Amendment_0009_SF30_Consolidated.pdf

PDF 382 KB Posted

Attached to
IRS ECC Cooling Tower Replacement Federal contract opportunity
Solicitation number
GS-03-P-16-DX-C-7004
Issued by
General Services Administration Public Buildings Service Region 3

About this file

Amendment 0009 dated 03 May 2016

View the file

Other files for this federal contract opportunity

Other files attached to IRS ECC Cooling Tower Replacement, newest first.
File Type Posted
Amendment_0011_SF30_Consolidated.pdf PDF
104416_-_FIRE_EXTINGUISHERS.PDF PDF
IRS_ECC_CT_Pre-Proposal_Site_Visit_04.22.16_Sign_in_Sheets_Consolidated.pdf PDF
Amendment_0010_SF30_Consolidated.pdf PDF
GDI_Info_-_IRS_CT_Replacement.xls.xlsx XLSX spreadsheet
Amendment_0008_SF30_Consolidated.pdf PDF
099123_-_INTERIOR_PAINTING.pdf PDF
099113_-_EXTERIOR_PAINTING.pdf PDF
Amendment_0007_SF30_Consolidated.pdf PDF
Amendment_0006_SF30_Consolidated.pdf PDF
Amendment_0005_SF30_Consolidated.pdf PDF
Amendment_0001_SF30_Consolidated.pdf PDF
GSA527-15_Contractor's_Qualifications_and_Financial_Information.pdf PDF
Amendment_0004_SF30_Consolidated.pdf PDF
Amendment_0003_SF30_Consolidated.pdf PDF
Amendment_0002_SF30_Consolidated.pdf PDF
Amendment_0004_04.14.2016.pdf PDF
Amendment_0003_04.13.2016.pdf PDF
Amendment_0002_04.12.2016.pdf PDF
Amendment_0001_Consolidated_04.11.2016.pdf PDF
IRS_FULL_SET_3-11-16.pdf PDF
2016-03-18_Bid_Document_Project_Manual.pdf PDF
REV_IRS_ECC_Cooling_Tower_Replacement_Project_Kearneysville_WV_The_Solicitation_Form_C201.pdf PDF
IRS_ECC_Cooling_Tower_SOW_03.22.2016.pdf PDF
IRS_ECC_Cooling_Tower_Replacement_Project_Kearneysville_WV_The_Agreement_Form_C101.pdf PDF
IRS_ECC_Cooling_Tower_Replacement_Project_Kearneysville_WV_Reps_ _Certs_Form_C301.pdf PDF
IRS_ECC_Cooling_Tower_Replacement_SF_1442_with_Price_Proposal_Bid_Sheet_03.16.2016.pdf PDF
Wage_Determination_WV37_Mod_2_dtd_02.19.2016.pdf PDF
IRS_Pre_Solicitation_Notice_02.22.2016.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

GSA Mid-Atlantic Region

U.S. General Services Administration 100 S. Independence Mall West Philadelphia, PA 19106 www.gsa.gov

RFP Solicitation Number: GS-03-P-DX-C-7004, issued March 24, 2016 Cooling Tower Replacement Internal Revenue Service – Enterprise Computing Center Kearneysville, WV

Amendment 0009, dated May 03, 2016

This represents Amendment 0009 issued against the above referenced Request for Proposal

(RFP).

1. The due date and time for receipt of proposals remains May 11, 2016 at 2:00 PM (Local Philadelphia Time).

2. This amendment must be acknowledged with your price proposal.

3. Contractors are advised the Government’s response has been modified to a question previously published in Amendment 0005.

Question 5B:

Drawing M506, detail 7 reflects a cross section of the underground trench which includes the new make-up/well water piping and shows a 8" OD and 4" ID dimension on those 2 lines. Per specification section 221116-3.12, D1 all of the underground water piping is called out to be ASTM B88, type K copper, which is typically a direct bury piping. There is no specification section which indicates the make-up water or the well water to be insulated or pre-insulated conduit piping.

Please clarify if insulation on the make-up/well water in underground applications is required?

The Government’s response is modified.

FROM:

The insulation for make-up/well water in underground applications are not required.

TO:

Insulation for make-up and well water piping in underground installations below the frost line is not required.

However, where make-up and well water piping in underground installations above the frost line and above grade installations are required to have insulation and heat trace according to P-506 Detail 3 'PRE-INSULATED PIPE THRU FLOOR DETAIL (BASE

BID)'.

4. Contractors are advised of the Government’s response to a question previously published in Amendment 0004 regarding the Bonding Capacity has been modified as follows:

QUESTION 4D:

In the Solicitation, page 16, (4) Bonding Capacity, it states this factor is a go/no-go to assess the offeror’s ability to provide an offer guarantee and performance & payment bonds sufficient to cover a project of this magnitude which is $10M.

Does GSA want a letter from our surety company for this section verifying the required information?

ANSWER:

FROM:

Yes. An Offer Guarantee (SF 24 - Bid Bond) is required for this project equal to 100% of the proposed price. If the proposed price is less than $10M, then the offeror shall provide a letter from their surety company verifying the Offeror has the financial capability to perform.

TO:

An Offer Guarantee (SF 24 - Bid Bond) is required for this project equal to 20% of the proposed price or $3 million, whichever is less. Reference The Solicitation Form C201 Section I.F. –FAR 52.228-1 Bid Guarantee (SEP 96), subparagraph (c) which reads:

The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less. (Page 8 of 34)

The Offeror shall provide a letter from their surety company verifying the Offeror has the financial capability to obtain payment and performance bonds in the amount of $10 million.

5. The Solicitation Form C201 Section II.D. Technical Proposal, sub section (4) Bonding Capacity (page 16 0f 34) is changed:

FROM: This is a go/no-go factor to assess the offeror’s ability to provide an offer guarantee and performance and payment bonds sufficient to cover a project of this magnitude. For this procurement, the minimum amount to be covered by the offer guarantee and bonding is $10 million.

TO: This is a go/no-go factor to assess the offeror’s ability to provide an offer guarantee and performance and payment bonds sufficient to cover a project of this magnitude. For this procurement, the minimum amount to be covered by the Offer

Guarantee is 20% of the bid price or $3 million whichever is less. Payment and Performance bonding capacity is $10 million. The Offeror shall provide a letter from their surety company verifying the Offeror has the financial capability to obtain payment and performance bonds in the amount of $10 million.

6. The following answers are provided for questions submitted by contractors regarding this

RFP:

A. QUESTION:

Pipe weld inspection criteria:

Specification section 232113.13 1.6B States that the piping welds should be made to ASME B31.9 standards. If the welds fail a visual inspection by owners third party, then random welds will be tested via X-ray inspection to ASME B31.1 Standards.

Due to the substantially different criteria in these two sections with ASME B31.1 being more stringent than ASME B31.9, a weld which is made to the ASME B31.9 standard cannot be expected to meet the inspection criteria for AMSE B31.1.

Please provide clarification?

ANSWER:

Piping welds should be made to ASME B31.1 (not B31.9) and tested per ASME B31.1 also.

B. QUESTION:

Spoils Removal Do all spoils need to be removed from the site or is there an area that we can dispose of somewhere on site?

GSA/IRS can find a temporary storage area for spoils but all spoils will need to be disposed of off-site.

C. QUESTION:

Document 003132-1.1.D references Document 002113 "Instructions to Bidders";

however, this section could not be found.

Please provide this section.

The section is not provided and the reference should be removed.

D. QUESTION:

Please confirm there is no cost associated with obtaining an ePM license for this project.

There is no cost associated with obtaining an ePM license.

E. QUESTION:

Please confirm the LEED submittals referenced in section 051200-1.6 are not required as the project is not seeking a LEED rating.

This is not a LEED project. Any reference to LEED submittal should be removed.

F. QUESTION:

It was mentioned at the site visit that there may be fire protection lines inside the existing building that need to be relocated in order to install new piping.

Please confirm this work is not required since it is not reflected in the drawings.

Fire protection piping was reviewed during design for conflicts. Several pipes are indicted to be relocated. If additional piping is to be relocated they should be noted on the required coordination drawings. If piping is required to be relocated for convenience, that shall be done at no additional cost to the government.

G. QUESTION:

It was mentioned during the second site visit that GSA intends on awarding all Options A through H associated with this contract, please confirm.

The GSA/IRS cannot make this commitment until final pricing is received. It is not immediately known if all options will or can be awarded.

H. QUESTION:

Temporary Boiler Operator Is a licensed operator required to operate the temporary boiler during the cooling tower testing period?

The manufacturer/provider of the temporary boilers would need to send a certified operator to install and run these boilers. They would need to be available during the commissioning process while the boilers are in use.

I. QUESTION:

Curbing Is curbing required between new blacktop and new concrete surfaces?

Blacktop pavement should be at the same grade as the path to the ramp. No curb required here.

J. QUESTION:

Cooling Tower Performance There is a wide range of required capacity between summer & winter duty. The winter duty requires more than double the cooling capacity of the summer duty. Summer Duty requires 6 tower cells to match existing and Winter Duty requires 12 larger cells. Further, leaving water temperature on the winter duty is below the factory recommendation for risk of freezing.

Please clarify.

The performance shall be based on summer conditions. The towers will do what they can for the winter. Flows and temperatures can be modified to obtain a valid selection.

K. QUESTION:

Electrical GFEP Breakers On drawing E101 note 2 and 5 call for 1P30A GFEP breakers to be added in existing panels. Panel 1DH4D1 and 1DH4D2 are I-Line type and the only available GFEP breakers are 3-pole breakers.

Please confirm the direction given on the drawings.

Specified heat trace controller and panel provides adequate ground fault protection.

Standard 30A/1P circuit breakers can be provided in Panelboards 1DH2D1 and 1DH4D2 in lieu of GFEP type.

L. QUESTION:

Electrical-Additional Breakers On drawing E101 and E102 they call for the addition of 1P20A breakers to panel 2U2A1, the Square D record drawings show that the panel is full of breakers.

Please confirm that there is space in the specified panelboard.

Panelboard 2U2A1 was furnished with the remaining spaces provided with spare breakers. Contractor shall utilize existing 20A/1P spare breakers for all required 20A circuits originating at Panelboard 2U2A1.

M. QUESTION:

Electrical-Additional Breakers On drawing E401 they call for the addition of one 1P20A breaker to panel 1R2D3, the record drawings show that the panel is full of breakers.

Please confirm that there is space in the specified panelboard.

Panelboard 1R2D3 was furnished with the remaining spaces provided with spare breakers. Contractor shall utilize existing 20A/1P spare breakers for all required 20A circuits originating at Panelboard 1R2D3.

N. QUESTION:

Electrical-Temporary Power Feed On drawing E802 they ask for temp power feed from MSS-1 and MSS-2, the record drawings show that there are spare breakers that could be used in lieu of adding new 1000A breakers.

Please confirm these are still available and are available for temporary use.

Existing spare breakers in MSS-1 and MSS-2 are Masterpact, and can be utilized in lieu of adding new 1000A breaker. Contractor shall provide new 1000A trip unit in existing spare as spare breakers currently contain 800A trip units.

O. QUESTION:

In reference Spec Section 013600.

Could it be clarified whether the government will be issuing the necessary, properly formatted COBie design files to the contractor immediately after award?

Could the software programs linked in the existing COBie file be listed in advance?

Since it is unknown how many corrections or changes may be needed to bring the format of the design file up to qualify standards indicated in the specifications, could this handled as an time and material allowance?

This specification section will be deleted from this project as COBie will not be used on this project.

In lieu of using the COBie system, GSA/IRS is requesting the attached Microsoft Excel Spreadsheet 'GDI Info - IRS CT Replacement'.xls be filled out in its entirety before the completion of the project. This is simply to provide data on the newly installed equipment like serial numbers, date of manufacture etc.

P. QUESTION:

Follow-up request regarding Paint Specifications:

Please confirm or clarify if the following items are to be painted:

09911309911 3.3 E & 3.6 According to the Schedule the following exterior elements are to be painted:

-- Concrete Cooling Tower foundations, above grade and below the cooling towers -- Concrete ramp up to the cooling tower platform lever -- The galvanized cooling tower platform and handrails -- Steel or galvanized anchor bolts -- The FRP grating on the cooling tower platform -- Any electrical panel boards, load Centers or Switchboards -- Plastic piping and conduit -- Metal conduit

REVISED: None of the items referred to in this question need to be painted.

Q. QUESTION:

Follow-up request regarding Paint Specifications:

09912309911 Section 1.2 A includes concrete, steel and iron, galvanized material copper, stainless steel fiberglass, plastic, etc. All of this, not specifically specified in the following sections is existing.

How much of the existing is to be painted?

Sections 3.3 E & 3.6 According to the Schedule the following interior elements are to be painted:

Exposed work in equipment rooms:

-- Equipment, including panelboards and switch gear -- Electrical gear in the new substation Option H -- Metal conduit -- Plastic conduit -- Pipe hangars and supports -- Tanks without factor finishes -- Duct, equipment and pipe insulation having cotton or canvas covering or other paintable jacket material -- What about the new VFDs not included in the paint schedule

REVISED: None of the items referred to in the question need to be painted.

R. QUESTION:

Soils at Structural Slab Page 3-4 of the Geo-Tech report states that “The onsite soils are not suitable for use as backfill.”

Is this at the structural slab only or does this include all the utility trenches?

On-site soils are not suitable for use as backfill for the structural slab and for utilities under the structural slab. For other utilities, per 4-1 of the Geo-Tech Report "the natural sandy soils are suitable for use as fill at the site." Naturally these materials would have to be separated out.

S. QUESTION:

Document 003133 Geotechnical Investigation and Engineering Report is included in the project manual but is not referenced on the Specification Matrix.

Geotechnical Investigation and Engineering Report shall be incorporated into the Specification Matrix by reference.

T. QUESTION:

Please confirm Allowance #3 for testing and inspections is to be used to cover all testing included in the contract documents, not only testing designated as Owner testing.

This was intended for Owner Testing only.

U. QUESTION:

Please clarify what is intended on drawing C501 under “Construction Sequence” where the construction time is indicated as approximately three months.

Revise Construction Time to 12 months.

V. QUESTION:

Cement Curb Drawing C502 Detail- Portland cement curb, reflects a detail where a concrete curb is shown between the new gravel and grass areas. The Civil drawings do not reflect the extent of this curb or locations where it may be required.

Please provide directive on if the curb is required and if so please indicate where it is required?

See Drawings C202, C203 and C204. A short length of 5 feet of curb is called for to guard the hydrant on the north side of the cooling tower.

W. QUESTION:

U/G Pipe and Fittings Drawing C502 reflects details for thrust blocks and buttresses for mechanical joint type pipe and fittings. Underground piping specification section 232113.13 3.2 calls out all butt welded joint, carbon steel, schedule 80 pipe and fittings.

Is the new underground pipe and fittings to be a different material than specified? If so please provide specifications for the piping and fittings required?

No. The underground pipe and fittings will be as specified. Use anchoring system per manufacturer's installation instructions.

X. QUESTION:

Buttresses / Thrust Blocks Drawing M405 Detail 1 Note 19 references Drawing C502 for thrust blocks/buttresses for the new condenser water piping. Underground piping specification section 232113.13

3.2 calls out all butt welded joint, carbon steel, schedule 80 pipe and fittings.

If the new Condenser water piping is per the specifications are concrete buttresses/thrust blocks still required?

Use anchoring system per manufacturer's installation instructions.

Y. QUESTION:

Soil Fill - Specification Section 312000, 3.13 SOIL FILL, B 3 thru 5 Engineered fill is defined as: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940/D 2940M; with at least 90 percent passing a 1-1/2-inch (37.5-mm) sieve and not more than 12 percent passing a No. 200 (0.075-mm) sieve. On-site soils or shale shall not be used in engineered fill.

The quantity of borrow is extensive; can local shale materials be used at any of the fill depths?

Material with larger gradation up to 4-inch diameter which can be readily placed in loose 6 inch layers can be used for fills greater than 24 inches below the slab subgrade elevation. Local shale materials containing pyrite are prohibited.

Z. QUESTION:

Shallow Foundations - Per Specification Section 003133, Article 3.3, Paragraph 2 and 3 It is noted that Boring B-5 shows this condition even shallower. Judging from Borings B- 3, B-4 and B-5 it appears that Drawing C502 may involve a larger undercut at the entire footprint of the cooling tower pad.

How far beyond that footprint should be replaced?

Replace a minimum of 12 inches outside of the footing.

topmostSubform[0]:
Page1[0]:
AmendmentNo[0]: 0009
Code[0]: 3PQCV
Code[1]:
AccountingData[0]:
A13[0]:
C13[0]:
D13[0]:
NameandTitleSigner[0]:
NameandTitleOfficer[0]:
Description[0]: Cooling Tower Replacement Project

Internal Revenue Service - Enterprise Computing Center 250 Murall Drive, Kearneysville WV 25430

See attached supplemental pages for details of this amendment.

FacilityCode[0]:
Code[2]: 3PQCV
IssuedBy[0]: General Services Administration

Contract Operations Branch - VA & WV Section 100 S. Independence Mall West Philadelphia, PA 19106

NameandAddress[0]:
AdministeredBy[0]: General Services Administration

Contract Operations Branch - VA & WV Section 100 S. Independence Mall West Philadelphia, PA 19106

ContractIDCode[0]:
ReqNumber[0]:
AmendmentNo[1]: GS-03-P-15-DX-C-7004
ModificationNo[0]:
ProjectNo[0]:
Page[0]: 1
Pages[0]: 11
EffectiveDate[0]: 05/03/2016
Dated9B[0]: 24 March 2016
Dated10B[0]:
CheckBox9[0]: Off
CheckBox10[0]: Off
CheckBox11[0]: 1
CheckBox13A[0]: Off
CheckBox13B[0]: Off
CheckBox13C[0]: Off
CheckBox13D[0]: Off
IsNot[0]: Off
Is[0]: Off
Extended[0]: Off
NotExtended[0]: 1
2016-05-03T17:20:33-0400
TRACY MEISTER
DateSigned[0]:
DateSigned[1]: 05/03/2016
Copies[0]: 1
CopiesReturned[0]:

File details come from the government source that posted it. Updated .