This is a Questions and Answers (Q&A) document for a federal contract solicitation for portable toilet and handwashing station rental services at MARSOC (Marine Special Operations Command) training locations.

The solicitation is a 100% small business set-aside with a base period and four option years, plus a potential six-month extension. The contract requires delivery, weekly service, pickup, and maintenance of approximately 153 portable toilets (designated as "Porta-Johns") during the base year, with roughly 169 units for each option year. Additionally, seven handwashing stations requiring weekly service are needed, with the contractor responsible for providing water, soap, paper towels, and wastewater removal. One "Each" in pricing represents a single unit delivered, serviced, and picked up for one listed event, regardless of event duration (ranging from three days to four weeks). Unit pricing should cover only delivery, pickup, weekly service, and cost per unit; additional services such as emergency pump-outs may be quoted separately for potential modification. The proposal due date is December 1, 2026, at 10:00 AM EST. Service Contract Act labor classification should use Laborer 23470 ($16.65 rate) or allow contractors to submit conformance requests for alternative classifications such as "Portable Toilet Servicer" or "Vacuum Truck Operator/Servicer." The previous contract, held by Chair and Equipment Rentals Inc. under contract H9225725P0001, was valued at $65,000 for base and all options. No ADA-accessible units are required, security clearances are not required, and driver lists are needed only before performance commencement, not before award.

View the file

Other files

File Type Posted
H9225727RE003 P01 SF 30.pdf PDF
H9225727RE003 P01 Conformed.pdf PDF
Solicitation - H9225727RE003.pdf PDF
WD 2015-4389 Rev 35.pdf PDF
PJ SOW FY27.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Q: The base pricing schedule lists 153 units under “MRTC Hand Washing Station,” while the corresponding option lines list 173 portable toilets and the SOW calls for 173 portable toilets and seven handwashing stations. Should CLIN 0001 be labeled “MRTC Portable Toilets,” and should the base quantity be 153 or 173?

A: CLIN 0001 Has been corrected to say Porta-Johns. The Base quantity should be 153 as October and November has already passed. Thus, those quantities have been removed from the total for the base year. ALL following Option Years will have roughly 169.

2. Q: Does the SOW’s total of 173 include the four toilets separately listed under the SERE and CD&I lines?

A: The SOW’s total of 173 does include the four toilets separately listed under the SERE and CD&I lines. The following CLINS have been adjusted to account for that.

3. Q: Please also confirm what one “Each” represents for pricing purposes.

A: Based on our previous contract “Each” encompasses the total cost of a

Porta-john to include services fees. The government is open to breaking down the CLINs farther based on any proposed pricing. Please just ensure it is clearly broken down so that if we need to add or subtract a Porta-john or handwashing station it is clear what that cost would be.

4. Q: The SOW identifies several training events beginning before the solicitation closing date of December 1, 2026.

A: Those dates are to help you price and have an expectation for the following option years. Depending on when we get this solicitation awarded will depend on the start date. Additionally, as is stated on the SOW, the Technical Point of Contact (TPOC) will confirm dates and location for each event listed on the SOW five days prior.

5. Q: Will an updated performance schedule be issued reflecting the anticipated contract award and commencement date?

A: One can be if it is requested. The SOW is fluid as dates and locations have the potential to shift which is why the TPOC will confirm those events 5 days prior.

6. Q: Option Period 5 dates: CLINs 5002 and 5003 show a period of performance from 19 Oct 2031, while CLINs 5001, 5004, and 5005 show 07 Dec 2031. Please confirm the correct start date for Option Period 5.

A: Dates have been updated to reflect the date of 07 Dec 2031. CLINS 5001 – 5005 are for the six-month extension and are used for pricing purposes during solicitation and will not be on the actual award.

7. Q: Could you confirm the correct quantities required for the base period and whether these quantities represent individual rental events or the number of units required simultaneously?

A: Question One confirms the quantities. The quantity only accounts for the number of porta-johns being requested in total for all of the events. It does not take into account a time frame for the event.

8. Q: Is one "Each" equal to one unit delivered, serviced, and picked up for one listed event, no matter how long the event runs? The events in the SOW run from 3 days to about 4 weeks.

A: Correct, one "Each" is equal to one unit delivered, serviced, and picked up for one listed event, no matter how long the event runs. So, if it says 4 each, we are requesting 4 individual POJs. If you need to break it down diƯerently, you can submit your suggested CLIN structure.

9. Q: The SOW says units will be serviced "weekly or by the request of the customer."

Are service calls beyond the weekly service part of the unit price, or will they be ordered and paid separately? If they are part of the unit price, how many extra service calls should we plan for per year?

A: They are part of this contract. It is unknown how many additional services may be required. As it all depends on the volume of students and training.

Last year, we requested zero additional services outside of the regular weekly services. If you need it to be listed/accounted for separately then we will need to have it listed as a price and if the situation arises, we are amenable to doing a modification to account for that additional cost.

10. Q: Are relocations at the customer's request part of the unit price? If so, how many relocations should we plan for per year?

A: Last year, there were zero relocations. We did, however, make changes to the SOW throughout the year, which is why confirming with the TPOC 5 days prior to an event mitigates this risk. Any relocation requirements will come before the required date.

11. Q: Are relocations between training locations included in the contractor’s fixed price, or will additional relocations be separately authorized and compensated?

A: If new requirements (i.e. more than the 173 anticipated PJs listed) are required we will have to do a modification to the contracts to account for that additional price. Which is why it is essential your pricing is clear so there are no questions when it comes to adding any additional PJ or handwashing stations.

12. Q: The SOW shows CLIN 0002 and CLIN 0003 running 21 Oct 2026 through 20 Oct 2027, and lists events from 13 Nov through 6 Dec 2026. The solicitation period of performance starts 7 Dec 2026. Please confirm the contractor is only responsible for events and service on or after 7 Dec 2026.

A: The vendor for this award will only be responsible for dates once the contract is awarded. The October dates listed on the SOW are to help you have a better understanding for all follow on Option Years.

13. Q: The award basis is lowest price technically acceptable. What must the quote include to be rated technically acceptable?

A: The vendor must provide complete pricing for everything that is requested in the 1449 in accordance with the SOW.

14. Q: Should the unit price include delivery, pickup, weekly service, additional service requested by the customer, and relocations? For the handwashing stations, please confirm the required service frequency and whether the contractor must provide water, soap, paper towels, and wastewater removal.

A: No, the price should only cover delivery, pickup, weekly service and the cost per each Porta-John. For handwashing stations, we would require weekly services. The vendor will support with water, soap, paper towels, and wastewater removal.

15. Q: Should pricing be submitted separately for the base period, each of the four option years, and the potential six-month extension?

A: The CLINS on the 1449 are broken out to account for the base period, option years, and potential six-month extension. So, yes pricing should be submitted separately.

16. Q: The schedule computes Amount as Quantity times Unit Price with no months multiplier. Please confirm the CLIN unit price is the per-unit price for the full 12-month delivery period, not a monthly rate.

A: The unit of issue “Each” account for each Porta-john or handwashing station being requested for that specified timeframe for any given event.

Some dates on the SOW run from 3 days to 4 weeks. If for CLINS 0002, 0003, or 0005 which are there for a full year and it makes more sense in your quote to do a 12-month delivery period or if there is a discount you apply, then the government is amenable to adjusting that unit of issue.

17. Q: Should contractors provide pricing per unit, per rental event, or for the entire contract period? Are delivery, pickup, cleaning, pumping, and relocation costs expected to be included in the unit price?

A: The price should only cover delivery, pickup, weekly service and the cost per each POJ. For handwashing stations, we would require weekly services. The vendor will support with water, soap, paper towels, and wastewater removal.

18. Q: The SOW requires weekly servicing. Are additional cleanings or emergency pump-outs anticipated, and if so, how should contractors account for these services in their pricing?

A: They are not anticipated if you quote a price for emergency pump-outs in your quote. Then if that situation occurs, we will be able to adequately compensate you in accordance with your solicitation pricing.

19. Q: Are there specific security clearances, vehicle requirements, or advance processing timelines that contractors and subcontractors must satisfy before entering MARSOC training locations?

A: No, having the contract and location will suƯice. We only have two requirements, in which an escort might be required. If this happens, we will support and coordination will occur through the TPOC.

20. Q: Will a designated technical representative coordinate training schedules, delivery locations, access arrangements, and service verification throughout performance?

A: A Technical Point of Contact will be identified in the contract. As well as each specified event having their own TPOC. The Contracting OƯicer will also be available for any assistance required.

21. Q: How many of the portable toilets must be ADA-accessible?

A: None of the PJ need to be ADA-accessible.

22. Q: Please confirm the lead time for Provost Marshal's Office passes and Visit Authorization Request / Visit Authorization Letter processing for subcontractor drivers, and whether a driver list is required before award or only before performance.

A: A driver’s list can help speed up the process prior to award. However, you will only need that before performance and once the contract has been awarded. We will work in coordinating with the required security gates.

23. Q: MRR OƯsite (34.41236, -77.649738) appears to be outside the installation.

Please confirm the location and any access requirements for that site.

A: It is outside the installation. Not tracking any access requirements at this time.

24. Q: Please confirm whether a limitation on subcontracting applies to this requirement and identify the governing clause and any applicable deviation.

A: Per FAR part 19 when doing a 100% small business set-aside there is no subcontracting plan required. Which ever company is listed on the contract will be held responsible for performing the contract.

25. Q: May a small-business prime contractor utilize a qualified local subcontractor for equipment rental, delivery, pumping, cleaning, and maintenance while retaining overall contract management and responsibility?

A: As long as you are a small business no sub-contracting plan is required.

However the work must occur, and the business that is awarded the contract will be responsible or ensuring that occurs.

26. Q: Are there any additional requirements for site visits, licensing, or past performance at the proposal stage?

A: At this time there are no additional requirements identified.

27. Q: Is there an incumbent contractor, and is previous contract pricing available?

A: The previous contractor was Chair and Equipment Rentals Inc., awarded under contract H9225725P0001 for a total contract value (base and all options) $65,000.00.

28. Q: Is this requirement a follow-on to contract H9225725P0001? If so, has the number of events or units changed from that contract?

A: Yes, this is a follow-on to contract H9225725P0001. The previous contract had a total number of porta-johns being maxed out at 200; thus, we were able to make as many changes to the SOW as we need to. So long as the total amount did not exceed 200 PJ.

29. Q: The SAM.gov notice shows a response date of Dec 1, 2027. Please confirm proposals are due Dec 1, 2026, 10:00 AM EST, as stated in SF-1449 Block 8 and the 52.212-1 addendum.

A: This was a mistake the response date is Dec 1, 2026 as per the SF-1449.

30. Q: Service Contract Act classification: WD 2015-4389 Rev 35 does not designate a classification for porta-john pumping, cleaning, and hand-washing station servicing. Please confirm which classification applies (Janitor 11150, Laborer

23470, or Truckdriver Light 31361), or whether a conformance request will be required.

A: It doesn’t specify and you can submit a conformance request under FAR 52.222-41 and 29 CFR 4.6 and propose a new classification (commonly titled “Portable Toilet Servicer,” “Portable Sanitation Technician,” or “Vacuum Truck Operator/Servicer”) with a rate commensurate with the duties, using the existing WD occupations as comparators. Although, at this time they can associate the requirement to being closest to 23470 Laborer ($16.65).