This is a Special Provisions document issued by the County of Sacramento Community Services Agency, Department of Transportation for Contract No. 41022, the Hazel Avenue at US-50 Interchange Segment 1 Tree Removal Project, a CUPCCAA Project. The project scope includes furnishing all labor, materials, and equipment necessary to perform traffic control, tree removal with stumps remaining two feet above grade, and related work as specified. Bids opened on November 12, 2026, with a contract completion time of twenty working days. The project requires strict compliance with the County of Sacramento 2024 Standard Construction Specifications dated November 1, 2024, and the State of California Department of Transportation Standard Specifications dated 2025. Key preliminary requirements include submission of a Baseline Schedule and Traffic Control Plans as the first order of work, with tree removal to be completed prior to January 31st to avoid nesting season restrictions. The contractor must obtain an Encroachment Permit from Caltrans under parent permit number 03-26-N-LT-1977 prior to any work within State right-of-way, with an onsite pre-construction meeting required a minimum of two weeks before work begins.
The contract includes significant insurance requirements: General Liability with limits of $2,000,000 per occurrence and $4,000,000 aggregate; Automobile Liability with a $2,000,000 combined single limit; and Contractor's Pollution Liability with $1,000,000 per occurrence and aggregate if hazardous materials are encountered. Liquidated damages for delay are assessed at $2,800 per calendar day for work exceeding twenty working days. Additional liquidated damages apply to freeway closures on US-50, ranging from $1,280 to $2,570 per ten-minute interval depending on the time of day, with damages limited to five percent of total bid per occurrence. The project includes detailed tree protection requirements, with all existing trees not designated for removal requiring inventory, arborist assessment, and protective measures. A Certified Arborist must be retained and approved at least four working days before clearing operations commence. No night work is permitted without written Engineer approval, and all traffic lanes must remain open daily by end of shift. Construction is suspended during the November/December holiday moratorium, defined as the four-day Thanksgiving weekend and December 18 through January 1.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COUNTY OF SACRAMENTO
COMMUNITY SERVICES AGENCY
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FOR:
HAZEL AVENUE AT US-50 INTERCHANGE
SEGMENT 1 TREE REMOVAL PROJECT
CUPCCAA PROJECT
CONTRACT NO. 41022
NOTE: THE COUNTY OF SACRAMENTO 2024 STANDARD CONSTRUCTION SPECIFICATIONS, DATED
NOVEMBER 1, 2024 AND THE STATE OF CALIFORNIA DEPARTMENT ON TRANSPORTATION STANDARD SPECIFICATIONS DATED 2025 ARE HEREBY MADE PART OF THESE SPECIFICATIONS. A COPY OF THE
SACRAMENTO STANDARD CONSTRUCTION SPECIFICATIONS MAY BE DOWNLOADED FROM THE
COUNTY WEBSITE AT HTTPS://SACCOUNTYSPECS.SACCOUNTY.GOV
Bids Open: November 12, 2026
DAVE DEFANTI, CONTRACT NO. 41022
Deputy County Executive DATE: October 23, 2026
RON E. VICARI, Director
Department of Transportation
COUNTY OF SACRAMENTO
COMMUNITY SERVICES AGENCY
DEPARTMENT OF TRANSPORTATION
HAZEL AVENUE AT US-50 INTERCHANGE
CUPCCAA PROJECT
COUNTY CONTRACT NO. 41022
SPECIAL PROVISIONS
GENERAL
TO BE SUPPLEMENTED WITH 2024 SACRAMENTO COUNTY STANDARD
CONSTRUCTION SPECIFICATIONS DATED NOVEMBER 1, 2024 AND THE STATE OF
CALIFORNIA DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATIONS
DATED 2025.
THE SPECIAL PROVISIONS CONTAINED HEREIN HAVE BEEN PREPARED BY OR
UNDER THE DIRECTION OF THE FOLLOWING REGISTERED PEOPLE:
ROADWAY:
SIGNED: ______________________
Jake W. Weir, PE
Registered Civil Engineer
06/30/28
72382
JAKE
W. WEIR
CIVIL
CONTRACT NO. 41022 HAZEL AVENUE AT US-50 INTERCHANGE
i
TABLE OF CONTENTS
SECTION 1 – TERMS AND DEFINITIONS .......................................................................................................................... - 1 -
1-1 GENERAL ............................................................................................................................................................... - 1 - 1-1.01 STATE STANDARD PLANS LIST .......................................................................................................................... - 1 -
SECTION 2 - BID REQUIREMENTS AND CONDITIONS ...................................................................................................... - 1 -
2-8 SUBCONTRACTORS ............................................................................................................................................... - 1 -
SECTION 3 - AWARD AND EXECUTION OF CONTRACT .................................................................................................... - 1 -
3-3 AWARD OF CONTRACT .......................................................................................................................................... - 1 - 3-9 INSURANCE ........................................................................................................................................................... - 2 -
3-9.01 GENERAL LIABILITY ........................................................................................................................................... - 2 - 3-9.02 AUTOMOBILE LIABILITY.................................................................................................................................... - 2 - 3-9.03 WORKERS COMPENSATION ............................................................................................................................. - 2 - 3-9.08 CONTRACTOR’S POLLUTION LIABILITY INSURANCE ......................................................................................... - 2 -
SECTION 4 – SCOPE OF WORK ........................................................................................................................................ - 3 -
4-11 LANDS AND RIGHTS-OF-WAY ................................................................................................................................ - 3 - 4-13 DESCRIPTION OF WORK ........................................................................................................................................ - 3 -
SECTION 5 - CONTROL OF WORK AND MATERIALS ........................................................................................................ - 4 -
5-6 CONTRACTORS DISMISSAL OF UNSATISFACTORY EMPLOYEES ............................................................................ - 4 - 5-14 SUBSTITUTIONS ..................................................................................................................................................... - 4 - 5-16 MATERIALS SAMPLING AND TESTING ................................................................................................................... - 4 -
5-16.01 CONTROL OF MATERIALS ............................................................................................................................... - 4 -
SECTION 6 – LEGAL RELATIONS AND RESPONSIBILITIES ................................................................................................. - 5 -
6-10.03 ENCROACHMENT PERMITS ............................................................................................................................ - 5 - 6-11 EXISTING UTILITIES ................................................................................................................................................ - 5 -
SECTION 7 – PROSECUTION OF THE WORK .................................................................................................................... - 6 -
7-1.01 ORDER OF WORK ............................................................................................................................................. - 6 - 7-8.01 ALLOWABLE TIMES AND HOURS OF WORK ..................................................................................................... - 6 - 7-8.02 OFF-PERIOD WORK .......................................................................................................................................... - 6 - 7-8.06 LANE AND ROAD CLOSURES DURING NOVEMBER/DECEMBER HOLIDAY SEASON .......................................... - 6 -
7-12 DELAYS .................................................................................................................................................................. - 7 - 7-15 TIME OF COMPLETION .......................................................................................................................................... - 7 -
SECTION 8 – MEASUREMENT AND PAYMENT ................................................................................................................ - 7 -
8-10 LIQUIDATED DAMAGES FOR DELAY ...................................................................................................................... - 7 -
SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE ............................................................................................ - 7 -
10-9 SANITARY REGULATIONS ...................................................................................................................................... - 7 - 10-13 PROTECTION OF EXISTING TREES .......................................................................................................................... - 8 -
10-13.01 ARBORIST SERVICES ................................................................................................................................... - 10 - 10-14 TEMPORARY HIGH-VISIBILITY FENCE .................................................................................................................. - 10 -ii
SECTION 12 - SAFETY, PUBLIC CONVENIENCE, AND TRAFFIC CONTROL ........................................................................ - 11 -
12-1 SAFETY................................................................................................................................................................. - 11 - 12-2.02 PEDESTRIAN AND BICYCLE ACCESS .............................................................................................................. - 11 -
12-3 PUBLIC SAFETY AND TRAFFIC CONTROL .............................................................................................................. - 11 - 12-3.04 FURNISHING, INSTALLING, AND MAINTAINING TEMPORARY TRAFFIC CONTROLS ..................................... - 12 - 12-3.07 CONSTRUCTION SIGNS ................................................................................................................................. - 12 - 12-3.14 FREEWAY CLOSURES ..................................................................................................................................... - 13 -
SECTION 15 – CLEARING AND GRUBBING .................................................................................................................... - 19 -
15-1 GENERAL ............................................................................................................................................................. - 19 - 15-1.02 TREES, SHRUBS, GROUND COVER, AND LAWNS .......................................................................................... - 19 -
APPENDIX .................................................................................................................................................................... - 21 -
BID PROPOSAL ....................................................................................................................................................................... A PERMIT NO. 03-26-N-LT-1977 ............................................................................................................................................... B
- 1 -
SECTION 1 – TERMS AND DEFINITIONS
The 2024 County of Sacramento, Community Services Agency Standard Construction Specifications, dated November 1, 2024 and these Special Provisions shall control all work to be done under this contract. In case of conflict between these Special Provisions and the Standard Construction Specifications, these Special Provisions shall take precedence over and be used in lieu of the conflicting portions.
Unless otherwise specified, the California Department of Transportation (State) Specifications, Revised Standard Specifications, and State Standard Plans, dated 2025, shall be the version used when referenced in these Special Provisions.
The Standard Construction Specifications, which are incorporated by reference in the Contract Documents, may be downloaded from the County website at https://saccountyspecs.saccounty.gov
1-1 GENERAL
1-1.01 STATE STANDARD PLANS LIST
The State Standard Plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the appendix.
Title Plan
Number
Temporary Traffic Control Systems
Traffic Control System Tables for Lane and Ramp Closures T9
Traffic Control System for Lane Closures on Freeways and Expressways T10
Temporary Water Pollution Control
Temporary Water Pollution Control Details (Temporary High Visibility Fence) T65
SECTION 2 - BID REQUIREMENTS AND CONDITIONS
2-8 SUBCONTRACTORS
The following is added to the end of Section 2-8, “Subcontractors,” of the Standard Construction
Specifications:
Before subcontracted work starts, the Contractor shall submit a Subcontracting Request form (CEM- 1201).
SECTION 3 - AWARD AND EXECUTION OF CONTRACT
3-3 AWARD OF CONTRACT
The Contractor’s attention is directed to the provisions in Section 3-3, “Award of Contract,” of the Standard Construction Specifications.
If the Agency awards the contract, the award is made to the lowest responsible and responsive bidder.
- 2 -
3-9 INSURANCE
Contractor’s attention is directed to Section 3-9, “Insurance”, of the Standard Construction Specifications.
3-9.01 GENERAL LIABILITY
Subparagraph of the first paragraph of section 3-9.01, “General Liability” of the Standard Construction Specifications is amended to read as follows:
Each Occurrence Two Million Dollars ($2,000,000)
Products and Completed Operations Aggregate Four Million Dollars ($4,000,000)
Personal and Advertising Injury Two Million Dollars ($2,000,000)
General Aggregate Four Million Dollars ($4,000,000)
Fire Damage One Hundred Thousand Dollars ($100,000)
3-9.02 AUTOMOBILE LIABILITY
Subparagraph of the third paragraph of Section 3-9.02, “Automobile Liability” of the Standard Construction Specifications is amended to read as follows:
Bodily Injury and Property Damage
Combined Single Limit Two Million Dollars ($2,000,000)
3-9.03 WORKERS COMPENSATION
Subparagraph of the first paragraph of Section 3-9.03, “Workers Compensation,” of the Standard Construction Specifications is amended to read as follows:
• Contractor must comply with applicable sections of Title 8; CCR; Chapter 4-Division of
Industrial Safety.
3-9.08 CONTRACTOR’S POLLUTION LIABILITY INSURANCE
Section 3-9.08 “Contractor's Pollution Liability Insurance” of the Standard Construction Specifications is amended to read as follows:
In the event that hazardous materials are identified prior to construction, or are encountered as an unforeseen condition during construction, the Contractor, or its environmental Subcontractor, shall procure, maintain, and keep in force at all times during the term of the Contract, at the Contractor’s sole expense, Contractor’s Pollution Liability insurance with limits not less than:
Each Occurrence or Claim One Million Dollars ($1,000,000)
General Aggregate One Million Dollars ($1,000,000)
- 3 -
SECTION 4 – SCOPE OF WORK
4-11 LANDS AND RIGHTS-OF-WAY
The Contractor’s attention is directed to Section 4-11, “Lands and Rights-of-Way,” of the Standard Construction Specifications and these Special Provisions.
The County rights-of-way shall be used only for purposes that are necessary to perform the required work.
The Contractor shall not occupy the rights-of-way, or allow others to occupy the rights-of-way, for purposes, which are not necessary to perform the required work. Determination of “necessary to perform work” will be made by the Engineer if necessary.
Use of the Contractor's work areas shall be at the Contractor's own risk, and the County shall not be held liable for any damage to or loss of materials or equipment located within such areas. Utilities, including but not limited to water or electricity, will not be provided and shall be the sole responsibility of the Contractor.
Residence trailers will not be allowed within the County rights-of-way.
No vehicles, construction equipment, mobile home/office, supplies, materials or facilities shall be driven, parked, stockpiled or located within the driplines of oak trees.
The Contractor shall remove all equipment, materials, and rubbish from the work areas, which the Contractor occupies; and shall leave the areas in a presentable condition.
Full compensation for complying with the requirements of this section shall be considered incidental to the project and no additional compensation will be allowed therefor.
4-13 DESCRIPTION OF WORK
The work to be performed under this contract includes the furnishing of all labor, materials, and equipment for:
Project work includes traffic control, tree removal with stump two feet above grade to remain, and doing all other work specified on the plans in the specifications.
Other items or details not mentioned above that are required by these Special Provisions shall be performed, placed, constructed, or installed in accordance with the Standard Construction Specifications and these Special Provisions. The construction, materials, and workmanship for items of work on the plans, but not specifically mentioned in these Special Provisions are referred to the Standard Construction Specifications for conformance.
- 4 -
SECTION 5 - CONTROL OF WORK AND MATERIALS
5-6 CONTRACTORS DISMISSAL OF UNSATISFACTORY EMPLOYEES
The following is to be added to Section 5-6:
The Contractor shall be polite to citizens encountered during the course of work. Loud music, foul language, and cursing are not permitted.
5-14 SUBSTITUTIONS
Should the Contractor seek approval of a product other than the brand or brands named in these specifications, it shall furnish written evidence that such product conforms in all respects to the specified requirements, and that it has been used successfully elsewhere under similar conditions. Where the specified requirements involve conformance to recognized codes or standards, the Contractor shall furnish evidence of such conformance in the form of test or inspection reports, prepared by a recognized agency, and baring an authorized signature.
Manufacturer’s standard data and catalog cut sheets will not be considered sufficient in themselves, and the Engineer will not be responsible for seeking further data from the manufacturer, or for otherwise researching the project. Failure to provide complete data will be cause for rejection of the proposal.
5-16 MATERIALS SAMPLING AND TESTING
When a reference is made in the specifications to the “Laboratory” or “Transportation Laboratory,” the reference shall mean the Sacramento County Materials Test Lab or other laboratories authorized by the Engineer to test materials and work involved in the contract. This laboratory is located at 9665 Agriculture Lane, Sacramento, CA 95827, telephone (916) 875-5330.
The County uses a Quality Assurance Program (QAP) that uses samples and tests to ensure a material is produced to comply with the Contract. The County may examine the records and reports of tests the prime contractor performs if they are available at the job site. Schedule work to allow time for QAP sampling and testing.
5-16.01 CONTROL OF MATERIALS
The Contractor’s attention is directed to Section 5-13, “Quality of Materials and Workmanship,” Section 5-16, “Materials Sampling and Testing,” and Section 5-17, “Approval of Materials,” of the Standard Construction Specifications.
All materials required to complete the Work under this Contract shall be produced or furnished, delivered, and installed by the Contractor unless otherwise specified in these Project Special Provisions. The Contractor shall be responsible for controlling the quality of materials entering the work and for the quality of the work performed. The Contractor shall perform and provide, at his sole expense, any necessary quality control testing to ensure the quality of materials and the quality of the Work performed. Any Work using non-compliant or unsatisfactory materials or any Work showing unsatisfactory workmanship shall be removed and replaced at the sole cost of the Contractor.
- 5 -
Certificates of Compliance, conforming to the provisions, “Certificates of Compliance,” of the State Specifications shall be furnished for all manufactured products unless otherwise waived by the Engineer.
SECTION 6 – LEGAL RELATIONS AND RESPONSIBILITIES
6-10.03 ENCROACHMENT PERMITS
The Contractor shall be required to obtain an Encroachment Permit from Caltrans for work within the Caltrans rights of way, under the Agency’s parent permit number (03-26-N-LT-1977), prior to any work within State right-of-way. A copy of the permit is located in Appendix B.
The Contractor must adhere to permitting conditions listed in the Agency’s parent permit. As part of the requirements of the permit, the Contractor must arrange an onsite pre-construction meeting with the Caltrans representatives, Permit inspector and Landscape Specialist, as well as County representatives/Engineer, a minimum of two (2) weeks prior to the start of work to discuss scope of work, schedule, and Traffic Control Plans (TCP).
No work will be allowed within Caltrans rights of way until the Agency has received a copy of the Contractor’s encroachment permits.
Full compensation for work involved in obtaining and complying with the requirements Caltrans encroachment permits shall be considered included in the contract prices paid for the various items of work involved and no additional time or compensation will be allowed therefor.
6-11 EXISTING UTILITIES
The Contractor’s attention is directed to Section 6-11.01 of the Standard Construction Specifications. After potholing for all utility lines within the proposed limits of excavation, the Contractor shall provide a pothole log to the engineer within 7 days of potholing showing the location of the utility pothole with reference to the centerline stationing and offset, elevation of the utility and existing surface, and size and type of utility.
All water valves, boxes and manhole covers encountered in the area to be paved with asphalt concrete shall be carefully referenced by the Contractor and locations of the valves and covers painted on the surface immediately after paving.
Removal of Sewer manhole covers is not permitted. The Contractor shall submit an Access Permit to SASD prior to entering any sewer manhole or sewer facility.
The overhead utility lines within the project limits will need to be protected in place unless otherwise shown on the plans.
Full compensation for conformance with all requirements of this section shall be considered incidental and included in the various bid items and no additional compensation will be allowed therefor.
- 6 -
SECTION 7 – PROSECUTION OF THE WORK
7-1.01 ORDER OF WORK
When required by these Special Provisions or Plans, the Contractor shall follow the sequence of operations as set forth therein.
Liquidated damages, as set forth elsewhere in these special provisions, shall be assessed if the working days are exceeded. No work may take place prior to receipt of the executed Contract and review of the prescribed bonds and insurance.
Contractor's attention is directed to Section 12, “Safety, Public Convenience, and Traffic Control,” of the Standard Construction Specifications and these Special Provisions. Any Special Signs (S1) that are required for detour or maintaining traffic shall be placed a minimum of 10 days in advance of the project start.
The first order of work shall be the following:
• Prepare and submit Baseline Schedule
• Prepare and submit Traffic Control Plans
The Contractor’s attention is directed to Section 6-11, “Existing Utilities,” of these Special Provisions.
At the end of each work day, all debris, branches, roots, removed fence, rubbish, and other debris in the work area shall be collected and placed in a suitable disposal bin or pile. Materials to be used later in construction shall be neatly stockpiled. All parts of the work shall be left in a neat and presentable condition at the end of the work shift.
Full compensation for Order of Work, as specified herein, shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed therefor.
7-8.01 ALLOWABLE TIMES AND HOURS OF WORK
No lane or road closures will be permitted outside of the allowable hours of work. All traffic lanes shall be open, each day, by the end of shift.
7-8.02 OFF-PERIOD WORK
Under no circumstances shall any night time work be performed prior to and without the written permission of the Engineer. In the event of permitted night work, the Contractor shall maintain a minimum of one ten-foot (10’) minimum clear lane(s) in each direction between the hours of 7pm and 6am.
7-8.06 LANE AND ROAD CLOSURES DURING NOVEMBER/DECEMBER HOLIDAY SEASON
The first sentence of Section 7-8.06, “Lane and Road Closures During November/December Holiday
Season,” of the Standard Construction Specifications is hereby revised to the following:
Except as provided in the Special Provisions or approved by the Agency, construction will be suspended, and no activities that interfere with public traffic can be conducted on designated streets during the holiday season (defined as the 4-day Thanksgiving weekend and December 18 through the January 1 holiday, also referred to as the “Holiday Moratorium”).
- 7 -
7-12 DELAYS
Contractor’s attention is directed to Section 7-12.02, “Unavoidable Delays,” of the Standard Construction Specifications.
No extension of time will be granted for a delay caused by a shortage of materials unless the Contractor furnishes to the Engineer documentary proof that he has made every effort to obtain such materials from all known sources, within reasonable reach of the work in a diligent and timely manner. The documentary proof shall indicate that the inability to obtain such materials, when originally planned, did in fact cause a delay in final completion of the entire work which could not be compensated for by revising the sequence of the Contractor's operations. The term "Shortage of Materials" as used in this section, shall not apply to materials, articles, parts, or equipment which are processed, made, constructed, fabricated, or manufactured to meet the specific requirements of the contract. Only the physical shortage of material will be considered under these provisions as a cause for extension of time. Delays in obtaining materials due to priority in filling orders will not constitute a shortage of materials.
No extension of time will be allowed for delay in delivery of traffic signal poles, luminaires, or traffic signal equipment.
7-15 TIME OF COMPLETION
As set forth in Section 7-15, "Time of Completion," of the Standard Construction Specifications, the time for completion of this contract shall be Twenty (20) working days.
SECTION 8 – MEASUREMENT AND PAYMENT
8-10 LIQUIDATED DAMAGES FOR DELAY
The Contractor shall pay liquidated damages for this contract to the County of Sacramento the sum of TWO
THOUSAND EIGHT HUNDRED DOLLARS ($2,800.00) per day for failure to complete all contract items, for each and every calendar day's delay in finishing the work in excess of the number of working days prescribed elsewhere in these Special Provisions.
SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE
The Contractor’s attention is directed to Section 7-1.01, "Order of Work," in these Special Provisions.
Area Plan for Emergency Response to Hazardous Materials Incidents in Sacramento County is on file with the Sacramento County Department of Transportation for Contractor’s reference:
• https://emd.saccounty.gov/content/dam/emd/docs/transition/AREA-PLAN-REVISED-10-7-2025-
MasterFile.pdf
10-9 SANITARY REGULATIONS
The Contractor’s attention is directed to Section 10-9 “Sanitary Regulations,” of the Standard Construction Specifications and to these Special Provisions.
- 8 -
CONTRACTOR shall be solely responsible for implementing the applicable COVID-19 guidelines from the California Department of Industrial Relations, Division of Occupational Safety and Health, and the applicable COVID-19 guidance from the Centers for Disease Control and Prevention for the protection of workers, including regulations concerning education, training, routine cleaning, on-site washing facilities, and the use of Personal Protective Equipment (PPE) at the workplace (collectively, "Guidelines").
Full compensation for implementing the Guidelines shall be considered as included in the prices paid for the various items of Work involved as specified in Section 8-3, "Work to be Done Without Direct Payment," of the Standard Construction Specifications and no additional compensation will be allowed therefor.”
10-13 PROTECTION OF EXISTING TREES
A. Protection of trees must be in accordance with Section 10.13, “Protection of Existing Trees,” of the Standard Construction Specifications, and these Special Provisions.
B. Unless designated for removal, all existing trees that are within or adjacent to the project limits which have drip-line root zone area and/or overhead limbs, or underground roots which encroach into the project limits, must receive tree protection.
C. Prior to construction, including clearing and grubbing operations, the Contractor must inventory and apply tree protection measures to existing trees that are not designated for removal, which have drip-line root zone area and/or overhanging branches or underground roots which encroach into the project limits.
D. The protected tree inventory must include each tree’s species name and each tree must be numbered and photographed in order to document their pre-construction health, vigor and structural condition.
Follow photographic image requirements specified in Section 11-2 “Preconstruction Photographs” of the Standard Construction Specifications.
E. The protected tree inventory must note each tree’s health, vigor and structural condition and must include descriptions of tree decay, wounds, disease, pests, structural defects, previous pruning, animal habitats, abiotic disorders, other stressors, and tree protection measures, all as noted by a Certified Arborist.
F. The tree inventory must note the date, seasonal dormancy and gauge the level of existing root-zone soil moisture. The inventory must note any existing irrigation systems and/or natural drainage sources of water which may be affected during construction.
G. Throughout the course of construction, the Contractor must adequately protect existing trees and apply protection measures to ensure tree health, vigor, and structural stability. Special attention to changes in daily temperatures, rainfall predictions, duration of climate heat waves, construction timing of root zone impacts, and construction timing of and tree protection measures are required to adequately prepare and protect trees from stress and damage during construction.
- 9 -
H. As directed by a Certified Arborist, additional tree protection mitigation techniques to reduce construction impacts to trees may require:
1) worker education about tree protection
2) supplemental watering
3) mechanical aeration coring to break-up compaction and improve water/oxygen percolation within the drip-line root zone area surface
4) root pruning and root invigoration
5) branch and limb pruning
6) dust control and leaf rinsing to reduce dust build-up on leaf surfaces
7) avoiding leaf scorch and other tree tissue burning by directing equipment exhaust pipes and/or engine heat away from tree surfaces
8) layer mulching of the surface within the drip-line root zone area in order to insulate the soil surface from sun exposure and to retain soil moisture
9) tree trunk protection devices such as board wrapping and/or fabric cushioning
10) root zone soil compaction protection such as steel plating over a layered mulch cushion
11) other measures as directed by a Certified Arborist
I. Tree protection zones must be delineated with temporary fence as indicated on the Plans or as directed by a Certified Arborist. Refer to these Special Provisions Section 10-13.02 regarding Type ESA temporary fence.
J. Supplemental watering of existing trees must be applied as needed throughout the project construction period in order to maintain tree health, vigor and structural integrity. Water must be applied in a slow-soaking or cycled manner as to allow water to percolate thoroughly into the drip-line root zone area to ensure deep soaking to roots with minimal surface run-off. Supplemental watering may be accomplished with soaker hoses, “tree-gators”; temporary irrigation systems, flood bubblers, contained flood irrigation, and/or cycled truck watering.
K. Trees that have died or that are exhibiting irreversible stress damages due to unauthorized construction impacts and/or lack of adequate tree protection measures must be replaced by the Contractor at Contractor’s cost, including payment of any environmental mitigation fees and/or tree value loss to the tree owner. Tree loss or damages due to tree-owner inflicted causes are not the responsibility of the Contractor.
L. During the final walk-through of the project, the pre-construction tree inventory will be compared to the final condition of the trees to determine the adequacy of project tree protection and to determine any additional application of tree protection measures, including tree replacement and/or environmental mitigation fee and/or tree value loss payment if required.
The contract ALLOWANCE for Protection of Existing Trees shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in protecting existing trees, as specified in these Special Provisions and as directed by the Engineer. The total amount to be paid for the work included in the ALLOWANCE for Protection of Existing Trees shall be the amount of the allowance actually utilized in the course of completing the work and no additional compensation will be allowed therefor.
- 10 -
10-13.01 ARBORIST SERVICES
The Contractor must provide arborist tree services in conformance with Section 10-13. “Protection of Existing Trees” of the County Standard Construction Specifications, International Society of Arboriculture (I.S.A.)
Pruning Standards, National Arborist Association Pruning Standards and these Special Provisions. Such services must include, but not necessarily be limited to, the removal of dead wood, crown cleaning, canopy weight reduction, minimum required vehicular clearance, and pruning of weak attached limbs.
All arborist tree services associated with the project must be done by or under the supervision of an arborist certified by the International Society of Arboriculture (I.S.A.). The Contractor shall submit to the County in writing the names, qualifications, business address, and contact information for one or more International Society of Arboriculture (I.S.A.) certified arborists, a minimum of four (4) working days prior to the start of clearing and grubbing operations, for review and approval.
Tree services must also include root cutting required for curb, utility trenching, and irrigation installation so as to minimize impacts on existing trees. All roots three inches (3”) in diameter or greater must be cut cleanly.
Trees to remain must be protected and any root or limb cutting of trees to remain must be per the direction of the certified arborist.
A certified arborist must evaluate the impact of root or limb cutting on each tree as necessary and make recommendations regarding safety and retention. If the arborist deems that the root or limb cutting is too severe and will cause the tree to die or become unsafe, he/she must make such recommendations in writing to the County Inspector.
The payment for all labor and material associated with arborist services for the protection of existing trees shall be included with the line item for Protection of Existing Trees, and no additional compensation will be allowed therefor.
10-14 TEMPORARY HIGH-VISIBILITY FENCE
The Contractor’s attention is directed to Section 10-13 “Protection of Existing Trees,” of the Standard Construction Specifications and to these Special Provisions.
Temporary High Visibility Fence shall be per State Standard Plans RSP T65.
The Contractor shall place Temporary High Visibility Fence as shown on the plans or as directed by the Engineer. Once the temporary high visibility fence is installed and PRIOR to any tree removal work, the Agency will inspect that the fence is in the correct locations relative to the environmentally sensitive areas.
The Contractor shall not perform any tree removals until the Agency has inspected and approved of the fence installation.
Payment per Lineal Foot of Temporary High Visibility Fence shall include full compensation for furnishing all labor and materials to install temporary high visibility fence as required and no additional compensation will be allowed therefor. Payment for Temporary High Visibility Fence shall also include removal of fence at the end of the contract.
- 11 -
SECTION 12 - SAFETY, PUBLIC CONVENIENCE, AND TRAFFIC CONTROL
12-1 SAFETY
The local Fire Department, Sheriff/Police Department, and California Highway Patrol shall be notified 24 hours in advance of construction work.
12-2.02 PEDESTRIAN AND BICYCLE ACCESS
The Contractor’s attention is directed to Section 12-2.02, “Pedestrian and Bicycle Access,” of the Standard Construction Specifications and to these Special Provisions.
Pedestrian traffic mitigation shall be in full compliance with the Sacramento County Standard Construction Specifications Section 12-2.02 and Sacramento County Department of Transportation (SacDOT) Traffic Control Templates (revised in February 2014) limiting pedestrian detour distance to 500 ft. The 2014 SacDOT Traffic Control Templates (TC-45 and TC-45.1) can help to provide information involving pedestrian traffic mitigation.
During working hours, at least one worker shall be assigned the responsibility to escort elderly, disabled or any other pedestrians in need of assistance through and/or around the construction work zone. The worker assigned this responsibility may also participate in other construction activities; however, the assigned worker shall be aware of his or her primary responsibilities for providing this assistance.
Full compensation for conforming to the requirements of this section shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed therefor.
12-3 PUBLIC SAFETY AND TRAFFIC CONTROL
The Contractor’s attention is directed to Section 12-3, “Public Safety and Traffic Control,” of the Standard Construction Specifications.
The Contractor shall be responsible for public safety and traffic control within the project limits and on the approaches to the project. Provisions for public convenience and safety, construction area traffic control, and hours of work shall be in accordance with the County of Sacramento Standard Construction Specifications, Sections 7-8 and 12, and these Special Provisions.
All traffic control devices including: signs, barricades, vertical panels, drums, warning lights, arrow boards, changeable message signs, cones and tubular markers that meet the requirements of American Traffic Safety Services Association (ATSSA), “Quality Standard for Work Zone Traffic Control Devices – 1992” shall be used on this project/this work.
Existing "No Parking" and/or "No Stopping" controls shall remain in effect as applicable. Work crews may park personal vehicles where no restrictions exist. Material delivery vehicles may stop along the roadway as commensurate with work requirements. No equipment or materials shall be parked or stored within any traffic lanes or within the public rights-of-way at any time, day or night, including holidays and weekends, without an approved lane or road closure.
- 12 -
12-3.04 FURNISHING, INSTALLING, AND MAINTAINING TEMPORARY TRAFFIC
CONTROLS
The Contractor’s attention is directed to Section 12-3.04, “Furnishing, Installing, and Maintaining Temporary Traffic Controls,” of the Standard Construction Specifications.
Lane closures/ramp closures will not be permitted. The Contractor’s attention is directed to Sections 7- 8.01, “Allowable Times and Hours of Work,” 7-8.02, “Off-Period Work,” and 12-3.14, “Freeway Closures,” of these Special Provisions.
The Contractor shall not place traffic control devices on private property without the permission of the property owner(s).
Each vehicle used to place, maintain, and remove components of a traffic control system on multilane highways shall be equipped with a type II flashing arrow sign which shall be in operation when the vehicle is being used for placing, maintaining, or removing said components. The sign shall be controllable by the operator of the vehicle while the vehicle is in motion. The flashing arrow sign shall not be used on the vehicles that are doing the placing, maintaining, and removing, of components of a traffic control system, and shall be in place before a lane closure requiring its use is completed.
If any component in the traffic control system is displaced, or ceases to operate or function as specified, from any cause, during the progress of the work, the Contractor shall immediately repair said component to its original condition or replace said component and shall restore the component to its original location.
When lane closures are made for work periods only, at the end of each work period, all components of the traffic control system, except portable delineators placed along open trenches or excavation adjacent to the traveled way shall be removed from the traveled way and shoulder. No equipment or materials shall be parked or stored within any traffic lanes or within the public right-of-way at any time of day or night, including holidays and weekends, without an approved lane or road closure.
The contract LUMP SUM price paid for Traffic Control (including signs) shall include preparation of traffic control plans and furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in preparation and installation, including, but not limited to, erecting, removing, storing, maintaining, relocating, replacing, and disposing of the components of the staging and traffic control system as required to maintain traffic as specified in the Standard Construction Specifications and as directed by the Engineer.
12-3.07 CONSTRUCTION SIGNS
Construction area and/or detour signs for temporary traffic control shall be furnished, installed, maintained, and removed when no longer required in conformance with the provisions in Section 12-3.07, “Construction Signs,” and Section 34-3, “Roadside Signs,” of the Standard Construction Specifications and these Special Provisions.
The Contractor shall not erect any signs on private property without prior written approval from the private property owner. The Contractor shall erect the construction area signs at the locations shown on the traffic control plans or as designated by the Engineer.
- 13 -
Construction area and detour signs associated with pedestrians shall conform to Section 12-3.04, “Furnishing, Installing, and Maintaining Temporary Traffic Controls,” of these Special Provisions.
The Contractor shall notify the appropriate regional notification center for operators of subsurface installations at least 2 working days, but not more than 14 calendar days, prior to commencing excavation for construction area sign posts. The regional notification centers include but are not limited to:
Notification Center Telephone Number
Underground Service Alert-Northern California (USA)
1-800-642-2444 1-800-227-2600
Excavations required to install construction area signs shall be performed by hand methods without the use of power equipment, except that power equipment may be used if it is determined there are no utility facilities in the area of the proposed post holes.
The Contractor may be required to cover certain signs during the progress of the work. Signs that are no longer required or that convey inaccurate information to the public shall be immediately covered or removed or the information shall be corrected. Covers for construction area signs shall be of sufficient size and density to completely block out the complete face of the signs. The retro-reflective face of the covered signs shall not be visible either during the day or at night. Covers shall be fastened securely so that the signs remain covered during inclement weather. Covers shall be replaced when they no longer cover the signs properly.
Full compensation for Construction Area Signs as specified herein, shall be considered as included in the prices paid for the various items of work involved and no additional compensation will be allowed therefor.
Full compensation for Construction Area Signs as specified herein, shall be considered as included in the LUMP SUM price paid for Traffic Control and no additional compensation will be allowed therefor.
12-3.14 FREEWAY CLOSURES
Shoulder closures on US-50 shall comply with Section 12-4.02, “Traffic Control Systems,” of the State Standard Specifications, except as modified below.
Add to the end of section 12-4.02C(1) of the State Specifications:
Keep the full width of the traveled way open to traffic when no active construction activities are occurring in the traveled way or within 6 feet of the traveled way.
Keep the full width of the ramp traveled way open for use by traffic on designated holidays.
For each 10-minute interval or fraction thereof past the time specified to open the closure, the amount for liquidated damages per interval shown in the table below is deducted. Liquidated damages are limited to 5 percent of the total bid per occurrence. Liquidated damages are not assessed if the Engineer orders the closure to remain in place beyond the scheduled pickup time.
- 14 -
Type of facility
Route Direction or segment Period Liquidated damages/interval
Mainline 50 EB/WB 1st half hour 2nd half hour
2nd hour and beyond
$1,280/10 minutes $1,930/10 minutes $2,570/10 minutes
Add to the end of section 12-4.02C(3)(a) of the State Specifications:
If work vehicles or equipment is parked on the shoulder within 6 feet of a traffic lane of a freeway or expressway, close the shoulder area as shown.
If work vehicles or equipment is parked on the shoulder within 6 feet of a traffic lane at local roads, close the shoulder area with fluorescent-orange traffic cones or portable delineators. Place the cones or delineators on a taper in advance of the parked vehicles or equipment and along the edge of the traveled way at 25-foot intervals to a point not less than 25 feet past the last vehicle or piece of equipment. Use at least 9 cones or delineators for the taper. Place advance warning signs as specified in section 12-4.02C(8) of the State Specifications.
Keep a minimum of 1 paved traffic lane at least 11 feet wide open for traffic in each direction of travel.
- 15 -
Replace section 12-4.02C(3)(f) of the State Specifications with:
Closure Restrictions for Designated Holidays and Special Days
Lane Closure Restrictions For Designated Holidays And Special Days
Thu Fri Sat Sun Mon Tues Wed Thu Fri Sat Sun Mon x
H xx
SD
xxx xxx
Legend:
Refer to lane requirement charts.
x The full width of the traveled way must be open for use by traffic after 06:00 hours.
xx The full width of the traveled way must be open for use by traffic.
xxx The full width of the traveled way must be open for use by traffic until 20:00 hours.
H Designated holiday
SD Special day
- 16 -
Replace section 12-4.02C(3)(g) of the State Specifications with:
Freeway lane closures must comply with the requirements shown in the following charts:
Chart No. G1
Freeway Lane Requirements
County: Sac Route/Direction: 50/EB Post Mile: 15.5/17.2
Closure limits: PM 15.5/17.2
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Mon– Thu
S S S S S S S S S S
Fri S S S S S S S S S S
Sat S S S S S S S S S S S
Sun S S S S S S S S S S S S
S Shoulder may be closed completely.
Work is allowed within the highway where a shoulder or lane closure is not required.
REMARKS:
Replace section 12-4.02C(3)(j) of the State Specifications with:
Comply with the requirements for the ramp lane closures shown in the following charts:
Chart No. J1
Ramp Lane Closure Requirements
County: Sac Route/Direction: 50/EB Post Mile: 15.5/17.2
Closure limits: SB Hazel Ave Loop On-Ramp to EB SR 50
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Mon–Thu S S S S S S S S S S
Fri S S S S S S S S S
Sat S S S S S S S S S S
Sun S S S S S S S S S S S
- 17 -
Chart No. J2
Complete Ramp Closure Hours
County: Sac Route/Direction: 50/EB Post Mile: 15.5/17.2
Closure limits: NB Hazel Ave to EB SR 50 Slip On-Ramp
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Mon– Thu
S S S S S S S S S S
Fri S S S S S S S S S S
Sat S S S S S S S S S S S S
Sun S S S S S S S S S S S S
Chart No. J3
Ramp Lane Closure Hours
County: Sac Route/Direction: 50/EB Post Mile: 15.5/17.2
Closure limits: EB SR 50 Off-Ramp to Folsom Blvd
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Mon– Thu
S S S S S S S S S
Fri S S S S S S S S S
Sat S S S S S S S S S S S
Sun S S S S S S S S S S S S S
- 18 -
Chart No. J4
County: Sac Route/Direction: 50/WB Post Mile: 15.5/17.2
Closure limits: SB Hazel Ave to WB SR 50 Slip On-Ramp
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Mon– Thu
S S S S S S S S S
Fri S S S S S S S S S
Sat S S S S S S S S S S S S S
Sun S S S S S S S S S S S S S S
Legend:
Chart No. J5
Complete Ramp Closure Hours
County: Sac Route/Direction: 50/WB Post Mile: 15.5/17.2
Closure limits: NB Hazel Ave to WB SR 50 Loop On-Ramp
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Mon– Thu
S S S S S S S S S S
Fri S S S S S S S S S S
Sat S S S S S S S S S S S
Sun S S S S S S S S S S S
Legend:
- 19 -
Chart No. J7
County: Sac Route/Direction: 50/WB Post Mile: 15.5/17.2
Closure limits: WB SR 50 Off-Ramp to Hazel Ave
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Mon– Thu
S S S S S S S S S
Fri S S S S S S S S
Sat S S S S S S S S S
Sun S S S S S S S S S S
Legend:
SECTION 15 – CLEARING AND GRUBBING
15-1 GENERAL
Clearing and grubbing shall conform to Section 15, “Clearing and Grubbing,” of the Standard Construction Specifications and these Special Provisions.
All excess materials and debris resulting from clearing and grubbing or excavation shall become property of the Contractor and shall be removed and disposed of outside of the Right of Way.
All County traffic signs that are affected by the work shall be maintained by the Contractor in accordance with Section 13-2.02 of the Standard Construction Specifications and these Special Provisions.
Contractor’s attention is directed to Section 15-1.02, “Trees, Shrubs, Ground Cover and Lawns,” of the Standard Construction Specifications and these Special Provisions for provisions regarding trees, tree stumps to be removed by the Contractor.
15-1.02 TREES, SHRUBS, GROUND COVER, AND LAWNS
Trees to be removed shall have all limbs and trunks cut down with trunk(s) remaining two feet above existing grade. Stump grinding is not included in the scope of work. Debris shall be hauled away and disposed of in a legal manner.
Trees slated for removal shall be removed prior to January 31st, in order to avoid the nesting season.
Any trees that are removed during the nesting season, which begins February 1st, shall be approved by the engineer, surveyed by the Agency, and may only be removed if no nesting birds are found.
- 20 -
Trees shown to be removed must be field marked by the Contractor and verified by the Engineer prior to any removal operations.
Care shall be taken during the removal of trees to avoid damage to existing underground facilities.