RESTORATION OF BACKFILL SPACE PROJECT NO. SNY00021
DANIEL PATRICK MOYNIHAN U.S. COURTHOUSE GSA-PBS, REGION 2
NEW YORK, NY
Section 00200-1
General Decision Number: NY120003 10/26/2012 NY3
Superseded General Decision Number: NY20100003
State: New York
Construction Types: Building, Heavy, Highway and Residential
Counties: Bronx, Kings, New York, Queens and Richmond
Counties in New York.
BUILDING & RESIDENTIAL CONSTRUCTION PROJECTS (includes single family homes and apartments up to and including 4 stories), HEAVY AND HIGHWAY CONSTRUCTION PROJECTS
Modification Number Publication Date
0 01/06/2012
1 01/13/2012
2 02/10/2012
3 02/17/2012
4 03/16/2012
5 03/23/2012
6 04/06/2012
7 05/04/2012
8 05/11/2012
9 05/25/2012
10 06/01/2012
11 06/15/2012
12 06/29/2012
13 07/06/2012
14 07/20/2012
15 08/03/2012
16 09/14/2012
17 10/05/2012
18 10/26/2012
ASBE0012-001 01/02/2012
Rates Fringes
Asbestos Workers/Insulator
Includes application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems.....................$ 61.08 26.59
HAZARDOUS MATERIAL HANDLER.......$ 30.00 9.10
BOIL0005-001 01/01/2012
Section 00200-2
BOILERMAKER......................$ 47.98 32%+21.75+a
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Thanksgiving Day, Memorial
Day, Independence Day, Labor Day and Good Friday, Friday after Thanksgiving, Christmas Eve Day and New Year's Eve
BRNY0001-001 07/01/2011
BRICKLAYER.......................$ 51.54 22.19
MASON - STONE....................$ 58.86 25.61
BRNY0001-002 06/01/2011
Pointer, cleaner and caulker.....$ 37.55 26.10
BRNY0004-001 01/01/2011
MARBLE MASON.....................$ 51.53 25.60
BRNY0007-001 01/01/2011
TERRAZZO FINISHER................$ 42.86 28.55
TERRAZZO WORKER/SETTER...........$ 44.39 28.55
BRNY0020-001 01/01/2011
MARBLE FINISHER..................$ 42.20 24.93
BRNY0024-001 07/01/2012
BRICKLAYER
MARBLE POLISHERS............$ 38.03 20.90
BRNY0052-001 12/05/2011
Tile Layer.......................$ 49.64 26.91
BRNY0088-001 12/05/2011
Section 00200-3
TILE FINISHER....................$ 39.28 23.91
CARP0001-009 07/01/2008
Carpenters:
Carpenters & Soft floor layers......................$ 43.02 35.96
CARP0740-001 07/01/2010
MILLWRIGHT.......................$ 46.19 44.93
CARP1456-004 01/01/2011
Dock Builder & Piledrivermen
DOCKBUILDERS................$ 46.21 38.36
CARP1456-005 01/01/2011
Diver Tender.....................$ 41.16 38.46
Diver............................$ 58.01 38.46
CARP1536-001 10/01/2010
Carpenters:
TIMBERMEN...................$ 42.63 31.32
ELEC0003-001 11/09/2011
ELECTRICIAN
Electricians................$ 51.00 23.672
Jobbing, and maintenance and repair work.............$ 25.30 15.13+a
PAID HOLIDAYS:
a. New Years Day, Martin Luther King, Jr.'s Birthday, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Election Day, Thanksgiving Day, the day after Thanksgiving Day, and Christmas Day
Section 00200-4
ELEC1049-001 04/06/2008
QUEENS COUNTY
Line Construction (Substation and Switching structures pipe type cable installation and maintenance jobs or projects;
Railroad electrical distribution/transmission systems maintenance (when work is not performed by railroad employees) Overhead and Underground transmission/distribution line work. Fiber optic, telephone cable and equipment)
Groundman...................$ 24.83 17.91
Heavy Equipment Operator....$ 33.10 17.91
Lineman and Cable Splicer...$ 41.38 17.91
Tree Trimmer................$ 23.06 9.84
ELEV0001-002 03/17/2012
ELEVATOR MECHANIC
Elevator Constructor........$ 55.20 26.105+a+b
Modernization and Repair....$ 43.79 25.955+a+b
a. PAID HOLIDAYS: New Year's Day, Good Friday, President's
Day, Memorial Day, Independence Day, Labor Day, Columbus
Day, Veteran's Day, Thanksgiving Day, Friday after
Thanksgiving, and Christmas Day.
b. PAID VACATION: An employee who has worked less than 5 years shall recieve vacation pay credit on the basis of 4% of his hourly rate for all hours worked; an employee who has worked 5 to 15 years shall receive vacation pay credit on the basis of 6% of his hourly rate for all hours worked;
an employee who has worked 15 or more years shall receive vacation pay credit on the basis of 8% of his hourly rate for all hours worked.
ENGI0014-001 07/01/2012
Pavement equipment operator
Asphalt Plants..............$ 51.32 25.88+a
Section 00200-5
Asphalt roller..............$ 60.85 25.88+a
Asphalt spreader............$ 62.51 25.88+a
Power Equipment Operator
(HEAVY & HIGHWAY)
GROUP 1....................$ 81.09 25.88
GROUP 10...................$ 58.43 25.88
GROUP 11...................$ 54.50 25.88
GROUP 12...................$ 55.73 25.88
GROUP 13...................$ 56.19 25.88
GROUP 14...................$ 42.11 25.88
GROUP 15...................$ 39.03 25.88
GROUP 2....................$ 66.70 25.88
GROUP 3....................$ 68.86 25.88
GROUP 4....................$ 67.21 25.88
GROUP 5....................$ 65.86 25.88
GROUP 6....................$ 63.18 25.88
GROUP 7....................$ 64.38 25.88
GROUP 8....................$ 62.51 25.88
GROUP 9....................$ 61.14 25.88
Steel erector
Compressors, Welding
Machines....................$ 39.86 24.15
Cranes, Hydraulic Cranes, 2 drum derricks, Forklifts, Boom Trucks......$ 67.71 24.15
Three drum derricks.........$ 70.50 24.15
Utility Laborer
Horizontal Boring Rig.......$ 56.24 24.15
Off shift compressors.......$ 46.38 24.15
Utility Compressors.........$ 36.37 24.15
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Tower crane
GROUP 2: Backhoes, power shovel, Hydraulic clam shells, moles and machines of a similar type
GROUP 3: Mine hoists and crane, etc. used as mine hoists
GROUP 4: Gradalls, keystones, cranes (with digging buckets), bridge cranes, trenching machines, vermeer cutter and machines of a similar nature
GROUP 5: Piledrivers, derrick boats, tunnel shovels
GROUP 6: All drills, and machines of a similar nature
GROUP 7: Back filling machines, cranes, mucking machines, dual drum pavers
GROUP 8: Mixers (concrete w/loading attachments), concrete pavers, cableways, land derricks, power house (low pressure units), concrete pumps
Section 00200-6
GROUP 9: Concrete plants, well drilling machines, stone crushers double drum hoist, power house (other than above)
GROUP 10: Concrete mixers
GROUP 11: Elevators
GROUP 12: Concrete breaking machine, Hoists (single drum), load masters, locomotive and dinkies over 10 tons
GROUP 13: Vibratory console
GROUP 14: Compressors (portable 3 or more in battery), tugger machine (caissons), well point pumps, chum drill
GROUP 15: Boilers, (high pressure, compressors (portable, single, or 2 in battery, not over 100' apart), pumps (river cofferdam and welding machines (except where arc is operated by members of local 15) push button machines, all engines irrespective of power (power pac) used to drive auxilliary equipment, air, hydraulic etc.
PREMIUMS ON CRANES (Crawler or Truck):
100' to 149' boom - add .50
150' to 249' boom - add .75
250' to 349' boom - add 1.00
350' to 450' boom - add 1.50
Premiums for Cranes on Steel Erection:
100' to 149' boom - add 1.75
150' to 249' boom - add 2.00
250' to 349' boom - add 2.25
350' to 450' boom - add 2.75
Tower crane - add 2.00
a. Paid Holidays: New Year's Day; Lincoln's Birthday;
Washington's Birthday; Memorial Day; Independence Day;
Labor Day; Veterans Day; Columbus Day; Election Day;
Thanksgiving Day; and Christmas Day; provided the employee works one day the payroll week in which the holiday occurs.
ENGI0014-002 07/01/2012
Power Equipment Operator
BUILDING & RESIDENTIAL
GROUP 1....................$ 58.57 24.15
GROUP 2....................$ 62.15 24.15
GROUP 3....................$ 61.06 24.15
GROUP 4....................$ 55.46 24.15
GROUP 5....................$ 41.32 24.15
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
Section 00200-7
GROUP 1: Double drum
GROUP 2: Stone derrick, cranes, hydraulic cranes, boom trucks
GROUP 3: 4 pole Hoist, Single Drum Hoists
GROUP 4: Fork lift, house cars, plaster (platform machine), plaster bucket, concrete pump and all other equipment used for hoisting material
GROUP 5: Compressors, welding machines (cutting concrete work), paint spraying, sand blasting, pumps (with the exclusion of concrete pumps), house car (settlement basis only), all engines irrespective of power (power pac) used to drive auxiliary equipment, air, hydraulic, etc., boilers
Premiums for Cranes:
100'-149' boom - add 1.75
150'-249' boom - add 2.00
250'-349' boom - add 2.25
350'-450' boom - add 2.75
Tower cranes add 2.00
a. PAID HOLIDAYS: New Year's Day, Lincoln's Birthday, Memorial Day, Independence Day, Labor Day, Veteran's Day, Columbus Day, Election Day, Thanksgiving Day, and Christmas
Day, provided the employee works one day in the payroll week in which the holiday occurs
IRON0040-002 07/01/2012
BRONX, NEW YORK, RICHMOND
IRONWORKER, STRUCTURAL...........$ 45.55 49.15
IRON0046-003 07/01/2011
IRONWORKER
METALLIC LATHERS AND
REINFORCING IRONWORKERS.....$ 40.00 24.97
IRON0197-001 07/01/2012
IRONWORKER
STONE DERRICKMAN............$ 40.50 35.93
Section 00200-8
IRON0361-002 07/01/2012
KINGS, QUEENS
Ironworkers:
(STRUCTURAL)................$ 45.55 49.15
IRON0580-001 07/01/2012
IRONWORKER, ORNAMENTAL...........$ 41.50 40.62
LABO0006-001 07/01/2011
Laborers:
BUILDING CONSTRUCTION
CEMENT AND CONCRETE
WORKERS....................$ 38.98 26.08
LABO0029-001 07/01/2012
Heavy
Blasters (hydraulic trac drill).....................$ 41.30 29.25
Blasters...................$ 40.55 29.25
Hydraulic Trac Drill.......$ 29.92 29.25
Jackhammers, Chippers, Spaders, Concrete
Breakers, All Other
Pneumatic Tools, Walk
Behind Self-Propelled
Hydraulic Asphalt and
Concrete Breaker...........$ 34.64 29.25
Powder Carriers............$ 31.08 29.25
Wagon; Airtrac; Quarry
Bar Drill Runners..........$ 35.07 28.00
LABO0078-001 12/01/2011
LABORERS
BUILDING CONSTRUCTION
ASBESTOS (Removal, Abatement, Encapsulation or Decontamination of asbestos); LEAD; &
Section 00200-9
HAZARDOUS WASTE LABORERS
(Hazardous Waste, Hazardous Materials, Biochemical and Mold
Remediation, HVAC, Duct
Cleaning, Re-spray
Fireproofing, etc).........$ 35.10 14.85
LABO0079-001 07/01/2012
Laborers Building Construction
Demolition Laborers
Tier A.....................$ 33.37 17.97
Tier B.....................$ 22.67 12.18
Mason Tenders...............$ 32.99 20.56
CLASSIFICATIONS
TIER A: Responsible for the removal of all interior petitions and structural petitions that can consist of sheet rock, block or masonry. Also, all structural slab openings for ducts, mechanical, shafts, elevators, slab openings and exterior walls where the building is not being completely demolitioned.
TIER B: Responsible for shoveling of debris into containers, pushing containers from the inside to the outside of the building.
LABO0147-001 07/01/2003
LABORERS (FREE AIR & TUNNEL).....$ 28.86 30.51
Maintenance Men, Inside Muck Lock Tenders, Pump Men, Electricians, Cement Finishers, Caulkers, Hydraulic Men, Shield Men, Monorail Operators, Motor Men, Conveyor Men, Powder Carriers, Pan Men, Riggers, Chuck Tenders, Track Men
Painters, Nippers, Brakemen, Cable Men, Hose Men, Grout
Men, Gravel Men, Form Workers, Concrete Workers, Tunnel
Laborers, Mole Nipper (one (1) Mole Sipper per Working
Shaft per Shift for up to and including Two (2) Moles
LABO0731-001 07/01/2011
Building, Heavy and
Residential Construction
UNSKILLED..................$ 38.20 30.27
UTILITY LABORER............$ 38.05 30.27
Section 00200-10
Heavy & Highway
Construction
LABORER/EXCAVATION
{Asbestos, Lead, Hazardous Waste Removal
(including soil)..........$ 36.64 26.21
Paid Holidays: Labor Day and Thanksgiving Day
LABO1010-001 07/01/2011
HIGHWAY CONSTRUCTION
Fence Installer & Repairer.$ 38.34 30.25
FORMSETTERS................$ 42.21 30.25
LABORERS...................$ 38.34 30.25
Landscape Planting &
Maintenance................$ 38.34 30.25
Maintenance Safety Surface.$ 38.34 30.25
Slurry/Sealcoater/Play
Equipment Installer........$ 38.34 30.25
Small Equipment Operator
(Not Operating
Engineer)..................$ 28.94 15.55+a
Small Equipment Operator
(Not Operating Engineer)...$ 38.34 30.25
Small Power Tools Operator.$ 38.34 30.25
FOOTNOTES:
a. PAID HOLIDAYS: Memorial Day, Fourth of July, Labor Day, Columbus Day, Election Day and Thanksgiving Day, provided the employee has worked one (1) day in the calendar week in which the said holiday occurs.
LABO1010-002 07/01/2011
Laborers-Asphalt Construction:
Micro Paver.................$ 44.86 30.25
Raker.......................$ 44.37 30.25
Screedperson................$ 44.86 30.25
Shoveler (Production
Paving Only)................$ 41.08 30.25
Small Equipment Operator
(Asphalt)...................$ 41.08 30.25
* PAIN0009-001 05/01/2012
GLAZIER..........................$ 40.00 32.89
Section 00200-11
Painters:
Painters, Drywall
Finishers, Lead Abatement
Worker......................$ 35.00 20.64
Spray, Scaffold and
Sandblasting................$ 38.00 20.64
PAIN0806-001 10/01/2012
Structural Steel and Bridge.$ 47.00 32.08
PAIN1974-001 06/27/2012
Drywall Tapers/Pointers.....$ 43.32 22.01
PLAS0262-001 02/01/2012
BRONX, NEW YORK AND RICHMOND COUNTIES:
PLASTERER........................$ 40.78 26.80
PLAS0262-002 02/01/2012
KINGS AND QUEENS COUNTIES
PLASTERER........................$ 40.78 26.80
PLAS0530-001 08/03/2005
PLASTERER
DRYWALL PLASTERERS..........$ 37.03 18.30
PLAS0780-001 07/01/2012
CEMENT MASON/CONCRETE FINISHER...$ 44.63 38.95
* PLUM0001-001 10/01/2012
PLUMBER
Section 00200-12
MECHANICAL EQUIPMENT AND
SERVICE
Any repair and/or replacement of the present plumbing system that does not change the existing roughing..........$ 33.21 16.05
PLUMBERS:...................$ 52.36 37.06
PLUM0638-001 06/27/2012
PLUMBER
SERVICE FITTERS.............$ 26.30 2.55
SPRINKLER FITTERS,
STEAMFITTERS................$ 51.25 49.54
Service Fitter work shall consist of all repair, service and maintenance work on domestic, commercial and industrial refrigeration, air conditioning and air cooling, stoker and oil burner apparatus and heating apparatus etc., including but not exclusively the charging, evacuation, leak testing and assembling for all machines for domestic, commercial and industrial refrigeration, air conditioning and heating apparatus. Also, work shall include adjusting, including capacity adjustments, checking and repairing or replacement of all controls and start up of all machines and repairing all defects that may develop on any system for domestic, commercial and industrial refrigeration and all air conditioning, air cooling, stoker and oil burner apparatus and heating apparatus regardless of size or type.
ROOF0008-003 06/01/2010
ROOFER...........................$ 37.75 28.86
SHEE0028-002 09/15/2011
SHEET METAL WORKER
BUILDING CONSTRUCTION.......$ 48.90 36.00
RESIDENTIAL CONSTRUCTION....$ 27.22 16.48
TEAM0282-001 07/01/2012
Truck drivers:
TRUCK DRIVERS:
Asphalt....................$ 37.47 38.5525+a
Euclids & Turnapulls.......$ 37.57 38.5525+a
Section 00200-13
High Rise..................$ 42.00 36.9125+a
FOOTNOTES:
PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Election Day, Veterans' Day (Armistice Day), Thanksgiving Day, Day after
Thanksgiving and Christmas Day. Employees working two (2) days in the calendar week in which a holiday falls are to be paid for such holiday, provided that they shape each remaining workday during such calendar week.
TEAM0813-001 12/01/1998
Truck drivers:
GROUP 1....................$ 19.49 3.61+a
GROUP 2....................$ 19.76 3.61+a
GROUP 3....................$ 19.90 3.61+a
GROUP 4....................$ 20.23 3.61+a
GROUP 5....................$ 20.40 3.61+a
GROUP 6....................$ 21.29 3.61+a
GROUP 7....................$ 22.40 3.61+a
GROUP 8....................$ 19.90 3.61+a
a. PAID HOLIDAYS: New Year's Day, Martin Luther King, Jr.'s
Birthday, Presidents' Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Thanksgiving Day, Christmas Day, Employee's Birthday, Two (2) Personal Days, and any holiday or day of mourning proclaimed as such by the State or
Federal Government.
TRUCK DRIVER CLASSIFICATIONS
GROUP 1: Closed body trucks with self contained loading unit up to and including 22 yard capacity
GROUP 2: Open trucks, rack body or trucks with no self contained mechanical loading device, up to 22 yard capacity. One-container tractor hoist
GROUP 3: 10 wheel, open trucks, container loaders, dino-master, over-cab loaders, rack body trucks, or any trucks 22 yards to and including 25 yards capacity
GROUP 4: Rubbish and garbage trucks, 26 yards to and including 31 yards
GROUP 5: Single axle working non-compactor containers up to
15 yards capacity on rubbish and garbage removal
Section 00200-14
GROUP 6: Roll-off trucks up to and including 42 yard capacity
GROUP 7: Roll-off truck with more than 42 yard capacity or any tractor trailer trucks
GROUP 8: One-container tractor hoist on construction and alteration debris removal
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.
Union Identifiers
An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be
July 1, 2011 in the above example.
Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rate.
0000/9999: weighted union wage rates will be published annually each January.
Section 00200-15
Non-Union Identifiers
Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007
5/13/2010. SU indicates the rates are not union rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.
Survey wage rates will remain in effect and will not change until a new survey is conducted.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the
Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Section 00200-16
Wage and Hour Administrator
U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
File details come from the government source that posted it. Updated .