Questions - Answers - Group 10.xls

XLS spreadsheet 75 KB Posted

Attached to
(Recovery) GSA/NCR Design-Build Construction Project Funding by the Recovery Act (Markey and Weaver Building's)
Solicitation number
GS-11P-10-YAC-0054
Issued by

About this file

Project Specific Questions and Answers

View the file

Other files

File Type Posted
List of Changes - Amendment-4 —
REPS-CERTS —
sf25a —
Agreement GS-11P-10-YA-C-0054 —
sf25 —
Solicitation GS-11P-10-YA-C-0054 —
List_of_Changes_-_Amendment-3_(GS-11P-10-YA-C-0054).doc DOC document
SF1442 —
List of Changes - Amendment-2 —
Solicitation_GS11P10YAC0054 —
Agreement_GS11P10YAC0054 —
Grp 10_Markey_HUD_List of Changes 3-15-10.pdf PDF
Grp 10_Markey_HUD_SOW 3-15-10.pdf PDF
Goals for Minorities —
Questions-Answers - General.xls XLS spreadsheet
Sign In Sheet 3.pdf PDF
3-8-10 Pre-Proposal Meeting Presentation FINAL.ppt PPT presentation
Sign In Sheet 1.pdf PDF
List of Changes —
Sign In Sheet 2.pdf PDF
Sign In Sheet 4.pdf PDF
ARRA.8(a) DB Competitive Solicitation GS11P10YAC0054.doc DOC document
WD-DC.doc DOC document
Group 10 - Markey Roof _Weaver Roof_ DB SOW rev 2-20-10.pdf PDF
ARRA.8(a) DB Competitive Agreement GS11P10YAC0054.doc DOC document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Group 10 Final

Group/Solicitation No.BuildingQuestionAnswer
Group 10 -0054Markey & WeaverMy firm is a small woman owned contracting business (NAICS – 236220) and we are interested in bidding as a prime contractor (or subcontractor) on the above referenced solicitation that is coming out thru G.S.A.. However, per the solicitation synopsis (link below) it appears that this solicitation will require that the prime bidder to be a 8(a) firm.The solicitation is a competitive 8a procurement.
Group 10 -0054Markey & WeaverWe are concerned whether there will be sufficient 8(a) contractors who will possess the interest and financial bonding capacity to be able to bid this challenging project. In addition, due the relatively new technology (Photovoltaic / Roof Solar) of work that may be required by this solicitation, and, due to the fact that the project will require Design and engineering work, we are further concerned that the interest from 8(a) firms will be very minimal. This could result in GSA not receiving enough qualified bids and obtaining a quality & competitive value for this important project bid opportunity. In light of these circumstances, would G.S.A. consider setting this project aside for small business interests to bid on as the prime contractor, and not exclusively for 8(a) contractors to bid on as the prime contractor.The solicitation is a competitive 8a procurement. That creates many opportunities for small and large businesses to partner with 8a firms to meet the needs of the government.
Group 10 -0054Markey & WeaverI am a roofing contractor interested in bidding above referenced project. Can we bid directly to you for roofing work or need to work with the General Contractor?The Solicitation is an 8a competitive Design/Build Contract. You can form a contractual relation with other vendors to meet intent of the solicitation.
Group 10 -0054Markey & WeaverWill there be access to the roof from inside the building?Personnel and small tool access only.
Group 10 -0054Markey & WeaverThe roofing work will generate a considerable amount of noise. Will this project require after hours work?Yes - For building information see Specification Section "Work Restrictions"
Group 10 -0054Markey & WeaverPlease outline specific access restrictions for the building for roofing operations, i.e., areas where we can and can not mobilize for our operations.There is no space on site to permanently set up storage or offices. Contractor will have to load materials by crane from street. Coordinate with DC Government for a permit. Deliveries can be made to loading dock after coordinating with building manager. Major deliveries shall be coordinated to occur on nights or week-ends.
Group 10 -0054Markey & WeaverIs there a specific form required for the Bid Guarantee? Standard Form 24 was not providedSF24 and SF1442 Forms have been included by Addendum for bonds and bids.
Group 10 -0054WeaverProject Requirement, Section 1, Para. 4.1.c Please define what work needs to be done off hours?All work associated with defoliation, deliveries and installation that would interfere with operations of the building or disruption of tenant.
Group 10 -0054WeaverProject Requirement, General - Please confirm that this document is 19 pages?Yes
Group 10 -0054WeaverPlease extend the deadline for questions until March 17th, 2010No
Group 10 -0054WeaverPlease extend the bid date to allow us to provide us to provide a more competitive bid price.No
Group 10 -0054WeaverWe could not locate the bid forms- Please provide a copy of the Bid Forms.Provided by this amendment