Solicitation #GS-11P-10-YA-C-0048 Theodore Roosevelt Building – Office of Personnel Management Amendment #1
A. Refer to Competitive Agreement part II.B, Contract Price Form. There are two options to be priced as identified in the following sample:
Line Item Name Price 0001 Base $ 0002 Allowance (for differing site conditions) $100,000.00 0003 Option # 1, Garage Lighting Replacement $ 0004 Option # 2, Lighting Replacement at Metal
Pan Ceiling
Total Contract Price (including all options and allowances)
B. Refer to Base Bid, Task 9 “VAV Conversion” please provide informational pricing as follows:
Task 9, VAV Conversion - floors SB, B, G, 1, 2, & 3 $____________ Task 9, VAV Conversion- floors 4, 5, 6 & 7 $____________
C. Refer to Design/Build Scope of Work for Building Systems and Lighting Improvements – Theodore Roosevelt Building (OPM), pages 1 through 18 of 18.
• Delete Design/Build Scope of Work for Building Systems and Lighting Improvements in its entirety and replace with revised Design/Build Scope of Work for Building Systems and Lighting provided with this amendment.
D. Refer to Solicitation 1.E Estimated Price Range, and “Project Requirements” Section
1.1 Project Summary.
• Estimated contract award amount is greater than $10,000,000
E. Refer to Project Requirements section I.18.2.K, criteria governing design. GSA is committed to incorporating the principles of sustainable design and energy efficiency into all of its building projects. As a means of evaluating and measuring our green building achievements, GSA buildings must be certified through the Leadership in Energy and Environmental Design (LEED) building rating system of the U.S. Green Buildings Council. Projects are encouraged to receive certification and at least LEED Silver level rating.
Within the LEED rating system for Existing Buildings, the contractor shall incorporate into the design specifications all necessary items necessary to accomplish at least a LEED Silver level rating. The contractor shall, working cooperatively with GSA, its consultants, and OPM Facility Management staffs, develop the LEED Score, complete a sustainable
Solicitation #GS-11P-10-YA-C-0048 Theodore Roosevelt Building – Office of Personnel Management Amendment #1 design commensurate with that score, and execute the construction work based on that design. The contractor shall also develop detailed specifications for equipment and systems commissioning plan that shall be executed during the construction phase in collaboration with an independent commissioning agent. The independent commissioning agent shall be brought to the project team under separate contract provided by GSA.
F. Refer to scope of work Attachment A - Lighting System Upgrades.
• Delete Attachment A in its entirety and replace with revised Attachment A provided with this amendment.
G. Refer to scope of work Attachment B – List of Data, Drawings and Reports.
• Delete Attachment B in its entirety and replace with revised Attachment B
H. Refer to scope of work Attachment F, Initial Lighting Study.
• Delete cover sheet of Attachment F and replace with new cover sheet for Attachment provided with this amendment.
I. Refer to scope of work wherein Attachment G, Lighting Designer Qualifications, was omitted from the solicitation. Attachment G is provided with this amendment.
J. Refer to scope of work Attachment K, Floor Plans for Lighting.
• Delete Attachment K in its entirety and replace with revised Attachment K
Solicitation #GS-11P-10-YA-C-0048 – Amendment One
Solicitation #GS-11P-10-YA-C-0048 – Amendment 1
DESIGN/BUILD SCOPE OF WORK FOR BUILDING SYSTEMS AND LIGHTING IMPROVEMENTS
THEODORE ROOSEVELT BUILDING (OPM)
VOLUME 1 - Project Requirements
SECTION 1 - INTRODUCTION
1. PROJECT SUMMARY
• PROJECT TITLE: Building Systems and Lighting Improvements
• BUILDING: Theodore Roosevelt Building (OPM) #DC0082ZZ
• LOCATION: 1900 E Street, NW, Washington, DC 20415
• PROJECT CONTROL NO.: SDC03025
• GSA WORK ITEM NO.: LDC00048
• ESTIMATED CONTRACT AWARD AMOUNT: TBD
The work shall be designed and constructed as a Design-Build project.
2. CONTRACT DOCUMENTS
2.1 Document Organization: The contract documents have been organized into three volumes as follows:
A. Volume 1- Project Requirements - This document and the Lighting Systems Upgrade Design/Build Scope of Work
B. Volume 2 - Project Design and Specifications: Contract Drawings and Specifications produced by the Contractor's Architect/Engineer under Section 2 of Volume 1, which, when approved and accepted by the Government shall become the basis for construction work under this contract.
C. Volume 3 - Bid Forms
3. NOT USED
4. PROJECT GOALS
4.1 Goals: The goals of the project include, but are not limited to:
A. This project is being implemented under the American Recovery & Reinvestment Act (ARRA). The overall goal is to reduce energy consumption, while improving the quality of lighting and the thermal comfort of the building’s occupants.
B. To prepare the required documentation and procure the work required to fully design and construct the building improvements described in detail in subsection 6 below titled PROJECT DETAILS.
Building Systems Improvements 1 of 18 3/3/2010 Theodore Roosevelt Building (OPM)
C. To establish work order priorities in order to carry out the work in an efficient manner, taking into account the needs and desires of the tenant agency and the realities of budget constraints and limitations.
D. The building will remain fully occupied during this work. All work shall be performed during "off-hours" (i.e. evening and night) and on weekends unless otherwise approved by GSA and the tenant agency. The Contractor shall coordinate all work activity with the Building Manager and the Contracting Officer's Technical Representative to ensure that proper security and access arrangements are made with minimal impact on the construction schedule.
E. Full compliance with all building's security regulations shall be observed by the Contractor.
F. Provision of the necessary cutting, patching, and repair of the existing building elements.
G. Design shall be in accordance with OSHA and applicable building code requirements.
H. To preserve and enhance the cultural property.
5. PROJECT SITE
5.1 The Theodore Roosevelt Building houses the central offices of the Office of Personnel Management (OPM) and is an “H” shaped building constructed in 1963. The one acre lot in the District of Columbia, on which the building is sited, is bound by E Street on the north, 19th and 20th streets on the east and west, respectively and Virginia Avenue on the south side. The OPM Building has seven stories above grade and three stories below grade. The above grade floors are primarily office use type space while the below grade levels - ground floor, basement, and subbasement, are a mixture of parking, mechanical and office space areas with an auditorium and cafeteria on the ground floor. The exterior building construction is a concrete structure with a limestone facade with near full height windows for the above grade floors.
5.2 The main mechanical room is located on the lowest level, the Subbasement, and contains the two main chillers and associated chilled water and condenser water pumps as well as the central control room.
The incoming GSA steam and pressure reducing stations are located on the Basement level. Cooling towers along with toilet exhaust fans and steam to hot water heat exchangers are located in the penthouse. The air handling units serving the above grade building office spaces are built-up type units with a filter bank, a chilled water coil with a circulating pump, and a supply and return fan.
For floors 1 through 7, there are 2 AHUs per floor situated in mechanical rooms on the perimeter of the building. For floors 1 through 6, the relief air louver/damper is located in a separate room on the north side of the building while the AHU room, where the outside air (OA) intake is located, is on the south side of the building. The units are capable of full air-side economizer. The existing OA intakes and exhaust for each unit consists of two sections – a minimum damper and an economizer damper. During full economizer, both sections are fully opened. The actuators connected to the dampers are fully modulating type. The return air ducts for each air handler run from the AHU room return plenum and terminate above the ceiling just outside the AHU room. Currently, the AHUs are constant volume type with reheat provided by duct mounted hydronic heating coils for zone temperature control. Included in this contract is the conversion of the constant volume air handling systems to variable air volume (VAV) systems for the air handling systems serving the three lower level floors and floors 1 through 7. (GSA will provide all available drawings and reports to the prospective contract awardees. Refer to list of available documents in Attachment B.)
5.3 Site working conditions (the following where divergent from, supersede provisions shown in Volume 2).
A. No space is available for a contractor's office or storage of construction materials in the building.
Building Systems Improvements 2 of 18 3/3/2010
B. During the contractor's working hours, no parking is permitted or available on site.
No space will be allocated for a contractor's trailer.
C. Specific public toilet facilities will be designated for use by the contractor’s personnel. The contractor is expected to leave the rest-rooms in clean and orderly condition for use by building occupants during the day.
6. PROJECT DETAILS
6.1 General: This section covers in general the existing building conditions and when taken together with other sections of this volume covers the expectations of the Government under this design and construction contract. The general scope of work is a series of improvements to the building’s mechanical, plumbing, electrical, lighting, control systems and the building windows that will enhance the energy efficiency of the building. Refer to the attached Lighting Improvements Design/Build Scope of Work for specific lighting tasks. There are several design and construction elements contained and described in this section which are not necessarily related. The following sections describe individually each task and the extent of the particular scope.
6.2 Task 1: Supply Air Temperature Reset. Provide existing Siemens’ building automation system with control capability for supply air temperature reset for each of the 14 air-handling units serving floors 1 through 7. Use zone temperature sensors, shown on the plans of the VAV Conversion bridging documents to reset the AHU supply air temperature to the highest temperature that can still satisfy the cooling demand in the warmest zone. Contractor shall provide commissioning and controls manufacturer (Siemens) training for operating personnel.
6.3 Task 2: Chilled Water Temperature Reset. Provide existing Siemens’ building automation system with control capability for chilled water temperature reset for the building chilled water system. Use water temperature and humidity sensors to reset the chilled water supply temperature to the highest temperature that can still satisfy cooling and dehumidification demand of the warmest and most humid zone. Contractor design engineer shall determine the appropriate locations for the humidity sensors for optimum control. Contractor shall provide commissioning and controls manufacturer (Siemens) training for operating personnel.
6.4 Task 3: Demand Controlled Ventilation. Provide necessary equipment, sensors and controls to deliver ventilation air on an “as needed” basis to AHUs serving occupied zones using measured CO2 levels to control ventilation air flow rates. Calibrated CO2 sensors shall be located in all zones served by the respective air handling units (AHUs). CO2 sensors shall be located in all zones with temperature sensors as indicated on the VAV Conversion Bridging Documents prepared by EBL Engineers. The control system shall monitor the CO2 sensors and modulate the associated ventilation air dampers when any single sensor exceeds a threshold setting. System shall be designed based on ASHRAE standards, in particular ASHRAE Standard 62.1, with respect to acceptable levels of CO2 in occupied spaces. Contractor shall provide commissioning and controls manufacturer (Siemens) training for operating personnel.
6.5 Task 4: Variable Toilet Room Exhaust. Provide the necessary equipment, sensors and controls required to operate the two existing constant volume toilet exhaust systems such that each of the two fans, located on the east and west sides of the penthouse and serving the toilet room cores, may operate at a variable flow rate in conjunction with toilet room occupancy. The east and west fan flow rates are 13095 cfm and 11250 cfm respectively, based on existing drawings. The design shall be implemented to use the existing ductwork with minor, if any, modifications. The Contractor shall also evaluate and determine if the existing fans and/or motors can be used or if replacement is essential. Contractor shall provide TAB, commissioning and equipment manufacturer training for operating personnel. Refer to the appropriate GSA MasterSpec section for equipment specifications.
6.6 Task 5: Adaptive Controllers for Elevators. Provide adaptive voltage controllers on 10 elevators to reduce voltage applied to motors when it is operating at a partial load. Adaptive voltage controllers shall be based on the “Motor Efficiency Controller” produced by Power Efficiency Corporation or an approved equal.
Building Systems Improvements 3 of 18 3/3/2010
A. Verify compatibility with the Building Elevator Manufacturer and submit an initial feasibility report.
B. Following approval of report by GSA, monitor the energy use of one elevator for four weeks prior to the installation of the motor controller and submit a report of the findings.
C. Install one controller at the same elevator and monitor performance for four weeks.
Submit results of findings with a comparison of the energy use without the controller as described in B above.
D. Install remainder of controllers in accordance with GSA approval and recommendations.
E. Provide commissioning of new system and manufacturer training of all operating personnel.
6.7 Task 6: Low Flow Water Closets and Urinals. Replace existing water closets, urinals, and associated flush valves in the First through Seventh Floor restrooms with low flow type and in accordance with GSA’s “Design/Build Guidance Criteria – Water Efficiency Requirements”. New water closets shall be 1.28 gallons per flush and urinals shall be 0.5 gallons per flush. Existing urinals are floor mounted with existing drains connected to the fixture at or below the floor slab.
The desire is that the new urinals are wall mounted with carriers and the drain piping modified for the new location. Contractor shall consider as a solution the installation of a furring wall to accommodate the new wall mounted urinals. Any new walls will require new ceramic tile to be installed consistent with the original design. New mounting heights and clearances shall be ADA compliant. Approximate fixture count is 168 water closets and 49 urinals.
6.8 Task 7: Window Retrofit. The existing building windows are single glazed units in an aluminum frame. Design, furnish and install an interior window product to be mounted behind the existing building windows throughout the building to increase the insulating value of the windows. The product shall consist of an all aluminum frame with ¼” laminated glass. Product shall be based on Maine Glass Interior Fixed Unit or approved equal. There are approximately 2,289 windows in the building. Currently, all existing windows are fitted with a blast resistant film. The Contractor shall perform and provide a blast analysis and accompanying design which will ensure the new window installation will not create an additional hazard should a blast scenario occur. The new and existing window combination shall, as a system, be in accordance with the most current GSA Blast Requirements. The design shall account for existing ceiling conditions, where in some locations, the ceiling height is lower the upper window opening. The design shall also account for internal shading devices (venetian blinds) which will likely require modification or relocation following window installation. The design shall also consider moving and reinstalling existing furniture to accommodate the new window product’s installation.
6.9 Task 8: Improve “E” Street Lobby Entrances Air Seal. Contractor shall examine the existing North and South Ground Floor, and North (E Street) first floor lobby entrances and provide solutions to reduce air infiltration through the existing entrances. This task shall include but not necessarily be limited to removing and replacing worn gaskets in existing door frames, stripping and replacing caulking or weather sealing, and adjusting, refurbishing or replacing existing thresholds and door operators to ensure air-tight closure.
6.10 Task 9: Variable Air Volume (VAV) Conversion. Provide design and construction services for the systemic renovation of the main airside heating and cooling systems at all floor levels (10 floors) of the Theodore Roosevelt Building in an effort to maximize energy savings and provide a greater degree of control and comfort to the building occupants. The energy savings and enhanced comfort will be a result of converting the existing constant volume systems to variable air volume (VAV)
Building Systems Improvements 4 of 18 3/3/2010 systems with variable air volume air handling units and VAV box terminal units. The conceptual drawings and Project Support Booklet prepared by EBL Engineers included in this solicitation document existing conditions for floors 1 through 7 and are issued to assist the proposers in preparing their proposals.
6.11 Task 10: Lighting Improvements. Refer to “Attachment A – Lighting Design/Build Scope of Work” for specific lighting tasks.
6.12 Task 11: Rooftop Photovoltaic (PV) Systems. This task involves the design and installation of a rooftop PV array as described beginning on page 366 of the scope document. The scope of this project is for a turn-key Design-Build installation of a rooftop photovoltaic system and related work as required. The power output of the system shall be approximately 93 kWDC. A monocrystalline type PV system design is anticipated.
SECTION 2 - PROFESSIONAL SERVICES
1. GENERAL
Provide the services of Registered Architects and/or Professional Engineers, experienced in the type of work contemplated, to furnish design, calculations, field survey, drawings, and specifications covering the proposed work.
2. ARCHITECTURAL REQUIREMENTS
2.1 Provide architectural services as necessary to convey the scope and quality of the construction work, repairs and alterations to be performed. Specify comprehensive patch and repair requirements for all disturbed surfaces and penetrated walls, floors, floor slabs, and ceilings. Specify new plumbing fixtures to meet low flush requirements previously described and work related to the replacement of the plumbing fixtures. Specify new interior window panels to increase insulating value of existing windows. Also, see Lighting Improvements Design/Build Statement of Work dated 22 February 2010 for additional architectural design scope of work.
3. STRUCTURAL REQUIREMENTS
3.1 Modifications to the building structure of any kind shall be included in the design documents and performed by a Registered Structural Engineer.
4. ELECTRICAL REQUIREMENTS
4.1 Provide circuiting, panel boards, panel board changes, starters, and miscellaneous wiring to accomplish the project tasks. Specify modifications to building control system. Also, see Lighting Improvements Design/Build Statement of Work dated 22 February 2010 for additional electrical design scope of work.
5. MECHANICAL REQUIREMENTS
5.1 Provide equipment, piping, ductwork, sensors, meters, actuators, control software and algorithms, and necessary appurtenances to accomplish the project tasks. Provide analysis, calculations, drawings, and specifications to accomplish the project tasks.
6. ENVIRONMENTAL REQUIREMENTS
6.1 Remove asbestos containing materials (ACM) that will be disturbed because of this project, if any.
Any asbestos-containing material (ACM) that will be disturbed as a result of the project shall be removed or handled as outlined in specification Section 02085 and/or 02085R.
6.2 The A/E will obtain the services of a qualified firm to conduct an asbestos assessment of the portion of the building scheduled for renovation. Qualified is defined as utilizing personnel who are U.S.
Environmental Protection Agency (EPA) accredited AHERA Inspectors/Management Planners or Project Designers. The assessment is to include the following:
Building Systems Improvements 5 of 18 3/3/2010
A. Search for any existing documentation. Contact the GSA Safety and Environmental Management Branch at (202) 708-5236 to review existing documentation.
B. Perform a walk-through inspection.
C. Sample any possible ACM not identified in existing documentation. Sampling should conform to the requirements found in 40 CFR 763.85. (Note: Qualified is defined as utilizing personnel who are EPA certified as AHERA Inspector/Management Planners or Project Designers.)
D. Any ACM that will be disturbed as a result of the project shall be removed or handled as directed in GSA PBS P 5800.36, Real Property Management and Safety Policy Handbook. Any required asbestos abatement shall be included in the construction cost estimate as well as the contract drawings and specifications. Hard copies of Specification 02085 and 02085R are available from the Safety, Environment and Fire Protection Branch.
6.3 Any lead-based paint (LBP) that will be disturbed as a result of the project shall be removed or handled in as outlined in specification Section 02090. The A/E will obtain the services of an industrial hygiene firm to conduct a lead-based paint assessment of the portion of the building scheduled for renovation. The assessment is to include the following:
A. Search of any existing documentation. Contact the GSA Safety, Environment and Fire Protection Branch at (202) 708-5236 to review existing documentation.
B. Perform an on-site walk-through inspection to verify existing conditions.
C. Sampling of any suspect lead-based paint not identified in existing documentation.
D. If lead painted materials are available for destructive testing, such as window sashes or frames that have been removed, the components shall be subjected to TCLP analysis. This will more definitively address the issue of lead disposal in the contract documents.
E. Any required abatement and lead waste disposal shall be included in the construction cost estimate as well as the contract drawings and specifications. Hard copies of Specification Section 02090 are available from the Safety, Environment and Fire Protection Branch.
7. FIRE PROTECTION ENGINEERING REQUIREMENTS
7.1 The building will be fully occupied during the work. The building’s fire and life safety systems must be maintained during the course of the work. A Professional Fire Protection Engineer shall assist and consult with the Design/Build team as necessary.
8. PHASING REQUIREMENTS
8.1 There are no phasing requirements. Provide sequencing of work to minimize disturbance to building occupancy.
9. DESIGN SUBMISSIONS
9.1 Refer to PBS –P100 Facilities Standards for the Public Building Service, Appendix A – Submission Requirements. All submissions in each phase of work shall be given to the GSA in drawing and/or written form and electronic files on compact disk (CD)
Sequential Submissions: The Contractor shall prepare and deliver design submissions as follows:
A. Concept Design Documents - approximately 25 percent documents showing D/B Contractors approach to the solution of each task.
Building Systems Improvements 6 of 18 3/3/2010
B. Construction Documents - approximately 50 percent documents showing typical conditions and typical solutions.
C. Construction Documents - approximating 95 percent (Pre-Final) documents accurately depicting/describing all work (demolition and new construction).
D. Construction Documents - approximating 100 percent (Final) documents accurately depicting/describing all work (demolition and new construction). Include all shop drawings with this submission
E. Presentation to NCPC and CFA: To be determined.
10. DESIGN DEVELOPMENT
10.1 Field Survey: Provide staff to survey the project site and to prepare dimensioned drawings reflecting existing conditions. These drawings will be subsequently used for the preparation of demolition and as backgrounds for new construction work.
10.2 Concealed Conditions: survey shall examine and record both exposed and concealed conditions that will impact the work.
10.3 Level of Development:
A. Following award, fully develop the project design to 50% through the preparation of typical drawings, materials, specifications, calculations and studies as necessary to fully document and support design solutions. Calculations shall read logically from the initial assumptions, through the calculation phase to sizing and decision solutions.
B. Pre-Final and Final Design Documents. The "Final" working drawings submitted shall accurately depict/describe all work (demolition and new construction) to be performed within all areas delineated on the respective floor plans. All drawings submitted shall be complete in all respects, and shall fully support the minimum needs of the construction Contractor. Submitted drawings and specifications shall be final versions.
10.4 Time of Performance (TOP): Attend a Time of Performance (TOP) meeting with the GSA Project Manager, Construction Engineer and Building Manager to provide an overview of the project and discuss how all GSA review comments have been addressed. Also discuss outages, phasing, switch over from the old to the new, working hours and any other special building requirements.
10.5 Product Data: Submit for review and approval all materials required to perform the work, including but not limited to all new products or equipment, rated capacities, pressure drops, performance and rating data, furnished specialties, and accessories.
11. FINAL DESIGN DOCUMENTS
11.1 Shop Drawing Documents: The drawings submitted shall accurately depict/describe all work (demolition and new construction) anticipated to be performed within all areas delineated on the floor plans. Specifications for materials shall be included with the drawings and shall address only that construction work to be provided. Drawings and specification submitted shall be in final form and shall reflect resolution of all previous review comments, and shall have the professional seals and signatures of the reviewing Registered Professional Engineers and/or Registered Architects.
A. Drawings shall clearly distinguish between new and existing work.
B. All drawings shall include graphic scales.
11.2 As-Built Drawings: Shop drawings shall be continuously annotated showing solution to problems not encountered during survey period or anticipated. The government shall be apprised of all modifications and each solution shall be submitted for approval within 15 days of change.
Building Systems Improvements 7 of 18 3/3/2010
Drawings shall have the professional seals and signatures of the reviewing Registered Professional Engineers and/or Registered Architects.
12. DRAWINGS, SPECIFICATIONS, CALCULATIONS
12.1 Drawing Standards:
A. Drawing levels of detail and quality of representation shall adhere to the AIA guideline "Architectural Graphic Standards". All drawings must be uniform sizewith each sheet including North-arrows, Key Plan, and graphic scales. All details and sections shall be "back referenced" to the appropriate drawings so that they are easily understood by those who have not been involved in their preparation. Title block shall be the GSA standard and shall include the project name and location.
12.2 CAD Standards
A. The PBS CAD Standard should be followed for all CAD drawing formatting. The PBS CAD Standard should be obtained via the Internet at:
http://www.gsa.gov/gsa/cm_attachments/GSA_DOCUMENT/CAD_standards_R2NY 1-k_0Z5RDZ-i34K-pR.pdf .
B. Drawings prepared in imperial units are acceptable for the tasks outlined in this project.
12.3 All drawings developed by the Contractor, if computer based, shall be prepared in a format which can be used directly, without conversion, on AutoCAD operating under Windows. Drawings shall be maintained on a compact disk (CD) with at least one back-up copy furnished with each original.
Drawings that are "shop drawings" may be prepared by manual drafting.
12.4 Specifications included in Volume 2 shall be edited, expanded, or otherwise modified, as needed to reflect the design, and quality control standards proposed by the Contractor. Specifications, if computer based, shall be prepared in a format which can be used directly, without conversion, by WORD 97 operating under Windows. Provide specifications on a compact disc (CD) with one back-up copy.
12.5 Submit engineering calculations as required for all disciplines at each submission. Submit engineering calculations prepared and/or approved by the registered professional engineer of appropriate discipline. The cover sheet of calculations should be stamped by the engineer.
13. DESIGN REVIEWS
13.1 Government Review: The Government will review the Contractor's submission at the 25%, 50%, 95% and 100% complete stage of the project. Design reviews will be performed by Government staff.
13.2 Purpose: The Government will provide reviews of Contractor design submissions to verify adherence to contract requirements. Design reviews by the government are not to be interpreted as resulting in an approval of the Contactor's apparent progress toward meeting contract requirements but are intended to discover any information which can be brought to the Contractor's attention which might prevent costly errors and/or misdirection. The Contractor shall remain completely responsible for designing and constructing the project in full accord with the requirements of this contract.
13.3 Resolution of Comments: The Contractor shall resolve all design review comments in writing, indicating one of the following: (1) Adoption and action taken (2) Adoption with Modifications and action taken, (3) Alternative resolution and action taken, or (4) Rejection. In cases other than unqualified adoption, the Contractor shall provide a statement as to why the reviewer's objection and/or recommendation is inappropriate. Design review comments shall not relieve the Contractor from compliance with terms and conditions of this contract. Contractor's comment resolution shall be transmitted to the Government within fourteen (14) calendar days of review comment receipt.
Building Systems Improvements 8 of 18 3/3/2010 Theodore Roosevelt Building (OPM) http://www.gsa.gov/gsa/cm_attachments/GSA_DOCUMENT/CAD_standards_R2NY1-k_0Z5RDZ-i34K-pR.pdf http://www.gsa.gov/gsa/cm_attachments/GSA_DOCUMENT/CAD_standards_R2NY1-k_0Z5RDZ-i34K-pR.pdf
13.4 Specification/Calculations: These submissions shall use standard white bond paper or formatted sheets, 8-1/2" x 11", bound in other than metal prongs, organized in a logical sequence, tabbed to each section heading. Calculation shall be titled with each analysis clearly indicating subject/problem being studied, applied references, assumptions, and analysis of answer. All numerical references to length, temperature, energy, mass, weight, work and power shall be presented in imperial (inch-pound) units.
14. DELIVERABLES
The Contractor shall provide the Government copies of all submission materials required for each Level of Development as follows:
14.1 Concept, Design Development, and Construction Documents: The documents submitted shall consist of one (1) set of full-size and (8) eight half-size prints of the drawings, draft specifications and calculations and a compact disc (CD). Submit all sets of these documents to the Project Manager or Contract Officer for distribution.
14.2 Shop Drawings: (5) Five sets of full size prints for each phase.
14.3 As-Built Documents: The final "deliverable" design documents submitted shall consist of eight sets of full-size prints and final specifications and a compact disk (CD).
15. CODE COMPLIANCE
15.1 Building Codes: All designs and construction work shall comply, as a minimum, with the latest edition of all applicable national and local codes and standards that govern federal construction.
Specifications in effect at the time of contract award shall be deemed to have legal force through the duration of this contract.
15.2 Submit a code analysis in the first review submission which addresses the specific portion of the building affected by this Project Description. The analysis should entail the following work:
A. Compile a list of applicable codes and Government Requirements documents.
B. List the applicable design document review authorities including the method of contacting them.
C. Prepare a comprehensive code analysis, which references each of the subsections of the codes and government criteria for this project. The code analysis should highlight any conflicts, which may exist between the codes and design criteria listed in this Scope of Work as they pertain specifically to this project.
D. Provide a synopsis of the pertinent code data, which applies to the work required by this Scope of Work on the cover sheet of the construction drawings. This list should include, as a minimum, the following information: the use group classification(s) and construction classification types(s). If applicable provide fire resistance ratings of the pertinent building elements, any special use and occupancy requirements, buildings occupant load, maximum length of exit access travel, and number of exits required.
Provide the following statement on the cover sheet:
“The design of this project conforms to the following applicable codes and Government requirements:”
The Architect and Engineer’s signed professional seal provided below this statement will certify compliance with the required design criteria and codes.
16. COORDINATION OF WORK
16.1 All work shall be coordinated with and approved by the following:
A. General Services Administration
Building Systems Improvements 9 of 18 3/3/2010
B. Not Used
17. SITE INVESTIGATION
A. All arrangements for on site survey and investigation required during the design phase shall be coordinated and scheduled through the Building Manager and COTR.
B. Comply with all building security provisions and HSPD-12 requirements. All personnel shall be 'escorted' at all times. Payment for escort services shall be included in the contractor's bid price.
18. CRITERIA GOVERNING DESGIN
18.1 Government Studies, Surveys, and Reports:
A. Historic Preservation Document #1 and #2, GSA PBS 1022.2 1981, and the GSA NCR Preservation Notebook Series and the National Park Service Preservation Briefs and Tech Notes, found in the GSA NCR Technical Resources Library.
18.2 Government Requirements:
A. PBS-P100 Facilities Standards for the Public Buildings Service, March 2003.
B. PBS-PQ 250 – Value Engineering Program Guide for Design and Construction, Volume 1, December 1992.
C. PBS-P 3440.5 – Project Estimating Requirements, August 24, 1981.
D. PBS-P 3440.7 – Estimating Construction Modifications, July 1983.
E. PBS-P 5800.36 “Real Property Management and Safety Policy Handbook,” May 10, 1994.
F. Life-Cycle Costing Manual for the Federal Energy Management Program, (NIST Handbook 135).
G. Instructions for Developing Construction Cost Estimates, October 1994.
H. Buy American Act
I. “General Guide for Editing Specifications”, April 1988.
J. AIA Masterspec Specifications with GSA Division One Supplements and the following GSA Regional Specifications:
(1) Safety and Health Section 01546
(2) Asbestos Abatement Procedures Section 02085
(3) Asbestos Abatement Roofing Removal Procedures Section 02085R
(4) Avian Excreta Section 02087
(5) Removal and Incineration of Fluorescent Light Ballast's Section 02089
(6) Removal and Disposal of Lead Based Paint Section 02090
(7) Firestopping Section 07270
(8) Vertical Transportation Section 14200 *NOTE: If this project requires specifications not provided by the AIA Arcom, GSA supplements or the specifications listed above; prepare specifications for those sections following the Construction Specification Institute (CSI) format and GSA’s “General Guide for Editing Specifications.”
K. Leadership in Energy and Environmental Design (LEED) of the U.S. Green Building Council.
L. Environmental Management Technical Guides, GSA Safety and Environmental Branch.
Building Systems Improvements 10 of 18 3/3/2010 Theodore Roosevelt Building (OPM) http://www.gsa.gov/Portal/gsa/ep/contentView.do?pageTypeId=8169&channelId=-13830&P=PCH&contentId=11449&contentType=GSA_BASIC http://ncr.gsa.gov/HistoricPreservation/toc.asp http://ncr.gsa.gov/HistoricPreservation/toc.asp http://w3.gsa.gov/web/p/hptp.nsf?Opendatabase http://w3.gsa.gov/web/p/hptp.nsf?Opendatabase http://www.wbdg.org/ccbref/ccbdoc.php?category=gsa&docid=275&ref=1 http://www.gsa.gov/gsa/cm_attachments/GSA_DOCUMENT/New_VEPG_Volume_I_R2Q-iK_0Z5RDZ-i34K-pR.pdf
M. HUD document; “Lead Based Paint Interim Guidelines for Hazard Identification and Abatement” dated June 1995.
N. “Streetscape Manual,” Architectural/Engineering Subgroup, August 1992.
www.nps.gov/streetscape/
O. The National Capital Urban Design and Security Plan. www.ncpc.gov.
P. Energy Policy Act of 1992 (PL 102-486).
Q. Federal Property Management Regulations (FPMR), Temporary Regulation D-76.
18.3 Codes and Regulations
A. International Building Code (IBC) maintained by the International Code Council
(ICC).
B. For all projects, the egress requirements of the National Fire Protection Association (NFPA 101), Life Safety Code shall apply in lieu of other code references.
C. For all projects, the electrical requirements of the National Fire Protection Association (NFPA), National Electric Code, have been adopted by GSA in lieu to the technical electrical requirements of the ICC Electrical Code.
D. Occupational Safety and Health Regulations for Construction; 29 CFR, Parts 1926 and 1910.
E. Environmental Protection Agency Regulations.
F. The Architectural Barriers Act Accessibility guidelines (ABAAS) are mandatory on all GSA projects. Current GSA policy also encourages compliance with the requirements of the American with Disabilities Act Accessibility Guidelines (ADAAG) where those requirements are stricter than ABAAS. The D/B Contractor’s A/E is responsible for checking whether there are local accessibility requirements. If they exist, the most stringent will prevail between local and ABA/ADA.
G. National Fire Protection Association (NFPA) Standards.
H. Applicable local codes and regulations.
18.4 Industry Standards
A. Occupational Safety and Health Standards.
B. American National Standards Institute (ANSI) Publications.
C. Underwriters Laboratories, Inc. (UL)
D. The Institute of Electrical and Electronics Engineers (IEEE), Inc., Publications.
E. National Electrical Manufacturers Association (NEMA) Publications.
When conflicts in the above list occur, the A/E shall notify the Government, and the Project Officer will acquire the necessary interpretation and guidance for the A/E.
SECTION 3 - CONSTRUCTION SERVICES
1. GENERAL
The Contractor shall provide all the necessary labor, materials, supervision, management, quality control plan, and testing to produce work conforming to the contract documents.
2. APPROVED CONTRACT DOCUMENTS
Building Systems Improvements 11 of 18 3/3/2010 Theodore Roosevelt Building (OPM) http://www.nps.gov/streetscape/ http://www.ncpc.gov/
After approval by the Government of drawings and specifications prepared by the Contractor's Architect/ Engineer, the following documents shall become the contract documents for this project and shall govern all aspects of construction:
A. Volume 1, Project Requirements
B. Volume 2, Project Design and Specifications as prepared by the Contractor and agreed to by the Government, C. Volume 3, Bid Forms
D. Design development documents, shop drawings, and as-built drawings
3. Not Used
4. MISCELLANEOUS SERVICES
4.1 Cutting, Patching, and Painting: Provide all cutting, drilling, and chasing to procure the work. Do not cut structural beams or major structural elements without the written review and approval of a Licensed Structural Engineer and the General Services Administration. Submit structural calculations sealed by licensed Structural Engineer to the Contracting Officer for approval. Patch areas with construction matching adjacent surfaces. Patched areas shall be neatly trimmed prior to patching. Feather all patches to provide a complete and finished surface. Paint all exposed work provided under the contract including all patched areas, exposed areas uncovered during demolition, to provide a complete and finished project. Paint patched areas plus surrounding areas to the nearest break in wall surface, or other building line to provide a neat and finished appearance. All paint shall match adjacent painted surfaces. Protect all surrounding areas including fixtures, furniture, floors and accessories from paint splatter and droppings. Clean-up and restore all areas splashed with paint. Firestop all penetrations
Building Systems Improvements 12 of 18 3/3/2010 through fire-rated walls, floor/ceiling, and roof/ceiling assemblies to maintain the required fire-resistance rating.
4.2 Working hours: Reference Specification, Section 01310 - Project Management and Coordination and Section 1 paragraph 4 of this Volume.
4.3 Cleaning: The premises will be occupied during performance of work under the contract. Reference Specification, Section 01310 - Project Management and Coordination.
4.4 Preliminary Inspection: Contractor shall examine all areas of the building, structure and site affected by the removal and demolition work, alterations and new construction work prior to initiation of design work.
5. COORDINATION OF CONSTRUCTION WORK
5.1 Government Occupancy: The building is scheduled to be occupied throughout the length of construction phase(s) and security requirements will be in place. The Contractor shall coordinate his work with the security and access requirements of the work areas with the GSA Project Manager and the tenant agency, prior to scheduling any work.
5.2 Coordination with Other Work Not in Contract: The Contractor shall coordinate the work of this contract with that of other contracts in the building at the time.
5.3 Construction Schedule and Phasing: All work shall be performed during "off-hours" (i.e. evening and night) and on weekends. Develop a phasing plan and work schedule in advance of performing the work. Coordinate all work activity with the Building Manager and the Contracting Officer's Technical Representative to ensure that proper security and access arrangements are made with minimal impact on the construction schedule.
SECTION 4 - CONTRACT ADMINISTRATION AND BID ANALYSIS
1. GENERAL
This section includes but is not limited to the following: Pre-bid services on the part of each bidder and the Government, Design and Construction Schedules, Bid Submission Requirements, Bid Assembly, Bid Evaluation and Award, Roles and Responsibilities, Quality Control Plan, Shop Drawings, Project Closeout.
2. DESIGN SCHEDULE
2.1 The design phase of the project shall be performed complete (including Government review time), within the time frame as indicated below after Notice to Proceed (NTP) for the design.
2.2 Coordination Meetings. Immediately after award, "mobilization" meetings shall be conducted to review contract requirements, address scheduling, introduce staff, and resolve questions. The meeting shall be initiated by the Contractor. (Also See Specification, Section 01310 - Project Management and Coordination, for additional requirements.)
2.3 The Government anticipates that the normal time required for the formal review and approval of submissions will be fifteen (15) working days from presentation to approval. The Contractor shall deliver all design documents required for review and approval by the government to the Contracting Officer's Representative in accordance with the following schedule:
Submission Required: Copies: 1/2 Size+Full Size Due:
A. Concept Submittal (25%) 8+1 4 wks after NTP
B. 50% Submittal 8+1 4 wks after Concept approval
C. Pre Final (95%) Submittal 8+1 4 wks after 50% approval
D. NCPC and CFA Presentations 16 reports Date TBD
E. TOP Meeting and Review submittal 2 wks after NCPC & CFA approval
Building Systems Improvements 13 of 18 3/3/2010
F. Final (100%) Submittal 8+1 4 wks after 95% approval
(One ea original vellums, unbound, four ea CDs of drawings, specifications cost estimates, Final Shop Drawing/Product Data. etc.)
G. PCCS (Post Construction Contract Services) and Site visits Duration of construction
Government rejection of submittals does not relieve the Contractor from responsibility of meeting the design schedule or construction schedule.
3. CONSTRUCTION SCHEDULE
3.1 The contractor shall prepare a progress schedule in a time scaled bar graph format, utilizing the most current version of Primavera Project Planner “Sure Track” demonstrating complete fulfillment of all Work shown in the contract documents. See Section 01311 – CRITICAL PATH METHOD
SCHEDULING
3.2 Construction performance shall not begin on any work until all design documents required by this document have been developed and completed by the Contractor to the 100% Final Design Document stage, and reviewed and accepted for construction by the government. (Concurrently with shop drawings submittals.)
3.3 The construction phase of the project shall be performed complete within 270 calendar days after approval of final submittal.
ROLES AND RESPONSIBILITIES
4.1 Contractor: The Contractor shall be solely responsible for the management (planning, supervision and contract coordination), design professional services, and construction (including all labor, equipment, materials and inspections) necessary to provide the design and construction services specified herein, complete and within established schedules, fulfilling all requirements of this document for a Design-Build contract.
4.2 Management. The Contractor shall provide individuals in the capacities of Contractor Principal, Project Coordinator, Construction Supervisor, and Inspection/Testing Agent(s).
A. Contractor Principal(s) shall have legal authority to represent the Contractor.
B. Project Coordinator shall be the single point of contact for coordinating with the Government.
C. Construction Supervisor shall coordinate construction work and associated contracts.
D. Inspection and testing agents must certify delivery and functional/ operating performance of contract work.
4.3 Professional Services. The Contractor shall provide all required design/engineering and consultant services by Registered Architects and Professional Engineers as described in this document.
A. Engineering/architectural principals and specialty contractor/ consultant principals shall have legal authority to represent associated firm(s).
B. Chief design engineers shall have sign-off authority for involved disciplines.
C. Senior engineers/architects are those who have significant influence over design development.
4.4, 4.5, 4.6, 4.7 Not Used
5. QUALITY CONTROL PLAN
5.1 General: The Contractor shall develop, provide, and maintain a Quality Control Plan during the design development phase and construction of the project, based upon the Design-Build contract
Building Systems Improvements 14 of 18 3/3/2010 http://pmcoe.gsa.gov/ requirements referenced within this Document. The Quality Control Plan shall address special factors impacting the construction of the project. This aspect of the Quality Control plan is intended to establish and document the methods, measures, and procedures to be used by the Contractor for performance of the work in an "occupied" building during "off-hours" and weekends. In addition, the Quality Control Plan is also intended to document those inspections/tests necessary to assure the Government that product delivery, quality and performance requirements have been met, and serve as an inspection coordination tool between the Contractor and the Government.
5.2 Content: The Quality Control Plan shall identify and address the special factors impacting the construction and specify the considerations and provisions to be made by the Contractor during construction of the project. Consideration and provisions proposed to accommodate special factors impacting the construction shall be outlined, and described in sufficient detail to clearly indicate all facets of how they relate to the coordinated construction of the project. The Contractor is not relieved from any requirements specified in this document should they not be included in the plan.
The Quality Control Plan shall also identify the equipment/system to be tested, exact test(s) to be performed, measured parameters, and the stage of construction development when tests are to be performed. The Contractor shall organize inspection/testing of equipment in accordance with a recognized method which delineates all facets of construction. The method shall identify all equipment items, subsystems, and/or components which influence operation, function, quality or referenced on timeline charts to identify when tests should be performed. The Contractor is not relieved from required performance test should these not be included in the plan. Special factors impacting construction include but are not limited to:
A. Government occupancy of the building during construction.
B. Work hour restrictions C. Construction phasing D. Power outages.
E. Security and access requirements F. Staging and storage area space limitations.
G. Asbestos removal and disposal H. Lead paint removal and disposal
5.3 Format: Quality Control Plan documents shall use…
This is the start of the file's text. The full file is on GovTribe.
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .