Att_1_-_PWS.pdf
PDF 190 KB Posted
- Solicitation number
- H9224018R0005
- Issued by
-
United States Special Operations Command
About this file
Draft Performance Work Statement
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources_Sought_H92240-18-R-0005.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
H92240-18-R-0005 – ATTACHMENT 1
Performance Work Statement Naval Special Warfare Command
11 Meter Rigid Inflatable Boat Repair, Maintenance and Upgrades
1. BACKGROUND
1.1 Naval Special Warfare Command (NSWC) and its subordinate commands utilize 11 Meter (11M)
Rigid Inflatable Boats (RIBs) as part of the operational and training regimen. The 11M RIBs require periodic maintenance as well as design upgrades in order to improve performance and extend usable life of the boats and associated equipment.
2. OBJECTIVES
2.1 The objective of this requirement is to establish a single firm fixed price (FFP) Indefinite Delivery Indefinite Quantity (IDIQ) contract for repair, maintenance and upgrade support services for the 11M RIBs.
3. SCOPE
3.1 The Contractor shall provide the personnel, management, materials, equipment and facilities (unless otherwise provided by the Government as stated in the Task Order) necessary to perform any required repair, maintenance and upgrade services for the fleet of 11M RIBs predominantly located in the San Diego, California locality. The scope includes pre-defined Work Packages as outlined in this Performance Work Statement (PWS), in addition to Over-and-Above Work Requests (OAWR) for physical installation of Engineering Change Proposals (ECPs), Non-Engineering Change Proposals (NECPs), and other emergent repairs or necessary upgrades to the 11M RIBs and their associated systems and equipment. All specific requirements for repairs, maintenance, upgrades, ECPs and NECPs shall be addressed in each Task Order. The Contractor is solely responsible for its work techniques and control and supervision of Contractor personnel in performance of the contract. The Contractor shall actively retain any and all appointments, licenses, certifications and permits required to perform work under this contract, and provide any evidence of such to the Government upon request. The Contractor shall comply with all applicable Federal, State, and Local laws regarding the use, handling, or disposal of hazardous materials required under the contract. Hazardous materials may include, but are not limited to, petroleum products, paints, and coatings.
4. REQUIREMENTS
4.1 The contractor perform repairs, maintenance and upgrades as specifically identified in each Task
Order. Pre-defined Work Packages are identified below (further defined in Exhibit 1 to the PWS) and represent historical requirements experienced for 11M RIB repair, maintenance and upgrade services.
4.1.1 WORK PACKAGE 1 – LOW LEVEL MAINTENANCE – TRAILER REPAIRS
4.1.2 WORK PACKAGE 2– MEDIUM LEVEL MAINTENANCE – TRAILER REPAIRS
4.1.3 WORK PACKAGE 3 – HIGH LEVEL MAINTENANCE – TRAILER REPAIRS
4.1.4 WORK PACKAGE 4 – LOW LEVEL MAINTENANCE - BOAT PRESERVATION
4.1.5 WORK PACKAGE 5 - HIGH LEVEL MAINTENANCE - BOAT PRESERVATION
4.1.6 WORK PACKAGE 6 –LOW LEVEL PLANNED MAINTENANCE AVAILIBILITY
(PMA) – BOAT PRESERVATION HULL AND TOPSIDE
4.1.7 WORK PACKAGE 7 – MEDIUM LEVEL MAINTENANCE – BOAT REPAIRS HULL
AND TOPSIDE
4.1.8 WORK PACKAGE 8 – HIGH LEVEL MAINTENANCE - BOAT REPAIRS HULL
AND TOPSIDE
4.1.9 WORK PACKAGE 9 – MEDIUM LEVEL MAINTENANCE – BOAT REPAIRS
MECHANICAL
4.1.10 WORK PACKAGE 10 – HIGH LEVEL MAINTENANCE – BOAT REPAIRS
MECHANICAL
4.1.11 PORT AND STARBOARD F/O BLADDER FLANGE
4.1.12 PORT AND STARBOARD BLADDER REPLACEMENT
4.1.13 BOLSTER AND FORWARD GUN MOUNT GUN BAGS
4.1.14 OVER AND ABOVE WORK
4.2 Work Packages may be further refined with new or revised Work Packages negotiated into the contract in the future, when necessitated by the Government’s observed recurring requirements for repair, maintenance and upgrade services.
4.3 Performance of the Work Packages shall include inspection by the Contractor. The Contractor shall notify the Government Contracting Officer Representative (COR) within 24 hours when any requirements for work outside the scope of the Task Order or Over-and-Above Work are identified.
The Contractor shall not perform work outside the scope of the Task Order or Over-and-Above Work, until a written Task Order, Task Order Modification, or explicit written authorization is given to the Contractor by the Government Contracting Officer (KO) authorizing the performance of OAWRs.
4.4 Work Completion Deadlines, unless longer timeframes otherwise permitted by the Task Order.
4.4.1 LOW LEVEL – No Later Than (NLT) 60 calendar days after receipt of order (ARO)
4.4.2 MEDIUM / HIGH LEVEL – NLT 90 calendar days ARO
4.4.3 ECPs / NECPs – NLT 60 calendar days ARO
4.4.4 OAWRs – NLT 90 calendar days ARO
4.5 Government Inspection.
4.5.1 Upon work completion, the Contractor shall perform a thorough walk-through inspection with the Government. The Contractor shall demonstrate to the Government in the walk-through inspection that all work has been performed as specified in the Task Order.
4.5.2 The Contractor will provide walk-through inspection for the Government within two (2) calendar days of Task Order completion, unless a longer timeframe is otherwise permitted by the COR.
4.5.3 At time of inspection, the Contractor shall provide an Inspection Summary Report (ISR) which provides at a minimum a list of all parts and materials installed or replaced by the Contractor.
4.5.4 If the Contractor’s work is determined unacceptable, requires rework, or otherwise fails to pass the Government Inspection, the Contractor shall perform any and all necessary rework as directed by the Government at no additional expense to the Government.
4.6 Monthly Status Report.
4.6.1 The Contractor shall submit a Monthly Status Report (MSR) summarizing work completed within the month and progress towards completion of each active Task Order.
The Contractor shall provide the MSR to the Government COR NLT the fifth (5th) calendar day of every month, for work performed in the preceding month.
4.7 Contractor Facilities.
4.7.1 Contractor facilities shall be within thirty (30) miles of the Government site, Naval
Amphibious Base (NAB) Coronado, California, unless otherwise specified in the Task Order.
4.7.2 Contractor facilities shall be capable of accommodating up to eight (8) 11M RIBs and their associated systems and equipment simultaneously.
4.7.3 Contractor shall be capable of accepting 11M RIBs delivered by either land or water and shall be capable of lifting/hoisting 11M RIBs from a trailer or from water.
4.7.4 The Contractor shall grant the Government access to the Contractor facilities during normal working hours (0700 to 1630 Monday through Friday excluding federal holidays) and any other times when work is being performed on the 11M RIBs and their associated systems and equipment.
4.8 Participate in a Post-Award Conference.
4.8.1 This meeting shall provide an introduction between the Contractor personnel and
Government personnel who will be involved with the contract. The meeting shall provide the opportunity to discuss technical, management and security issues. The Post Award Conference will aid both the Government and Contractor in achieving a clear and mutual understanding of all requirements, and identify and resolve any potential issues. The Contractor shall be prepared to discuss any items requiring clarification and gather information as necessary to support each deliverable. The Contractor shall provide a written summary of the Post-Award Conference.
5. DELIVERABLES
Description Num ber
PWS
Ref.
Delivery Date
Inspection Summary Report
(ISR)
0001 4.5 Upon Government Inspection; within two (2) calendar days of Task Order completion
Monthly Status Report
(MSR)
0002 4.6 5th calendar day of every month, for work performed in the preceding month
Post Award Conference Minutes
0003 4.8 5 calendar days after Post Award Conference
Contractor Manpower Reporting
0004 6.0 Annually NLT 31 October and at contract completion
6. CONTRACTOR MANPOWER REPORTING
6.1 The Contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Naval Special Warfare Command via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk at help desk at: http://www.ecmra.mil.
7. CONTRACTOR TRAVEL
7.1 Contractor travel outside the San Diego, California locality is not anticipated, unless otherwise specified and negotiated at the Task Order level.
8. SECURITY
8.1 Security will be in accordance with the attached DD254. Contractor team individual(s) supporting this task will be cleared at the “Secret” level at the start of the task. Contractor will require access to NIPRNET/SIPRNET computer systems only at government facilities. Contractor will be authorized to courier classified information up to the “Secret” level in performance of official duties upon approval of and designation by the Government COR.
8.2 The contractor shall ensure requirements for obtaining and verifying personnel security clearances, for verifying security clearances and indoctrination of visitors, for controlling access to restricted areas, for protecting government property, and for the security of automated and non-automated management information systems and data are fulfilled. The Contractor's management system shall prevent unauthorized disclosure of classified and sensitive unclassified information. The Government shall be immediately notified if any security incident or any indication of a potential unauthorized disclosure or compromise of classified or sensitive unclassified information.
8.3 Contractor shall establish appropriate administrative, technical, and physical safeguards to protect any and all nonpublic Government data to ensure the confidentiality, integrity, and availability of Government data.
8.4 Contractor must be able to obtain personnel and vehicle access to military installations. Contractor is responsible for coordinating all necessary access through the local Military Pass and Decal Office.
9. SAFETY
9.1 Contractor Responsibility
9.1.1 Nothing in the Performance Work Statement, nor any Government action or failure to act in performance of the contract shall relieve the contractor of its responsibility for the safety of the contractor's personnel and property, the Government's personnel and property, and the general public. Furthermore, nothing in this PWS shall relieve the contractor of its responsibility for complying with applicable Federal, State, and Local http://www.ecmra.mil/ http://www.ecmra.mil/ laws, ordinances, codes and regulations (including those requiring applicable licenses and permits) in connection with the performance of this contract.
10. GOVERNMENT PROVIDED PARTS/MATERIALS
10.1 Port/Starboard impeller housings, unless otherwise specified and negotiated at the Task Order level.
11. QUALITY CONTROL
11.1 The contractor shall implement and maintain a Quality Control Plan (QCP) to ensure work performed conforms to the scope of work and meets the requirements under this PWS. The QCP shall, at a minimum provide a method for performing inspections; identifying, correcting and preventing problems/defective service; addressing customer complaints, and improving the quality of services over the life of the contract.
12. QUALITY ASSURANCE
12.1 The Government reserves the right to perform inspections and surveillance to evaluate the Contractor’s compliance to the contract terms and performance of the requirements in the PWS. The Government will make every effort to ensure that the surveillance methods used are conducted in an objective, fair, and consistent manner. The Government will assign a Contracting Officer’s Representative (COR) who will be responsible for monitoring performance in accordance with the requirements of the PWS and the Quality Assurance Surveillance Plan (QASP). The COR will make every effort to ensure that the surveillance methods used are conducted in an objective, fair, and consistent manner.
12.2 Contract Discrepancy Report (CDR). In the event of unsatisfactory contractor performance, the Contracting Officer (KO) will issue a CDR that will explain the circumstances and findings concerning the incomplete or unsatisfactory service. The contractor shall acknowledge receipt of the CDR and respond in writing as to how he/she shall correct the unacceptable performance and avoid a recurrence. The Government will review the contractor's corrective action response to determine acceptability and will use any completed CDR as part of an overall evaluation of Contractor performance when determining present or future contractual actions.
13. APPLICABLE DOCUMENTS
Document Web link (if applicable)
ANSI/ISO/ASQ Q9000-2005, Quality Management Systems - Fundamentals and Vocabulary
Available upon request
ANSI/ISO/ASQ Q9001-2015, Quality Management Systems - Requirements
Available upon request
Program Specific Policy, Technical Manuals, MILSPECS and Drawings for Maintenance and Equipment Requirements
Available upon request
14. PLACE OF PERFORMANCE
14.1 Contractor facilities shall be within thirty (30) miles of the Government site, Naval Amphibious Base (NAB) Coronado, California, unless otherwise specified in the Task Order.
14.2 Government facilities aboard Naval Amphibious Base (NAB) Coronado, California, when specified in the Task Order.
15. PERIOD OF PERFORMANCE
15.1 Date of contract award through a five (5) year ordering period
EXHIBIT 1 – WORK PACKAGES
WORK PACKAGE 1 – LOW LEVEL MAINTENANCE – TRAILER REPAIRS
Note: Report any defective parts found to the designated Government representative.
1 Block trailer and remove all wheels.
2 Support axles and disconnect "U" bolts holding axles to springs.
3 Disconnect flexible brake lines at caliper and frame ends and drain brake fluid from system. Lines should be blown clean with air.
4 Remove bleeder fittings from each caliper assembly.
5 Remove six (6) leaf springs and equalizers from trailer. Contractor will provide new OEM leaf springs.
6 Remove three (3) axles from trailer.
7 Protect and remove brake components on axles prior to sandblasting.
8 Sandblast leaf springs (6 ea), equalizers (4 ea), and U-bolt back plates (6 ea) to white metal.
9 Paint equalizers (4 ea), and U-bolt back plates (6 ea) with gray CeRam Kote 54® in accordance with manufacturer’s specifications.
10 Prepare and preserve external surfaces of six new MYCO springs with ZRC Worldwide ZRC® cold galvanizing paint in accordance with the manufacturer’s specifications.
11 Prepare and preserve new axle “U” bolts (24 ea) with CeRam Kote 54® in accordance with manufacturer’s specifications. “U” bolts will be sandblasted and CeRam Kote 54® in accordance with manufacturers specifications taking care to protect the threaded area.
12 Power tool clean rusty spots and preserve up to ten square feet of trailer frame with ZRC Worldwide ZRC® cold galvanizing paint in accordance with the manufacturers specifications.
13 Remove existing and install all new reflective tape on trailers IAW OEM.
14 Install axles and springs with new CeRam Kote’d "U" bolts, nuts, spring bolts, spring bushings and hanger bushings from MYCO Trailers, Inc.
15 Remove existing and install new wheel bearing seals, wheel bearings, bearing races, disc brakes pads, and brake hoses. Install new hub (six each per trailer) diaphragm, air cap and super seal kit. Refer to NECP 026.
16 Remove existing and install new brake line hoses 17 Fill brake system (new DOT 5 fluid) and bleed air from lines. Test for zero leaks.
18 Remove all bunk boards, replacing damaged boards, padding, and sail cloth IAW OEM and re-install.
19 Prepare and preserve bunk brackets and trailer support wheel.
20 Polish outer surfaces of aluminum wheels, fenders and stowage box to a level greater than 60 GU at 60 degrees and reinstall using anti-seize on lug nuts and torque to OEM specs. Polish type is at contractor discretion.
WORK PACKAGE 2– MEDIUM LEVEL MAINTENANCE – TRAILER REPAIRS
Note: Report any defective parts found to the designated Government representative.
1 Block trailer and remove all wheels.
2 Support axles and disconnect "U" bolts holding axles to springs.
3 Disconnect flexible brake lines at caliper and frame ends and drain brake fluid from system. Lines should be blown clean with air.
4 Remove bleeder fittings from each caliper assembly.
5 Remove six (6) leaf springs and equalizers from trailer. Contractor will provide new OEM leaf springs.
6 Remove three (3) axles from trailer.
7 Protect and remove brake components on axles prior to sandblasting.
8 Sandblast axles (3 ea), leaf springs (6 ea), equalizers (4 ea), and U-bolt back plates (6 ea) to white metal.
9 Paint axles (3 ea), equalizers (4 ea), and U-bolt back plates (6 ea) with gray CeRam Kote 54® in accordance with manufacturer’s specifications.
10 Prepare and preserve external surfaces of six new MYCO springs with ZRC Worldwide ZRC® cold galvanizing paint in accordance with the manufacturer’s specifications.
11 Prepare and preserve new axle “U” bolts (24 ea) with CeRam Kote 54® in accordance with manufacturer’s specifications. “U” bolts will be sandblasted and CeRam Kote 54® in accordance with manufacturers specifications taking care to protect the threaded area.
12 Power tool clean and preserve twenty square feet of trailer frame with ZRC Worldwide ZRC® cold galvanizing paint in accordance with the manufacturers specifications.
13 Remove existing and install all new reflective tape on trailers IAW OEM.
14 Install axles and springs with new CeRam Kote’d "U" bolts, nuts, spring bolts, spring bushings and hanger bushings from MYCO Trailers, Inc.
15 Remove existing and install new wheel bearing seals, wheel bearings, bearing races, disc brakes pads, and brake hoses. Install new hub (six each per trailer) diaphragm, air cap and super seal kit. Refer to NECP 026.
16 Remove existing and install new brake line hoses 17 Fill brake system (new DOT 5 fluid) and bleed air from lines. Test for zero leaks.
18 Remove all bunk boards, replacing damaged boards, padding, and sail cloth IAW OEM and re-install.
19 Prepare and preserve bunk brackets and trailer support wheel.
20 Polish outer surfaces of aluminum wheels, fenders and stowage box to a level greater than 60 GU at 60 degrees and reinstall using anti-seize on lug nuts and torque to OEM specs. Polish type is at contractor discretion.
21 Remove existing tilt and jacking cylinders, protect rams and zerk fitting, prepare and preserve with CeRam Kote
54® and install.
WORK PACKAGE 3 – HIGH LEVEL MAINTENANCE – TRAILER REPAIRS
Note: Report any defective parts found to the designated Government representative.
1 Block trailer and remove all wheels.
2 Support axles and disconnect "U" bolts holding axles to springs.
3 Disconnect flexible brake lines at caliper and frame ends and drain brake fluid from system. Blow lines clean with air.
4 Remove bleeder fittings from each caliper assembly. Contractor will provide new OEM leaf springs.
5 Remove six (6) leaf springs and four equalizers from trailer.
6 Remove three (3) axles from trailer.
7 Protect and remove brake components on axles prior to sandblasting.
8 Sandblast axles (3 ea), leaf springs (6 ea), equalizers (4 ea), and U-bolt back plates (6 ea) to white metal.
9 Paint axles (3 ea), equalizers (4 ea), and U-bolt back plates (6 ea) with gray CeRam Kote 54® in accordance with manufacturer’s specifications.
10 Prepare and preserve external surfaces of six new MYCO springs with ZRC Worldwide ZRC® cold galvanizing paint in accordance with the manufacturer’s specifications.
11 Provide new “U” bolts, nuts, spring bolts, spring bushings, hanger bushings from MYCO Trailers, Inc. Prepare and preserve new axle “U” bolts (24 ea) with CeRam Kote 54® in accordance with manufacturer’s specifications.
“U” bolts will be sandblasted and CeRam Kote 54® in accordance with manufacturers specifications taking care to protect the threaded area.
12 Power tool clean and preserve entire trailer frame with ZRC Worldwide ZRC® cold galvanizing paint in accordance with the manufacturers specifications.
13 Provide and install all new reflective tape on trailers.
14 Install axles and springs with new CeRam Kote’d "U" bolts, nuts, spring bolts, spring bushings and hanger bushings from MYCO Trailers, Inc.
15 Remove existing and install new wheel bearing seals, wheel bearings, bearing races, disc brakes pads, and brake hoses. Install new hub (six each per trailer) diaphragm, air cap and super seal kit. Refer to NECP 026.
16 Remove existing and install new brake line hoses 17 Remove existing and install all hydraulic system hoses with new hoses having SS (stainless steel) end fittings. Test for Zero leaks.
18 Remove existing and install new bleeder fittings.
19 Fill brake system (new DOT 5 fluid) and bleed air from lines. Test for zero leaks.
20 Polish outer surfaces of aluminum wheels, fenders and stowage box to a level greater than 60 GU at 60 degrees and reinstall using anti-seize on lug nuts and torque to OEM specs. Polish type is at contractor discretion.
21 Remove existing and install two new fenders. Install new “NO STEP” stickers on both fenders IAW OEM.
22 Replace all bunks and recover with the new sailcloth material/padding IAW OEM and install with new SST nuts.
All nuts will be double nutted and paint striped.
23 Remove existing and install new winch, cable (1/4” 30’ SST) and hook.
24 Remove existing and install new air flask.
25 Remove existing and install new air pressure relief valve. Refer to NECP 028.
26 Remove existing and install new glad hand pairs of flexible air lines and stowage clips.
27 Remove existing and install new forward wheel hydraulic cylinder.
28 Prepare and preserve with CeRam Kote 54® master cylinder, tilt and jacking cylinders (protect rams and zerk fitting), and hydraulic pump, spool valve, and relay valve.
29 Prepare and preserve bunk brackets and trailer support wheel.
30 Remove existing and install new jack arm pin (1 each) and tilt pins (2 each) to include chain and retaining pins
(OEM specs).
31 Provide and install new bow chock blocks and SST fasteners. (double nut and paint stripe) Refer to NECP 027.
32 Remove existing and install new tilt/jack three way valve (total of two valves per trailer). Test for zero leaks.
WORK PACKAGE 4– LOW LEVEL MAINTENANCE - BOAT PRESERVATION
1 Remove the following metal components from boat for preservation: (1) Water jet compartment hatches and frames (see note below); (2) 3rd and 4th row slick bolster handrails; (3) arch support brackets and mounts; (4) engine compartment aft hand rail and (5) fuel priming pumps.
NOTE: Water jet hatches and frames will only be removed if tread master repairs are also required for that area. If no tread master repairs are required, water jet hatches and frames will be prepared and preserved in-place.
2 Sandblast all removed components to near white metal.
3 Apply gray CeRam Kote 54® in accordance with manufacturers specifications to all components 4 Reinstall all components using new SST hardware and pins.
5 Prepare and preserve the exterior of both water jets with Interlux Trilux 33 Antifouling Bottom Paint in accordance with the manufacturer’s specifications.
WORK PACKAGE 5 HIGH LEVEL MAINTENANCE - BOAT PRESERVATION)
1 Remove the following metal components from boat for preservation:
(1) Hold #1 hatch and frame; (2) Hold #2 hatch and frame; (3) Console hatch and frame; (4) Console handrails (3ea); (5) battery tray; (6) console terminal board plate; (7) arch support brackets and mounts; (8) Water jet compartment hatches and frames (see note below); (9) engine compartment hatch hinges; (10) Comm station plates (3 each); (11) Swim platform strut; (12) swim platform backing plates (9 each); (13) 3rd and 4th row slick bolster handrails; (14) 2nd row bolster handrail; (15) arch handrail; (16) engine compartment aft hand rail; (17) fuel priming pumps; (18) Radar arch and ground plane; (19) port and stbd engine compartment air intake louvers;
(20) forward and aft gun mounts; (21) kingpost; (22) Comm Box foundation; (23) IR strobe/mast light and BFT/MARBAND antenna standoff platforms (2 ea).
NOTE: Water jet hatches and frames will only be removed if tread master repairs are also required for that area. If no tread master repairs are required, water jet hatches and frames will be prepared and preserved in-place.
2 Sandblast all removed components to near white metal.
3 Apply gray CeRam Kote 54® in accordance with manufacturers specifications to all components
Government Check point: After all arch components have been replaced, THE GOVERNMENT will provide test equipment and conduct an air tight test of the RADOM to check for zero leaks.
Reinstall all components using new SST hardware and pins.
5 Prepare and preserve the exterior of both water jets with Interlux Trilux 33 Antifouling Bottom Paint in
WORK PACKAGE 6 – LOW LEVEL PLANNED MAINTENANCE AVAIL (PMA) - BOAT
PRESERVATION HULL AND TOPSIDE
1 Repair damaged bolster upholstery (four square feet).
2 Repair hull scratches, gouges and nicks (five square feet).
3 Repair topside scratches, gouges and nicks (three square foot).
4 Repair port and stbd engine compartment knife edge (two feet of edge repairs total) 5 Apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to all repaired areas in accordance with the manufacturers specifications.
6 Accomplish an allover buff of the craft’s fiberglass components.
WORK PACKAGE 7 – MEDIUM LEVEL MAINTENANCE – BOAT REPAIRS HULL and TOPSIDE
1 Remove sponsons (2 each) and bra 2 Repair hull scratches, gouges and nicks (ten square feet).
3 Repair topside scratches, gouges and nicks (five square feet) 4 Prepare, sand and preserve throttle, bucket & gearbox bezels.
5 Apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to all repaired areas in accordance with manufacturer’s specifications.
6 Clean Hold #1, remove interferences, apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to compartment completely in accordance with manufacturers specifications and reinstall interferences.
7 Clean Hold #2, remove interferences, apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to compartment completely in accordance with manufacturers specifications and reinstall interferences.
8 Clean console interior deck, apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to compartment deck in accordance with manufacturer’s specifications.
9 Clean under-console bilge area.
10 Apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to bottom side of engine compartment hatches and around perimeter in trough, to include port and stbd air intake hoods, in accordance with manufacturer’s specifications.
11 Remove existing and provide and install all new engine compartment insulation.
12 Provide and install stainless steel ratchet straps and securing straps in Hold #2 (5 ea) and 72" console securing strap.
13 Provide and install new canvas radar arch covers (2 each).
14 Provide and install port and starboard console bags and new Velcro.
15 Provide and install Global Positioning System (GPS) and Radar monitor cover and track.
16 Apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to 3rd and 4th row slick bolsters in accordance with manufacturer’s specifications.
17 Accomplish cleaning and apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to engine and water jet compartments (all upper, lower and side horizontal and vertical surfaces) completely in accordance with manufacturer’s specifications.
18 Strip down, prepare and apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to bolster frames and the five (5) each bolster shells in accordance with manufacturers specifications
19 Provide and install new velcro and edging and upholstery for bolster shells 20 Remove existing and install new Treadmaster non-skid on forward deck, swim platform and engine covers.
21 Accomplish an allover buff of the craft’s fiberglass components.
22 Repair port and stbd engine compartment knife edge (two feet of edge repairs total) 23 Replace damaged engine compartment port and stbd Treadmaster sections.
WORK PACKAGE 8 – HIGH LEVEL MAINTENANCE - BOAT REPAIRS HULL and TOPSIDE accordance with the manufacturer’s specifications.
1 Remove sponsons (2 each) and bra.
2 Replace low bow (SST) sponson bra track.
3 Repair hull scratches, gouges and nicks caused by trailering and other miscellaneous damage (six square feet).
4 Repair topside scratches, gouges and nicks (four square feet).
5 Prepare, sand and preserve throttle, bucket & gearbox bezels.
6 Remove interferences to port and stbd blower motor mount bracket, sandblast to white metal, power coat grey, install brackets using new SST fasteners and install all interferences.
7 Apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to all repaired areas to match base in accordance with manufacturer’s specifications.
8 Clean Hold #1, remove interferences, apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to compartment completely in accordance with manufacturers’ specifications and reinstall interferences.
9 Clean Hold #2, remove interferences, apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to compartment completely in accordance with manufacturer’s specifications and reinstall interferences.
10 Clean console interior deck, gunnels, and bulkheads, apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to compartment deck in accordance with manufacturer’s specifications.
NOTE: Special care should be taken around electrical components and wiring.
11 Clean under-console bilge area (all surfaces).
12 Apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to forward vertical side of transom aft of 4th row slick bolster in accordance with manufacturers specifications.
13 Accomplish cleaning and apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to engine and waterjet compartments (all upper, lower and side horizontal and vertical surfaces) completely in accordance with manufacturer’s specifications.
14 Apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to bottom side of engine compartment hatches and around perimeter in trough, to include port and stbd air intake hoods, in accordance with manufacturer’s specifications.
15 Remove existing and provide and install all new engine compartment insulation.
16 Provide and install a new anchor chain bag in Hold #1.
17 Provide and install port and starboard Teflon anchor protective tracks in Hold #1.
18 Provide and install stainless steel ratchet straps and securing straps in Hold #2 (5 ea) and 72" console securing strap.
19 Provide and install hydraulic container bag in Hold #2.
20 Provide and install new radar arch covers (2 each).
21 Provide and install foot pump bag.
22 Provide and install port and starboard console bags and new Velcro.
23 Provide and install Global Positioning System (GPS) and Radar cover and track.
24 Provide and install console splash shield.
25 Provide and install Port and Starboard aft rope bags.
26 Provide and install engine compartment stowage bags.
27 Provide and install 5 each bolster seat pad latch cover straps.
28 Remove existing and reinstall all Treadmaster non-skid and Ensulite foam on entire deck and on the outboard section of bolster number four as per the original design.
29 Apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to 3rd and 4th row slick bolsters in accordance with manufacturer’s specifications.
30 Strip down, prepare and apply Armorcote Gel Coat, CCP FV 951-AA-438 Gray to bolster frames and the 5 each bolster shells in accordance with manufacturer’s specifications.
31 Provide and install all new upholstery for bolster shells with new Velcro and edging and upholstery for slick bolsters.
32 Remove existing and install new NAV and ENG gauge panels (2 each).
33 Accomplish an all over buff of the craft’s fiberglass components.
34 Reinstall sponsors (2 each) and bra.
35 Repair port and stbd engine compartment knife edge (two feet of edge repairs total) 36 Replace damaged engine compartment port and stbd Treadmaster sections.
WORK PACKAGE 9 – MEDIUM LEVEL MAINTENANCE – BOAT REPAIRS MECHANICAL
1 Provide and install a new acrylic scratch resistant windshield.
2 Provide and install new DIN rails for the console terminal boards. Remove corrosion, preserve and paint mounting platforms.
3 Inspect and replace all electrical wafers, spacers and end pieces that show any visual corrosion on wafer/spacer/end piece components or lead connections.
Government Check point: Government will inspect prior to repairs to damaged lead connections to determine course of action.
4 Clean the terminals on all console terminal boards, switches and miscellaneous components.
5 Remove the guide vane chamber disassembling steering nozzle and reversing bucket and replace new bushings, locking plates and associated fasteners from port and stbd jets.
Government Check point: Government will inspect scratches/gouges and make determination if port/stbd impeller housings are to be replaced.
6 If directed, remove existing and install new (GPM) port/stbd impeller housings.
7 Shim impellers as required to provide proper clearance in accordance with OEM.
Government Check point: Government to verify proper clearance. (Clearance specification is .004mm to .008mm).
8 Assemble jets in accordance with OEM.
9 Remove existing and install blower hoses with new orange hose and aluminum vents (OEM).
10 Power tool clean and preserve all hydraulic hose fittings in engine compartment and jet compartment.
11 Flush and replenish jet bearing housings with clean oil as specified by OEM.
WORK PACKAGE 10 – HIGH LEVEL MAINTENANCE – BOAT REPAIRS MECHANICAL
1 Provide and install a new acrylic scratch resistant windshield.
2 Provide and install new DIN rails for the console terminal boards. Remove corrosion, preserve and paint mounting platforms.
3 Inspect and replace all electrical wafers, spacers and end pieces that show any visual corrosion on wafer/spacer/end piece components or lead connections.
Government Check point: Government will inspect prior to repairs to damaged lead connections to determine course of action.
4 Clean the terminals on all console terminal boards, switches and miscellaneous components.
5 Remove the guide vane chamber disassembling steering nozzle and reversing bucket and replace new bushings, locking plates and associated fasteners from port and stbd jets.
Government Check point: Government will inspect scratches/gouges and make determination if port/stbd impeller housings are to be replaced.
6 If directed, remove existing and install new (GPM) port/stbd impeller housings.
7 Shim impellers as required to provide proper clearance in accordance with OEM.
Government Check point: Government to verify proper clearance. (Clearance specification is .004mm to .008mm).
8 Assemble jets in accordance with OEM.
9 Remove existing and install blower hoses with new orange hose and aluminum vents (OEM).
10 Power tool clean and preserve all hydraulic hose fittings in engine compartment and jet compartment.
11 Flush and replenish jet bearing housings with clean oil.
12 Replace control cables for port and stbd throttle, shift and bucket. (Total of six cables per craft) 13 Provide and install port and stbd trim tab indicator cables.
14 Provide and install new port and stbd backflush cables.
NOTE: Ensure backflush valves do not bind. Must operate freely and fully open and close as per OEM.
15 Provide and install forward & aft spotlight connector caps and chains (2 each).
16 Remove the battery parallel solenoid and recondition and reinstall.
WORK PACKAGE 11 – PORT AND STARBOARD F/O BLADDER FLANGE
1 Remove existing interferences on port and stbd fuel tank decking/soft patch.
2 Remove existing port and stbd soft patch lid outer ring fasteners.
3 After removing the soft patches, clean the top of the fuel cell area as much as possible.
CAUTION: If using any kind of solvent to clean this area, do not allow any solvent to leak in between the fuel cell and the bladder as it could possibly harm the fuel cell bladder and/or foam.
4 Tag, disconnect and plug hoses as necessary to prevent fuel system contamination.
5 Remove fuel hoses from plates and console bulkhead.
6 Remove fuel bladder plates by evenly loosening the ¼” bolts holding the plates to the fuel bladder.
NOTE: OEM recommends media-blasting fuel bladder plates to clean off all of contamination.
NOTE: When removing gaskets from the fuel plates ensure fuel tank does not get contaminated.
7 Install new, gaskets, FRP fuel plate tab, and fasteners.
8 Install existing port and stbd soft patches using new hardware 9 Install new Ensulite foam, treadmaster and interferences in console compartment.
10 Paint any disturbed surfaces as required.
11 Dispose of all hazardous material IAW required laws and regulations.
WORK PACKAGE 12 – PORT AND STARBOARD BLADDER REPLACEMENT
1 Remove existing interferences on port and stbd fuel tank decking/soft patch.
2 Remove existing port and stbd fuel tank tops.
3 Disconnect and plug hoses as necessary to prevent fuel system contamination.
4 Remove existing port and stbd fuel bladders and fuel tank block insulation.
NOTE: Contractor will document and report damaged areas found on bladders.
5 Remove all fuel/water and debris from port and stbd fuel tank compartments.
6 Inspect fuel tank bulkheads for cracks and submit one legible copy, in hard copy or electronic media, of a report listing results.
7 Install new port and stbd fuel tank block insulation, fuel bladders, and fuel foam using new hardware and wedges.
8 Install new port and stbd tank tops and all interferences.
9 Install existing port and stbd soft patch using new hardware 10 Install new Ensulite foam, treadmaster and interferences in console compartment.
11 Sand glassed areas and clean.
12 Paint any disturbed surfaces as required.
13 Dispose of all hazardous material IAW required laws and regulations.
WORK PACKAGE 0013 – BOLSTER AND FORWARD GUN MOUNT GUN BAGS
1 Manufacturer bolster and forward gun mount gun bags as per provided sample.
WORK PACKAGE 0014 – OVER AND ABOVE WORK
1. Emergent repair type work
2. Engineering Change Proposals – As Directed By Special Operations Command, Combat Craft Division
3. Non-Engineering Change Proposals (Manufacturer’s OEM Recommended Changes)
EXHIBIT 2 – PERFORMANCE REQUIREMENTS SUMMARY (PRS)
Performance Objective Performance Standard
Acceptable Quality Level
(AQL)
Method of Surveillance
Incentive
PRS #1. Completion of LOW LEVEL Work Packages and ECPs / NECPs
No Later Than (NLT) 60 calendar days after receipt of order (ARO)
Timely 95% of the time
COR
Observation and review of Contractor Monthly Status Report (MSR)
Positive/Negative reporting in the Contractor Performance Assessment Reporting System
(CPARS)
PRS #2. Completion of
MEDIUM / HIGH
LEVEL Work Packages and OAWRs
NLT 90 calendar days ARO
Timely 95% of the time
COR
Observation and review of Contractor MSR
Positive/Negative reporting in the CPARS
PRS #3. Servicing up to eight (8) 11M RIBs and their associated systems and equipment simultaneously
Adherence to established work completion deadlines
Timely 95% of the time
COR
Observation and review of Contractor MSR
Positive/Negative reporting in the CPARS
PRS #4. Error-free work Government Inspection reveals no unacceptable service requiring rework
Fully acceptable 95% of the time
100% Government Inspection
Positive/Negative reporting in the CPARS. The Government may deny the Contractor payment equal to the value of the unperformed or poorly performed services or require Contractor re-work at no additional cost.
PRS #5. Quality parts and materials
Only new, original equipment manufacturer
(OEM)
recommended parts and materials are used
100% of the time
100% Government Inspection and review of Contractor Inspection Summary Report
(ISR)
Positive/Negative reporting in the CPARS. The Government may deny the Contractor payment equal to the value of the substandard parts and materials or require Contractor re-work at no additional cost.
PRS #6. Customer Service
Contractor demonstrates reasonable and cooperative behavior, a commitment to customer satisfaction, and a concern for the interest of the Government customers
No more than 2 valid complaints per year for failure to demonstrate reasonable, cooperative, or professional behavior
COR
Observation, Customer feedback
Positive/Negative reporting in the CPARS
| 4. REQUIREMENTS |
| 4.1 The contractor perform repairs, maintenance and upgrades as specifically identified in each Task Order. Pre-defined Work Packages are identified below (further defined in Exhibit 1 to the PWS) and represent historical requirements experienced for... |
| 4.1.1 WORK PACKAGE 1 – LOW LEVEL MAINTENANCE – TRAILER REPAIRS |
| 4.1.2 WORK PACKAGE 2– MEDIUM LEVEL MAINTENANCE – TRAILER REPAIRS |
| 4.1.3 WORK PACKAGE 3 – HIGH LEVEL MAINTENANCE – TRAILER REPAIRS |
| 4.1.4 WORK PACKAGE 4 – LOW LEVEL MAINTENANCE - BOAT PRESERVATION |
| 4.1.5 WORK PACKAGE 5 - HIGH LEVEL MAINTENANCE - BOAT PRESERVATION |
| 4.1.6 WORK PACKAGE 6 –LOW LEVEL PLANNED MAINTENANCE AVAILIBILITY (PMA) – BOAT PRESERVATION HULL AND TOPSIDE |
| 4.1.7 WORK PACKAGE 7 – MEDIUM LEVEL MAINTENANCE – BOAT REPAIRS HULL AND TOPSIDE |
| 4.1.8 WORK PACKAGE 8 – HIGH LEVEL MAINTENANCE - BOAT REPAIRS HULL AND TOPSIDE |
| 4.1.9 WORK PACKAGE 9 – MEDIUM LEVEL MAINTENANCE – BOAT REPAIRS MECHANICAL |
| 4.1.10 WORK PACKAGE 10 – HIGH LEVEL MAINTENANCE – BOAT REPAIRS MECHANICAL |
| 4.1.11 PORT AND STARBOARD F/O BLADDER FLANGE |
| 4.1.12 PORT AND STARBOARD BLADDER REPLACEMENT |
| 4.1.13 BOLSTER AND FORWARD GUN MOUNT GUN BAGS |
| 4.1.14 OVER AND ABOVE WORK |
| 4.2 Work Packages may be further refined with new or revised Work Packages negotiated into the contract in the future, when necessitated by the Government’s observed recurring requirements for repair, maintenance and upgrade services. |
| 4.3 Performance of the Work Packages shall include inspection by the Contractor. The Contractor shall notify the Government Contracting Officer Representative (COR) within 24 hours when any requirements for work outside the scope of the Task Order or... |
| 4.4 Work Completion Deadlines, unless longer timeframes otherwise permitted by the Task Order. |
| 4.4.1 LOW LEVEL – No Later Than (NLT) 60 calendar days after receipt of order (ARO) |
| 4.4.2 MEDIUM / HIGH LEVEL – NLT 90 calendar days ARO |
| 4.4.3 ECPs / NECPs – NLT 60 calendar days ARO |
| 4.4.4 OAWRs – NLT 90 calendar days ARO |
| 4.5 Government Inspection. |
| 4.5.1 Upon work completion, the Contractor shall perform a thorough walk-through inspection with the Government. The Contractor shall demonstrate to the Government in the walk-through inspection that all work has been performed as specified in the Ta... |
| 4.5.2 The Contractor will provide walk-through inspection for the Government within two (2) calendar days of Task Order completion, unless a longer timeframe is otherwise permitted by the COR. |
| 4.5.3 At time of inspection, the Contractor shall provide an Inspection Summary Report (ISR) which provides at a minimum a list of all parts and materials installed or replaced by the Contractor. |
| 4.5.4 If the Contractor’s work is determined unacceptable, requires rework, or otherwise fails to pass the Government Inspection, the Contractor shall perform any and all necessary rework as directed by the Government at no additional expense to the G... |
| 4.6 Monthly Status Report. |
| 4.6.1 The Contractor shall submit a Monthly Status Report (MSR) summarizing work completed within the month and progress towards completion of each active Task Order. The Contractor shall provide the MSR to the Government COR NLT the fifth (5th) cale... |
| 4.7 Contractor Facilities. |
| 4.7.1 Contractor facilities shall be within thirty (30) miles of the Government site, Naval Amphibious Base (NAB) Coronado, California, unless otherwise specified in the Task Order. |
| 4.7.2 Contractor facilities shall be capable of accommodating up to eight (8) 11M RIBs and their associated systems and equipment simultaneously. |
| 4.7.3 Contractor shall be capable of accepting 11M RIBs delivered by either land or water and shall be capable of lifting/hoisting 11M RIBs from a trailer or from water. |
| 4.7.4 The Contractor shall grant the Government access to the Contractor facilities during normal working hours (0700 to 1630 Monday through Friday excluding federal holidays) and any other times when work is being performed on the 11M RIBs and their ... |
| 4.8 Participate in a Post-Award Conference. |
| 4.8.1 This meeting shall provide an introduction between the Contractor personnel and Government personnel who will be involved with the contract. The meeting shall provide the opportunity to discuss technical, management and security issues. The Pos... |
File details come from the government source that posted it.