Section_J.5_Attachment_(5)_OASIS_Self_Scoring_Worksheet_(SAMPLE_ONLY).xlsx
XLSX spreadsheet 22 KB Posted
- Solicitation number
- GS00Q-13-DR-0001-P1P3P4
About this file
Section J.5 Attachment (5) OASIS Self Scoring Worksheet (SAMPLE ONLY)
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OASIS SELF-SCORING WORKSHEET
| OASIS SOLICITATION No. GS00Q-13-DR-0001-P1P3P4 |
| ON-RAMP POOLS 1, 3 & 4 |
| SECTION J.5. Attachment (5) |
SAMPLE SELF SCORING WORKSHEET
| OFFEROR NAME: ACME CORPORATION | |||||
| Section | Scored Evaluation Criteria | Point Value | Enter YES or NO for each question as applicable | Score | These notes are for sample purposes only. The Offeror must not add notes to their Section J.5.1. Att. (5A) |
| L.5.3. | VOLUME 3 – RELEVANT EXPERIENCE | ||||
| L.5.3.2.1. | Relevant Experience (Primary) Project under an OASIS NAICS or PSC Code | ||||
| Is EACH Project reported under any NAICS code or PSC Code identified in Section L.5.1.2.? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 150 | YES | 150 | Project 1 was reported under an OASIS SB NAICS Code | |
| Project 2: Task Order No. ABCDEFG-0001 | 150 | YES | 150 | Project 2 was reported under an OASIS SB PSC Code | |
| Project 3: Task Order No. JKLMNOP-0007 | 150 | YES | 150 | Project 3 was reported under an OASIS SB NAICS Code | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 150 | NO | 0 | Project 4 was not reported under an OASIS SB NAICS/PSC Code | |
| Project 5: Task Order No. QRSTUV-0012 | 150 | NO | 0 | Project 5 was not reported under an OASIS SB NAICS/PSC Code | |
| SUBTOTAL SCORE FOR SECTION L.5.3.2.1. ONLY: | 450 | ||||
| L.5.3.2.2. | Relevant Experience (Primary) Project Value | ||||
| Is EACH Project $5M OR MORE on an annual basis but, LESS THAN $10M on an annual basis, including Options? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 25 | YES | 25 | Project 1 was valued at $3M/yr. | |
| Project 2: Task Order No. ABCDEFG-0001 | 25 | NO | 0 | Project 2 was valued at $10M/yr. | |
| Project 3: Task Order No. JKLMNOP-0007 | 25 | NO | 0 | Project 3 was valued at $24M/yr. | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 25 | NO | 0 | Project 4 was valued at $35M/yr. | |
| Project 5: Task Order No. QRSTUV-0012 | 25 | NO | 0 | Project 5 was valued at $60M/yr. | |
| Is EACH Project $10M OR MORE on an annual basis but, LESS THAN $20M on an annual basis, including Options? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 50 | NO | 0 | Project 1 was valued at $3M/yr. | |
| Project 2: Task Order No. ABCDEFG-0001 | 50 | YES | 50 | Project 2 was valued at $10M/yr. | |
| Project 3: Task Order No. JKLMNOP-0007 | 50 | NO | 0 | Project 3 was valued at $24M/yr. | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 50 | NO | 0 | Project 4 was valued at $35M/yr. | |
| Project 5: Task Order No. QRSTUV-0012 | 50 | NO | 0 | Project 5 was valued at $60M/yr. | |
| Is EACH Project $20M OR MORE on an annual basis but, LESS THAN $50M on an annual basis, including Options? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 75 | NO | 0 | Project 1 was valued at $3M/yr. | |
| Project 2: Task Order No. ABCDEFG-0001 | 75 | NO | 0 | Project 2 was valued at $10M/yr. | |
| Project 3: Task Order No. JKLMNOP-0007 | 75 | YES | 75 | Project 3 was valued at $24M/yr. | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 75 | YES | 75 | Project 4 was valued at $35M/yr. | |
| Project 5: Task Order No. QRSTUV-0012 | 75 | NO | 0 | Project 5 was valued at $60M/yr. | |
| Is EACH Project $50M OR MORE on an annual basis, including Options? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 100 | NO | 0 | Project 1 was valued at $3M/yr. | |
| Project 2: Task Order No. ABCDEFG-0001 | 100 | NO | 0 | Project 2 was valued at $10M/yr. | |
| Project 3: Task Order No. JKLMNOP-0007 | 100 | NO | 0 | Project 3 was valued at $24M/yr. | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 100 | NO | 0 | Project 4 was valued at $35M/yr. | |
| Project 5: Task Order No. QRSTUV-0012 | 100 | YES | 100 | Project 5 was valued at $60M/yr. | |
| SUBTOTAL SCORE FOR SECTION L.5.3.2.2. ONLY: | 325 | ||||
| L.5.3.2.3. | Relevant Experience (Primary) Projects with Performance/Integration of Additional Core Disciplines | ||||
| Does EACH Project Integrate AT LEAST 5 out of 6 Core Disciplines BUT NO MORE THAN 5 out of 6 Core Disciplines? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 75 | NO | 0 | Project 1 integrated 3 Core Disciplines | |
| Project 2: Task Order No. ABCDEFG-0001 | 75 | NO | 0 | Project 2 integrated 4 Core Disciplines | |
| Project 3: Task Order No. JKLMNOP-0007 | 75 | NO | 0 | Project 3 integrated 4 Core Disciplines | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 75 | YES | 75 | Project 4 integrated 5 Core Disciplines | |
| Project 5: Task Order No. QRSTUV-0012 | 75 | NO | 0 | Project 5 integrated 6 Core Disciplines | |
| Does EACH Project Integrate ALL 6 out of 6 Core Disciplines? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 100 | NO | 0 | Project 1 integrated 3 Core Disciplines | |
| Project 2: Task Order No. ABCDEFG-0001 | 100 | NO | 0 | Project 2 integrated 4 Core Disciplines | |
| Project 3: Task Order No. JKLMNOP-0007 | 100 | NO | 0 | Project 3 integrated 4 Core Disciplines | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 100 | NO | 0 | Project 4 integrated 5 Core Disciplines | |
| Project 5: Task Order No. QRSTUV-0012 | 100 | YES | 100 | Project 5 integrated 6 Core Disciplines | |
| SUBTOTAL SCORE FOR SECTION L.5.3.2.3. ONLY: | 175 | ||||
| L.5.3.2.4. | Relevant Experience (Primary) Projects with Multiple Locations | ||||
| Does EACH Project have performance in AT LEAST 2 but NO MORE THAN 4 different locations? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 50 | NO | 0 | Project 1 was performed in one location | |
| Project 2: Task Order No. ABCDEFG-0001 | 50 | NO | 0 | Project 2 was performed in one location | |
| Project 3: Task Order No. JKLMNOP-0007 | 50 | NO | 0 | Project 3 was performed in one location | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 50 | YES | 50 | Project 4 was performed in three locations | |
| Project 5: Task Order No. QRSTUV-0012 | 50 | NO | 0 | Project 5 was performed in five locations | |
| Does EACH Project have performance in 5 OR MORE different locations? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 100 | NO | 0 | Project 1 was performed in one location | |
| Project 2: Task Order No. ABCDEFG-0001 | 100 | NO | 0 | Project 2 was performed in one location | |
| Project 3: Task Order No. JKLMNOP-0007 | 100 | NO | 0 | Project 3 was performed in one location | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 100 | NO | 0 | Project 4 was performed in three locations | |
| Project 5: Task Order No. QRSTUV-0012 | 100 | YES | 100 | Project 5 was performed in five locations | |
| SUBTOTAL SCORE FOR SECTION L.5.3.2.4. ONLY: | 150 | ||||
| L.5.3.2.5. | Relevant Experience (Primary) Projects with Subcontracting/Teaming | ||||
| Does EACH Project have Subcontracting/Teaming with AT LEAST 4 separate subcontractors? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 100 | NO | 0 | Project 1 included no subcontracting | |
| Project 2: Task Order No. ABCDEFG-0001 | 100 | NO | 0 | Project 2 included one subcontractor | |
| Project 3: Task Order No. JKLMNOP-0007 | 100 | NO | 0 | Project 3 included no subcontracting | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 100 | YES | 100 | Project 4 included three subcontractors | |
| Project 5: Task Order No. QRSTUV-0012 | 100 | YES | 100 | Project 5 included four subcontractors | |
| SUBTOTAL SCORE FOR SECTION L.5.3.2.5. ONLY: | 200 | ||||
| L.5.3.2.6. | Relevant Experience (Primary) Projects with Ancillary Support Services and Products | ||||
| Does EACH Project have Ancillary Support SERVICES? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 50 | YES | 50 | Project 1 included Ancillary Support Services | |
| Project 2: Task Order No. ABCDEFG-0001 | 50 | YES | 50 | Project 2 included Ancillary Support Services | |
| Project 3: Task Order No. JKLMNOP-0007 | 50 | NO | 0 | Project 3 included no Ancillary Support Services | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 50 | NO | 0 | Project 4 included no Ancillary Support Services | |
| Project 5: Task Order No. QRSTUV-0012 | 50 | YES | 50 | Project 5 included Ancillary Support Services | |
| Does EACH Project have Ancillary Support PRODUCTS? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 50 | YES | 50 | Project 1 included Ancillary Support Products | |
| Project 2: Task Order No. ABCDEFG-0001 | 50 | YES | 50 | Project 2 included Ancillary Support Products | |
| Project 3: Task Order No. JKLMNOP-0007 | 50 | NO | 0 | Project 3 included no Ancillary Support Products | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 50 | NO | 0 | Project 4 included no Ancillary Support Products | |
| Project 5: Task Order No. QRSTUV-0012 | 50 | YES | 50 | Project 5 included Ancillary Support Products | |
| SUBTOTAL SCORE FOR SECTION L.5.3.2.6. ONLY: | 300 | ||||
| L.5.3.2.7. | Relevant Experience (Primary) Projects with Cost-Reimbursement (any type) | ||||
| Are any projects PREDOMINATELY Cost-Reimbursement? SCORING CREDIT IS LIMITED TO A MAXIMUM OF TWO PROJECTS ONLY. Type the word Yes or No in Column D for EACH project. | |||||
| Project 5: Task Order No. QRSTUV-0012 | 100 | YES | 100 | Project 5 was the ony project that was predominately cost-remiburseable. | |
| Project N/A | 100 | NO | 0 | N/A | |
| SUBTOTAL SCORE FOR SECTION L.5.3.2.7. ONLY: | 100 | ||||
| L.5.3.2.8. | Relevant Experience (Primary) Projects with OCONUS Locations | ||||
| Do any projects involve work in an OCONUS Location? SCORING CREDIT IS LIMITED TO A MAXIMUM OF TWO PROJECTS ONLY. Type the word Yes or No in Column D for EACH project. | |||||
| Project 5: Task Order No. QRSTUV-0012 | 100 | YES | 100 | Project 5 was the ony project that included OCONUS work | |
| Project N/A | 100 | NO | 0 | N/A | |
| SUBTOTAL SCORE FOR SECTION L.5.3.2.8. ONLY: | 100 | ||||
| L.5.3.3.1. | Relevant Experience (Secondary) Projects with Mission Spaces | ||||
| Has the Offeror been awarded projects in AT LEAST 2 different Mission Spaces but, NO MORE THAN 2 different Mission Spaces? Type the word Yes or No in Column D | 50 | NO | 0 | The Offeror provided support to 4 different Mission Spaces | |
| Has the Offeror been awarded projects in AT LEAST 3 different Mission Spaces but, NO MORE THAN 3 different Mission Spaces? Type the word Yes or No in Column D | 100 | NO | 0 | ||
| Has the Offeror been awarded projects in AT LEAST 4 different Mission Spaces but, NO MORE THAN 4 different Mission Spaces? Type the word Yes or No in Column D. | 150 | YES | 150 | ||
| Has the Offeror been awarded projects in AT LEAST 5 different Mission Spaces? Type the word Yes or No in Column D. | 200 | NO | 0 | ||
| SUBTOTAL SCORE FOR SECTION L.5.3.3.1. ONLY: | 150 | ||||
| L.5.3.3.2. | Relevant Experience (Secondary) Projects with Multiple Award Contracts/BPAs and Task Orders | ||||
| Has the Offeror has been awarded AT LEAST 2 Multiple Award Contracts but, NO MORE THAN 5 Multiple Award Contracts, with AT LEAST 10 total Task Order Awards combined? Additionally, have AT LEAST 3 Task Orders been awarded under EACH of the Multiple Award Contracts? Type the word Yes or No in Column D for EACH project. | 50 | NO | 0 | The Offeror had been awarded 6 MACS with 28 Task Orders. All MACs had at least two Task Orders each | |
| Has the Offeror has been awarded AT LEAST 5 Multiple Award Contracts but, NO MORE THAN 25 Multiple Award Contracts, with AT LEAST 10 total Task Order Awards combined? Additionally, have AT LEAST 3 Task Orders been awarded under EACH of the Multiple Award Contracts? Type the word Yes or No in Column D for EACH project. | 100 | YES | 100 | ||
| Has the Offeror been awarded AT LEAST 10 Multiple Award Contracts with AT LEAST 50 total Task Order Awards combined? Additionally, have AT LEAST 3 Task Orders must have been awarded under EACH of the Multiple Award Contracts? Type the word Yes or No in Column D for EACH project. | 150 | NO | 0 | ||
| SUBTOTAL SCORE FOR SECTION L.5.3.3.2. ONLY: | 100 | ||||
| L.5.4. | VOLUME 4 – PAST PERFORMANCE | ||||
| L.5.4.1. through L.5.4.3 | Relevant Experience (Primary) Projects (Past Performance) | ||||
| Does EACH Project Average a Past Performance Score between 3.50 and 3.74? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 350 | NO | 0 | Project 1 Past Performance score was 3.81 | |
| Project 2: Task Order No. ABCDEFG-0001 | 350 | NO | 0 | Project 2 Past Performance score was 4.16 | |
| Project 3: Task Order No. JKLMNOP-0007 | 350 | NO | 0 | Project 3 Past Performance score was 4.36 | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 350 | NO | 0 | Project 4 Past Performance score was 4.62 | |
| Project 5: Task Order No. QRSTUV-0012 | 350 | NO | 0 | Project 5 Past Performance score was 4.90 | |
| Does EACH Project Average a Past Performance Score between 3.75 and 3.99? Type the word "Yes" or "No" in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 400 | YES | 400 | Project 1 Past Performance score was 3.81 | |
| Project 2: Task Order No. ABCDEFG-0001 | 400 | NO | 0 | Project 2 Past Performance score was 4.16 | |
| Project 3: Task Order No. JKLMNOP-0007 | 400 | NO | 0 | Project 3 Past Performance score was 4.36 | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 400 | NO | 0 | Project 4 Past Performance score was 4.62 | |
| Project 5: Task Order No. QRSTUV-0012 | 400 | NO | 0 | Project 5 Past Performance score was 4.90 | |
| Does EACH Project Average a Past Performance Score between 4.00 and 4.24? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 450 | NO | 0 | Project 1 Past Performance score was 3.81 | |
| Project 2: Task Order No. ABCDEFG-0001 | 450 | YES | 450 | Project 2 Past Performance score was 4.16 | |
| Project 3: Task Order No. JKLMNOP-0007 | 450 | NO | 0 | Project 3 Past Performance score was 4.36 | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 450 | NO | 0 | Project 4 Past Performance score was 4.62 | |
| Project 5: Task Order No. QRSTUV-0012 | 450 | NO | 0 | Project 5 Past Performance score was 4.90 | |
| Does EACH Project Average a Past Performance Score between 4.25 and 4.49? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 500 | NO | 0 | Project 1 Past Performance score was 3.81 | |
| Project 2: Task Order No. ABCDEFG-0001 | 500 | NO | 0 | Project 2 Past Performance score was 4.16 | |
| Project 3: Task Order No. JKLMNOP-0007 | 500 | YES | 500 | Project 3 Past Performance score was 4.36 | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 500 | NO | 0 | Project 4 Past Performance score was 4.62 | |
| Project 5: Task Order No. QRSTUV-0012 | 500 | NO | 0 | Project 5 Past Performance score was 4.90 | |
| Does EACH Project Average a Past Performance Score between 4.50 and 4.74? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 550 | NO | 0 | Project 1 Past Performance score was 3.81 | |
| Project 2: Task Order No. ABCDEFG-0001 | 550 | NO | 0 | Project 2 Past Performance score was 4.16 | |
| Project 3: Task Order No. JKLMNOP-0007 | 550 | NO | 0 | Project 3 Past Performance score was 4.36 | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 550 | YES | 550 | Project 4 Past Performance score was 4.62 | |
| Project 5: Task Order No. QRSTUV-0012 | 550 | NO | 0 | Project 5 Past Performance score was 4.90 | |
| Does EACH Project Average a Past Performance Score between 4.75 and 5.00? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 600 | NO | 0 | Project 1 Past Performance score was 3.81 | |
| Project 2: Task Order No. ABCDEFG-0001 | 600 | NO | 0 | Project 2 Past Performance score was 4.16 | |
| Project 3: Task Order No. JKLMNOP-0007 | 600 | NO | 0 | Project 3 Past Performance score was 4.36 | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 600 | NO | 0 | Project 4 Past Performance score was 4.62 | |
| Project 5: Task Order No. QRSTUV-0012 | 600 | YES | 600 | Project 5 Past Performance score was 4.90 | |
| SUBTOTAL SCORE FOR SECTION L.5.4.1 through L.5.4.3. ONLY: | 2500 | ||||
| L.5.4.4 | Total Small Business Goals | ||||
| Does EACH project meet or Exceed Total Small Business PercentGoals on U.S Federal Government Projects? Type the word Yes or No in Column D for EACH project. | |||||
| Project 1: Contract No. ABCDEF-15-C-0001 | 200 | YES | 200 | Project 1 exceeded small business goals | |
| Project 2: Task Order No. ABCDEFG-0001 | 200 | YES | 200 | Project 1 exceeded small business goals | |
| Project 3: Task Order No. JKLMNOP-0007 | 200 | YES | 200 | Project 1 exceeded small business goals | |
| Project 4: Contract No. DEFGHI-13-C-0012 | 200 | YES | 200 | Project 1 exceeded small business goals | |
| Project 5: Task Order No. QRSTUV-0012 | 200 | YES | 200 | Project 1 exceeded small business goals | |
| SUBTOTAL SCORE FOR SECTION L.5.4.4 ONLY: | 800 | ||||
| L.5.5. | VOLUME 5 – SYSTEMS, CERTIFICATIONS, AND CLEARANCES | ||||
| L.5.5.1. through L.5.5.10. | Systems, Certifications, and Clearances | ||||
| Does the Offeror have each of the following? Type the word Yes or No in Column D for EACH System, Certification, or Clearance. | |||||
| Approved Purchasing System | 500 | YES | 500 | The Offeror has an Approved Purchasing System | |
| Current FPRA, FPRR, and/or Approved Billing Rates | 200 | NO | 0 | The Offeror does not have Current FPRA, FPRR, and/or Approved Billing Rates | |
| EVMS ANSI/EIA Standard-748 | 200 | NO | 0 | The Offeror does not have EVMS ANSI/EIA Standard-748 | |
| Acceptable Estimating System | 200 | NO | 0 | The Offeror does not have an Acceptable Estimating System | |
| CMMI Continious Representation Capability Level 3 Majority | 100 | NO | 0 | The Offeror has CMMI Maturity Level 4 | |
| CMMI Maturity Level 3 or higher | 200 | YES | 200 | The Offeror has CMMI Maturity Level 4 | |
| ISO 9001:2008 | 200 | NO | 0 | The Offeror does not have ISO 9001:2008 | |
| IS0 17025 | 100 | NO | 0 | The Offeror does not have IS0 17025 | |
| ISO 14001:2004 | 100 | YES | 100 | The Offeror has ISO 14001:2004 | |
| AS9100 | 100 | NO | 0 | The Offeror does not have AS9100 | |
| Secret FCL (If taking credit for Top Secret, answer No to Secret) | 100 | NO | 0 | The Offeror has a Top Secret FCL | |
| Top Secret FCL | 200 | YES | 200 | The Offeror has a Top Secret FCL | |
| SUBTOTAL SCORE FOR SECTIONS L.5.5.1. through L.5.5.10 ONLY: | 1000 | ||||
| TOTAL POINTS SCORED: | 6,350 |