About this file
This Request for Proposal (RFP) is issued by the Michigan Department of Technology, Management and Budget, Financial Services, and Procurement division for a deep cleaning contract at the General Services Building in Dimondale, Michigan. The State seeks an experienced contractor to perform detailed cleaning of the Print Shop facility, which measures approximately 100 feet by 85 feet by 21 feet in height. The scope of work includes brushing, vacuuming, and blowing off paper dust and residue from beams, walls, conduits, and printing equipment using curtained work areas, followed by thorough vacuuming repeated until complete. Additionally, the contractor must clean both the exterior (approximately 200 feet) and interior (minimum 100 feet) of the air handling unit servicing the shop, with optional pricing for additional interior cleaning beyond the 100-foot minimum. The project requires a final wipe-down of all horizontal surfaces from floor to 7 feet in height. A mandatory site visit is scheduled for July 21, 2021, at 10:00 a.m. at 7461 Crowner Drive, Dimondale, Michigan 48821, with attendance limited to two people per bidder; attendance is mandatory, and bids from non-attendees will be automatically disqualified. The proposal deadline is August 4, 2021, at 3:00 p.m. Eastern time, with an anticipated contract begin date to be determined. Bidders must submit questions by July 21, 2021, at 5:00 p.m. Eastern, with answers posted by July 22, 2021.
The pricing structure requires contractors to provide separate hourly rates for cleaning labor during two time periods: 4:00 p.m. to 12:00 a.m. Monday through Friday and 6:00 a.m. to 6:00 p.m. Saturday and Sunday, along with HVAC duct work cleaning costs per 10 feet of interior and exterior work, all materials costs, and equipment rental fees. Contract Activities must be completed within 21 business days of order receipt, and invoices must be submitted within 45 days of project completion or they will not be paid. Contractors must maintain commercial general liability insurance with minimum limits of $1,000,000 per occurrence and $2,000,000 general aggregate, an umbrella policy of $5,000,000, automobile liability coverage of $1,000,000 per accident, and workers' compensation and employers' liability insurance, with the State named as an additional insured. Contractors must provide their own equipment, with an electric scissor lift highly recommended for accessing high rafters and HVAC systems. The contract is evaluated on general requirements (50 points), project plan (30 points), and vendor questions worksheet (20 points), with proposals scoring 80 or more points eligible for pricing evaluation. Liquidated damages are assessed at $1,000 for late or improper completion plus $100 per day for each day the contractor fails to remedy the issue, and $1,000 per individual per day for unauthorized removal of key personnel.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michigan.gov/MiProcurement proposal instructions Department of Technology, Management and Budget – Financial Services – Procurement General Services Building – Print Shop Detailed Cleaning Request for Proposal No. 171 210000002316 Solicitation Manager Name: Rob Telesz Direct Phone:517-241-5539 Email: teleszr1@michigan.gov Main Phone: 1-855-MI-PURCH 1-855-647-8724 This is a Request for Proposal (RFP) for:
A contracted vendor to deep clean the Print Shop at the General Services Building in Dimondale, MI.
RFP Timeline
| Event |
| Time |
| Date |
| RFP issue date |
| N/A |
| Wednesday, July 14, 2021 |
| Mandatory Site Visit |
| 10:00 a.m. Eastern |
| Wednesday, July 21, 2021 |
| Deadline for bidders to submit questions about this RFP |
| 5:00 p.m. Eastern |
| Wednesday, July 21, 2021 |
| Anticipated date the State will post answers to bidder questions on www.michigan.gov/SIGMAVSS |
| 4:00 p.m. Eastern |
| Thursday, July 22, 2021 |
| Proposal deadline* |
| 3:00 p.m. Eastern |
| Wednesday, August 4, 2021 |
| Anticipated contract begin date |
| TBD |
| TBD |
*A bidder’s proposal received at 3:00:01 p.m. Eastern is late and subject to disqualification.
This RFP is subject to change. Check www.michigan.gov/SIGMAVSS for current information.
1. PROPOSAL PREPARATION. The State recommends reading all RFP materials prior to preparing a proposal, particularly these Proposal Instructions and the Vendor Questions Worksheet. Bidders must follow these Proposal Instructions and provide a complete response to the items indicated in the table below. References and links to websites or external sources may not be used in lieu of providing the information requested in the RFP within the proposal. Include the bidder’s company name in the header of all documents submitted with your proposal.
RFP Structure and Documentation
| Document |
| Description |
| Bidder Response Instructions |
| Cover Page |
| Provides RFP title and number, important dates, and contact information for Solicitation Manager |
| Informational |
| Proposal Instructions |
| Provides RFP instructions to bidders |
| Informational |
| Confidential Treatment Form |
| Required verification on whether bidder’s proposal contains confidential information |
| Bidder to complete and submit by proposal deadline |
| Vendor Questions Worksheet |
| Questions to bidders on background and experience |
| Bidder to complete and submit by proposal deadline |
| Schedule A – Statement of Work |
| Statement of work |
| Bidder to complete and submit by proposal deadline |
| Schedule B – Pricing |
| Pricing for goods and services sought by the State through this RFP |
| Bidder to complete and submit by proposal deadline |
| Contract Terms |
| Provides legal terms for a contract awarded through this RFP |
| Deemed accepted by bidder unless information required in the Evaluation Process section of this document is submitted by proposal deadline |
2. CONTACT INFORMATION FOR THE STATE. The sole point of contact for the State concerning this RFP is listed on the Cover Page. Contacting any other State personnel, agent, consultant, or representative about this RFP may result in bidder disqualification.
3. MANDATORY SITE VISIT. A mandatory site visit will be held on Wednesday, July 21, 2021 @ 10:00 at the General Services Building located 7461 Crowner Drive Dimondale, MI 48821. Scott Davis, the facility manager for the General Services Building will be in the lobby to meet vendors. You will need to sign the sign-in sheet. Please bring a valid ID and proper inspection/measuring tools with you. Please follow the current CDC guidelines as far as wearing a mask. You must attend the mandatory site visit. If a bid is received and the contractor did not attend the mandatory site visit, the bid will automatically be disqualified.
The purpose of the pre-proposal meeting is to discuss the RFP and the work to be performed and may include an inspection of the facility to receive the goods or services sought in this RFP. Statements made by the Solicitation Manager or designee at a pre-proposal meeting are not considered modifications to the RFP. If, however, the Solicitation Manager determines modifications to the RFP are warranted after the meeting, modifications will be posted in writing on www.michigan.gov/SIGMAVSS as explained in the Modifications section of this document.
Attendance at the pre-proposal meeting is limited to [2] people per bidder. If the pre-proposal meeting is mandatory, a bidder may be disqualified by being late. Subcontractor sign-in is permitted in lieu of the bidder as evidence of attendance. Accessibility requests for reasonable accommodations at the pre-proposal meeting should be made with the Solicitation Manager at least 10 business days before the date of the meeting. Accommodation requests received outside this time period cannot be guaranteed.
4. MODIFICATIONS. The State may modify this RFP at any time. Modifications will be posted on www.michigan.gov/SIGMAVSS. This is the only method by which the RFP may be modified.
5. QUESTIONS. Bidder questions about this RFP must be emailed to the Solicitation Manager no later than the time and date specified on the Cover Page. In the interest of transparency, only written questions are accepted. Answers to questions will be posted on www.michigan.gov/SIGMAVSS. Submit questions using the format below; a Microsoft Excel format or similar is suggested.
| Q # |
| Document and Section |
| Page # |
| Bidder Question |
6. DELIVERY OF PROPOSAL.
Electronic – The bidder must submit its proposal, all attachments, and any modifications or withdrawals electronically through www.michigan.gov/SIGMAVSS. The price proposal should be saved separately from all other proposal documents. The bidder should submit all documents in a modifiable (native) format (examples include but are not limited to Microsoft Word or Excel and Google Docs or Sheets). In addition to submitting documents in a modifiable format, the bidder may also submit copies of documents in PDF. Attachment file size is limited to 6 MB per document. Bidder’s failure to submit a proposal as required may result in disqualification. The proposal and attachments must be fully uploaded and submitted prior to the proposal deadline. Do not wait until the last minute to submit a proposal, as the SIGMA VSS system requires the creation of an account and entry of certain information, in addition to uploading and submitting the materials. The SIGMA VSS system will not allow a proposal to be submitted after the proposal deadline identified in the solicitation Closing On/Closing Date fields (Summary view/Detail view), even if a portion of the proposal has been uploaded.
Questions on how to submit information or how to navigate in the SIGMA VSS system can be answered by calling (517) 284-0540 or (888) 734-9749. The Solicitation Manager will not provide assistance related to the submittal of the proposal and all attachments on the day of the proposal deadline. Responsibility for a complete submission lies with the bidder.
7. MANDATORY MINIMUM REQUIREMENTS. To avoid disqualification, the bidder must provide documentation to support the following:
· Insurance: Contractor must be insured. Contractor must attach company Certificate of liability Insurance Form when submitting proposal. Form must include the following language: The State of Michigan, its departments, divisions, agencies, offices, commissions, officers, employees, and agents as ADDITIONAL INSUREDS
· Equipment: Contractor must be able to provide its own equipment for the completion of the entire project.
Only proposals meeting the mandatory minimum requirements will be considered for evaluation.
8. EVALUATION PROCESS. The State will evaluate each proposal based on the following factors:
| Technical Evaluation Criteria |
| Weight |
| 1. |
| General Requirements – Schedule A, Statement of Work, Section 1 |
| 50 |
| 2. |
| Project Plan – Schedule A, Statement of Work, Section 9 |
| 30 |
| 3. |
| Vendor Questions Worksheet |
| 20 |
| Total |
| 100 |
Proposals receiving 80 or more technical evaluation points will have pricing evaluated and considered for award.
The State may utilize all bidder information, without regard to a proposal’s technical score, to determine fair market value for goods or services sought. The State is not obligated to accept the lowest price proposal. If applicable, the State’s evaluation will include consideration of a bidder’s qualified disabled veterans/service-disabled veteran owned business(QDV/SDVOB) status under MCL 18.1261(8). Additional information on the SDVOB preference is available at: Michigan.gov/SDVOB.
The State strongly encourages strict adherence to the Contract Terms. The State reserves the right to deem a bid non-responsive for failure to accept the Contract Terms. Nevertheless, the bidder may submit proposed changes to the Contract Terms in track changes (i.e., visible edits) with an explanation of the bidder’s need for each proposed change. Failure to include track changes with an explanation of the bidder’s need for the proposed change constitutes the bidder’s acceptance of the Contract Terms. General statements, such as that the bidder reserves the right to negotiate the terms and conditions, may be considered non-responsive.
The State may but is not required to conduct an on-site visit to tour and inspect the bidder’s facilities; require an oral presentation of the bidder's proposal; conduct interviews, research, reference checks, and background checks; and request additional price concessions at any point during the evaluation process.
9. NOTICE OF DEFICIENCY. The State reserves the right to issue a Notice of Deficiency to bidders if the State determines after the proposal deadline that a portion of the RFP was deficient, unclear, or ambiguous. Failure to respond to a Notice of Deficiency timely may be cause for disqualification.
10. CLARIFICATION REQUEST. The State reserves the right to issue a Clarification Request to a bidder to clarify its proposal if the State determines the proposal is not clear. Failure to respond to a Clarification Request timely may be cause for disqualification.
11. RESERVATIONS. The State reserves the right to:
a. Disqualify a bidder for failure to follow these instructions.
b. Discontinue the RFP process at any time for any or no reason. The issuance of an RFP, your preparation and submission of a proposal, and the State’s subsequent receipt and evaluation of your proposal does not commit the State to award a contract to you or anyone, even if all the requirements in the RFP are met.
c. Consider late proposals if: (i) no other proposals are received; (ii) no complete proposals are received; (iii) the State received complete proposals, but the proposals did not meet mandatory minimum requirements or technical criteria; or (iv) the award process fails to result in an award.
d. Consider an otherwise disqualified proposal if no other proposals are received.
e. Disqualify a proposal based on: (i) information provided by the bidder in response to this RFP; (2) the bidder’s failure to complete registration on www.michigan.gov/SIGMAVSS ; or (3) if it is determined that a bidder purposely or willfully submitted false or misleading information in response to the RFP.
f. Consider prior performance with the State in making its award decision.
g. Consider overall economic impact to the State when evaluating proposal pricing and in the final award recommendation. This includes but is not limited to: considering principal place of performance, number of Michigan citizens employed or potentially employed, dollars paid to Michigan residents, Michigan capital investments, job creation, tax revenue implications, and economically disadvantaged businesses.
h. Consider total-cost-of-ownership factors (e.g., transition and training costs) when evaluating proposal pricing and in the final award recommendation.
i. Refuse to award a contract to any bidder that has failed to pay State taxes or has outstanding debt with the State.
j. Enter into negotiations with one or more bidders on price, terms, technical requirements, or other deliverables.
k. Award multiple, optional-use contracts, or award by Contract Activity.
l. Evaluate the proposal outside the scope identified in the Evaluation Process section of this document if the State receives only one proposal.
12. AWARD RECOMMENDATION. The contract will be awarded to the responsive and responsible bidder who offers the best value to the State, as determined by the State. Best value will be determined by the bidder meeting the minimum point threshold and offering the best combination of the factors stated in the Evaluation Process section of this document, and price, as demonstrated by the proposal. The State will post an Award Recommendation and Evaluation Synopsis on www.michigan.gov/SIGMAVSS or in the manner it was originally published.
13. DEBRIEF MEETING AND BID PROTEST. The State will post an Award Recommendation and Evaluation Synopsis which will provide instructions on how to request a debrief meeting.
If you wish to initiate a protest of the award, you must submit your written protest to teleszr1@michigan.gov no later than 3:00 p.m., 3 calendar days after posting the Award Recommendation and Evaluation Synopsis or by 3:00 p.m. the next business day if that date falls on a state holiday or weekend. The State reserves the right to adjust this timing and will publish any change.
Additional information about the protest process is available at www.michigan.gov/micontractconnect under the “Programs and Policies” link.
14. STATE ADMINISTRATIVE BOARD. Contracts equal to $250,000 or greater than require approval by the State Administrative Board. The State Administrative Board’s decision is final; however, its approval does not constitute a contract. The award process is not complete until the awarded contractor receives a contract fully executed by all parties.
15. GENERAL CONDITIONS. The State will not be liable for any costs, expenses, or damages incurred by a bidder participating in this solicitation. The bidder agrees that its proposal will be considered an offer to do business with the State in accordance with its proposal, including the Contract Terms, and that its proposal will be irrevocable and binding for a period of 180 calendar days from date of submission. If a contract is awarded to the bidder, the State may, at its option, incorporate any part of the bidder’s proposal into a contract. This RFP is not an offer to enter into a contract. This RFP may not provide a complete statement of the State’s environment or contain all matters upon which agreement must be reached. Other than verified trade secrets, proposals submitted via www.michigan.gov/SIGMAVSS are the State’s property.
16. CONFIDENTIAL TREATMENT FORM AND THE FREEDOM OF INFORMATION ACT. All portions of the bidder’s proposal and resulting contract are subject to disclosure as required under Michigan’s Freedom of Information Act (FOIA), MCL 15.231, et seq. However, some information may be exempt from disclosure. Under MCL 18.1261(13)(b), records containing “a trade secret as defined under section 2 of the uniform trade secrets act, 1998 PA 448, MCL 445.1902,” are exempt from disclosure under FOIA. In addition, “financial or proprietary information” submitted with a bidder’s proposal is exempt from disclosure under FOIA. A bidder’s failure to comply with this Section is grounds for rejecting a bidder’s proposal as non-responsive. As a part of its proposal, each bidder must follow the procedure below.
SUBMIT A COMPLETED “CONFIDENTIAL TREATMENT FORM” (CT FORM) WITH YOUR BID. Completion and submission of the CT Form is required regardless of whether the bidder seeks confidential treatment of information. Failure to submit a completed CT Form may be cause for disqualification from the solicitation process.
Complete and sign Section 1 of the CT Form if the bidder does NOT request confidential treatment of information contained in its proposal; or
i. Complete and sign Section 2 of the CT Form if the bidder requests confidential treatment of certain information. Bidder must also submit a “Public Copy” of the proposal with the trade secret, financial, and proprietary information redacted and clearly labeled as the “Public Copy.”
b. FOIA REQUESTS. If a FOIA request is made for a bidder’s proposal, the Public Copy may be distributed to the public along with the bidder’s CT Form. The CT Form is a public document and serves as an explanation for the redactions to the Public Copy. Do not put any trade secret, financial, or proprietary information in the CT Form. Do not redact the CT Form itself.
c. NO ADVICE. The State will not advise a bidder as to the nature or content of documents entitled to protection from disclosure under FOIA or other laws, as to the interpretation of such laws, or as to the definition of trade secret or financial or proprietary information. Nothing contained in this provision will modify or amend requirements and obligations imposed on the State by FOIA or other applicable law.
d. FAILURE TO REQUEST CONFIDENTIAL TREATMENT. Failure to request material be treated as confidential as specified herein relieves the State, its agencies, and personnel from any responsibility for maintaining material in confidence.
e. Bids containing a request to maintain an entire proposal as confidential may be rejected as non-responsive. Bidders may not request confidential treatment with respect to resumes, pricing, and marketing materials. The State reserves the right to determine whether material designated as exempt by a bidder falls under MCL 18.1261 or other applicable FOIA exemptions. If a FOIA request is made for materials that the bidder has identified as trade secret, financial, or proprietary information, the State has the final authority to determine whether the materials are exempt from disclosure under FOIA.
f. Bidder forever releases the State, its departments, subdivisions, officers, and employees from all claims, rights, actions, demands, damages, liabilities, expenses and fees, which arise out of or relate to the disclosure of all or a portion of bidder’s proposal submitted under this RFP. Bidder must defend, indemnify and hold the State, its departments, subdivisions, officers, and employees harmless, without limitation, from and against all actions, claims, losses, liabilities, damages, costs, attorney fees, and expenses (including those required to establish the right to indemnification), arising out of or relating to any FOIA request, including potential litigation and appeals, related to the portion of bidder’s proposal submitted under this RFP that bidder has identified as a trade secret, or financial or proprietary information. The State will notify bidder in writing if indemnification is sought. The State is entitled to: (i) regular updates on proceeding status; (ii) participate in the defense of the proceeding; (iii) employ its own counsel; and to (iv) retain control of the defense, or any portion thereof, if the State deems necessary. Bidder will not, without the State’s written consent (not to be unreasonably withheld), settle, compromise, or consent to the entry of any judgment in or otherwise seek to terminate any claim, action, or proceeding. If a State employee, official, or law is involved or challenged, the State may control the defense of that portion of the claim. Any litigation activity on behalf of the State, or any of its subdivisions under this Section, must be coordinated with the Department of Attorney General. An attorney designated to represent the State may not do so until approved by the Michigan Attorney General and appointed as a Special Assistant Attorney General.
confidential treatment form INSTRUCTIONS. Complete either Section 1 or Section 2 of this CT Form and sign where indicated. This CT Form must be signed by the individual who signed the bidder’s proposal. A completed CT Form must be submitted with your proposal, regardless of whether your proposal contains confidential information.
Failure to submit a completed CT Form with your bid is grounds for rejecting the proposal as non-responsive. See the Confidential Treatment Form and The Freedom of Information Act (FOIA) sections of the Proposal Instructions for additional information.
Section 1. CONFIDENTIAL TREATMENT IS NOT REQUESTED This section must be completed, signed, and submitted with the proposal if the bidder does not request confidential treatment of any material contained in the proposal.
By signing below, the bidder affirms that confidential treatment of material contained in their proposal is not requested.
RFP Number
RFP Title
Signature
Date
Printed Name, Title, Company
Section 2. CONFIDENTIAL TREATMENT IS REQUESTED This section must be completed, signed, and submitted with the proposal if bidder requests confidential treatment of any material contained in the proposal. Submission of a completed CT Form is required to request confidential treatment.
Provide the information in the table below. Bidder may add rows or additional pages using the same format shown in the table. Bidder must specifically identify the information to be protected as confidential and state the reasons why protection is necessary.
The CT Form will not be considered fully complete unless, for each confidentiality request, the bidder: (1) Identifies the Proposal Page #, Section #, and Paragraph #, (2) Identifies whether the material is a Trade Secret (TS), Proprietary Financial Information (FI), or Proprietary Information (PI), (3) Explains the specific legal grounds that support treatment of the material as TS, FI, or PI. Bidders must provide a complete justification as to how the material falls within the scope of an applicable FOIA Exemption or relevant case law. Bidders must not simply cite to an applicable exemption or case name, and (4) Provides the contact information for the person at Bidder’s organization authorized to respond to inquiries by the State concerning the material.
(1) Proposal Page #, Section #, Paragraph # (2) Material is Trade Secret (TS), Proprietary Financial Information (FI), Proprietary Information (PI) (3) Applicable FOIA Exemption with Written Justification (4) Bidder Contact Information
By signing below, the bidder affirms that confidential treatment of material contained in their proposal is requested and has attached to this form a redacted “Public Copy” of the bidder’s proposal.
RFP Number
RFP Title
Signature
Date
Printed Name, Title, Company vendor questions worksheet Provide a detailed response to each question. “You” and “company” refers to the bidder.
| Information Sought |
| Bidder Response |
1. Contact Information
Bidder’s sole contact person during the RFP process. Include name, title, address, email, and phone number.
Person authorized to receive and sign a resulting contract. Include name, title, address, email, phone number and vendor customer code in SIGMA VSS.
2. Company Background Information
Legal business name and address. Include business entity designation, e.g., sole proprietor, Inc., LLC, or LLP.
What state was the company formed in?
Phone number.
Website address.
Number of years in business and number of employees.
Legal business name and address of parent company, if any.
Has there been a recent change in organizational structure (e.g., management team) or control (e.g., merger or acquisition) of your company? If the answer is yes: (a) explain why the change occurred and (b) how this change has affected your company.
Discuss your company’s history. Has growth been organic, through mergers and acquisitions, or both?
Has bidder ever been debarred, suspended, or disqualified from bidding or contracting with any entity, including the State of Michigan? If yes, provide the date, the entity, and details about the situation.
Has your company been a party to litigation against the State of Michigan? If the answer is yes, then state the date of initial filing, case name and court number, and jurisdiction.
Within the last 5 years, has your company or any of its related business entities defaulted on a contract or had a contract terminated for cause? If yes, provide the date, contracting entity, type of contract, and details about the termination or default.
State your gross annual sales for each of the last 5 years.
If receiving a contract under this RFP will increase your gross revenue by more than 25% from last year’s sales, explain how the company will scale-up to manage this increase.
Describe partnerships and strategic relationships you think will bring significant value to the State.
State the physical address of the place of business that would have primary responsibility for this account if bidder is awarded a contract under this RFP.
3. Qualified Disabled Veteran/Service-Disabled Veteran-Owned Business Program
| Under MCL 18.1261, a “qualified disabled veteran” means a business entity that is 51% or more owned by 1 or more veterans with a service-connected disability. A “service-connected disability” means a disability incurred or aggravated in the line of duty in the active military, naval, or air service as described in 38 USC 101(16). Are you a qualified disabled veteran? |
| Enter YES or NO. |
To demonstrate qualification as a qualified disabled veteran, you must provide:
(a) Proof of service and conditions of discharge (DD214 or equivalent);
(b) Proof of service-connected disability (DD214 if the disability was documented at discharge or Veterans Administration Rating Decision Letter or equivalent if the disability was documented after discharge); and
(c) Legal documents setting forth the ownership of the business entity.
In lieu of the documentation identified above, you may provide proof of certification by the National Veterans Business Development Council.
Enter the names of documents submitted with your proposal to demonstrate status as a qualified disabled veteran.
4. Participation in RFP Development or Evaluation
| Did your company, an employee, agent, or representative of your company, or any affiliated entity participate in developing any component of this solicitation? For purposes of this question, business concerns, organizations, or individuals are affiliates of each other if, directly or indirectly: (1) either one controls or has power to control the other or (2) a third-party controls or has the power to control both. Indicia of control include, but are not limited to, interlocking management or ownership, identity of interests among family members, shared facilities or equipment, and common use of employees. |
| Enter YES or NO. |
If you enter “YES”, you are not eligible for contract award or to work as a subcontractor for the awarded vendor.
| If you are awarded a contract under this solicitation, in order to provide the goods or services required under a resulting contract, do you intend to partner or subcontract with a person or entity that assisted in the development of this solicitation? |
| Enter YES or NO. |
If you enter “YES,” you are not eligible for contract award. An awarded vendor may not partner or subcontract with anyone to provide goods and services required under a resulting contract if that subcontractor or partner assisted in the development of this solicitation.
| Will your company, or an employee, agent, or representative of your company, participate in the evaluation of the proposals received in response to this RFP? |
| Enter YES or NO. |
If you enter “YES”, you are not eligible for contract award or to work as a subcontractor for the awarded vendor.
5. State of Michigan Experience and Prior Experience
Does your company have experience working with the State of Michigan? If so, please provide a list (including the contract number) of the contracts you hold or have held with the State for the last 10 years.
Describe at least 3 relevant experiences from the last 5 years supporting your ability to successfully manage a contract of similar size and scope for the work described in this RFP.
Experience 1
Company name.
Contact name.
Contact role at time of project.
Contact phone.
Contact email.
City.
State.
Zip.
1. Project name and description of the scope of the project.
2. What role did your company play?
3. How is this project experience relevant to the subject of this RFP?
Dollar value.
Start and end date (mm/yy – mm/yy)
Status (completed, live, other – specify phase)
Results obtained.
Experience 2
Company name.
Contact role at time of project.
City.
1. Project name and description of the scope of the project.
Dollar value.
Start and end date (mm/yy – mm/yy)
Status (completed, live, other – specify phase)
Results obtained.
Experience 3
Company name.
Contact role at time of project.
City.
1. Project name and description of the scope of the project.
Dollar value.
Start and end date (mm/yy – mm/yy)
Status (completed, live, other – specify phase)
Results obtained.
6. Standard Contract Terms
Bidder must affirm agreement with the attached Contract Terms. If not in agreement, written exceptions in accordance with the Evaluation Process section of the Proposal Instructions must be provided with Bidder’s proposal.
7. Michigan Economic Impact
Number of employees currently employed at locations within the State of Michigan.
Number of additional employees to be employed at locations within the State of Michigan if awarded this Contract (if any)
Minimum wage paid to employees employed at locations within the State of Michigan.
Average wage paid to employees employed at locations within the State of Michigan.
Percentage of employees employed at locations within the State of Michigan that are covered by employer-provided health insurance.
8. Labor and Environmental Laws Compliance
Bidder must disclose any violations of state or federal labor and employment laws and regulations received within the past five years.
Bidder must disclose any violations of state or federal environmental laws and regulations received within the past five years.
9. Other
| Classification of Employees. I certify that the company has properly classified its employees in accordance with federal/state labor and employment laws. |
| Enter YES or NO. |
| Abusive Labor Practices. The Contractor certifies that it will not furnish any Deliverable that was produced fully or partially by forced labor, forced or indentured child labor, or indentured servitude. |
| Enter YES or NO. |
| Certification of Michigan Business- Public Act 431 of 1984, Sec. 268. I certify that the company has, pursuant to the provisions of Sec 268 of Public Act 431 of 1984, filed a Michigan Business Tax Corporate Income Tax Return. I certify that the company has, pursuant to the provisions of Sec 268 of Public Act 431 of 1984, filed a Michigan Income Tax return showing income generated in, or attributed to the State of Michigan. I certify that the company has, pursuant to the provisions of Sec 268 of Public Act 431 of 1984, withheld Michigan Income Tax from compensation paid to the company’s owners and remitted the tax to the Michigan Department of Treasury. |
| Enter YES or NO. |
| Iran Linked Business- Public Act 517 of 2012. I certify that the Company is not an Iran-Linked business as defined by Public Act 517 of 2012. |
| Enter YES or NO. |
| Clean Corporate Citizen. I certify that the Company is a Clean Corporate Citizen as defined by the Environmental Protection Act, 1994 PA 451. |
| Enter YES or NO. |
| Convict Labor. The Contractor certifies that if using convict labor, it is complying with all applicable state and federal laws and policies. |
| Enter YES or NO. |
| SOM Debt/Tax Payment. All SOM tax/debts. I certify that all applicable State of Michigan taxes are paid, and that no outstanding debt is owed to the State of Michigan. |
| Enter YES or NO. |
| Authorization to Verify Information Provided by Vendor. I authorize the State to verify that all information provided in this registration, in bidding and contracting documents, and any attachments or supplement documents and processes are accurate. |
| Enter YES or NO. |
Contractor must enter company name here.
Schedule A – statement of work contract activities Request for Proposal (RFP) No. 171 21000000002316 General Services Building – Print Shop Detailed Cleaning This schedule identifies the anticipated requirements of any Contract resulting from this RFP. The term “Contractor” in this document refers to a bidder responding to this RFP, as well as the Contractor who is awarded the contract. The term “bidder” is used to identify where specific responses to the RFP are required.
The Contractor must respond to each requirement or question and explain how it will fulfill each requirement. Attach any supplemental information and appropriately reference within your response.
IMPORTANT NOTE TO CONTRACTORS/BIDDERS: There are specific requirements for which acceptance must be simply acknowledged through a checkbox(es), and others that require further explanation. Click one checkbox and complete the entries as identified.
BACKGROUND
The print shop at the General Services Building contains several large and small printing presses, a paper cutter, and several other printing equipment. When this equipment runs, dust or residue from the paper enters the print shop and clings to the rafters, walls, and all of the equipment. The paper dust has accumulated to a thickness that is cause for concern from both a fire and health hazard.
SCOPE
We are looking for an experienced contractor to thoroughly clean the entire print shop from roof to floor which is approximately 100’ x 85’ x 21’ and to also clean the air handling unit which services the shop. The contractor will be brushing, vacuuming, and blowing off the beams, walls, conduits, etc. in a curtained workspace followed by a thorough vacuuming. This process will be completed several times until the entire print shop has been thoroughly cleaned. Once all cleaning services have been performed, a final wipe down of all horizontal surfaces from the floor to 7’ off the ground must be performed.
REQUIREMENTS
Insurance: Contractor must be insured. Contractor must attach company Certificate of liability Insurance Form when submitting proposal. Form must include the following language: The State of Michigan, its departments, divisions, agencies, offices, commissions, officers, employees, and agents as ADDITIONAL INSUREDS
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
Bidder must describe in complete details how they comply with the above requirement(s):
Equipment: Contractor must be able to provide its own equipment for the completion of the entire project. Due to the height of the rafter and HVAC system, an electric scissor lift is highly recommended for this project. The General Services Building has a loading dock that the electric scissor lift can be delivered on.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
Bidder must describe in complete details how they comply with the above requirement(s):
1. General Requirements
1.1. Service Specifications
A. The Contractor must brush, vacuum, and blow paper dust and residue off the beams, walls, floors, conduits and print equipment in the entire print shop until no paper dust or residue is remaining. Hours of service must be from 4:00 p.m. – 12:00 a.m. Monday – Friday and 6:00 a.m. – 6:00 p.m.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe in complete details how they will comply with the above requirement(s):
B. The Contractor must provide and hang curtains to prevent the dust and residue from going to other parts of the print shop when brushing, vacuuming, and blowing off the beams, walls, conduits, and print equipment. The equipment (Printer’s copiers, cutters, etc.) that are located with the area that have curtains hung, must be protected against dust, debris and falling equipment. If the equipment being used to clean is accidently falls onto any of the print shop equipment and the equipment is not properly covered to protect from the falling equipment being used to clean, the contractor must pay for the damages of the equipment.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe in complete details how they will comply with the above requirement(s):
C. The Contractor must thoroughly clean the exterior and interior of the air handling system that runs through the print shop. The exterior length of the air handling is approximately 200’. The interior portion of the unit to be cleaned will be determined once the unit is open. At least a minimum of 100’ of the interior will be cleaned. Requesting a quote amount of 10’ if additional interior cleaning services are needed. This unit is approximately 20’ off the ground.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe in complete details how they will comply with the above requirement(s):
D. The Contractor must remove all equipment being used and all paper dust and residue when finished. A final dusting sweeping of the entire floor must be performed after all equipment and paper dust and residue has been removed.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe in complete details how they will comply with the above requirement(s):
E. Once all of the dust, cleaning, equipment, etc has been removed, vendor must perform a final wipe down of all horizontal surfaces form floor to 7’ off of the ground in the project area.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe in complete details how they will comply with the above requirement(s):
1.2. Recall Requirements and Procedures
Describe any recall requirements and procedures.
Bidder must provide detailed information as requested in the above requirement(s). If none, enter N/A.
1.3. Quality Assurance Program
Explain your Quality Assurance Program(s).
Bidder must provide detailed information as requested in the above requirement(s):
1.4. Incentives
Explain any special incentives or services including, but not limited to, return policies, trade-in programs, quantity discounts, etc.
Bidder must provide detailed information as requested in the above requirement(s). If none, enter N/A.
1.5. Transition
A. Contract Execution:
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe how they comply with the above requirement(s):
B. Post-Contract Transition: Invoices must be sent within 45 days after the project has been completed. Any invoices received after 45 days will result in a non-payment of invoice.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe how they will comply with the above requirement(s):
2. Service Requirements
2.1. Timeframes
All Contract Activities must be delivered within 21 business days from receipt of order. The receipt of order date is pursuant to the Notices section of the Standard Contract Terms.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe in complete details how they comply with the above requirement(s):
2.2. Meetings
The Contractor must attend the following meetings:
The mandatory site visit.
The State may request other meetings as it deems appropriate.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
3. Staffing
3.1. Contractor Representative
The Contractor must appoint a contract representative specifically assigned to this project who will respond to the program managers inquiries regarding the Contract Activities, answer questions related to ordering and delivery, etc.
The Contractor must notify the Contract Administrator at least 7 calendar days before removing or assigning a new Contractor Representative.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
3.2. Non-Key Personnel
The Contractor must notify the Contract Administrator at least 10-calendar days before removing or assigning non-key personnel.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
3.3. Organizational Chart
The Bidder must provide an overall organizational chart that details staff members, by name and title, and subcontractors - either in this response box or identified here as an attachment to this RFP labelled as Attachment B.
3.4. Customer Service Toll-Free Number
The Contractor must specify its toll-free number for the State to contact the Contractor Representative who must be available for calls during the hours of 7 am to 5 pm EST Monday through Friday, at a minimum. Identify customer service availability for this proposal by hours and days of the week.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
The Bidder must specify its toll-free number for the State to make contact with the Contractor Representative.
Identify customer service availability for this proposal by hours and days of the week.
3.5. Disclosure of Subcontractors
If the Contractor intends to utilize subcontractors, the Contractor must disclose the following:
· The legal business name; address; telephone number; a description of subcontractor’s organization and the services it will provide; and information concerning subcontractor’s ability to provide the Contract Activities.
· The relationship of the subcontractor to the Contractor. Of the total bid, the price of the subcontractor’s work. Whether the Contractor has a previous working experience with the subcontractor. If yes, provide the details of that previous relationship.
· A complete description of the Contract Activities that will be performed or provided by the subcontractor.
Bidder must provide detailed information as requested in the requirement(s):
The legal business name, address, telephone number of the subcontractor(s):
A description of subcontractor’s organization and the services it will provide and information concerning subcontractor’s ability to provide the Contract Activities:
The relationship of the subcontractor to the Bidder:
Whether the Bidder has a previous working experience with the subcontractor.
If yes, provide the details of that previous relationship:
A complete description of the Contract Activities that will be performed or provided by the subcontractor:
Of the total bid, the price of the subcontractor’s work:
3.6. Security
The Contractor will be subject the following security procedures:
· SOM ID badges must be worn at all times.
· Personnel must wear clearly identified uniforms.
· Personnel must be escorted by a SOM employee when on-site.
The Contractor must explain any additional security measures in place to ensure the security of State facilities.
The Contractor’s staff may be required to make deliveries to or enter State facilities. The State may require the Contractor’s personnel to wear State issued identification badges.
The Contractor must: (a) explain how it intends to ensure the security of State facilities, (b) whether it uses uniforms and ID badges, etc., (c) identify the company that will perform background checks, and (d) the scope of the background checks.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe how they comply with the above requirement(s):
4. Pricing
4.1. Price Term
Pricing is firm for the entire length of the Contract.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
5. Ordering
5.1. Authorizing Document
The appropriate authorizing document for the Contract will be a Purchase Order.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
6. Delivery
6.1. Delivery Programs
The Contractor must explain in detail its delivery programs (e.g., standard delivery and quick-ship), including any limitations such as quantity.
The Contractor must explain the transportation method (e.g., UPS, FedEx, Contractor fleet, or other third-party carrier) it intends on utilizing in delivery of the Contract Activities.
Bidder must describe how they comply with the above requirement(s):
6.2. Packaging and Palletizing
Packaging must be optimized to permit the lowest freight rate. Shipments must be palletized whenever possible using manufacturer's standard 4-way shipping pallets.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe how they comply with the above requirement(s):
7. Acceptance
7.1. Acceptance, Inspection and Testing
The State will use the following criteria to determine acceptance of the Contract Activities:
· Entire print shop from floor to ceiling is clean of paper dust and residue.
· All paper dust and residue has been removed from the facility.
· All equipment and cleaning supplies have been removed from the facility.
· Entire HVAC system, both interior and exterior is clear of paper dust and residue.
· The final wipe down of all horizontal surfaces form floor to 7” off of the ground in the project area has been performed.
· Program Manager acceptance sign-off
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
7.2. Final Acceptance
Final acceptance approved by Program Manager after all criteria in 7.1 have been completed.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
8. Invoice and Payment
8.1. Invoice Requirements
All invoices submitted to the State must include: (a) date; (b) purchase order; (c) quantity; (d) description of the Contract Activities; (e) unit price; (f) shipping cost (if any); (g) vendor-generated invoice number; and (h) total price. Invoices will be paid once the program manager has approved that all the services listed on the invoice have been performed.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
8.2. Payment Methods
The State will make payment for Contract Activities by EFT.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must explain their process for accepting the PCard payment method. If an account needs to be created on your purchasing platform, please submit documentation that shows the steps for completing this process.
8.3. Procedure
Invoices must be submitted to DTMB-Accounts-Payable@michigan.gov after the services have been provided. Invoices will be paid once the services listed on the invoice have been provided and the program manager has approved the invoice.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
9. Project Plan The Contractor to propose a detailed project plan on how the service will carry out throughout the entire project. The plan must include timelines.
Upon Contract Award: A final project plan must be submitted for final approval within 7-calendar days of receiving the purchase order. The plan must also include: (a) the Contractor's organizational chart with names and title of personnel assigned to the project, which must align with the staffing stated in accepted proposals; and (b) the project breakdown showing sub-projects, tasks, and resources required.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must provide detailed information as required above – either in this response box or identified here as an attachment to this RFP.
10. Liquidated Damages Late or improper completion of the Contract Activities will cause loss and damage to the State and it would be impracticable and extremely difficult to fix the actual damage sustained by the State. Therefore, if there is late or improper completion of the Contract Activities the State is entitled to collect liquidated damages in the amount of $1,000 and an additional $100 per day for each day Contractor fails to remedy the late or improper completion of the Work.
Unauthorized Removal of Key Personnel will interfere with the timely and proper completion of the Contract, to the loss and damage of the State, and it would be impracticable and extremely difficult to fix the actual damage sustained by the State. Therefore, the State may assess liquidated damages against Contractor as specified below.
· The State is entitled to collect $1,000 per individual per day for the removal of any Key Personnel without prior approval of the State.
· The State is entitled to collect $1,000 per individual per day for an unapproved or untrained key personnel replacement.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
11. Additional Requirements
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .