GSA - Domestic Recirc - Project Manual 2024 12 16.pdf

PDF 1 MB Posted

Attached to
RFP 47PD5326R0051 ND0047ZZ Domestic Recirculation Repairs Fargo, ND
Solicitation number
47PD5326R0051
Issued by
Not on record

About this file

This is a specification document for a federal construction contract for the Fargo Federal Courthouse domestic recirculation system project (Project 2446) located at 655 1st Avenue N, Fargo, North Dakota. The contract is a single prime mechanical contractor bid-by-invitation only arrangement with GSA as the federal agency.

The specifications cover comprehensive plumbing and mechanical work including: domestic water piping systems (copper tube with soldered joints), pipe supports and hangers, flow meters, pressure gauges, piping insulation (glass fiber with specific R-values), identification and labeling systems, and selective demolition of existing mechanical equipment. Key material requirements include Type L hard-drawn copper for piping 1.5 inches and smaller and Type M for larger sizes, NSF 61 and NSF 372 certified components for potable water systems, glass fiber insulation meeting ASTM C547 standards, and all work must comply with ASME B31.9 building services piping code. The contractor must submit shop drawings within 30 days of contract award, maintain one-year warranties on all equipment and materials, provide operations and maintenance manuals in PDF and hard-copy formats, and perform system disinfection per AWWA C651 standards. Work includes ceiling and wall patching, painting, acoustic ceiling repair, gypsum board assembly repairs, and security plaster repair with specific fire-rating requirements. The specification references GSA Project Manager Jim Boisjolie and Property Manager Travis Mart for coordination, requires 48-hour notice for any work affecting building operations, and prohibits hot work, welding, and open flames except in specified attic spaces. All submittal procedures, administrative requirements, and general conditions are detailed across multiple specification sections with emphasis on quality assurance, testing protocols, and compliance with applicable federal, state, and local codes and standards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FARGO FEDERAL COURTHOUSE

BUILDING NUMBER ND0047ZZ

655 1ST AVE N

DOMESTIC RECIRCULATION SYSTEM

FARGO, NORTH DAKOTA

PROJECT NUMBER: 2446

BIDS BY INVITATION ONLY

BID DATE & TIME: Refer to GSA Information

BID PACKAGES COVERED THIS SPECIFICATION:

- SINGLE PRIME — MECHANICAL CONTRACTOR

SECTION 00 0105

CERTIFICATIONS PAGE

SPECIFICATIONS FOR THE: FARGO

FEDERAL COURTHOUSE

BUILDING NUMBER ND0047ZZ

655 1ST AVE N

DOMESTIC RECIRCULATION SYSTEM

FARGO, NORTH DAKOTA

PROJECT NO. 2446

ARCHITECT

I hereby certify that this specification was prepared by me or under my direct supervision, and that I am a duly Registered Architect under the laws of the state of North Dakota.

Date: December 16, 2024 Registration No. ND 1808

MECHANICAL CONSULTANT

I hereby certify that this specification was prepared by me or under my direct supervision, and that I am a duly Registered Engineer under the laws of the state of North Dakota.

Date: December 16, 2024 Registration No. ND 28007

END OF SECTION

Project No. 2446 01 0110–1 TABLE OF CONTENTS

SECTION 00 0110

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

00 0101 - Project Title Page 1

00 0105 - Certifications Page 1

00 0110 - Table of Contents 1

SPECIFICATIONS

DIVISION 01 -- GENERAL REQUIREMENTS

01 0400 - Project Coordination 1

01 1000 - Summary of Work 1

01 3000 - Administrative Requirements 1 - 3

01 5000 - Temporary Facilities and Controls 1 - 2

01 6000 - Product Requirements and Substitutions 1 - 2

01 7800 - Closeout Submittals 1 – 2

DIVISION 02 – EXISTING CONDITIONS

02 4120 – Cutting and Patching 1-4

DIVISION 09 – FINISHES

09 2300 – Security Plaster Repair 1-4

09 2900 – Gypsum Board Assemblies 1-4

09 5100 – Acoustic Ceilings 1-3

09 9900 – Paint and Coatings 1-7

DIVISION 22 -- PLUMBING

22 0060 – Plumbing & Piping Demolition 1-3

22 0100 – Plumbing General Requirements 1-6

22 0150 – Plumbing & Piping Material & Methods 1-3

22 0519 – Meters and Gauges for Plumbing Piping 1-2

22 0553 – Identification for Plumbing Piping and Equipment 1-3

22 0719 – Plumbing Piping Insulation 1-3

22 1005 – Plumbing Piping 1-5

Project No. 2446 01 0400–1 PROJECT COORDINATION

SECTION 01 0400

PROJECT COORDINATION

1.01 COORDINATION

A. Contractor shall coordinate on site work by providing a 48-hour notice. Disruption of services that is not prescheduled and approved will not be permitted.

B. Communication is of the utmost importance and the proper lines of communication often avoid unnecessary delays and misunderstandings.

GSA Project Manager – Jim Boisjolie, 701-561-2368, james.boisjolie@gsa.gov

Property Manager – Travis Mart, 701-566-6126, travis.mart@gsa.gov

C. Progress Meetings:

1. Required Attendance:

a. GSA staff, as needed.

b. Contractor's project manager and field superintendent/foreman. Subcontractors and suppliers as appropriate to the agenda.

c. All Contracts shall have any subcontractor(s), who are within a 2-week window of starting work, present at the progress meetings for the purpose of coordination of their work with all others working on the site.

D. Onsite Coordination Meetings:

1. The Mechanical Contractor's Superintendent shall conduct a brief daily coordination meeting with site superintendents/foremen of other contractors, and all subcontractor foremen that are working on site, for the purposes of onsite communication, coordination and dissemination of information.

E. Schedule Coordination:

1. The overall construction schedule is managed by the Mechanical Contractor. All subcontractors are responsible for coordinating their work through the Mechanical Contractor and cooperating with all trades to ensure the work progress of others is not impeded.

END OF SECTION

mailto:james.boisjolie@gsa.gov mailto:travis.mart@gsa.gov

Project No. 2446 01 1000–1 SUMMARY OF WORK

SECTION 01 1000

SUMMARY OF WORK

PART 1 GENERAL

1.01 CONTRACT DESCRIPTION

A. Refer to GSA Contract Documents.

1.02 DESCRIPTION OF DEMOLITION AND CONSTRUCTION

A. Scope of work is shown on drawings and described in these specifications.

B. Expansion and modification to the existing domestic recirculation system. Provide ceiling and wall patching, and painting, and any other work contained in the Contract Documents.

1.03 OWNER OCCUPANCY

A. Owner intends to continue to occupy buildings adjacent to this project during the entire construction period.

B. Cooperate with Owner to minimize conflict and to facilitate Owner / Tenant operations.

C. Schedule the Work to accommodate Owner / Tenant occupancy.

1.04 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas noted on Drawings, special considerations should be given to scheduling work within Holding Areas (where Security Plaster repair occurs) and closely coordinated with Owner.

B. The use of open flame, hot work, and welding is not allowed on the project.

C. Tobacco is not permitted on building grounds or in buildings and structures. Anyone caught using tobacco products on campus will be removed from the jobsite.

D. Consuming prepared foods is allowed on the construction site and within the building. If this privilege is abused, food will no longer be allowed within the building and must be consumed in a job trailer or outside the building.

E. Radios, tape players, compact disk players, digital device players etc. will not be allowed.

F. Owner reserves the right to halt all work on the construction site if the work is interfering with nearby facilities until that interference is corrected. Owner will provide the contractor with adequate information so this condition could be avoided; however, Owner activities may not be interrupted.

G. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

H. Existing building spaces may not be used for storage.

I. Utility Outages and Shutdown:

1. Limit disruption of utility services to hours the building is unoccupied.

2. Do not disrupt or shutdown life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Owner and authorities having jurisdiction.

3. Contractor shall provide a minimum of 48 hour notice of utility or service shutdowns.

4. Limit shutdown of utility services to 4 hours at a time, arranged at least 48 hours in advance with

Owner.

5. Prevent accidental disruption of utility services to other facilities.

Project No. 2446 01 3000–1 ADMINISTRATIVE REQUIREMENTS

SECTION 01 3000

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Progress meetings.

B. Submittals in general are to be electronic (PDF). If hard copies are required, then submit in accordance with this section.

C. Submittals for review, information, and project closeout.

D. Number of copies of submittals.

E. Submittal procedures.

1.02 PROJECT COORDINATION

A. Project Coordinator: Construction Manager.

B. Cooperate with the Project Coordinator in allocation of mobilization areas of site, for field offices and sheds, for site access, traffic, and parking facilities.

C. During construction, coordinate use of site and facilities through the Project Coordinator.

D. Comply with Project Coordinator's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.

E. Comply with instructions of the Project Coordinator for use of temporary utilities and construction facilities.

F. Coordinate field engineering and layout work under instructions of the Project Coordinator.

G. Make the following types of submittals to Architect through the Project Coordinator:

1. Requests for interpretation.

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Design data.

6. Manufacturer's instructions and field reports.

7. Applications for payment and change order requests.

8. Progress schedules.

9. Coordination drawings.

10. Correction Punch List and Final Correction Punch List for Substantial Completion.

11. Closeout submittals.

PART 2 PRODUCTS (NOT USED)

2.01 NOT USED

PART 3 EXECUTION

3.01 PROGRESS MEETINGS

A. Schedule and administer meetings throughout the progress of the Work at maximum monthly intervals.

B. Attendance Required: Job superintendent, major Subcontractors and suppliers, Owner, Architect, as appropriate to agenda topics for each meeting.

C. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

Project No. 2446 01 3000–2 ADMINISTRATIVE REQUIREMENTS

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.

3.02 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

B. Submit to Architect for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

C. Samples will be reviewed only for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 7800 - Closeout Submittals.

3.03 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

7. Other types indicated.

B. Submit for Architect's knowledge as contract administrator or for Owner. No action will be taken.

3.04 SUBMITTALS FOR PROJECT CLOSEOUT

A. Submit Correction Punch List for Substantial Completion.

B. Submit Final Correction Punch List for Substantial Completion.

C. When the following are specified in individual sections, submit them at project closeout:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Other types as indicated.

D. Submit for Owner's benefit during and after project completion.

3.05 NUMBER OF COPIES OF SUBMITTALS

A. Documents for Review:

1. Small Size Sheets, Not Larger Than 8-1/2 x 11 inches (215 x 280 mm): Submit the number of copies that Contractor requires, plus two copies that will be retained by Architect.

B. Documents for Information: Submit 5 copies.

Project No. 2446 01 3000–3 ADMINISTRATIVE REQUIREMENTS

C. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect.

1. After review, produce duplicates.

2. Retained samples will not be returned to Contractor unless specifically so stated.

3.06 SUBMITTAL PROCEDURES

A. Shop Drawing Procedures:

1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting the Contract Documents and coordinating related Work.

2. Generic, non-project specific information submitted as shop drawings do not meet the requirements for shop drawings.

B. Transmit each submittal with a copy of the approved submittal form.

C. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix.

D. Identify Project, Contractor, Subcontractor or Supplier, pertinent drawing and detail number, and specification section number, as appropriate on each copy.

E. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents.

F. Schedule submittals to expedite the Project, and coordinate submission of related items.

G. For each submittal for review, allow 15 days excluding delivery time to and from the Contractor.

H. Identify variations from Contract Documents and Product or system limitations that may be detrimental to successful performance of the completed Work.

I. Provide space for Contractor and Architect review stamps.

J. When revised for resubmission, identify all changes made since previous submission.

K. Distribute reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

L. Submittals not requested will not be recognized or processed.

Project No. 2446 01 5000–1 TEMPORARY FACILITIES

AND CONTROLS

SECTION 01 5000

TEMPORARY FACILITIES AND CONTROLS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Temporary utilities.

B. Temporary telecommunications services.

C. Temporary sanitary facilities.

D. Temporary Controls: Barriers, enclosures, and fencing.

E. Security requirements.

F. Vehicular access and parking.

G. Waste removal facilities and services.

H. Field offices.

1.02 FIELD OFFICE AND OTHER FACILITIES:

A. The Contractor shall provide the following facilities:

a. Sanitary facilities on site may be used. If the privilege is abused, then the contractor will need to provide an outdoor portable toilet.

b. Fire extinguishers as required during construction.

B. Construction telephone: Each contractor is responsible for his own phone service.

C. Temporary enclosures, etc.:

1. Temporary enclosures such as may be required for protection against the dust and debris from spreading through the building.

2. Each contractor shall be responsible for the removal of his ladders providing access to the work at the end of each working day. Entrances shall be barricaded or locked daily against entry by the Mechanical Contractor.

1.03 TEMPORARY LIGHT AND POWER:

A. Extension cords are to be furnished by each respective contractor or sub-contractor as they are required from the sub-panels.

B. Cost of the construction power usage from both the temporary and permanent services shall be paid for by the Owner.

C. All contractors will be held responsible for diligently supervising the use of electricity and lamps as abuse and waste of these items may be cause for a backcharge against the respective contractor as directed by the Architect.

D. The Architect shall be the sole judge of the amount of temporary wiring or lamps needed in case of dispute.

1.04 TEMPORARY WATER SUPPLY:

A. Hose for water distribution around the building shall be furnished by the respective contractors requiring same.

B. The cost, if any, for all water used by any or all contractors during the construction shall be paid for by the Owner.

C. If water supply at or available to the construction site is inadequate, requiring water to be hauled to the site, then costs for water and transportation of same are to be borne by the respective contractor needing water for their work.

1.05 SIGNAGE

A. Provide signage around construction site; limit access with doors or gates with locks. Do not alter or impede building egress paths.

1.06 VEHICULAR ACCESS AND PARKING

Project No. 2446 01 5000–2 TEMPORARY FACILITIES

AND CONTROLS

A. Comply with regulations relating to use of streets and sidewalks, access to emergency facilities, and access for emergency vehicles.

B. Coordinate access and haul routes with governing authorities and the Construction Manager. Provide and maintain access to fire hydrants, free of obstructions.

C. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking.

1.07 WASTE REMOVAL

A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.

B. Provide containers with lids. Remove trash from site periodically.

C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.

Project No. 2446 01 6000–1 PRODUCT REQUIREMENTS

AND SUBSTITUTIONS

SECTION 01 6000

PRODUCT REQUIREMENTS AND SUBSTITUTIONS

PART 1 GENERAL

1.01 SUBMITTALS

A. Product Data Submittals: Submit manufacturer's standard published data. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.

B. Shop Drawing Submittals: Prepared specifically for this Project; indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

C. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns.

PART 2 PRODUCTS

1.01 NEW PRODUCTS

A. Provide new products unless specifically required or permitted by the Contract Documents.

B. Where all other criteria are met, Contractor shall give preference to products that:

1. If used on interior, have lower emissions.

2. If wet-applied, have lower VOC content.

3. Have a published GreenScreen Chemical Hazard Analysis.

1.02 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Use any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Use a product of one of the manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:

Submit a request for substitution for any manufacturer not named.

PART 3 EXECUTION

3.01 SUBSTITUTION PROCEDURES

A. Instructions to Bidders specify time restrictions for submitting requests for substitutions during the bidding period. Comply with requirements specified in this section.

B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents.

C. A request for substitution constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product.

2. Will provide the same warranty for the substitution as for the specified product.

3. Will coordinate installation and make changes to other Work that may be required for the

Work to be complete with no additional cost to the Owner.

4. Waives claims for additional costs or time extension that may subsequently become apparent.

D. Substitution Submittal Procedure:

1. Submit three copies of request for substitution for consideration. Limit each request to one proposed substitution.

2. Submit shop drawings, product data, and certified test results attesting to the proposed product equivalence. Burden of proof is on proposer.

3. Foss Architecture & Interiors will notify Contractor in writing of decision to accept or reject request.

Project No. 2446 01 6000–2 PRODUCT REQUIREMENTS

AND SUBSTITUTIONS

3.02 TRANSPORTATION AND HANDLING

A. Package products for shipment in manner to prevent damage; for equipment, package to avoid loss of factory calibration.

B. If special precautions are required, attach instructions prominently and legibly on outside of packaging.

C. Coordinate schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials.

D. Transport and handle products in accordance with manufacturer's instructions.

E. Transport materials in covered trucks to prevent contamination of product and littering of surrounding areas.

F. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.

G. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage, and to minimize handling.

H. Arrange for the return of packing materials, such as wood pallets, where economically feasible.

3.03 STORAGE AND PROTECTION

A. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication.

B. Store and protect products in accordance with manufacturers' instructions.

C. Store with seals and labels intact and legible.

D. Store sensitive products in weather tight, climate controlled, enclosures in an environment favorable to product.

E. For exterior storage of fabricated products, place on sloped supports above ground.

F. Protect products from damage or deterioration due to construction operations, weather, precipitation, humidity, temperature, sunlight and ultraviolet light, dirt, dust, and other contaminants.

G. Comply with manufacturer's warranty conditions, if any.

H. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.

I. Prevent contact with material that may cause corrosion, discoloration, or staining.

J. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.

K. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.

Project No. 2446 01 7800–1 CLOSEOUT SUBMITTALS

SECTION 01 7800

CLOSEOUT SUBMITTALS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Project Record Documents.

B. Operation and Maintenance Data.

C. Warranties and bonds.

1.02 RELATED REQUIREMENTS

A. Section 01 3000 - Administrative Requirements: Submittals procedures, shop drawings, product data, and samples.

B. Individual Product Sections: Specific requirements for operation and maintenance data.

C. Individual Product Sections: Warranties required for specific products or work.

1.03 SUBMITTALS

A. Project Record Documents: Submit documents to Foss Architecture & Interiors for review.

B. Operation and Maintenance Data:

1. For equipment, or component parts of equipment put into service during construction and operated by the Owner, submit completed documents within ten days after acceptance.

2. Submit one copy of completed documents 15 days prior to final inspection. This copy will be reviewed and returned after final inspection, with Foss Architecture & Interiors comments.

Revise content of all document sets as required prior to final submission.

3. Submit two sets of revised final documents in final form within 10 days after final inspection.

C. Warranties and Bonds:

1. For equipment or component parts of equipment put into service during construction with the Owner's permission, submit documents within 10 days after acceptance.

2. Make other submittals within 10 days after Date of Substantial Completion, prior to final Application for Payment.

3. For items of Work for which acceptance is delayed beyond Date of Substantial Completion, submit within 10 days after acceptance, listing the date of acceptance as the beginning of the warranty period.

PART 3 EXECUTION

1.01 PROJECT RECORD DOCUMENTS

A. Maintain on site one set of the following record documents; record actual revisions to the Work:

1. Drawings.

2. Addenda.

3. Change Orders and other modifications to the Contract.

4. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by the Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress.

E. Record Drawings : Legibly mark each item to record actual construction including:

1. Field changes of dimension and detail.

2. Details not on original Contract drawings.

1.02 OPERATION AND MAINTENANCE DATA

A. Source Data: For each product or system, list names, addresses and telephone numbers of

Subcontractors and suppliers, including local source of supplies and replacement parts.

B. Product Data: Mark each sheet to clearly identify specific products and component parts, and data applicable to installation. Delete inapplicable information.

C. Drawings: Supplement product data to illustrate relations of component parts of equipment and

Project No. 2446 01 7800–2 CLOSEOUT SUBMITTALS systems, to show control and flow diagrams. Do not use Project Record Documents as maintenance drawings.

D. Typed Text: As required to supplement product data. Provide logical sequence of instructions for each procedure, incorporating manufacturer's instructions.

1.03 WARRANTIES AND BONDS

A. Obtain warranties and bonds, executed in duplicate by responsible Subcontractors, suppliers, and manufacturers, within 10 days after completion of the applicable item of work. Except for items put into use with the Owner's permission, leave date of beginning of time of warranty until Date of Substantial completion is determined.

B. Verify that documents are in proper form, contain full information, and are notarized.

C. Co-execute submittals when required.

D. Retain warranties and bonds until time specified for submittal.

E. Manual: Bind in commercial quality 8-1/2 by 11 inch (216 by 279 mm) three D side ring binders with durable plastic covers.

F. Cover: Identify each binder with typed or printed title WARRANTIES AND BONDS, with title of

Project; name, address and telephone number of Contractor and equipment supplier; and name of responsible company principal.

G. Table of Contents: Neatly typed, in the sequence of the Table of Contents of the Project Manual, with each item identified with the number and title of the specification section in which specified, and the name of product or work item.

H. Separate each warranty or bond with index tab sheets keyed to the Table of Contents listing.

Provide full information, using separate typed sheets as necessary. List Subcontractor, supplier, and manufacturer, with name, address, and telephone number of responsible principal.

Project No. 2446 02 4120–1 CUTTING AND PATCHING

SECTION 02 4120

CUTTING AND PATCHING

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Selective demolition of building elements for alteration purposes.

B. Appendix with the Asbestos Final Report survey. This project does not include asbestos abatement.

C. Lead procedures.

1.02 REFERENCE STANDARDS

A. 29 CFR 1926 - U.S. Occupational Safety and Health Standards; current edition.

B. NFPA 241 - Standard for Safeguarding Construction, Alteration, and Demolition Operations; 2013.

PART 2 PRODUCTS

2.01 MATERIALS

A. Demolished materials shall become the Contractor’s property to legally dispose of.

Materials noted or requested to be salvaged or turned over to the Owner shall be stored at or transferred to Owner’s location.

PART 3 EXECUTION

3.01 GENERAL PROCEDURES AND PROJECT CONDITIONS

A. Comply with other requirements specified in Section 01 7000.

B. Comply with applicable codes and regulations for demolition operations and safety ofadjacent structures and the public.

1. Obtain required permits.

2. Comply with applicable requirements of NFPA 241.

3. Use of explosives is not permitted.

4. The use of open flame, hot work, and welding is not allowed on the project in the attic space.

5. Take precautions to prevent catastrophic or uncontrolled collapse of structures to be removed;

do not allow worker or public access within range of potential collapse of unstable structures.

6. Provide, erect, and maintain temporary barriers and security devices.

7. Use physical barriers to prevent access to areas that could be hazardous to workers or the public.

8. Conduct operations to minimize effects on and interference with adjacent structures and occupants.

9. Do not close or obstruct roadways or sidewalks without permit.

10. Conduct operations to minimize obstruction of public and private entrances and exits; do not obstruct required exits at any time; protect persons using entrances and exits from removal operations.

11. Obtain written permission from owners of adjacent properties when demolition equipmentwill traverse, infringe upon or limit access to their property.

C. Do not begin removal until receipt of notification to proceed from the Owner.

D. Do not begin removal until built elements to be salvaged or relocated have been removed.

E. Protect existing structures and other elements that are not to be removed.

1. Provide bracing and shoring.

2. Prevent movement or settlement of adjacent structures.

3. Stop work immediately if adjacent structures appear to be in danger.

F. Minimize production of dust due to demolition operations; do not use water if that will result inice, flooding, sedimentation of public waterways or storm sewers, or other pollution.

G. If hazardous materials are discovered during removal operations, stop work and notify the Architect and the Owner; hazardous materials include regulatedasbestos containing materials, lead, PCB's, Project No. 2446 02 4120–2 CUTTING AND PATCHING and mercury.

H. Hazardous Materials: Comply with 29 CFR 1926 and state and local regulations.

I. Perform demolition in a manner that maximizes salvage and recycling of materials.

1. Dismantle existing construction and separate materials.

2. Set aside reusable, recyclable, and salvageable materials; store and deliver to collection point or point of reuse.

3.02 SELECTIVE DEMOLITION FOR ALTERATIONS

A. Drawings showing existing construction and utilities are based on casual field observationand existing record documents only.

1. Verify that construction and utility arrangements are as shown.

2. Report discrepancies to the Architect before disturbing existing installation.

3. Beginning of demolition work constitutes acceptance of existing conditions that would be apparent upon examination prior to starting demolition.

B. Maintain weatherproof exterior building enclosure except for interruptions required for replacement or modifications; take care to prevent water and humidity damage.

C. Remove existing work as indicated and as required to accomplish new work.

1. Remove rotted wood, corroded metals, and deteriorated masonry and concrete; replace with new construction specified.

2. Remove items indicated on drawings.

D. Services (Including but not limited to HVAC, Plumbing, Electrical, and

Telecommunications): Remove existing systems and equipment as indicated.

1. Maintain existing active systems that are to remain in operation; maintain access to equipment and operational components.

2. Where existing active systems serve occupied facilities but are to be replaced with new services, maintain existing systems in service until new systems are complete and ready for service.

3. See Section 01 1000 for other limitations on outages and required notifications.

4. Verify that abandoned services serve only abandoned facilities before removal.

5. Remove abandoned pipe, ducts, conduits, and equipment, including those above accessible ceilings; remove back to source of supply where possible, otherwise cap stub and tag with identification.

E. Protect existing work to remain.

1. Prevent movement of structure; provide shoring and bracing if necessary.

2. Perform cutting to accomplish removals neatly and as specified for cutting new work.

3. Repair adjacent construction and finishes damaged during removal work.

4. Patch as specified for patching new work.

3.03 ASBESTOS IN CONSTRUCTION

A. If materials are encountered during demolition that are considered to be or may contain asbestos the contractor shall stop working with that material and notify GSA and the architect immediately for further review and direction.

3.04 LEAD IN CONSTRUCTON / DEMOLITION

A. Contractor shall comply with OSHA Lead in Construction Standard (29 CFR 1926.62).

B. See appendix to this section which shows the areas of testing and the results.

C. If the contractor is going to disturb (e.g. grind, abrade, weld, cut, sand, etc.) any paints or coatings with any detectable level of lead, then submit to GSA for review a lead paint Method of Procedure (MOP) providing how they intend to comply with OSHA Lead in Construction Standard requirements.

D. It is the Contractor's responsibility as the employer of the employees doing the lead work to comply with the OSHA Lead in Construction Standard (29 CFR 1926.62). The contractor's OSHA defined Competent Person, as defined by 29 CFR 1926.62(b), will have to evaluate the lead concentrations present, the work to be performed, work practices to be used and make a determination of what they need to do to comply with the standard. The contractor should try to avoid or minimize paint disturbing activities like

Project No. 2446 02 4120–3 CUTTING AND PATCHING grinding, abrading, welding, torch burning, cutting, sanding.

E. All work involving the disturbance of lead containing materials need to meet the requirements of the OSHA Lead in Construction Standard at 29 CFR 1926.62 including proper employee training, exposure monitoring, engineering controls, work practices, work area demarcation and/or isolation, and prompt cleanup of lead bearing debris. In addition, any welding, cutting, or heating of lead painted metal surfaces or pipes would also need to meet applicable requirements of 29 CFR 1926.353(c)(2)(i) and 29 CFR 1926.354(c)(1) if performed in an enclosed space. GSA requires a written lead work Method of Procedure (MOP) describing all of this for review and acceptance prior to the work being performed.

F. The following is a list of some items that the contractor shall follow in the performance of their work:

1. Use workers that are properly trained per the OSHA Lead standard.

2. Use PPE as determined by the OSHA defined competent person.

3. Use lay down poly sheeting in work areas and demarcate work areas with signage.

4. Conduct initial exposure assessment and monitoring as required by the standard.

5. If paint needs to be scrapped off, use wet scraping, HEPA vac at point of scrape, etc.

6. Promptly clean up dust and debris.

7. Workers shall practice good hygiene practices in accordance with the OSHA standard.

8. Manage waste stream appropriately.

3.05 EXECUTION

A. GSA BUILD GREEN STANDARDS - SALVAGED, OR RE-USED BUILDING MATERIAL

1. Items and material located in the existing space, or to be removed from the existing space during the demolition phase, are eligible for reuse in the construction phase of the project. The reuse of items and materials is preferable to recycling them; however, items considered for reuse must be in refurbishable condition, and must meet quality standards as approved by GSA.

B. GSA BUILD GREEN STANDARDS - CONSTRUCTION WASTE MANAGEMENT

1. Recycling construction waste means providing all services necessary to furnish construction materials or wastes to organizations, which will employ these materials, or wastes in the production of new materials. Recycling includes required labor and equipment necessary to separate individual materials from the assemblies of which they form a part.

The Contractor shall submit to the Government their proposal to dispose of or recycle construction waste. Where the small quantity of material, the extraordinarily complex nature of the waste disposal method, or prohibitive expense for recycling would represent a genuine hardship, the Government may permit alternative means of disposal.

The Contractor will recycle the following items during both the demolition and construction phases of the project, subject to economic evaluation and feasibility:

• Ceiling grid and tile,

• Light fixtures, including proper disposal of any transformers, ballasts and fluorescent light bulbs,

• Duct work and HVAC equipment,

• Wiring and electrical equipment,

• Aluminum and/or steel doors and frames,

• Hardware,

• Drywall,

• Steel studs,

• Carpet, carpet backing, and carpet padding,

• Wood,

• Insulation, Project No. 2446 02 4120–4 CUTTING AND PATCHING

• Cardboard packaging,

• Pallets,

• Windows and glazing materials,

• All miscellaneous metals (as in steel support frames for filing equipment), and

• All other finish and construction materials.

If any waste materials encountered during the demolition or construction phase are found to contain lead, asbestos, PCBs (such as fluorescent lamp ballasts), or other harmful substances, they are to be handled and removed in accordance with State and Federal laws and requirements concerning hazardous waste.

In addition to providing “one-time” removal and recycling of large-scale demolition items such as carpeting or drywall, the Contractor will provide continuous facilities for the recycling of incidental construction waste during initial construction.

Construction materials recycling records shall be maintained and accessible to the Contracting Officer. Records shall include materials recycled or landfilled, quantity, date, and identification of hazardous wastes.

3.06 DEBRIS AND WASTE REMOVAL

A. Remove debris, junk, and trash from site.

B. Remove from site all materials not to be reused on site.

C. Leave site in clean condition, ready for subsequent work.

D. Clean up spillage and wind-blown debris from public and private lands.

SECTION 09 2300

SECURITY PLASTER REPAIR

Project No. 2446 09 2300–1 SECURITY PLASTER REPAIR

PART 1 GENERAL:

1.01 DESCRIPTION:

A. The extent of the plaster work is shown on the Drawings and in schedules.

B. The types of plastering required include:

1. Security plaster repair ( including framing and security lath)

1.02 QUALITY ASSURANCE:

A. Reference Standards:

ASTM C 150, Portland Cement.

ASTM C 144, Aggregate for Masonry Mortar.

ASTM C 207, Hydrated Lime for Masonry Purposes.

B. Fire Resistance Ratings: Comply with the requirements of the applicable designs as indicated (by UL or other recognized authority) for the ratings indicated, including the requirements to comply with governing regulations.

C. ANSI Standards: Comply with applicable requirements of ANSI A42.1 and A42.2, except where more detailed or more stringent requirements are indicated including those of the plaster manufacturer. Options therein are installer's option unless otherwise indicated.

1.3 SUBMITTALS:

Manufacturer's Data Plaster: For information only, submit two copies of the manufacturer's product specifications and installation instructions for each material, and include other data as may be required to show compliance with these specifications.

Distribute an additional copy of each installation instruction to the installer.

1.4 PRODUCT HANDLING:

Except for sand and water, deliver materials to the site in sealed containers or bags identified with manufacturer's name, brand, type and grade. Store materials in a dry, well-ventilated space, under cover and off the ground.

PART 2 - PRODUCTS:

2.1 ACCEPTABLE MANUFACTURERS: National Gypsum Co. (Gold Bond), United States

Gypsum Co., Georgia-Pacific and Standard Drywall Products.

2.2 PORTLAND CEMENT PLASTER MATERIALS:

General: Provide either neat or ready-mixed (where applicable) materials, at installer's option, complying with ANSI A42.2.

Base-Coat Cement: Portland cement, ASTM C 150, Type I.

Base-Coat Lime: Special finishing hydrated lime, Type S.

Base-Coat Aggregate: Sand.

Base-Coat Fiber: Fiberglass 1/2" shorts as manufactured by L.O.F. or equal.

Prepared Finish-Coat: Factory-prepared finish for Portland cement plaster, type recommended by the manufacturer for the color and texture indicated.

Project No. 2446 0092300–2 SECURITY PLASTER REPAIR

2.3 MIXES: (Security plaster):

First Coat: 1 part portland cement to 4 parts sand to 20 lbs. lime, plus 1-part Acryl 60 to 3 parts water.

Second Coat: 1 part portland cement to 5 parts sand to 20 lbs. lime, plus 1-part Acryl 60 to 3 parts water.

Finish Coat: Match existing believed to be: Acrylic plaster mix as per manufacturer's instructions. Products by Dryvit or STO are approved. Color and finish/texture picked by Architect.

2.4 BONDING MATERIALS:

Acid Etch Solution: Muriatic acid, mixed one part acid to 6-to-10 parts water.

Bonding Agent: Vinyl polymerization type, complying with MIL-B-19235 and ASTM C 631.

Bonding Additive: Acrylic-based emulsion for bonding exterior and interior Portland cement plaster base-coat to solid substrates (if any). Use as additive to strengthen base coat.

Products: Quick-Cure Ad-Liquid (Finestone Corp.); Marvoc (Larsen Products Corp.);

or Acryl 60 (Std. Dry Wall Prod.) Akkro - 7t by Tamms.

2.5 CEILING SUSPENSION/FURRING MATERIALS:

Runner Channels: 2" cold rolled channels. 16 ga. minimum Cross Furring: 3/4 x .03 lb. per ft. cold-rolled channel.

Hangers: Wire or rod type of size shown or, if not shown, sized to comply with ANSI A42.4.

Provide “uplift control mechanisms. Be sure to provide double channels wired over the hanger wires at security plaster, thus preventing plaster from being uplifted/raised up.

(Uplift control mechanism) At security plaster: Hanger wire shall be 8 ga. galvinized wire spaced along the runner channels no more than 24” centers. See Reference Specification.

2.6 LATH SYSTEMS:

Security Lath: Amico’s Security Lath, # ASL .50-13R 16 ga. steel, pregalvanized, with vinyl coated kraft paper backing, weighing .82 lbs/sf. Install onto framing with 16 ga. tie wires, spacings as recommended. Install to studs with Amico Secura clips, spaced per recommendations of AMICO.

Closure Perimeter Angle at Security Plaster Ceilings: Match existing, believed to be Amico’s 2 piece closure strips.

2.7 TRIM & ACCESSORIES

AmIco’s X66 or equivalent; 1” ground.

Expansion/ Control Joints: Double J Trim or equivalent. .

PART 3 - EXECUTION:

3.1 INSPECTION:

Verify that surfaces to be plastered are free of dust, loose particles, oil, and other foreign matter which would affect bond of plaster coats.

Examine construction, grounds, and accessories to insure that finished plaster surfaces will be true to line, level, and plumb, without requiring additional thickness of plaster.

3.2 PROTECTION:

Protect finished surfaces installed prior to plastering by covering.

Project No. 2446 0092300–3 SECURITY PLASTER REPAIR

Maintain protection in place until completion of Work.

3.4 PREPARATION FOR PLASTERING:

Clean plaster bases and substrates to be plastered, removing loose materials, coatings and other substances which might impair the work.

Cover chases and similar openings in the surfaces to receive plaster with metal lath strip reinforcing, extending not less than 6" beyond edges of opening.

Install diagonal strips of metal lath at corners of openings in plaster, where base is not metal lath or reinforcement and control or expansion joints do not extend to corners.

Install temporary grounds and screeds as required to control plaster thickness and comply with tolerances.

3.5 INSTALLATION OF METAL LATHING:

Security Lath: Wire tie to suspension system or metal per recommendations of manufacturer. Using 16 ga. wire ties, at spacings, manufacturer’s recommendations.

Install metal reinforcement for exterior portland cement plaster. Comply with ANSI A42.3;

and with manufacturer's instructions for stretching and nailing.

3.6 INSTALLATION OF PLASTERING ACCESSORIES:

Anchor each flange of accessories 8" o.c. to plaster base.

Miter or cope accessory corners, and install with tight joints accurately aligned.

Set accessories plumb, level and true to line with a tolerance of 1/8" in 10'-0".

Install metal corner beads at external corners.

Install casing beads at terminations of plaster work, except where plaster is indicated to pass through other work and be concealed by lapping work, and except where special screeds, bases or frames act as casing beads including interior metal door frames.

At "Control Joints" and "Expansion Joints" set pair of casing beads back to back, with metal strip behind to only one side of joint. At "Expansion Joints" space beads 1/4" apart for interior work, 3/8" apart for exterior work.

3.7 INSTALLATION OF SUSPENDED SECURITY PLASTER CEILING: (See Room Finish

Schedule for locations.)

Install a continuous perimeter security L shaped closure piece (2 piece closure by AMICO) anchored to concrete block walls.

Space 2" Main runner channels at 24" o.c., and space hangers along channels at 24" o.c.

Secure hangers to channels and to building structure only by looping and wire-tying wherever possible.

Secure with inserts in cast-in-place concrete.

Secure with eye bolts and expansion devices (of type which will not fail at elevated temperature) in precast concrete.

Project No. 2446 0092300–4 SECURITY PLASTER REPAIR

Level runner channels to a tolerance of 1/8" in 12'-0".

Furring Channels: Space ¾" furring members 12" (twelve inches) o.c. except as otherwise indicated.

3.8 INSTALLATION OF PLASTER:

General: Comply with ANSI A42.1 and A42.2; and with manufacturer's instructions which are more detailed or more stringent.

Mechanically mix plaster materials at the project site; do not hand mix except where small amounts are needed, using less than one bag of plaster material.

Sequence plaster installation properly with the installation and protection of other work, so that neither will be damaged by the installation of the other.

Plaster flush with built-in metal items or accessories which act as a plaster ground, unless otherwise shown. Where plaster is not terminated at metal by casing beads, cut base-coat free metal before plaster sets and groove finish coat at the junctures with metal.

Apply thickness and number of coats of plaster as indicated; comply with ANSI standards if not otherwise indicated.

Security Plaster: Install in 3 coats to approximately 1 " grounds with sand-float finish.

Cure Portland cement plaster by maintaining each coat in a moist condition for 2 days following application; keep enclosed and fog-spray (after initial set) as required to prevent dry-out. Cure gypsum plaster per manufacturer's recommendation.

3.09 CLEANING AND PROTECTION:

Remove temporary protection and enclosure of other work.

Promptly remove plaster from door frames, windows and other surfaces which are not to be plastered. Repair floors, walls and other surfaces which have been stained, marred or otherwise damaged during the plastering work. When plastering work is completed, remove unused materials, containers and equipment and clean floors of plaster debris.

Installer shall advise the Contractor of requirements for the protection of plaster from deterioration and damage during the remainder of the construction period.

SECTION 09 2900

GYPSUM BOARD ASSEMBLIES

Project No. 2446 09 2900-1 GYPSUM BOARD ASSEMBLIES

PART 1 - GENERAL:

1.01 RELATED WORK:

A Section 09 9000 - Painting and Coating.

B. Security Lath and Plaster(ceilings): See Section 09 2300.

1.02 SECTION INCLUDES:

A. Steel framing assemblies repair such as non-load bearing steel studs, which receive gypsum board products.

B. Gypsum board panel products fastened to steel framing

C. All other miscellaneous accessories and products specified herein.

D. Suspension systems or framing for ceilings and soffits.

1.03 SUBMITTALS /SAMPLES:

A. Submit recommended specifications and requirements of gypsum board manufacturer including control joint placement locations at walls and ceilings.

B. Submit samples of termination trim, mouldings, proposed to be used on this project.

Trim shall be provided in 12” lengths, indicating finish specified.

1. Verify with Architect the quantity of samples of each item.

1.04 REFERENCE STANDARDS:

A. Drywall Construction Handbook by United States Gypsum Co.

B. Applicable ASTM standards referenced in the specification.

C. Gypsum Association's Fire Design Manual and Recommended Specifications for

Application and

1. Finishing of Gypsum Board (GA-216);

2. GA-214, Recommended Specifications: Levels of Gypsum Board Finish.

3. GA 223 - Gypsum Panel Product Types, Uses, Sizes and Standards

4. GA 600 - Fire Resistance Design Manual D. ASTM Standards: (Latest Editions)

1. C645 - Non-Structural Steel Framing Members AISI S240- Non Structural Steel Framing, ( IBC 2018) C955 – Structural Steel (load bearing) Framing Members.

2. C754 - Installation of Steel Framing Members to Receive Screw-Attached

Gypsum Panel Products

3. C 840, Specification for Application and Finishing of Gypsum Board.

4. C 1047, Specification for Accessories for Gypsum Wallboard and Gypsum Veneer

Base.

5. C 1280, Specification for Application of Gypsum Sheathing Board.

6. C 1396, Specification for Gypsum Board.

7. D 5420, Test Method for Impact Resistance of Flat, Rigid Plastic Specimen by Means of a Striker Impacted by a Falling Weight (Gardner Impact)

8. E 695, Standard Method of Measuring Relative Resistance of Wall, Floor, and Roof

Construction to Impact Loading.

Project No. 2446 09 2900-2 GYPSUM BOARD ASSEMBLIES

9. ASTM A568 - Standard Specification for Steel, Sheet, Carbon, and High-Strength, Low-Alloy, Hot-Rolled and Cold-Rolled

10. ASTM A653 - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot Dip Process

15. ASTM C840 Application and Finishing of Gypsum Board

16. ASTM C1278 - Fiber-Reinforced Gypsum Panel

17. ASTM C1396 - Standard Specification for Gypsum Board.

18. ASTM C1629 - Standard Classification for Abuse-Resistant Non-decorated Interior

Gypsum Panel Products and Fiber-Reinforced Cement Panels.

19. ASTM D3273 - Standard Test Method for Resistance to Growth of Mold on the

Surface of Interior Coatings in an Environmental Chamber.

20. ASTM E413 - Classification for Rating Sound insulation

E. SSMA – Steel Stud Code Compliance Certification Program.

SFIA - Steel Stud Code Compliance Certification Program.

F. SFIA or SSMA - Manufacturer Qualifications: Member in good standing with Steel

Framing Industry Association or Steel Stud Manufacturers Association.

G. UL - Underwriters Laboratories Inc.

2.01 MANUFACTURERS:

A. Gypsum Board and related Products: Unless otherwise indicated, standard items by U.S.

Gypsum are specified, with equivalent products by National Gypsum/Gold Bond, Temple- Inland,…