Pricing_Sheet_-_Yates_GC_(Revised).pdf

PDF 47 KB Posted

Attached to
General Construction Services for the Sidney Yates Exterior Restoration Project in Washington, D. C.
Solicitation number
GS-11P-15-MK-C-0032
Issued by

About this file

Pricing Sheet - Yates GC (Revised)

View the file

Other files

File Type Posted
Amendment_5_SF30.pdf PDF
Wage_Determination_8.14.2015.pdf PDF
SF1442-14a_Yates_GC_(revised).pdf PDF
Pricing_Sheet_-_Yates_GC_9.1.docx DOCX document
13300_Submittals-YatesRevised.pdf PDF
Amendment_4_SF30.pdf PDF
17350_FirePrevention.pdf PDF
20879_BirdExcrement.pdf PDF
Yates_GC_Questions_ _Answers.pdf PDF
52.225-12_Corrected_Buy_American_Act_Provision.pdf PDF
Amendment_3.pdf PDF
Sidney_Yates_Exterior_Site_Map.pdf PDF
Amendment_3_Attachment.pdf PDF
Pricing_Sheet.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
Yates_GC_-_Amendment_2.pdf PDF
SF LLL.pdf PDF
GSA527-99a —
SF_24-98.pdf PDF
Amendment 1.pdf PDF
Certificate of Procurement Integrity.pdf PDF
Wage Determination DC150002 7.17.15.pdf PDF
Yates GC SOW.pdf PDF
SF1442-14a Yates GC.pdf PDF
Yates Exterior Restoration Project - GC RFP Final.pdf PDF
Yates Exterior Restoration Project - GC Agreement —
Past Performance Questionnaire.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor Name:__________________________________ Date: ___________ Solicitation No.: GS-11P-15-MK-C-0032

GENERAL CONSTRUCTION SERVICES FOR THE SIDNEY YATES EXTERIOR

RESTORATION PROJECT IN WASHINGTON, D.C.

BASE CONTRACT, OPTIONS & UNIT PRICES

I. BASE CONTRACT OFFER: $____________________

I.A The Offeror’s Base Contract Offer shall include the requirements listed in the statement of work, specifications and drawings and prices for the following estimated quantities for specific tasks:

Task Estimated Quantity

Total price

1 Hazardous Material Abatement (Lead Based Paint Abatement)

500 SF

2 Rebuild parapets 100 LF

3 Grout Injections – no mortar within 1” of the face of the brick (500 CF projecting bands and 400 CF flat field brick)

900 CF

4 Grouting, Pointing and Resetting Masonry at gutters

600 LF

5 Remove, Reset and re-align Brick (numbers and types of brick for the cost)

In accordance with drawings

I.A Total

Total Base Contract Offer (I + I.A) $_____________________

II. OPTION I: Trailer $_____________________

Contractor Name:__________________________________ Date: ___________ Solicitation No.: GS-11P-15-MK-C-0032

III. Unit Prices:

A unit price provides an amount proposed by the Contractor, stated on the Pricing Sheet, as a price per unit of measurement for materials or services, which are to be included in the Total Contract Offer. Unit prices include all necessary material and labor costs, overhead, profit, taxes, shipping and other related expenses for the added or deducted work. The estimated quantities listed are for evaluation purposes only. Only the unit price will be incorporated into the contract award upon acceptance by the Government. The unit prices accepted will be used in the event of a change order requiring either an addition or deduction to the requirements of the Contract Documents. No allowance will be established for the unit prices and estimated quantities listed below. See the Agreement, Section II.A(3) Unit Prices for information regarding the use of unit prices in change orders to the contract. The schedule of unit prices is as follows:

Unit Price

Number Description:

Estimated Quantity

Based Upon

Unit Price Total Price

Flash, strip, sand, and paint fifth floor windows

20 windows each

Flash, strip, sand, and paint large windows typically located on the fourth floor windows each

3 Flash, strip, sand, and paint large windows typically located on the third floor windows each

4 Flash, strip, sand, and paint large windows typically located on the second floor windows each

5 Flash, strip, sand, and paint windows typically located on the first floor windows each

6 Flash, strip, sand, and paint windows typically located at the basement windows each

7 Replace window sills 15 sills each 8 Replace gutters and all associated components

500 LF

LF

9 Provide brick molds based on drawings 7 total each 10 Repoint mortar joints

Repoint Flat Wall Joints 50 CF CF Repoint Shaped Bricks 100 CF CF

11 Repair masonry bands 500 LF LF 12 Provide means and methods to heat work areas facilitating winter/cold weather work.

3000 SF

SF

13 Provide off hours staffing to monitor active heating of work areas noted in Unit Price #12 hours hour

14 Set and secure granite capstones at moats 10 capstones each

15 Reset guard rail 4 guard rails each post

16 Replace slate shingles and all associated roofing components

500 SF

SF

17 Abatement of lead paint 400 SF SF Total Unit Price Offer $

IV. TOTAL CONTRACT OFFER:: (I + I.A + II + III) $_____________________