This Performance Work Statement (PWS) details a contract for repowering six Patrol Boat Lights (PBLs) for Naval Special Warfare Command - Group FOUR (NSWG4). The scope requires the contractor to remove 12 existing E-tec outboard motors and install 12 Yamaha 150 hp outboards (six F150XC and six LF150XC engines), including associated hardware such as binnacle controls, wire harnesses, gauges, switch assembly panels, control cables, and aluminum propellers. The work will be performed at the contractor's facility within 50 miles of Stennis, MS, with each boat to be completed within 30 business days of component delivery.

The contract includes specific requirements for quality control, with the contractor required to implement a Quality Control Plan and maintain high standards of service. The government reserves the right to conduct inspections and issue Contract Discrepancy Reports for unsatisfactory performance. Additional requirements include compliance with hazardous material handling regulations, filing warranty documentation, and reporting all contractor labor hours via sam.gov annually by October 31. The contractor must provide all necessary personnel, tools, parts, and supervision to return the patrol boats to full operational capability and readiness.

View the file

Other files for this federal contract opportunity

Other files attached to Patrol Boat Repowering, newest first.
File Type Posted
Attachment 1 PWS 250409.pdf PDF
H9224025Q0016-0002.pdf PDF
QNA Set 2.pdf PDF
H9224025Q0016-0001.pdf PDF
QNA Set 1.pdf PDF
H9224025Q0016.pdf PDF
Attachment 1 PWS 250313.pdf PDF
Attachment 2 DoL WD 2015-5147 241223.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement (PWS) Naval Special Warfare Command - Group FOUR

Patrol Boat Repowering

1. OBJECTIVES:

1.1. NSWG4 requires repowering of Patrol Boat Lights (PBLs).

2. SCOPE:

2.1. The contractor shall provide all personnel, tools, parts, supervision and other items necessary to perform the services identified herein. The contractor will provide and remove current outboards of six PBLs and associated hardware and install 12 Yamaha 150 hp outboards, to include all required hardware, gauges, and wiring on the PBL. Accomplishing the installation of the engines on the PBL’s is required to return the craft to its operational capability and readiness

3. REQUIREMENTS/SERVICES:

3.1. Remove 12 outboard E-tec motors, engine controls, oil tanks, gauges, and pumps.

3.2. 12 Yamaha 150 outboard engines (already on-hand) shall be installed, broken down as 6 F150XC, 6

LF150XC, Yamaha engines. Each craft (for a total of six craft) will have two Yamaha engines installed per craft as follows: 1 F150XC, 1 LF150XC Yamaha engine.

3.3. Install Yamaha (6) Dual twin engine binnacle control (chrome).

3.4. Install (12) Yamaha wire harness.

3.5. Install (6) Yamaha Command Link, round 3 Gauge kit.

3.6. Install (6) Yamaha twin switch assembly panels.

3.7. Install (6) Yamaha 24’ control cable.

3.8. Install (12) 14-1/2” X 17M aluminum props.

3.9. File warranty and provide all OEM documents.

4. HAZARDOUS MATERIAL USE, HANDLING, OR DISPOSAL:

4.1. The contractor shall comply with all Federal, State, and Local laws regarding the use, handling, or disposal of hazardous materials (petroleum products, paints, coatings, etc.).

4.2. The contractor assumes all responsibility if spillage of hazardous fluids or material are to enter the marine environment.

5. VESSEL INSPECTION & ACCEPTANCE:

5.1. The government will all work and conduct operational testing of the outboards and all associated equipment and ensure installation and operation is satisfactory prior to pick-up/acceptance.

6. DELIVERABLES:

Description Num ber

PWS

Ref.

Delivery Date

Contractor Manpower Reporting

0002 7.1 Annually NLT 31 October and/or at contract completion.

7. CONTRACTOR MANPOWER REPORTING:

7.1 The Contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the NSWG4 via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://sam.gov. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk on the sam.gov website.

8. QUALITY CONTROL:

8.1. The contractor shall implement and maintain a Quality Control Plan (QCP) to ensure work performed conforms to the scope of work and meets the requirements under this PWS. The QCP shall, at a minimum provide a method for performing inspections; identifying, correcting and preventing problems/defective service; addressing customer complaints, and improving the quality of services over the life of the contract.

9. QUALITY ASSURANCE:

9.1. The Government reserves the right to perform inspections and surveillance to evaluate the Contractor’s compliance to the contract terms and performance of the requirements in the PWS.

9.2. Contract Discrepancy Report (CDR). In the event of unsatisfactory contractor performance, the CO will issue a CDR that will explain the circumstances and findings concerning the incomplete or unsatisfactory service. The contractor shall acknowledge receipt of the CDR and respond in writing as to how he/she shall correct the unacceptable performance and avoid a recurrence. The Government will review the contractor's corrective action response to determine acceptability and will use any completed CDR as part of an overall evaluation of Contractor performance when determining present or future contractual actions.

10. SECURITY

10.1. N/A

11. PLACE OF PERFORMANCE:

11.1 . All repairs shall be done at the contractor’s facility. The contractor’s facility shall be within 50 miles of

Stennis, MS. The government will provide delivery and pick-up of the PBL’s (One PBL at a time).

12. PERIOD OF PERFORMANCE:

12.1. Completion of work will be no more than 30 business days from delivery of necessary components to facilitate repair.

File details come from the government source that posted it. Updated .