HACL Security Surveillance.pdf

PDF 3 MB Posted

Attached to
Security Surveillance Access Control & Network Infrastructure Restoration & Upgrade
Solicitation number
26-09
Issued by
Hudson County, New Jersey

About this file

This Request for Proposals document is issued by the Housing Authority of the City of Linden (HACL), a New Jersey public housing agency, for the restoration, upgrade, and modernization of security surveillance, access control, and network infrastructure at Ann J. Ferguson Towers, a 201-unit senior and public housing facility located at 1601 Dill Avenue, Linden, New Jersey. The September 13, 2025 lightning strike and associated power surge damaged critical electrical and low-voltage infrastructure, creating elevated security and safety risks for elderly and disabled residents. The Authority seeks a complete, turnkey solution including approximately 118 IP cameras, 2 high-definition elevator cameras, an enterprise network video recorder or recording platform, access control systems for five controlled openings, four 48-port managed Layer 3 PoE++ switches, two 2000VA/1800W UPS units, one wireless access point, five new Category 6 data drops, four electrical outlets, surge protection, grounding and bonding improvements, and all associated installation, testing, commissioning, training, and documentation. A mandatory pre-proposal site visit is scheduled for November 24, 2026 at 10:30 a.m. Questions must be submitted by December 1, 2026 at 2:30 p.m., and completed proposals must be submitted through the Housing Agency Marketplace eProcurement portal by December 15, 2026 at 12:30 p.m. The successful respondent must execute the contract within seven days of receiving the notice of award. The contract term is one year unless earlier terminated, with renewal subject to the Housing Authority's sole discretion and mutual written agreement.

Pricing shall consist of three separate system totals—Camera System, Access Control System, and Network Upgrade—plus a combined Project Total, with all costs including labor at applicable New Jersey prevailing wage and fringe benefit rates, materials, freight, delivery, mobilization, removal, disposal, programming, testing, training, essential documentation, permits, warranty, overhead, and profit. The project is expected to be funded in whole or in part through HUD Emergency Safety and Security Grant funds, subject to funding availability, grant eligibility, environmental review, and other applicable conditions. No unit prices or hourly rate schedules are requested; any scope adjustment requires a written amendment or change order with an agreed lump sum price. Respondents must provide a detailed unpriced equipment schedule, identify all required recurring charges by system and year, and disclose assumptions, substitutions, exclusions, and dependencies. The Housing Authority reserves the right to reject any and all proposals and waive informalities. All proposals shall remain valid for ninety days after the submission deadline. The RFP is issued pursuant to a fair and open process in accordance with N.J.S.A. 19:44A-20.4 et seq. Evaluation factors include technical approach and compliance (30 points), relevant experience and qualifications (20 points), implementation and support plan (20 points), price and lifecycle cost (25 points), and public-sector compliance and completeness (5 points).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HOUSING AUTHORITY OF THE

CITY OF LINDEN

REQUEST FOR PROPOSALS

SECURITY SURVEILLANCE ACCESS CONTROL AND

NETWORK INFRASTRUCTURE RESTORATION &

UPGRADE

Under a Fair and Open Process in Accordance

With N.J.S.A. 19:44A-20.4 et seq.

PROPOSALS MUST BE SUBMITTED BY

December 15, 2026 at 12:30 p.m.

To:

Dr. Marlene Berghammer

Executive Director

Housing Authority of the City of Linden

1601 Dill Avenue

Linden, New Jersey 07036

Advertisement

The Housing Authority of the City of Linden (“Housing Authority”) is requesting proposals for

SECURITY SURVEILLANCE ACCESS CONTROL AND NETWORK INFRASTRUCTURE RESTORATION

& UPGRADE

Agency Contact Person: Dr. Marlena Berghammer, Executive Director

Email: mberghammer@lindenha.org

Site Visit: November 24, 2026 at 10:30 a.m.

Questions Deadline: December 1, 2026, at 2:30 p.m.

Bid Submission Deadline: December 15, 2026, at 12:30 p.m.

The Request for Proposals (“RFP”) documents can be obtained on the eProcurement-Housing Agency

Marketplace:

1. Please access the portal at ha.internationaleprocurement.com (no” www”).

2. Click on the “Login” button located in the upper left side corner.

3. Follow the on-screen directions.

4. If you experience any issues accessing or registering on the eProcurement

Marketplace, please contact Customer Support at (866-526-9266).

No hard copies should be delivered or mailed to the Linden Housing Authority.

How to submit a complete proposal in response to this RFP. The proposed fees must be submitted by the proposer through the eProcurement Marketplace only. All pricing must be entered in the designated fields within the Marketplace. Any proposer who fails to submit pricing as directed may, at the Agency’s discretion, be rejected without further consideration. Additionally, there is no charge by the Marketplace for entering costs online.

Respondents are responsible for ensuring that their proposals are uploaded to the Housing Agency eProcurement Marketplace by the deadline specified above. Proposals received after the deadline for any reason shall not be considered.

All responses submitted are subject to these instructions and to the Instructions to Offerors, Non-

Construction form HUD-5369-B. The failure to abide by these instructions in any way, including but not limited to the failure to submit all required documentation, may lead to the proposal being rejected as non-responsive.

The Housing Authority reserves the right to reject any and all proposals and/or to waive any informality in responses. No proposals may be withdrawn within sixty (60) days after the submission deadline.

In accordance with the criteria included in the RFP, the contract(s) shall be awarded to the respondent(s) who submit the proposal(s) most advantageous to the Housing Authority, cost and other factors considered. The successful respondent will be required to execute the Housing Authority’s contract within seven (7) days of receiving the notice of award.

This RFP is being issued pursuant to a fair and open process in accordance with N.J.S.A. 19:44A-20.4 et seq.

mailto:gbelcher@lindenha.org

Housing Authority of the City of Linden

Request for Proposals – Security Surveillance Access Control & Network Infrastructure

Restoration and Upgrade

TABLE OF CONTENTS

Proposal Instructions

1. Purpose

2. Terms and Conditions

3. Scope of Services

4. Qualifications

5. Proposal Requirements

6. Submission of Proposals

7. Evaluation Criteria

8. Americans with Disabilities Act Language

9. Mandatory Affirmative Action Language

Proposal Documents

1. Proposal Checklist

2. Acknowledgment of Addenda

3. Fee Proposal Form

4. Certification Regarding Non-Debarment

5. Non-Collusion Affidavit

6. Statement of Ownership

7. Affirmative Action Compliance Notice

8. HUD-Forms

9. Disclosure of Investment Activities in Iran

10. Certification of Non-Involvement in Russia or Belarus

11. Notice of Intent to Subcontract

12. Subcontractor Utilization Form

Contract Documents

1. Form of Contract i

1. Terms and Conditions

Any requests for clarification as to the meaning of any provision of this Request for Proposals shall be uploaded to the Housing Agency Marketplace eProcurement website no later than

December 15, 2026, at 12:30 p.m. If deemed necessary by the Housing Authority, an addendum will be issued to all individuals who registered on the eProcurement website. Failure of any proposer to receive any such addendum shall not relieve them of an obligation under their proposal as submitted.

All proposals shall remain valid for a period of sixty (60) calendar days after the date specified for receipt of proposals. All costs of the proposal process, interviews, and related expenses are solely the responsibility of the respondent.

HACL reserves the right to reject any or all proposals, to waive informalities and minor irregularities, and/or modify or cancel this Request for Proposals. Proposals which appear unrealistic in terms of management commitments or are indicative of failure to comprehend the complexity of this RFP and subsequent contracts may be rejected.

Respondents are requested and advised to be as complete as possible in their response. The

Housing Authority reserves the right to 1) contact any respondent to clarify their proposal; 2) contact any past/current clients of the respondent; 3) solicit information from any available source concerning any aspect of the proposal; and 4) seek and review any other information deemed pertinent to the evaluation process.

1 PURPOSE AND BACKGROUND

1.1 Authority and Property

HACL is a public housing agency that operates Ann J. Ferguson Towers, a 201-unit senior and public housing facility at 1601 Dill Avenue, Linden, New Jersey. The building includes resident floors, elevators, stairwells, offices, community areas, service areas, exterior approaches, gates, and parking areas.

1.2 Emergency Condition

On September 13, 2025, a lightning strike and associated power surge damaged portions of the building’s electrical and low-voltage infrastructure. The event caused widespread failure or instability affecting network video recording, Power over Ethernet switching, cameras, access-control controllers and power supplies, cabling and terminations, uninterruptible power supplies, and surge-protection devices. The resulting loss of surveillance and access-control visibility presents elevated security and safety risks for elderly and disabled residents.

1.3 Procurement Objective

The Authority seeks a complete, operational, maintainable, and resilient solution that restores camera coverage and controlled access, modernizes the supporting network, preserves usable existing infrastructure where field-verified, and reduces the risk of recurrence through appropriate surge protection, grounding, bonding, UPS protection, and documentation.

Requirements are expressed by function, quantity and performance rather than by supplier, manufacturer or product model. Equivalent equipment meeting these requirements may be proposed.

Respondents shall identify proposed equipment and demonstrate compatibility, while disclosing assumptions, substitutions, exclusions, recurring charges and dependencies.

1.4 Funding and Budget Control

The project is expected to be funded in whole or in part through HUD Emergency Safety and

Security Grant funds, subject to funding availability, grant eligibility, environmental review and other applicable conditions. HACL shall confirm its independent cost estimate, approved grant scope and budget before award. Pricing shall consist of three system totals and a combined project total.

Any scope adjustment requires a written amendment or change order with an agreed price; no prebid unit prices are requested.

2 PROCUREMENT SCHEDULE AND COMMUNICATIONS

2.1 Single Point of Contact

Submit procurement communications through Housing Agency Marketplace to the designated

Authority contact. Respondents must not seek nonpublic procurement information from

Commissioners, residents, staff or consultants outside the authorized process. Material information and interpretations will be shared through written addenda or an equally administered controlled disclosure process.

2.2 Site Visit and Field Verification

The Authority will conduct a pre-proposal conference and site visit on November 24, 2026 at 10:30 a.m. Each respondent is responsible for inspecting accessible conditions, verifying pathways and device locations, and identifying conflicts before submitting a proposal. Any proposed change to the requirements must be stated as an exception; silence constitutes acceptance.

2.3 Questions and Addenda

Questions must be received by the deadline on the cover. Oral interpretations are not binding. Only a written addendum issued by the Authority may modify this RFP. Respondents must acknowledge every addendum on the form provided.

3 SCOPE OF WORK

3.1 General Turnkey Responsibility

Provide a turnkey project, including project management, field verification, installation coordination, lawful removal and disposal, procurement, delivery, cabling, electrical coordination, programming, integration, testing, commissioning, training, essential closeout records, warranty and support.

Routine scope does not require a separately engineered design or a formal shop drawing package.

Professional design permits and documentation expressly required by the authority having jurisdiction or applicable law remain mandatory and shall be included in the price.

3.2 Demolition and Reuse

• Remove failed, abandoned, or replaced cameras and associated equipment as directed;

protect and legally

• dispose of removed materials.

• Test existing cabling, coaxial pathways, molding, racks, cabinets, power circuits, door and gate hardware,

• and other proposed reused components before reliance on them.

• Reuse existing door and gate hardware only where compatible, code-compliant, serviceable, and accepted

• in writing by HACL.

• Maintain an asset disposition log and return any equipment designated by HACL.

3.3 Video Surveillance System

• Furnish and install approximately 118 IP cameras and 2 high-definition elevator cameras, subject to field verification and Authority approval.

• Provide an enterprise network video recorder or recording platform sized for at least 128 channels, remote viewing, user permissions, health monitoring, export, and audit functionality.

• Provide all camera mounts, junction boxes, licenses, encoders or analog-to-IP converters, patching, PoE capacity, storage, and accessories required for a complete system.

• Configure image quality, fields of view, privacy masks where required, time synchronization, motion/event settings, retention, user roles, and secure remote access.

• Provide at least 30 days of usable retention of ON-MOTION RECORDING for every camera. This means retaining recorded motion events for a minimum of 30 calendar days before overwrite; it does not require 30 days of continuous recording. Size net usable storage after formatting, redundancy and reserved capacity. Provide a concise calculation identifying resolution, frame rate, codec, bitrate, motion activity assumptions and pre-event and post-event recording settings. An unsupported motion percentage is not sufficient; explain how the assumptions reflect each monitored area and allow for periods of higher activity.

• Label every device, cable, switch port, and rack termination consistently with the as-built documents.

3.4 Access Control System

• Furnish, install, program, test, and commission a centrally managed access-control system for five controlled openings: main entrance, office entrance, back door, back gate, and parking-lot gate.

• Provide controllers, readers, credentials, request-to-exit devices, power supplies, enclosures, interfaces, network connectivity, software and licenses needed for a complete system.

• Include 300 credentials or tokens, with the credential type and included quantity identified in the equipment schedule. Include programming and enrollment arrangements. No per-credential or additional credential unit prices are requested.

• Integrate or reuse existing locks, strikes, magnetic locks, gate operators, and related hardware only after field testing and written approval.

• Preserve code-compliant egress and required fail-safe or fail-secure operation. Coordinate fire-alarm interfaces and inspections where applicable.

• Configure schedules, access levels, event logs, alarm conditions, operator permissions, backup procedures, and reporting.

3.5 Supporting Network Upgrade

• Provide four 48-port managed Layer 3 PoE++ switches, each with a minimum 600-watt PoE budget, or approved equivalents sized for the final load and growth allowance.

• Provide two 2000VA/1800W online double-conversion UPS units with network management and appropriate rack or tower installation, or approved equivalents.

• Provide one enterprise dual-band wireless access point or approved equivalent for the designated location.

• Provide five new Category 6 data drops to Authority-designated locations, terminated, labeled, certified, and documented.

• Design and configure separate voice, data, video/security, access-control, and management

VLANs as applicable; document addressing, routing, and security settings.

• Install four electrical outlets in the janitor closets on the 2nd, 5th, 8th, and 10th floors, subject to field verification and performance by properly licensed personnel.

3.6 Surge Protection Grounding and Resilience

• Evaluate the grounding, bonding, electrical distribution, low-voltage pathways, IDF/MDF racks, exterior device runs, and building entry points serving the project.

• Provide properly rated surge protective devices and grounding/bonding improvements for affected panels, racks, network equipment, exterior cameras, access-control equipment, gates, and other vulnerable circuits.

• Provide a concise installation description identifying proposed surge protection and grounding/bonding provisions, locations and coordination responsibilities. A separately engineered plan is not required unless mandated by code, permit or the authority having jurisdiction.

• Test and document grounding/bonding and surge-protection installation at closeout.

3.7 Installation Coordination and Essential Documentation

Use existing drawings, manufacturer product information, marked up plans and concise schedules wherever adequate. Avoid duplicate formal submittal cycles, presentation drawings, rack elevations or extensive engineered documentation unless specifically required by law or the permitting authority. Essential compliance, installation approval and acceptance records remain included in the system totals.

PHASE MINIMUM DELIVERABLES

Before installation Concise equipment and quantity schedule; NDAA compliance evidence;

storage sizing summary; installation schedule; material exceptions and permit requirements.

Coordination Confirm device locations, views, pathways, access hardware reuse, network settings and surge protection with HACL. Use marked up plans or schedules where sufficient; no standalone engineered shop drawing package unless legally required.

Installation and testing Coordinate resident access and outages; label equipment; test every camera and opening, recording, remote viewing, power protection and network functions; correct defects.

Training and closeout Provide operator and administrator instruction, device/location list, simple marked up final layout, configuration backups, licenses, warranties, secure credential transfer and test results.

4 TECHNICAL AND PERFORMANCE REQUIREMENTS

4.1 General Standards

• New, current-production, commercial-grade equipment from established manufacturers; no gray-market, refurbished, or end-of-life equipment without prior written approval.

The complete system shall be NDAA compliant with the applicable restrictions of Section 889 of the

FY 2019 National Defense Authorization Act and, where federal award funds apply, 2 C.F.R.

200.216. Do not provide prohibited covered telecommunications or video surveillance equipment or services, including systems using covered equipment as a substantial or essential component or critical technology. Provide manufacturer compliance evidence for proposed cameras, recorders, converters and other covered components, identify the actual equipment manufacturer where private labeled, and provide a signed contractor statement confirming compliance. This requirement is a performance and compliance standard and does not prescribe a brand.

• Compliance with manufacturer requirements, applicable building and electrical codes, fire and life-safety requirements, accessibility requirements, cybersecurity requirements, and

Authority policies.

• Open, documented interfaces and exportable recordings, logs, configurations, and reports.

The Authority must retain ownership and administrative control of all configurations, credentials, video, and project documentation.

• Encryption in transit and at rest where supported; unique accounts; role-based access;

multifactor

• authentication for remote or administrative access where supported; secure default configuration; prompt security updates.

• No cloud-hosted service, recurring license, remote support tunnel, or third-party data transfer may be used unless fully disclosed and approved by HACL.

4.2 Camera Minimums

CAMERA CLASS MINIMUM PERFORMANCE

4 MP fixed IP Minimum 4-megapixel resolution; H.265/H.264; WDR; low-light capability; vandal-resistant housing where exposed; PoE; ONVIF compatibility or equivalent documented interoperability.

8 MP fixed or vari-focal IP Minimum 8-megapixel resolution; motorized vari-focal lens where specified; H.265/H.264; WDR; low-light; outdoor rating when exterior; PoE.

180-degree exterior Minimum 8-megapixel panoramic coverage; 24/7 color or equivalent low-light performance; outdoor and vandal-resistant rating;

appropriate analytics disclosed.

Elevator camera Minimum 5-megapixel HD image or approved equivalent; reuse existing coax only after testing; include converters, isolation, and elevator coordination.

4.3 Recording and Storage

State net usable storage, redundancy design, channel count, recording throughput, export formats, health alerts, supported viewing methods and initial and recurring license requirements. Preserve evidentiary exports with date, time and integrity information. The mandatory retention is at least 30 days of usable ON-MOTION RECORDING for every camera, under the approved settings and supported activity assumptions in Section 3.3. Verify motion capture, playback and exports at commissioning and verify the available retention history after 30 days of operation. Remedy any retention shortfall at no additional cost without reducing approved image quality or motion coverage. A disk capacity label or brief commissioning test alone does not demonstrate 30 days of actual retention.

4.4 Cybersecurity and Privacy

• Submit a cybersecurity description covering account management, MFA, encryption, vulnerability and patch management, logging, remote access, backups, incident notification, and end-of-support policy.

• Identify all data stored offsite or in the cloud, its location, retention, sub processors, and deletion method.

• Notify HACL of any suspected unauthorized access affecting HACL systems or information without unreasonable delay and no later than the period required by the contract or applicable law.

• Do not use Authority video, credentials, resident information, system metadata, or recordings for advertising, model training, product development, or any purpose unrelated to the contract.

4.5 Warranty and Support

Include not less than a one-year workmanship warranty after final acceptance and pass through all manufacturer warranties. State proposed response times for critical, high, and routine incidents;

support hours; escalation process; spare-parts approach; remote-support controls; and pricing for optional maintenance after warranty. Warranty must include labor, travel, configuration, and replacement coordination unless expressly excluded in the price proposal.

5 CONTRACTOR QUALIFICATIONS AND RESPONSIBILITIES

• At least five years of demonstrated experience delivering comparable commercial or multifamily video surveillance, access-control, structured-cabling, and managed-network projects, or an equivalent record acceptable to HACL.

• At least three relevant client references, preferably including public housing, senior housing, government, education, healthcare, or occupied multifamily properties.

• Manufacturer certifications or documented authorization for proposed core platforms, plus appropriately licensed electrical, fire-alarm, elevator, locksmith, or low-voltage subcontractors where required.

• A designated project manager and qualified lead technicians with resumes or experience summaries.

• Ability to meet federal debarment, equal employment opportunity, affirmative action, business registration, ownership disclosure, insurance, and other statutory requirements.

• A safety plan, resident-sensitive work practices, background screening consistent with law and Authority policy, and identification badges for onsite personnel.

Respondents must identify every subcontractor and the work assigned. The prime contractor remains fully responsible for performance. Substitutions require prior written approval.

6 PROPOSAL SUBMISSION REQUIREMENTS

Organize the proposal in the following order. Material omissions may render a proposal non-responsive.

TAB REQUIRED CONTENT

1 Cover letter signed by an authorized representative; legal name, address, contact information, entity type, and acknowledgment of the proposal validity period.

2 Executive summary and confirmation of ability to provide a turnkey system.

3 Technical approach, equipment schedule, architecture, storage calculations, access-control design, network/VLAN design, surge/grounding approach, and disclosed exceptions.

4 Implementation plan, schedule, staffing, resident-impact controls, outage and cutover plan, testing, training, and closeout.

5 Qualifications, licenses, certifications, project team, subcontractors, and three references.

6 Warranty, support, cybersecurity, data handling, licensing, and lifecycle information.

7 Completed Appendix B with three system totals and combined total, detailed unpriced equipment schedule, required recurring charges, and disclosed assumptions. No unit prices.

8 Completed checklist, addenda acknowledgment, ownership disclosure, non-collusion affidavit, debarment certification, Iran and Russia/Belarus certifications, affirmative-action evidence, business registration, W-9, insurance evidence, and required HUD forms.

Proposals must remain valid for at least ninety days after the due date, unless a different period is stated by addendum. The Authority will not reimburse proposal preparation, site visit, interview, or negotiation costs.

7 PRICE PROPOSAL

THIS IS A PREVAILING WAGE PROJECT. Each system total shall include all required labor at applicable prevailing wage and fringe benefit rates, supervision, materials, freight, delivery, lifts, tools, mobilization, removal, disposal, programming, testing, training, essential documentation, permits, warranty, overhead and profit. State legally applicable taxes, if any. Identify exceptions expressly; do not omit necessary components of a complete functional system.

Provide only three base system prices: Total for Camera System, Total for Access Control System, and Total for Network Upgrade, plus their combined Project Total. Provide a detailed UNPRICED schedule of included devices and equipment with quantities, functions, technical descriptions and proposed manufacturer/model information so HACL can assess compliance. No equipment unit prices, add/deduct unit prices, hourly rate schedule or individual labor prices are requested. Identify required recurring charges by system and year; do not hide mandatory charges in optional maintenance.

Allocate shared mobilization, project management, testing, permits and closeout costs among the three system totals without duplication. Allocate the four electrical outlets and common network surge/grounding work to Network Upgrade; allocate camera specific cabling and accessories to

Camera System and access specific hardware/interfaces to Access Control System. Any change requires prior written approval and an agreed lump sum price with supporting scope information. No prebid unit price schedule is required.

8 EVALUATION AND AWARD

The QPA and counsel shall determine and publish the legally appropriate award method before advertisement based on the installation, equipment and public works scope. The scoring table below is a draft only and applies only if HACL approves a competitive proposal process. If public bidding is required, the final solicitation shall instead state the lowest responsive and responsible bidder standard and include the applicable bid documents. No proposer should be asked to bid under an unresolved award method.

EVALUATION FACTOR MAXIMUM POINTS

Technical approach and compliance with scope 30

Relevant experience, qualifications, and references 20

Implementation, safety, commissioning, training, and support plan 20

Price, lifecycle cost, and value 25

Public-sector compliance and completeness 5

TOTAL 100

The final solicitation shall identify whether the three system totals are evaluated and awarded as a combined project or whether separate system awards are permitted, and how recurring charges and alternates, if any, affect evaluated price. HACL shall resolve these matters before publication;

component totals alone do not authorize partial award.

8.1 Responsibility Review

Before award, HACL may require evidence of financial capacity, staffing, licensing, manufacturer authorization, insurance, performance history, legal compliance, and ability to complete the project on schedule. False or misleading statements are grounds for rejection or termination.

9 CONTRACT TERMS AND COMPLIANCE

9.1 Contract Term and Schedule

The contract begins upon written notice to proceed and continues through final acceptance and the warranty period. The respondent must propose a detailed schedule and state the number of calendar days from notice to proceed to substantial completion and final completion. No work may begin before written authorization and satisfaction of applicable preconditions.

9.2 Insurance

Before contract execution, the successful respondent must provide certificates and endorsements in forms acceptable to HACL. Unless revised by addendum or contract, minimum coverage shall include workers’ compensation as required by law; employer’s liability of $500,000; commercial general liability of $1,000,000 per occurrence and $2,000,000 aggregate; automobile liability of

$1,000,000 combined single limit; umbrella/excess liability of $2,000,000; and cyber/professional liability of $1,000,000 where applicable to design, programming, remote access, or hosted services.

HACL and designated parties must be included as additional insureds where appropriate. Final requirements are subject to risk-manager and counsel review.

9.3 Indemnification and Damage

The contractor shall defend, indemnify, and hold harmless HACL and its Commissioners, officers, employees, and agents from claims, losses, damages, and expenses arising from the contractor’s negligent acts, omissions, breach, or willful misconduct, to the fullest extent permitted by law. The contractor is responsible for damage to the building, systems, residents’ property, or third-party property caused by its work.

9.4 Federal and HUD Requirements

• 2 CFR Part 200 procurement and applicable cost principles, as incorporated by the funding terms.

• Use the applicable HUD construction or nonconstruction instructions, certifications and contract conditions identified by HACL after classification of the final scope. Do not apply nonconstruction forms automatically to public works installation.

• Federal debarment and suspension requirements; the contractor and covered principals must be eligible for federal awards.

• Equal Employment Opportunity, Section 3, and other HUD requirements to the extent applicable to the funding and contract.

• Records retention, audit access, grant reporting, and cooperation with HACL, HUD, and authorized auditors.

• Federal labor standards, including applicable Davis-Bacon or HUD determined wage requirements, Section 3, domestic preference, Buy America, environmental review and bonding shall apply as required by the funding and scope. HACL shall attach applicable determinations and clauses before advertisement. These requirements do not displace the confirmed New Jersey prevailing wage obligation.

9.5 New Jersey Requirements

• New Jersey Business Registration Certificate requirements.

• THIS IS A PREVAILING WAGE PROJECT. Contractors and subcontractors performing covered work shall comply with the New Jersey Prevailing Wage Act, N.J.S.A. 34:11-56.25 et seq., and Public Works Contractor Registration Act, N.J.S.A. 34:11-56.48 et seq. Maintain required registration, pay applicable wages and fringe benefits, and submit certified payroll for each payroll period within the required ten day deadline through New Jersey Wage Hub and to the public body as required. HACL shall obtain and include the project specific wage determination and applicable updates. Include compliance and labor costs in the three system totals; no separate unit labor prices are requested.

• N.J.S.A. 10:5-31 and N.J.A.C. 17:27 affirmative-action and equal-employment requirements.

• Statement of Ownership disclosure under applicable New Jersey law.

• Disclosure of investment activities in Iran and certification regarding prohibited Russia or

Belarus activities, using current State forms.

• Political contribution and fair-and-open process requirements, together with all other applicable procurement statutes and regulations.

9.6 Permits and Codes

The contractor shall identify, obtain, and close out all permits and inspections required for its work, unless the Price Proposal expressly assigns a permit fee to HACL. All work must comply with applicable codes and be performed by properly licensed trades. The contractor shall coordinate elevator, fire-alarm, gate, electrical, and other specialty work.

9.7 Payment and Acceptance

Invoices must correspond to approved milestones and include supporting documentation. HACL may withhold payment for incomplete, defective, undocumented, or noncompliant work. Final payment is conditioned on final acceptance, closeout documents, lien releases if applicable, resolution of punch-list items, and delivery of all administrative credentials, licenses, and warranties.

9.8 Changes Termination and Funding

HACL may authorize lawful scope or quantity changes by prior written change order setting out the revised work and agreed lump sum adjustment. No automatic add/deduct unit price mechanism is included. The contract shall contain termination for cause and convenience provisions and remain subject to lawful appropriation and continued funding.

9.9 Public Records

Proposal materials may become public records under applicable law. A respondent claiming confidentiality must clearly mark specific portions and state the legal basis. Blanket confidentiality markings are discouraged and do not bind HACL.

APPENDIX A DEVICE AND LOCATION SCHEDULE

Quantities are based on the current site concept and must be field verified. Final placement and fields of view require LHA approval. “IP” quantities total approximately 118; elevator cameras total

2.

AREA LOCATION DISTRIBUTION QTY CAMERA CLASS

Resident hallways 10 floors 3 per floor 30 8 MP IP

Stairwell landings 11 floors 3 per floor 33 4 MP IP

Elevator lobbies 11 floors 1 per floor 11 4 MP IP

Trash chute rooms 11 floors 1 per floor 11 4 MP IP

Mailbox area First floor 1 1 4 MP IP

Front entrance door First floor 1 1 4 MP IP

Offices Five offices 1 each 5 4 MP IP

Community room First floor 3 3 4 MP IP

Back door First floor 1 1 4 MP IP

Laundry room Designated area 1 1 4 MP IP

North wing hallway First floor 1 1 8 MP IP

South wing hallway First floor 1 1 8 MP IP

Boiler room Service area 1 1 4 MP IP

Tenant Services room Designated room 2 2 4 MP IP

Maintenance office Designated area 2 2 4 MP IP

Supply / employee Designated room 1 1 4 MP IP room

Elevators Two elevator cars 1 each 2 5 MP HD

/converted

Front entrance area Exterior 1 1 8 MP IP

Front building / Exterior 4 4 8 MP 180 degree parking color

Left side / door / Exterior 1 1 8 MP 180 degree color

Rear building / Exterior 4 4 8 MP 180 degree color

Right side / parking Exterior 1 1 8 MP 180 degree color

Back gate Exterior 1 1 8 MP vari-focal IP

Parking-lot gate Exterior 1 1 8 MP vari-focal

IP

Access Controlled Openings

OPENING REQUIREMENT

Main entrance Reader/controller/credential access; reuse door hardware only if accepted

Office entrance Reader/controller/credential access; reuse door hardware only if accepted

Back door Reader/controller/credential access; reuse door hardware only if accepted

Back gate Reader/controller/credential access; interface existing gate hardware if accepted

Parking-lot gate Reader/controller/credential access; interface existing gate operator if accepted

APPENDIX B PRICE PROPOSAL FORM

Respondent: ________________________________________________

Prices shall remain firm for ninety days after the proposal deadline. Provide a detailed unpriced included equipment schedule. Each of the three system totals below must include its allocated labor, prevailing wage compliance, equipment, accessories, essential documentation, testing, warranty and all other mandatory costs. Do not submit unit prices or individual labor rates.

ITEM BASE SCOPE PRICE

1. TOTAL FOR CAMERA SYSTEM including cameras, elevator $____________ conversion, recording platform, 30-day motion recording storage, licenses, accessories, cabling and installation

2. TOTAL FOR ACCESS CONTROL SYSTEM including five $____________ openings, controllers, readers, 300 credentials, interfaces, programming and installation

3. TOTAL FOR NETWORK UPGRADE including switches, UPS $____________ protection, access points, five data drops, four electrical outlets and allocated surge/grounding work

COMBINED PROJECT TOTAL sum of the three system totals $____________

Included Devices and Equipment

Attach an UNPRICED equipment schedule organized by Camera System, Access Control System and Network Upgrade. For each included device or equipment group, state quantity, function, performance description, proposed manufacturer and model, new or reused status, licenses and included accessories. Include usable recording storage and the motion retention calculation. Supplier names and models are not prescribed by LHA; bidders must identify their own proposed equipment to demonstrate compliance and NDAA status.

Recurring Charges and Proposal Authorization

Identify any required recurring charge by system and year using the table below, and state which first year charges are included in the system totals. Identify optional post warranty service separately; it is not authorized by this form. State NONE if no recurring charges or exclusions apply.

No per device or per hour pricing is requested.

Required Charges by System and Year

CHARGE YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5

Camera System required charges $_____ $_____ $_____ $_____ $_____

Access Control System

Required charges $_____ $_____ $_____ $_____ $_____

Network Upgrade required charges $_____ $_____ $_____ $_____ $_____

Proposed substantial completion: ______ calendar days after Notice to Proceed.

Proposed final completion: ______ calendar days after Notice to Proceed.

Authorized Representative: __________________________ Title: __________________

Signature: __________________________________________ Date: __________________

AMERICANS WITH DISABILITIES ACT OF 1990

Equal Opportunity for Individuals with Disability

The contractor and the Housing Authority of the City of Linden (hereafter “owner”) do hereby agree that the provisions of Title II of the Americans With Disabilities Act of 1990 (the "Act") (42

U.S.C. 12101 et seq.), which prohibits discrimination on the basis of disability by public entities in all services, programs, and activities provided or made available by public entities, and the rules and regulations promulgated pursuant there unto, are made a part of this contract. In providing any aid, benefit, or service on behalf of the owner pursuant to this contract, the contractor agrees that the performance shall be in strict compliance with the Act. In the event that the contractor, its agents, servants, employees, or subcontractors violate or are alleged to have violated the Act during the performance of this contract, the contractor shall defend the owner in any action or administrative proceeding commenced pursuant to this Act. The contractor shall indemnify, protect, and save harmless the owner, its agents, servants, and employees from and against any and all suits, claims, losses, demands, or damages, of whatever kind or nature arising out of or claimed to arise out of the alleged violation. The contractor shall, at its own expense, appear, defend, and pay any and all charges for legal services and any and all costs and other expenses arising from such action or administrative proceeding or incurred in connection therewith. In any and all complaints brought pursuant to the owner’s grievance procedure, the contractor agrees to abide by any decision of the owner which is rendered pursuant to said grievance procedure. If any action or administrative proceeding results in an award of damages against the owner, or if the owner incurs any expense to cure a violation of the ADA which has been brought pursuant to its grievance procedure, the contractor shall satisfy and discharge the same at its own expense.

The owner shall, as soon as practicable after a claim has been made against it, give written notice thereof to the contractor along with full and complete particulars of the claim, If any action or administrative proceeding is brought against the owner or any of its agents, servants, and employees, the owner shall expeditiously forward or have forwarded to the contractor every demand, complaint, notice, summons, pleading, or other process received by the owner or its representatives.

It is expressly agreed and understood that any approval by the owner of the services provided by the contractor pursuant to this contract will not relieve the contractor of the obligation to comply with the Act and to defend, indemnify, protect, and save harmless the owner pursuant to this paragraph.

It is further agreed and understood that the owner assumes no obligation to indemnify or save harmless the contractor, its agents, servants, employees and subcontractors for any claim which may arise out of their performance of this Agreement. Furthermore, the contractor expressly understands and agrees that the provisions of this indemnification clause shall in no way limit the contractor’s obligations assumed in this Agreement, nor shall they be construed to relieve the contractor from any liability, nor preclude the owner from taking any other actions available to it under any other provisions of the Agreement or otherwise at law.

MANDATORY AFFIRMATIVE ACTION LANGUAGE

N.J.S.A. 10:5-31 and N.J.A.C. 17:27

(MANDATORY EQUAL EMPLOYMENT OPPORTUNITY LANGUAGE)

Goods, Professional Service and General Service Contracts

During the performance of this contract, the contractor agrees as follows:

The contractor or subcontractor, where applicable, will not discriminate against any employee or applicant for employment because of age, race, creed, color, national origin, ancestry, marital status, affection or sexual orientation or sex. Except with respect to affection or sexual orientation, the contractor will take affirmative action to ensure that such applicants are recruited and employed, and that employees are treated during employment, without regard to their age, race, creed, color, national origin, ancestry, marital status, affection or sexual orientation or sex. Such action shall include, but not be limited to the following: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the public agency compliance officer setting for the provisions of this nondiscrimination clause.

The contractor or subcontractor, where applicable will, in all solicitations or advertisements for employees placed by or on behalf of the contractor, state that all qualified applicants will receive consideration for employment without regard to age, race, creed, color, national origin, ancestry, marital status, affection or sexual orientation or sex.

The contractor or subcontractor, where applicable, will send to each labor union or representative or workers with which it has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the agency contracting officer, advising the labor union or workers' representative of the contractor's commitments under this act and shall post copies of the notice in conspicuous places available to employees and applicants for employment.

The contractor or subcontractor, where applicable, agrees to comply with any regulations promulgated by the Treasurer pursuant to N.J.S.A. 10:5-31 et seq., as amended and supplemented from time to time and the Americans with Disabilities Act.

The contractor or subcontractor agrees to make good faith efforts to employ minority and women workers consistent with the applicable county employment goals established in accordance with

N.J.A.C. 17:27-5.2 or a binding determination of the applicable county employment goals determined by the Division, pursuant to N.J.A.C. 17:27-5.2.

The contractor or subcontractor agrees to inform in writing its appropriate recruitment agencies including, but not limited to, employment agencies, placement bureaus, colleges, universities, labor unions, that it does not discriminate on the basis of age,, creed, color, national origin, ancestry, marital status, affection or sexual orientation or sex, and that it will discontinue the use of any recruitment agency which engages in direct or indirect discriminatory practices.

The contractor or subcontractor agrees to revise any of its testing procedures, if necessary, to assure that all personnel testing conforms with the principles of job-related testing, as established by the statutes and court decisions of the State of New Jersey and as established by applicable Federal law and applicable Federal court decisions.

In conforming with the applicable employment goals, the contractor or subcontractor agrees to review all procedures relating to transfer, upgrading, downgrading and layoff to ensure that all such actions are taken without regard to age, creed, color, national origin, ancestry, marital status, affection or sexual orientation or sex, consistent with the statutes and court decisions of the State of New Jersey, and applicable Federal law and applicable Federal court decisions.

The contractor and its subcontractors shall furnish such reports or other documents to the Executive

Director of the Housing Authority of the City of Linden, Division of Contract Compliance and EEO as may be requested by the office from time to time in order to carry out the purposes of these regulations, and public agencies shall furnish such information as may be requested by the Division of

Contract Compliance & EEO for conducting a compliance investigation pursuant to Subchapter 10 of the Administrative Code at N.J.A.C. 17:27.

PROPOSAL CHECKLIST

Completion and/or submission of the following items are mandatory:

Read, Initialed

Item and Submitted

Support for Qualifications

Support for Evaluation Factors

Acknowledgement of Addenda

Fee Proposal Form

Certification of Non-Debarment

Non-Collusion Affidavit

Statement of Ownership

Affirmative Action Compliance Notice

HUD-Forms

Disclosure of Investment Activities in Iran

Certification of Non-Involvement in Russia or Belarus

W-9 Form

New Jersey Business Registration Certificate

Certificate of Insurance ______________

Chapter 271 Political Contribution Disclosure Form ______________

The undersigned hereby acknowledges that they have completed and/or submitted the above-listed mandatory items. The undersigned also hereby acknowledges that the Housing Authority may, in its discretion, reject any proposal as non-responsive for the failure to include any of the above-listed mandatory items.

Name of Company:

Signature of Respondent’s Agent:

Name and Title of Respondent’s Agent:

Date:

ACKNOWLEDGEMENT OF ADDENDA

The Respondent hereby acknowledges receipt of the following Addenda to the Request for

Proposals:

Addendum No. Dated:

Signature of Respondent’s Agent

Subscribed and sworn to before me

This day of , 20

Notary Public of

My commission expires

Signature of Notary Public

FEE PROPOSAL FORM

The proposer certifies that it has reviewed the complete RFP and that the prices below include all costs necessary to perform the mandatory scope, except charges expressly identified as variable or optional. Attach additional detail when necessary.

A. One-Time Implementation / Transition Fee: $

B. Fixed Monthly Management, Support, and Optimization Fee: $ per month

C. Included Usage: voice minutes; SMS/MMS messages;

email messages; other:

D. Voice Usage Above Included Amount: $ per minute. State whether carrier, transcription, text-to-speech, and platform charges are included:

E. Messaging Usage Above Included Amount: SMS $ each; MMS $ each; other messaging $ each.

F. Required Third-Party Platform or License Charges Not Included Above (identify provider, unit, and price):

G. Required Integration Charges: PHA-Web or successor system $ ;

CRM/ticketing $ ; other $ .

H. Training and Documentation: Included / $ (circle or explain).

I. Optional Services and Rates (attach itemized schedule):

J. Travel or On-Site Charges, if authorized in advance:

K. Total Evaluated First-Year Price, using HACL’s stated evaluation assumptions:

Evaluation assumptions: [HACL TO INSERT ESTIMATED ANNUAL VOICE MINUTES, MESSAGE VOLUME, NUMBER OF INTEGRATIONS, AND ANY OTHER QUANTITIES USED TO

COMPARE PROPOSALS ON AN EQUAL BASIS].

No mandatory fee or charge omitted from this form or the attached price schedule may be invoiced unless added through a lawful written contract modification.

Company: Authorized Representative:

Signature: Date:

CERTIFICATION REGARDING NON-DEBARMENT, SUSPENSION,

INELIGIBILITY AND VOLUNTARY EXCLUSION

I, residing in

(name of affiant) (name of municipality)

In the County of and State of , Of full age, being duly sworn according to law on my oath depose and say that:

and/or its principals have never, at any time, been suspended

(name of firm) debarred, declared ineligible, or voluntarily excluded by the Department of Housing and Urban

Development, the Department of Justice, the General Services Administration, the Internal

Revenue Service, or any other federal agency or the Federal Government, and/or the New Jersey

Department of Labor or any other state agency or the State of New Jersey.

NON-COLLUSION AFFIDAVIT

I, residing in

(name of affiant) (name of municipality) in the County of and State of , of full age, being duly sworn according to law on my oath depose and say that:

I am of

(title or position) (name of firm) the entity submitting this Proposal for , and

(type of services) that I executed the said Proposal with full authority to do so that said firm has not, directly or indirectly entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free, competitive bidding in connection with the above named project; and that all statements contained in said proposal and in this affidavit are true and correct, and made with full knowledge that the Housing Authority of the City of Linden relies upon the truth of the statements contained in said Proposal and in the statements contained in this affidavit in awarding the contract for the said project.

I further warrant that no person or selling agency has been employed or retained to solicit or secure such contract upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee, except bona fide employees or bona fide established commercial or selling agencies maintained by .

STATEMENT OF OWNERSHIP

Name of Business:

I certify that the list below contains the names and home addresses of all stockholders holding 10% or more of the issued and outstanding stock of the undersigned.

OR

I certify that no one stockholder owns 10% or more of the issued and outstanding stock of the undersigned.

Check the box that represents the type of business organization:

Partnership Limited Liability Company Corporation Sole Proprietorship

Limited Partnership Limited Liability Partnership Subchapter S Corporation

Sign and notarize the form below, and, if necessary, complete the stockholder list below.

Stockholders:

Name: Name:

Home Address: Home Address:

% of Ownership: % of Ownership:

Name:

Home Address:

Name:

Home Address:

% of Ownership: % of Ownership:

AFFIRMATIVE ACTION COMPLIANCE NOTICE

N.J.S.A. 10:5-31 AND N.J.A.C. 17:27

GOODS AND SERVICES CONTRACTS

(INCLUDING PROFESSIONAL SERVICES)

This form is a summary of the successful bidder’s requirement to comply with the requirements of N.J.S.A.

10:5-31 and N.J.A.C. 17:27-1 et seq.

The successful bidder shall submit to the public agency, after notification of award but prior to execution of this contract, one of the following three documents as forms of evidence:

(a) A photocopy of a valid letter that the contractor is operating under an existing Federally approved or sanctioned affirmative action program (good for one year from the date of the letter);

OR

(b) A photocopy of a Certificate of Employee Information Report approval, issued in accordance with

N.J.A.C. 17:27-4;

OR

(c) A photocopy of an Employee Information Report (Form AA302) provided by Division and distributed to the public agency to be completed by the contractor in accordance with N.J.A.C.

17:27-4.

The successful vendor may obtain the…