Questions - Group 2 Final.xls

XLS spreadsheet 63 KB Posted

Attached to
(Recovery) GSA/NCR Design-Build Construction Project Funded by the Recovery Act (OPM Theodore Roosevelt)
Solicitation number
GS-11P-10-YAC-0048
Issued by

About this file

Questions - Group 2 Final

View the file

Other files

File Type Posted
sf24 —
ARRA.8(a)_DB_Competitive_Agreement_GS11P10YAC0048(Amendment_5).doc DOC document
List_of_Changes_(Amendment 5).doc DOC document
Solicitation_GS11P10YAC0048(Amendment_4).doc DOC document
SF1442 —
List of Changes —
SF1442 —
Questions - Group 2 - Global Final.xls XLS spreadsheet
ARRA.8(a)_DB_Competitive_Agreement_GS11P10YAC0048(Amendment 3).doc DOC document
GS-11P10YAC-0048_Attachment B_ Ca1960 HOK.pdf PDF
GS-11P10YAC-0048_Attachment B_ HOK Summer Controls.pdf PDF
Goals for Minorities —
Sign In Sheet 4.pdf PDF
Sign In Sheet 2.pdf PDF
3-8-10 Pre-Proposal Meeting Presentation FINAL.ppt PPT presentation
Sign In Sheet 3.pdf PDF
List of Changes —
Sign In Sheet 1.pdf PDF
sf25 —
sf25b —
ARRA.8(a)_DB_Competitive_Agreement_GS11P10YAC0048(Amendment1).doc DOC document
Group 2_OPM-Theodore Roosevelt —
sf25a —
ARRA.8(a)_DB_Competitive_Solicitation_GS11P10YAC0048(Amendment1).doc DOC document
FOB8 - Document Transmittal Form - 0048.doc DOC document
REPS-CERTS —
List of Changes —
WD-DC.doc DOC document
ARRA.8(a) DB Competitive Agreement GS11P10YAC0048.doc DOC document
ARRA.8(a) DB Competitive Solicitation GS11P10YAC0048.doc DOC document
TRB ARRA SOW.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Group 2 - 12 Mar 10

Group/Solicitation No.QuestionAnswer
Group 2 -0048Is there a specific form required for the Bid Guarantee? Standard Form 24 was not providedBid Guarantee form SF24 has been issued by ammendment.
Group 2 -0048In reference to Section I.B of the Solicitation, is a signature required on The Agreement?Yes
Group 2 -0048In reference to Section II.A.5 of the Solicitation, Other Documents as required, are there other documents required not available on the website?Additional drawings/documents may be available for GSA facilities and may be viewed at the Technical Resource Center (Library) in room 2021 of GSA's Regional Office Building at 301 7th Street, SW, Washington, DC. Photocopies or prints of SBU documents may be made and taken away provided proper protocol for secure custody is followed. For most efficient service, appointments are advised. Contact the Contract Specialist if you would like to make an appointment and mention which building you are interested in. CADD files of building floor plans will be provided to the successful offeror following issuance of Notice To Proceed.
Group 2 -0048Do the Document Security forms for SBU information need to be submitted?Yes
Group 2 -0048Is there a bid form being provided?Bid Forms have been modified where required and have been included by Addendum
Group 2 -0048Is the GSA providing a bid schedule?See the Solicitation
Group 2 -0048Are there Liquidated Damages? If so, what are they?Group 2 - Liquidated Damages are $885 per day.
Group 2 -0048Are there completed CAD drawings of existing conditions available?CADD Files of Floor Plans will be provided to the succesful offeror.
Group 2 -0048If there are no CAD drawings, is a full building survey required?CADD Files of Floor Plans will be provided to the succesful offeror.
Group 2 -0048Is there a comprehensive hazardous material report available for review prior to bid?NO
Group 2 -0048Please clarify all LEED requirements.See the Solicitation Amendment Number 1
Group 2 -0048Please clarify if the contractor will be responsible for temporary utility charges.There will be no utility charges for work conducted within the facility using accepted tools and methods.
Group 2 -0048Will GSA be hiring a 3rd party commissioning agent?GSA intends to employ an independent commissioning agent.
Group 2 -0048Please clarify Escort requirements and confirm if the government will be providing the Escorts if required at no cost to Contractor.Escorts are required.Escorts will be provided by the Government at no cost to the contractor.
Group 2 -0048Please provide page 366 of Amendment I- Task II.Refer to the solicitation.
Group 2 -0048Is there a requirement for Photovoltaic for Amendment 1?Refer to the solicitation, the intent of the amendment is to emphasise that there is a Photovoltaic requirement.
Group 2 -0048In reference to Scope of Work page 4 of 18, item 6.8 Task 7, in order to meet the GSA Blast Requirements do you anticipate removal of all existing windows and installation of structural subframes, and reinstallation of the original windows with interior pRemoval of existing windows is not anticipated. New windows shall be installed on the interior side in a "Blast-Storm" configuration so as to optimize thermal efficiency while protecting occupants in accordance with applicable GSA requirements.
Group 2 -0048Given that the majority of the SBU release forms were posted 3/5/10 (3 business days), could you please consider extended the RFI cutoff date?The ARRA Program Team has been charged to expedite the delivery of these projects. The Proposal Deadlines will remain as stated in the Solicitations.
Group 2 -0048Please provide as-built information.Additional drawings/documents may be available for GSA facilities and may be viewed at the Technical Resource Center (Library) in room 2021 of GSA's Regional Office Building at 301 7th Street, SW, Washington, DC. Photocopies or prints of SBU documents may be made and taken away provided proper protocol for secure custody is followed. For most efficient service, appointments are advised. Contact the Contract Specialist if you would like to make an appointment and mention which building you are interested in. CADD files of building floor plans will be provided to the successful offeror following issuance of Notice To Proceed.
Group 2 -0048The SOW includes an energy analysis, giving AHU sizes. Please confirm the actual AHU sizes will be as determined by the design build team's load analysis and 100% design.Yes
Group 2 -0048The Site Investigation escort costs are required to be paid for by the contractor. How much does an escort cost per hour?Escorts are required. Escorts will be provided by the Government at no cost to the contractor.
Group 2 -0048Site Investigation is all escorted work. Does construction work also require 100% escorts?Yes
Group 2 -0048Is the ceiling space sufficient to fit new equipment above existing space?The design must fit the existing space.
Group 2 -0048What is the floor-to-floor height of the building? The ceiling height and the depth of the structure?See drawings provided in this Amendment
Group 2 -0048Section 1140 Paragraphs 1.3 and 1.4 "Gov't Occupancy" and "Working Hours" are somewhat contradictory. Does the GSA anticipate that areas of the building will be shut down and the construction will be phased? Does the GSA anticipate that all work will be accomplished after working hours.Building is occupied, work will be accomplished after working hours.
Group 2 -0048In reference to Scope of Work page 4 of 18, item 6.8 Task 7, in order to meet the GSA Blast Requirements do you anticipate removal of all existing windows and installation of structural subframes, and reinstallation of the original windows with interiorRemoval of existing windows is not anticipated. New windows shall be installed on the interior side in a "Blast-Storm" configuration so as to optimize thermal efficiency while protecting occupants in accordance with applicable GSA requirements.
Group 2 -0048, Group 4 -0049, Group 5 -0046, Group 7 -0044, Group 9 -0053Request for Construction Documents/Document Security Notices were provided for all of the above referenced projects to obtain documents via CD, however as of yesterday they were not available. When will these CDs be available for pickup?Group 1 - CD was available 8 March. Group 3 - CD is available 12 March at Noon, Group 5 - CD is available 12 March at Noon, No CDs are being provided for Groups 2, 4, 8, 9, and 10. See Solicitaions and Addemdums for additional information.