SOW_-_Structural_and_water_Instrusion_Repair_Project.pdf
PDF 193 KB Posted
- Solicitation number
- GS-11-P-17-YT-C-0076
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GP_Corridor_Previous_Study_Drawings.docx | DOCX document | |
| Sign_In_Sheet.pdf | ||
| Structural_RFI.pdf | ||
| Structural_RFI.pdf | ||
| Sign_In_Sheet.pdf | ||
| Reps_&_Certs_GSA_GS-11-P-17-YT-C-0076.pdf | ||
| Solicitation_Package_GS-11-P-17-YT-C-0076_Repair_Water_Damage_Revised.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. General Services Administration Project Name Date
PROJECT DESCRIPTION
3/20/2017
I. PROJECT IDENTIFICATION
PROJECT TITLE Structural and Water Intrusion Repair Project
BUILDING Dept. of Energy: Forrestal, DC0093ZZ
LOCATION 1000 Independence Ave. Washington, DC 20585
PROJECT CONTROL NUMBER TBD
GSA WORK ITEM NO(S). TBD
II. BACKGROUND
Repair structural column, beams, slabs, and wall damages due to water intrusion within GK- 010, GK-016, GP-196, and GP-corridor locations. Continual leaks cause numerous occupant relocations and closure of a vital auditorium conference facility and damage to its audio/visual equipment. Mold issues require frequent air quality testing and ponding water causes slip hazards for employees. The project area cuts through the GP corridor and small auditorium, and the expansion joint jogs at grid line K from grid line 22 to grid line 23. The area is below the South Building and North Building Ground Floor areas below. The project area is located within a public corridor that is one of the main connections between two parts of the building – it will be disruptive as the work may take longer than other projects with the installation of the column. There are significant concerns about continued spalling of the delaminated concrete in this area. Given the sizes of the columns in this area, “sister” columns may be added to support column repair/replace.
III. OBJECTIVES
1. Contractor shall provide all labor, material, equipment and supervision to investigate extent of water damage/structural damage in the designated areas. Contractor will survey area of work, define extent of delamination and design corrosion protection system for area. Survey is to include testing for mold due to water intrusion.
Scope of Work Page 2 of 17
2. Contractor shall provide all labor, material, equipment and supervision to provide design to perform repairs/remediation of all known damages/issues in designated areas caused by water intrusion.
3. Contractor shall provide all labor, material, equipment and supervision to perform corrective actions prescribed in the final approved design.
IV. SCOPE OF SERVICES
The following includes, but is not limited to the work required to fulfill the objectives of this project as necessary for each technical discipline.
GENERAL REQUIREMENTS
1. Contractor shall provide all labor, material, equipment and supervision to investigate extent of water damage/structural damage in the designated areas. Contractor will survey area of work, define extent of delamination, define means & methods of structural concrete repairs and design corrosion protection system for area. Survey is to include testing for mold due to water intrusion.
2. Contractor shall provide all labor, material, equipment and supervision to provide design to perform structural repairs/remediation of all known damages/issues in designated areas caused by water intrusion.
3. Contractor shall provide all labor, material, equipment and supervision to perform corrective actions prescribed in the final approved design. Construction activities include but are not limited to:
a. Concrete columns, beams, slabs, and wall repairs within project area.
i. Structural Beam – Approx. 4’x4’, approx. 15 LF within GP Corridor
ii. Structural Wall – Approx. 70 LF within GP Corridor (affected area approx.
210 SF)
iii. Underside slab – Approx. 70 LF within GP Corridor (approx. 1050 SF)
iv. All sizes and quantities are approximations and require site survey verification.
b. Sheeting and shoring activities involving “sister” column and column repairs.
c. Corrosion Protection activities within project area. Current methodology includes the following but is not intended to limit or constrain the vendor’s project plan if an alternate CP plan is optimal.
i. Phase 1
Install titanium mesh
Install rectifier & connect to mesh, keeping accessible for maintenance
Scope of Work Page 3 of 17
Install reference cell accessible for maintenance
Install Wiring circuit and ground
Install temporary electrolyte, cellulose with lime
ii. Phase 2
Mobilization & demolition
Personnel and FF&E relocations
Remove temporary electrolyte
Remove titanium mesh, rectifier, ref cell & circuitry
Drill 1/2” diameter holes to install anodes for galvanic protection
Install galvanic protection
Install formwork and inject high strength concrete.
d. In order to address the structural issues/repairs required with this project it will require the removal of existing gunite/concrete ceiling panels (each approx.
15’x10’)
i. Removed panels will not be re-installed unless within the main hallway (GK
Hallway)
ii. Removal of existing panels will need to take into account existing lighting systems attached to the panels.
iii. For panels which have been removed and will not be reinstalled, waterproof lighting will need to be installed.
e. All existing utilities that cross the area under repair are to be temporarily located and reinstalled or protected from damage during construction.
i. GC responsible to facilitate all outages required to perform construction activities.
4. A dust proof screen wall will need to be constructed within the GP Corridor (containing the project zone) to prevent any material, dust or debris entering/exiting the work area.
The screen wall will be sturdy enough to prevent any debris breaking through the barrier – contractor will provide sample of screening material. This screen wall will be the first task of the project and will be the last item to be removed.
5. Detailed procedures will be provided for any work that impacts the building systems, including but not limited to power, mechanical, building controls, fire alarm, life safety, lighting, network
6. Cutovers to new systems will require detailed procedures to be submitted to GSA/DOE four weeks prior to the work being scheduled for approval.
7. All new systems will need to be commissioned / tested to be approved by GSA/DOE prior to final acceptance
Scope of Work Page 4 of 17
8. Delaminated concrete will be removed from the walls and the underside of slabs.
9. Design/Survey Activities:
a. A/E shall utilize government supplied CAD floor plans if available, otherwise A/E shall develop floor plans to document the area of work, and develop details to illustrate their findings.
b. Survey site to confirm existing conditions, observe water leaks, and observe conditions of structural column, slabs, and walls.
c. Document the findings and the construction relationship between the designated spaces in the GP corridor.
d. Analyze survey data and map findings to perform an analysis of the structure.
Provide graphic illustrations of findings and analysis.
e. Report shall include discussion of potential impact of recommended construction on building utilities and tenant occupancy.
f. Review existing drawings for the area of study. The effort will be to document the structure for this area above and below to determine the sizes of the elements and their configuration.
g. Develop findings based on research and analysis. Report shall include a discussion on appropriate phasing considerations.
h. The work of the design phase is to include but not limited to all surveys, research, presentations, calculations, and meetings necessary to complete the study.
i. Meet with key government stakeholder regarding findings, options, risks, and recommendations including a preliminary cost estimate at each submission.
j. Perform testing for mold during the survey phase to determine any hazardous conditions. Testing shall be in compliance with all applicable industry codes, regulations and PBS P-100.
10. Perform all construction activities prescribed in the final design submission.
11. To design this project to be within construction cost limitations. The design is to include but not limited to all surveys, research, presentations, contract drawings, specifications, calculations and cost estimates necessary to complete the project.
12. Construction Activities:
a. Maintenance, Repair and Inspection by Federal Government: Federal Government reserves the right to make any test, inspection, repair and/or performance
Scope of Work Page 5 of 17 oversight it deems necessary to ensure that all performance requirements are being maintained and met.
b. Pre-work site inspection to confirm existing conditions: Contractor shall contact the GSA project manager for site inspections and technical questions.
c. All affected utilities in the designated spaces that will remain need to be protected during the construction phase.
d. All disruptive/noise producing work will need to be performed after normal business hours (Weekdays 6pm-6am , Fri 6pm-Mon 6am)
e. All trash/demo materials should be removed from the building daily.
13. Temporary corrosion protection will be installed based on design.
a. Once temporary corrosion protection is complete, the permanent CP plugs will be installed and the concrete walls, columns, beams and slabs will be repaired.
b. Current CP Methodology includes: Installation of titanium mesh while keeping accessible for maintenance and temporary electrolyte & cellulose with lime.
Permanent CP plugs install anodes for galvanic protection.
14. Ten days after receipt of NTP, contractor will schedule a kick off meeting with the GSA/DOE to present an implementation and phasing plan for the project including a detailed project schedule identifying all key tasks, milestones and deliverables.
15. Detailed procedures for any work that impacts the building systems, including but not limited to power, mechanical, building controls, fire alarm, life safety, lighting, network format based on DOE/GSA Standards
a. All scheduled work must take into account NSOF standard Preventative Maintenance blackout periods
16. A safety plan will need to be submitted and approved prior to work starting on-site.
17. A U.S. Dept of Energy work control permit will need to be submitted and approved prior to work starting on-site.
18. The Government will occupy the building during the entire period of the construction.
The Contractor shall not interfere or disrupt the activities of the tenants in any way.
Coordination of the work must take into account the daily tenant activities.
19. HSPD-12 Badges will be issued for all supervisorial personnel. Temporary Badges will be issued for all employees on-site without HSPD-12 badges (access memo). All employees on site must be U.S. citizens.
Scope of Work Page 6 of 17
ARCHITECTURAL REQUIREMENTS
1. Develop a clear statement of requirements for the designated areas based on interviews with client representatives including building management, DOE representatives and GSA personnel.
2. Review existing information relating to the designated areas including but not limited to drawings and specifications, prior upgrade modifications, reports and studies.
3. Complete a detailed site survey of the designated areas including measurements of the existing space & existing drawings to ensure the final design fits within the allocated space.
4. Perform site visit to verify “as built” conditions – collect existing drawings.
5. Develop a project plan defining the tasks involved and the areas needed to determine the extent of the problems
6. Investigate the existing condition of the designated areas to determine the condition of the existing waterproofing issues and repair solutions
7. Present the design to key government stake holders for approval
8. Develop cost estimates for the approved project in accordance with GSA standards (P100)
9. Provide clear repair recommendations to allow the design to proceed and designer to produce complete construction documents.
10. Comply with all Architectural requirements prescribed by all applicable codes.
STRUCTURAL REQUIREMENTS
1. Perform site visit to verify “as built” conditions.
2. Provide structural design repairs for the affected columns, beams, slabs and walls.
3. Study the existing conditions revealed by the excavation to determine the condition of the concrete structure and the repairs required
4. Present the design to key government stake holders for approval
Scope of Work Page 7 of 17
5. Develop cost estimates for the approved project in accordance with GSA standards (P100)
6. Review existing conditions, determine where the construction joints are located that may indicate areas of water infiltration.
7. Review structural columns, slabs, walls and beams in the project area to determine repair recommendations.
8. Comply with all Structural requirements prescribed by all applicable codes.
CIVIL REQUIREMENTS
1. Develop plans required for Management of Traffic and obtaining if required Private Space Permits
TESTING REQUIREMENTS
1. To determine the condition of the concrete elements, test samples need to be sent to a certified testing laboratory to determine the strength and chemical composition of concrete core samples.
2. Submit a report based on the results of the testing that quantifies the results of the tests and provides information on the levels of deterioration in the concrete with projections of its life expectancy.
3. Provide recommendations on how to mitigate the continued deterioration of the concrete along with square foot cost estimates for the various repair options.
ELECTRICAL REQUIREMENTS
1. Perform site visit and accurately document all existing electrical systems and fire-life-safety alarm systems that cross the work area. Provide sufficient information to allow systems to either be temporarily relocated or protected. Provide details of all disconnect locations for each system or circuit so that they can be safely relocated.
2. Provide design to allow contractor to temporarily relocate utilities to allow the removal and installation of panels.
3. Perform site visit to verify “as built” conditions.
4. Confirm that no electrical systems are impacted by the work
5. All work shall comply with NEC, all applicable Codes, PBS P100, and all applicable Federal Regulations.
Scope of Work Page 8 of 17
MECHANICAL REQUIREMENTS
1. Perform site visit and accurately document all existing mechanical, plumbing, sprinkler systems that cross the work area and provide adequate details to allow for the systems to be relocated or protected. For any piping, document the locations of any shut off valves.
2. Provide design to allow contractor to temporarily relocated utilities to allow for the removal and installation of panels.
3. Perform site visit to verify “as built” conditions.
4. Confirm that no mechanical systems are impacted by the work
5. Comply with all Mechanical Requirements prescribed by all applicable codes.
SECURITY REQUIREMENTS
1. Provide security plan for the construction area – all staff entering the building must be US Citizens, staff working outside of the building must have valid permits to work in the USA.
PLUMBING REQUIREMENTS
1. If recommended, develop a drainage solution to allow for the water to be controlled as to where it will enter the building and to reduce the incidence of water infiltration in the designated areas.
2. All work shall comply with NEC, all applicable Codes, PBS P100, and all applicable Federal Regulations.
ENVIRONMENTAL REQUIREMENTS
1. It is not anticipated that Asbestos-Containing Materials (ACM) or Lead-Based Paint (LBP) will be encountered during work activities. However, work area should be inspected prior to starting work and if material suspect to be ACM’s or LBP's are encountered, all work activities in that area shall cease immediately and bulk asbestos and/or lead paint chip sampling shall be conducted. If the materials sampled are determined necessary for removal, under Section 3.02 of Specifications Section 01546, Scope of Work Page 9 of 17 then the contractor shall adhere to the specification and the requirements of specification Section 02085 for asbestos removal and 02090 for removal and disposal of lead-based paint.
V. CRITERIA GOVERNING PROJECT
Services to be performed by the GC under this Scope of Work shall conform to the latest issues of the following criteria as of the date of Notice to Proceed.
1. GOVERNMENT REQUIREMENTS
a) PBS-P100 Facilities Standards for the Public Buildings Service,
b) PBS-P120 Project Estimating Requirements,
c) Cost Estimating Policy Handbook
d) Instructions for Developing Construction Cost Estimates,
e) Energy Policy Act of 1992 (PL 102-486).
f) Energy Policy Act of 2005 (Public Law 109 - 58).
g) GSA — Building Commissioning Guide
h) GSA — PBS National Environmental Policy Act (NEPA) Desk Guide
i) Executive Order 13123 Sustainable Design and Development for Federal
Agencies.
j) Executive Order 13101 Greening The Government Through Waste Prevention, Recycling, And Federal Acquisition.
k) Title 10 - Energy. CFR Part 436 - Federal Energy Management and Planning
Programs.
l) Title 10 - Energy. CFR Parts 433, 434, and 435 - Federal Energy Management and
Planning Programs.
m) National Environmental Policy Act of 1969 (NEPA)
n) Buy American Act
o) AIA Masterspec Specifications with GSA Division One
Supplements and the following GSA Regional Specifications:
Supplementary Instruction to Bidders - Section 00120 Supplementary Conditions - Section 00800 For bidder and all specialists - Section 00900 Safety and Health - Section 01546 Asbestos Abatement Procedure- Section 02085 Small PCB Items and Mercury Lamps- Section 02089
Scope of Work Page 10 of 17
Control of Lead Based Paint- Section 02090
*NOTE: If this project requires specifications not provided by the AIA, GSA supplements or the specifications listed above, prepare specifications for those sections following the Construction Specification Institute (CSI) format and GSA's "General Guide for Editing Specifications."
a) Leadership in Energy and Environmental Design (LEED) of the U.S. Green Building Council.
b) Environmental Management Technical Guides, GSA Safety and Environmental Branch.
c) Metric Guide for Federal Construction.
d) Preferred Metric Units for General use by the Federal Government, Federal
Standard 376B,
e) Federal Property Management Regulations (FPMR), Temporary
Regulation D-76.
f) The National Capital Urban Design and Security Plan. www.ncpc.gov.
g) Energy Policy Act of 1992 (PL 102-486).
2. CODES/STANDARDS/REGULATIONS
a) The Public Buildings Amendments of 1988, Public Law 100-678, section 21, requires that for new construction and renovation projects, GSA shall, to the maximum extent feasible, be in compliance with one of the nationally recognized model building codes and with other applicable nationally recognized codes. The current edition of each applicable code, in effect at the time the design contract is awarded, shall be used throughout the project's design and construction. The GSA National Capital Region (NCR) uses the following code on all projects:
(i) International Building Code (IBC) maintained by the International Code Council (ICC).
b) For all projects, the egress requirements of the National Fire Protection Association (NFPA 101), Life Safety Code shall apply in lieu of other code references.
c) For all projects, the electrical requirements of the National Fire Protection Association (NFPA), National Electric Code, have been adopted by GSA in lieu to the technical electrical requirements of the ICC Electrical Code.
Scope of Work Page 11 of 17
d) International Plumbing Code (IPC).
e) Occupational Safety and Health Regulations for Construction; 29 CFR, Parts
1926 and 1910.
f) Environmental Protection Agency Regulations.
g) Uniform Federal Accessibility Standards (UFAS) is mandatory on all GSA projects. Current GSA policy also encourages compliance with the requirements of the American with Disabilities Act Accessibility
h) Guidelines (ADAAG) where those requirements are stricter that UFAS. The A/E is responsible for checking whether there are local accessibility requirements. If they exist, the most stringent will prevail between local and UFAS/ADA.
i) Applicable local codes and regulations.
j) National Fire Protection Association (NFPA) Standards.
k) Resource Conservation and Recovery Act (RCRA) and 40 Code of Federal
Regulations CFR) 260 – 266
l) NIOSH, Technical Information #76-130,
m) Lead Exposure and Design
n) NEC ( National Electrical Code).
3. INDUSTRY STANDARDS
a) Occupational Safety and Health Standards.
b) American National Standards Institute (ANSI) Publications.
c) The Institute of Electrical and Electronics Engineers (IEEE), Inc., Publications.
d) National Electrical Manufacturers Association (NEMA) Publications.
e) Federal Information Processing Standard 175: Federal Building Standard for
Telecommunication Pathways and Spaces (see also Electronic Industries Association (EIA/TIA Standard 568-A and related bulletins).
f) Federal Information Processing Standard 174-1:Federal Building Telecommunications Wiring Standard (see also Electronic Industries Association EIA/TIA Standard 569 and related bulletins).
g) Mechanical Standards reference in GSA PBS - P100.
h) Electronic Industries Association (EIA) Publications.
i) ASHRAE Handbooks and ASHRAE Standard 62-89,
j) ASHRAE Standard 90.1-
Scope of Work Page 12 of 17
*NOTE: When conflicts in the above list occur, the GC shall notify the Government and the GSA Project Manager will acquire the necessary interpretation and guidance for the
GC.
4. CAD Standards - The National CAD/CIFM Standards should be followed for all CAD drawing formatting. The National Capital Region (NCR) CAD standards are available through the Regional CAD Coordinator and are considered supplements to the national standards. (PBS-P100)
5. Submit engineering calculations for all disciplines at each submission. Prepare engineering calculations prepared and/ or approved by the registered engineer of appropriate discipline. The cover sheet of calculations should be stamped by the engineer.
6. The Scope of Services indicated is not intended to limit the innovative analysis and research of the Contractor. Variation from the Scope of Services will be considered by GSA, if the proposed change is within the survey budget limitations, meets the objectives for the project, and results is an improved survey report. All proposed changes in the Scope of Work must be approved by GSA.
VI. SPECIAL CONSIDERATIONS
COORDINATION
General Services Administration Haag, Stephen M. Project Manager
7TH & D STREETS SW 7720
WASHINGTON DC 20407-0001
Phone:(202) 586-6688 Cell:(202) 236-7396 Email: Stephen.Haag@gsa.gov
Department Of Energy Clint Cleveland Building Manager 1000 Independence Ave.
Washington, DC 20585 Phone: 202-586-6944
Scope of Work Page 13 of 17
Email: Clint.Cleveland@hq.doe.gov
MEETINGS
1. Attend a Preconstruction Meeting to provide an overview of the project to GSA tenant representatives and address questions concerning the project. Provide the completed construction schedule with all activities including start and end dates for distribution and discussion. If changes are required, promptly modify and redistribute.
2. Attend all scheduled progress meetings as scheduled with GSA.
3. Provide meeting minutes to the GSA Project Manager within Three (3) working days of all project meetings.
4. Prior to construction, a representative of the A/E, who is familiar with the project, shall attend the Site Visit(s), indicated in section 00120 of the specifications and lead the group through the project area, giving a brief description of the work, and providing any clarifications necessary to the construction documents. The A/E’s representative will also attend the Pre-Construction Meeting to answer questions and participate in coordination for the construction phase.
5. Provide Post Construction Contract Services (PCCS). The A/E shall review all shop drawings and submittals for conformance with the design and codes, including a maximum of six (6) site visits. The A/E shall recommend whether the shop drawings should be approved or resubmitted. In addition, the A/E shall send a copy of all shop drawings with approval letters to the project manager. The team shall inspect and review the construction and complete the final inspection.
6. When directed by the Contracting Officer’s Representative, the A/E will, at no cost to the government promptly prepare clarification drawings or specifications to enable the construction contractor to understand the requirements of the construction contract drawings. Change order documents, including estimates, required due to A/E errors, omissions, or failure to comply with GSA design requirements shall be prepared under the A/E's design phase contract at no additional expense to the Government, when requested by the Contracting Officer's Representative.
7. During the course of construction, technical support shall be provided for the resolution of unforeseen conditions or other issues related to the scope of this project. The A/E representative shall conduct a site visit as directed by the P.M., to review the work in place, assessing conformance with the design intent, and the progress of construction.
Scope of Work Page 14 of 17
8. A/E shall develop commissioning requirements as part of the specifications for the project. Identify all functional and performance testing/certification requirements for designed features, systems, components, equipment, and materials to achieve programmed performance goals, including testing procedures.
9. During the construction phase, the A/E shall witness the commissioning processes as requested by the PM, and certify its performance to conform to the design intent.
SUBMITTALS
1. Before any work commences, the Contracting Officer must approve all submittals.
Manufacturer's data shall be provided and annotated to show the specific model, type, and size of each item.
2. Submit a construction schedule 10 days after notice to procreed.
3. Submit cut sheets of products for approval prior to ordering and installing.
4. Design Submission Schedule:
a. 35% Submission:
Review conditions and provide design recommendations.
1 Electronic File, 4 Hard Copies
b. 95% Submission:
Incorporate all review comments and documents from 35% review.
1 Electronic File, 4 Hard Copies
c. Final Design Submission:
To include drawings, specifications, cost estimates, narrative updates, calculations, and incorporate all 95% review documents.
1 Electronic File, 4 Hard Copies (Full Size)
FEE AND PAYMENT
1. Prior to final payment under this work order, the Contractor shall furnish the Government with a release of all claims against the Government under the applicable portions of this contract other than such claims as the Contractor may except by description and stated amount of each claim.
2. Any security IDs issued by GSA or the Tenant Agency for the purposes of this task shall be returned to GSA prior to the Final Payment.
Scope of Work Page 15 of 17
3. In consideration of the Contractor’s performance of the services required under this work order, the Government shall compensate the Contractor with monthly progress payments.
DRAFT SCHEDULE TO ESTABLISH PERIOD OF PERFORMANCE
Action Duration
Site Survey 4 Weeks
35% Design Submission 3 Weeks
GSA/DOE Review 2 Weeks
95% Design Submission 3 Weeks
GSA/DOE Review 2 Weeks
Final Design Submission 4 Weeks
GSA/DOE Review 2 Weeks
Construction Mobilization 4 Weeks
Construction 16 Weeks
GSA/DOE Review 2 Weeks
Punch-list Resolution 2 Weeks
Closeout 2 Weeks
TOTAL 46 Weeks
REVISIONS
1. Prior to approval by GSA of the documents listed, the Contractor shall correct or revise any drawings and documents without additional cost to comply with the provisions of this document.
2. The normal required review time by GSA is Ten (10) working days.
3. All formal submissions are subject to update and editing to reflect feedback from GSA.
Describing the changes in the review documents as a written response without making changes in the contract documents is considered non-responsive.
Scope of Work Page 16 of 17
4. The government shall not be liable for any additional contractor costs due to changes or revisions in the requirements of this document which would increase the scope of services as originally negotiated and agreed to, unless such changes or revisions are authorized and approved by the Contracting Officer in writing. All requests for changes or revisions received by the contractor shall therefore be referred to the Contracting Officer for his or her approval.
5. Not less than seven (7) calendar days prior to the final acceptance testing of the entire system, and for use during the instruction period hereinafter specified, provide four (4) bound copies of an Operation and Maintenance Manual to the Contracting Officer’s Representative. The manual shall include an index, copies of all approved shop drawings and submittal materials (updated to as-built), and a complete parts list of all components. The manual shall also include, for each item, the manufacturer's name, the serial number of the part, an ordering number, if appropriate, and a physical description of the part.
AS-BUILT DRAWINGS
1. Prepare and submit to the Contracting Officer six (6) sets of detailed “As-Built” drawings to reflect the location and size of repairs. The drawing shall be submitted before final payment is made.
END SCOPE OF WORK