*** This excerpt was missing from the Project Information section I, on page 6 / 37 of the “Agreement” issued with the RFP on March 24, 2015.
J. 7th Floor Construction Narrative
Summary: This solicitation contains two parts. The first part is the base (USAID 7th Floor Project – Mobility Design Lab Phase 2). The second part is the option (USAID Restroom & Corridor Renovation). Both parts should be priced separately.
Objective: Indentifying scope of work information between the FINAL IFC (inclusive of Addendums 1&2)for the USAID 7th Floor Project – Mobility Design Lab Phase 2 and Restroom & Corridor Renovation Bid Documents (IFC Submission 7/28/2014), in an effort to prevent duplication of scope of work and pricing.
Subject: The scope of work for the base project (USAID 7th Floor Project – Mobility Design Lab Phase 2) includes Area A2 and Area B1 (Area A1 construction is 90% complete, see note 90 on AD 00 00 in Addendum-1 ) as shown on FINAL IFC AD 00 01 Construction Sequencing Plan Existing with De-Scoping of Area B2-Restroom and Corridor with Elevator Lobby areas from the base.
Action: The intent is to provide the GC/Offerers a difinitive dividing line or scope of work for areas Area A2 and Area B1, and the removal/de-scoping of all major renovation work associated with in the Area B2 Restrooms and Corridors with Elevator Lobbies, which is now inclusive in the option package for the USAID Restroom & Corridor Renovation.
Currently, FINAL IFC Documents dated 11/18/2013, do not clearly spell out the scope of work between the base and option packages, so we submit this document to serve as a modification and stipulate the following inclusions and exclusions to the drawings:
a) FINAL IFC Drawings dated 11/18/2013 (USAID 7th Floor Project – Mobility Design Lab Phase 2) will not require any modifications at this time.
b) SOW Clarification for Pricing between Base and Option: Specific scope of work items to be included will consist of the following: For the base, between Column Lines P thru F and 13 & 14, primarily the 7th floor space perimeter dividing partition that separates the office space from the corridor 701 & 702, will need to price ALL renovations associated with this perimeter partition, i.e., Demo, Storefront & Glazing, Metal Studs & Drywall for ‘infill at existing‘ and/or any additional Bulkheads that are to be installed up to the underside of the ceiling slab. On the Office Space side (Areas A2/B1), complete installation of all associated trades. For the option, on the Corridor Side (Area B2), pricing shall include furnish and install any drywall up to flashing, sand and make ready for paint.
c) The information provided in the following pages that are listed in the FINAL IFC Cover Sheet G 00 01 sole purpose, is for identifying Area-B2 Restrooms and Corridors with Elevator Lobby areas scope of work, but not limited to Details, Flooring & RCP drawings, Sections, Finishes & Door Hardware Schedules, IT/AV/Security and MEP are still included in these pages as well as for the areas for Area A2 and Area B1. G0001; G0003; D0001; D0002; D0003; D0004; D0005; AD0000; AD0001; AD0101; AD0102; AD0103; AD0104; AD0105; AD0106; AD0107; AD0108; AD0109; AD0110; AD0401; AD0501; AD0603; AD0604; MD0101; M0101; M0102; E0101; E0102; E0201; E0202; E0203; E0204; E0401; E0402; E0403; E0404; P0101; P0102; P0501; ES0101; FA0101; FP0101; AV0101; TD0101.