFLICTS OF INTEREST (OCCI) (DEC 2005)

(a) An offeror shall identify in its proposal, quote, bid or any resulting contract, any potential or actual Organizational and Consultant Conflicts of Interest (OCCI) as described in FAR Subpart 9.5. This includes actual or potential conflicts of interests of proposed subcontractors. If an offeror identifies in its proposal, quote, bid or any resulting contract, a potential or actual conflict of interests the offeror shall submit an Organizational and Consultant Conflicts of Interest Mitigation Plan to the contracting officer. The Organizational and Consultant Conflicts of Interest Mitigation Plan shall describe how the offeror addresses potential or actual conflicts of interest and identify how they will avoid, neutralize, or mitigate present or future conflicts of interest.

(b) Offerors must consider whether their involvement and participation raises any OCCI issues, especially in the following areas when:

(1) Providing systems engineering and technical direction.

(2) Preparing specifications or work statements and/or objectives.

(3) Providing evaluation services.

(4) Obtaining access to proprietary information.

(c) If a prime contractor or subcontractor breaches any of the OCCI restrictions, or does not disclose or misrepresents any relevant facts concerning its conflict of interest, the government may take appropriate action, including terminating the contract, in additional to any remedies that may be otherwise permitted by the contract or operation of law.

52.216-19 ORDER LIMITATIONS. (OCT 1995)

(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $100, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.

(b) Maximum order. The Contractor is not obligated to honor:

(1) Any order for a single item in excess of $1,500,000;

(2) Any order for a combination of items in excess of $10,000,000; or

(3) A series of orders from the same ordering office within 60 days that together call for quantities exceeding the limitation in subparagraph (1) or (2) above.

(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) above.

(d) Notwithstanding paragraphs (b) and (c) above, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within 5 days after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons.

Upon receiving this notice, the Government may acquire the supplies or services from another source.

52.216-22 INDEFINITE QUANTITY. (OCT 1995)

(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the "maximum". The Government shall order at least the quantity of supplies or services designated in the Schedule as the "minimum".

(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after the end of the period of performance on the order.

52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 15 days prior to the expiration of the current performance period.

52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within 15 days;

provided that the Government gives the Contractor a preliminary written notice of its intent to extend at 30 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 120 months.

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JULY 2013)

(a) Definitions. As used in this clause--

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is ``not dominant in its field of operation'' when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts--

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it ( ) is, ( ) is not a small business concern under NAICS Code - assigned to contract number .

(Contractor to sign and date and insert authorized signer's name and title).

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil/

252.216-7006 ORDERING (MAY 2011)

(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the contract schedule. Such orders may be issued from date of award through the end of the base period (and any option years, if exercised).

(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

(c)(1) If issued electronically, the order is considered ``issued'' when a copy has been posted to the Electronic Document Access system, and notice has been sent to the Contractor.

(2) If mailed or transmitted by facsimile, a delivery order or task order is considered ``issued'' when the Government deposits the order in the mail or transmits by facsimile. Mailing includes transmittal by U.S. mail or private delivery services.

(3) Orders may be issued orally only if authorized in the schedule.

(End of Clause)

252.225-7043 ANTITERRORISM/FORCE PROTECTION POLICY FOR DEFENSE CONTRACTORS

OUTSIDE THE UNITED STATES (JUN 2015)

(a) Definition. United States, as used in this clause, means, the 50 States, the District of Columbia, and outlying areas.

(b) Except as provided in paragraph (c) of this clause, the Contractor and its subcontractors, if performing or traveling outside the United States under this contract, shall--

(1) Affiliate with the Overseas Security Advisory Council, if the Contractor or subcontractor is a U.S. entity;

(2) Ensure that Contractor and subcontractor personnel who are U.S. nationals and are in-country on a non-transitory basis, register with the U.S. Embassy, and that Contractor and subcontractor personnel who are third country nationals comply with any security related requirements of the Embassy of their nationality;

(3) Provide, to Contractor and subcontractor personnel, antiterrorism/force protection awareness information commensurate with that which the Department of Defense (DoD) provides to its military and civilian personnel and their families, to the extent such information can be made available prior to travel outside the United States; and

(4) Obtain and comply with the most current antiterrorism/force protection guidance for Contractor and subcontractor personnel.

(c) The requirements of this clause do not apply to any…