GROUP4-10-R-J037_Specs_Vol_I.pdf

PDF 2 MB Posted

Attached to
Tampa Harbor, Maintenance Dredging, 34 and 43-Foot Project, Hillsborough Bay (HB)
Solicitation number
GROUP4-10-R-J037
Issued by

About this file

GROUP4-10-R-J037 Specifications Volume 1

View the file

Other files

File Type Posted
Group_4-10-R-J037_Revision_0005.pdf PDF
Group_4-10-R-J037_Revision0004.pdf PDF
Group_4-10-R-J037_Revision0003.pdf PDF
Group_4-10-R-J037_Revision0002.pdf PDF
17-026_xyz.7z 7Z file
17-026a.7z 7Z file
17-097.7z 7Z file
Group_4-10-R-J037_Revision_0001.pdf PDF
GROUP4-10-R-J037_Plans.pdf PDF
St-Pete-Hbr-GDR-2017.pdf PDF
Tampa_Harbor_MD_FY17_GDR_updated_15March2017.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GROUP4-10-R-J037

Jacksonville District

Tampa Harbor, Maintenance Dredging 34 and 43-Foot Project, Hillsborough Bay (HB), Ybor Channel, Upper and Lower Sparkman, Port Sutton and East Bay, and St. Petersburg Harbor, Maintenance Dredging, 24-Foot Project, Entrance Channel and Turning Basin

Hillsborough and Pinellas Counties, Florida

Construction Solicitation and Specifications Task Order

27 JUNE 2017

GROUP4-10-R-J037 SF 1442-A1

ADDENDUM TO THE STANDARD FORM 1442

Tampa Harbor, Maintenance Dredging, 34 and 43-Foot Project, Hillsborough Bay (HB), Ybor Channel, Upper and Lower Sparkman, Port Sutton and East Bay, and St. Petersburg

Harbor, Maintenance Dredging, 24-Foot Project, Entrance Channel and Turning Basin, Hillsborough and Pinellas Counties, Florida

SPECIAL NOTIFICATION: THIS OPPORTUNITY IS AVAILABLE ONLY TO THE FOLLOWING

CONTRACTORS AWARDED A CONTRACT UNDER SOLICITATION NUMBER

W912EP-10-R-0026: Orion Marine Construction (W912EP-13-D-0003); Cavache, Inc.

(W912EP-13-D-0004); Cashman Dredging & Marine Contracting (W912EP-13-D-0005);

Cottrell Contracting Corporation (W912EP-13-D-0006); Great Lakes Dredge & Dock Company, LLC (W912EP-13-D-0007); Dutra Dredging Company (W912EP-13-D-0008);

Marinex Construction, Inc. (W912EP-13-D-0009); Norfolk Dredging Company (W912EP-13- D-0010); Mike Hooks, Inc. (W912EP-13-D-0011); Weeks Marine, Inc. (W912EP-13-D-0012);

Southern Dredging Co., Inc. (W912EP-13-D-0013); Manson Construction Company (W912EP-13-D-0014); C. F. Bean LLC (W912EP-13-D-0015) PROPOSALS WILL NOT BE

CONSIDERED FROM ANY ENTITY OTHER THAN THE PREVIOUSLY LISTED FIRMS

INCLUDED IN THE Group 4 Dredging MATOC Pool.

TECHNICAL EVALUATION: The award of the task order will be made on the basis of Lowest Price, Technical Acceptable (LPTA); the technical evaluation factors are:

(1) Availability of technically acceptable dredge(s).

(2) Past performance, to include the MATOC (The government reserves the right to obtain copies of all Contractor Performance Assessment Reporting System (CPARS) records contained in the US Army Corps of Engineers CPARS database for the Prime Contractor (Offeror) and all Major Sub-Contractors).

SUBMISSION REQUIREMENTS: Contractors are required to submit the following:

(1) A letter on company letterhead identifying the dredge(s) the contractor proposes to do the work and the location of dredge(s). The identified dredge(s) must also have been found technically acceptable by the Contracting Officer prior to the proposal due date.

(2) Completed Bid Schedule (see Section 00010A)

(3) Bid Guarantee per Section 00700, Clause 52.228-1 and Section 00100A, Paragraph 2.4(c) of the MATOC

(4) Completed “Addendum to the Standard Form 1442 with the latest revision”.

(5) Revisions – Offers must acknowledge receipt of this Revision by completing “Notice to Offerors--Blocks 14, 15 and 20” of each revision.

THE FOLLOWING INFORMATION IS APPLICABLE ONLY TO THIS TASK ORDER:

Block 9 -- For additional information contact:

Tonya M. Rogers 904-232-1084 Tonya.M.Rogers@usace.army.mil.

Block 10 -- Magnitude of Construction is between $5,000,000.00 and $10,000,000.00.

GROUP4-10-R-J037 SF 1442-A2

Block 11 -- The Contractor shall begin performance within 45 calendar days and complete it within 180 calendar days after receiving notice to proceed. This performance period is mandatory. NOTE: If there are optional line items, refer to FAR 52.211-10 for breakdown of period of performance.

Block 12 -- The contractor must furnish any required performance and payment bonds within 10 calendar days after award of the task order.

Block 13 -- Sealed offers to perform the work required shall be delivered to the following address not later than July 25, 2017 at 2:00 P.M. Local Time.

USA Engineer District, Jacksonville Contracting Division 701 San Marco Blvd Jacksonville, Florida 32207-8175

NOTICE TO OFFERORS: Offerors are to complete Blocks 14, 15, and 20 below:

Block 14 -- Name and Address of Offeror (including Zip Code):

DUNS: ___________________ CAGE: _______________

Block 15 -- Telephone No. (include area code): _____________________

Block 20 -- Name and Title of Person Authorized to Sign Offer (type or print):

Type/Print ________________________________________________

Signature: ________________________________________________ e-Mail: ________________________________________________

Offer Date: _______________________________________________

Block 26 -- This Task Order will be administered by:

Tampa Resident Office 4211 W. Boy Scout Blvd Suite 170 Tampa, FL 33607-5767

Block 27 -- Payment will be made by:

USACE Finance Center 5722 Integrity Drive

ATTN: CEFC-AO-P

Millington, TN 38054-5005

SECTION 00010A

LINE ITEMS AND PRICING SCHEDULE

TAMPA HARBOR, MAINTENANCE DREDGING, 34-FOOT AND 43-FOOT PROJECT

ST. PETERSBURG HARBOR MAINTENANCE DREDGING, 24-FOOT PROJECT

HILLSBOROUGH AND PINELLAS COUNTIES, FLORIDA

GROUP4-10-R-J037 00010A-1 DRAFT

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

BASE

TAMPA HARBOR

UPPER AND LOWER SPARKMAN,

PORT SUTTON AND EAST BAY

0001 MOBILIZATION AND DEMOBILIZATION 1 JOB $_______________

0002 EXCAVATION, UNCLASSIFIED

(ESTIMATED QUANTITY - SEE NOTE 4) 141,000 CUBIC YARD $___________ $_______________

0003 TURBIDITY MONITORING 1 JOB $_______________

0004 ENDANGERED SPECIES OBSERVERS 1 JOB $_______________

0005 MOBILIZATION AND DEMOBILIZATION FOR 1 JOB $_______________

SEA TURTLE TRAWLING AND RELOCATION

(HOPPER DREDGES ONLY) (SEE NOTE 5)

0006 SEA TURTLE TRAWLING AND RELOCATION 1 DAY $______________ $_______________

(HOPPER DREDGES ONLY) (SEE NOTES 5 & 6)

0007 STANDBY TIME (SEE NOTES 7 & 8) 24 HOUR $______________ $_______________

0008 BIRD MONITORING 1 JOB $______________ $_______________

TOTAL BASE (LINE ITEMS 0001 THROUGH 0008) $_______________

OPTION A

UPPER SPARKMAN STA. 73+50

TO YBOR STA. 40+00

0009 EXCAVATION, UNCLASSIFIED

(ESTIMATED QUANTITY - SEE NOTE 4) 19,000 CUBIC YARD $___________ $_______________

0010 TURBIDITY MONITORING 1 JOB $_______________

0011 ENDANGERED SPECIES OBSERVERS 1 JOB $_______________

0012 MOBILIZATION AND DEMOBILIZATION FOR 1 JOB $_______________

SEA TURTLE TRAWLING AND RELOCATION

(HOPPER DREDGES ONLY) (SEE NOTE 5)

0013 SEA TURTLE TRAWLING AND RELOCATION 1 DAY $______________ $_______________

(HOPPER DREDGES ONLY) (SEE NOTES 5 & 6)

0014 STANDBY TIME (SEE NOTES 7 & 8) 24 HOUR $______________ $_______________

0015 BIRD MONITORING 1 JOB $______________ $_______________

TOTAL OPTION A (LINE ITEMS 0009 THROUGH 0015) $_______________

TOTAL BASE AND OPTION A (LINE ITEMS 0001 THROUGH 0015) $_______________

(CONTINUED ON NEXT PAGE)

TAMPA HARBOR, MAINTENANCE DREDGING, 34-FOOT AND 43-FOOT PROJECT

ST. PETERSBURG HARBOR MAINTENANCE DREDGING, 24-FOOT PROJECT

HILLSBOROUGH AND PINELLAS COUNTIES, FLORIDA

GROUP4-10-R-J037 00010A-2 DRAFT

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

OPTION B

ST. PETE HARBOR TURNING BASIN

0016 INTERIM MOBILIZATION 1 JOB $_______________

0017 EXCAVATION, UNCLASSIFIED

(ESTIMATED QUANTITY - SEE NOTE 4) 78,000 CUBIC YARD $___________ $_______________

0018 TURBIDITY MONITORING 1 JOB $_______________

0019 ENDANGERED SPECIES OBSERVERS 1 JOB $_______________

0020 MOBILIZATION AND DEMOBILIZATION FOR 1 JOB $_______________

SEA TURTLE TRAWLING AND RELOCATION

(HOPPER DREDGES ONLY) (SEE NOTE 5)

0021 SEA TURTLE TRAWLING AND RELOCATION 1 DAY $______________ $_______________

(HOPPER DREDGES ONLY) (SEE NOTES 5 & 6)

0022 STANDBY TIME (SEE NOTES 7 & 8) 24 HOUR $______________ $_______________

0023 BIRD MONITORING 1 JOB $______________ $_______________

TOTAL OPTION B (LINE ITEMS 0016 THROUGH 0023) $_______________

TOTAL BASE AND OPTIONS A AND B (LINE ITEMS 0001 THROUGH 0023) $_______________

OPTION C

ST. PETE HARBOR ENTRANCE CHANNEL

STA. 56+00 TO STA. 60+00

0024 EXCAVATION, UNCLASSIFIED 9,000 CUBIC YARD $___________ $_______________

(ESTIMATED QUANTITY - SEE NOTE 4)

0025 TURBIDITY MONITORING 1 JOB $_______________

0026 ENDANGERED SPECIES OBSERVERS 1 JOB $_______________

0027 MOBILIZATION AND DEMOBILIZATION FOR 1 JOB $_______________

SEA TURTLE TRAWLING AND RELOCATION

(HOPPER DREDGES ONLY) (SEE NOTE 5)

0028 SEA TURTLE TRAWLING AND RELOCATION 1 DAY $______________ $_______________

(HOPPER DREDGES ONLY) (SEE NOTES 5 & 6)

0029 STANDBY TIME (SEE NOTES 7 & 8) 24 HOUR $______________ $_______________

0030 BIRD MONITORING 1 JOB $______________ $_______________

TOTAL OPTION C (LINE ITEMS 0024 THROUGH 0030) $_______________

TOTAL BASE PLUS OPTIONS A, B AND C (LINE ITEMS 0001 THROUGH 0030) $_______________

TAMPA HARBOR, MAINTENANCE DREDGING, 34-FOOT AND 43-FOOT PROJECT

ST. PETERSBURG HARBOR MAINTENANCE DREDGING, 24-FOOT PROJECT

HILLSBOROUGH AND PINELLAS COUNTIES, FLORIDA

GROUP4-10-R-J037 00010A-3 DRAFT

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

OPTION D

ST. PETE HARBOR ENTRANCE CHANNEL

STA. 5+00 TO STA. 56+00

0031 EXCAVATION, UNCLASSIFIED 10,000 CUBIC YARD $___________ $_______________

(ESTIMATED QUANTITY - SEE NOTE 4)

0032 TURBIDITY MONITORING 1 JOB $_______________

0033 ENDANGERED SPECIES OBSERVERS 1 JOB $_______________

0034 MOBILIZATION AND DEMOBILIZATION FOR 1 JOB $_______________

SEA TURTLE TRAWLING AND RELOCATION

(HOPPER DREDGES ONLY) (SEE NOTE 5)

0035 SEA TURTLE TRAWLING AND RELOCATION 1 DAY $______________ $_______________

(HOPPER DREDGES ONLY) (SEE NOTES 5 & 6)

0036 STANDBY TIME (SEE NOTES 7 & 8) 24 HOUR $______________ $_______________

0037 BIRD MONITORING 1 JOB $______________ $_______________

TOTAL OPTION D (LINE ITEMS 0031 THROUGH 0037) $_______________

TOTAL BID (LINE ITEMS 0001 THROUGH 0037) $_______________

NOTES:

(1) SEE SECTION 00100: "INSTRUCTIONS TO OFFERORS".

(2) OFFERORS MUST PROVIDE PRICING FOR ALL ITEMS.

(3) ALL SPECIFICATION REFERENCES TO "LUMP SUM" SHALL APPLY TO LINE ITEMS INDICATING "JOB" AS THE UNIT.

(4) QUANTITY INCLUDES REQUIRED DEPTH, ALLOWABLE OVERDEPTH, AND SHOALING ESTIMATED TO OCCUR BETWEEN DATES OF SURVEYS SHOWN ON DRAWINGS AND COMMENCEMENT OF DREDGING. ACTUAL QUANTITIES MAY DIFFER

FROM ESTIMATED QUANTITIES.

(5) THE GOVERNMENT RESERVES THE RIGHT TO EXERCISE OPTION ITEMS ANY TIME PRIOR TO DEMOBILIZATION OF EQUIPMENT. SEE CLAUSE 52.217-7 of SECTION 00700. THE CONTRACTOR SHALL NOTIFY THE CONTRACTING OFFICER, IN WRITING, A MINIMUM OF 7 DAYS PRIOR TO THE ANTICIPATED DATE OF THE DEMOBILIZATION OF A DREDGE PLANT.

(6) SEA TURTLE TRAWLING AND RELOCATION WILL ONLY BE PAID FOR IF THE CONTRACTOR IS REQUIRED TO PERFORM THE WORK UNDER THE PROVISIONS OF THIS CONTRACT. SEE SECTION 01 57 20: ENVIRONMENTAL PROTECTION FOR

PROVISIONS TO INITIATE SEA TURTLE TRAWLING AND RELOCATION.

(7) STANDBY TIME MAY BE EXERCISED WHEN THE DREDGE PLANT IS NOT IN OPERATION AT THE DIRECTION OF THE CONTRACTING OFFICER. THIS LINE ITEM IS NOT SUBJECT TO THE VARIATION IN ESTIMATED QUANTITY CLAUSE, AND

PAYMENT WILL ONLY BE MADE FOR ACTUAL STANDBY TIME REQUIRED BY THE CONTRACTING OFFICER.

(8) THIS LINE ITEM IS FOR BIDDING PURPOSES ONLY. ACTUAL QUANTITIES MAY DIFFER FROM ESTIMATED QUANTITIES. THIS LINE ITEM IS NOT SUBJECT TO THE VARIATION IN ESTIMATED QUANTITIES CLAUSE, AND PAYMENT WILL ONLY BE MADE FOR

ACTUAL DAYS PERFORMED.

SECTION 00010A, Attachment A

INSTRUCTIONS FOR TECHNICAL INQUIRIES AND QUESTIONS

Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) 17 July 2017, Close of Business. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.

All timely questions and approved answers will be made available through ProjNet. Approved answers to all timely questions will also be posted on the FedBizOps in the form of a report generated from ProjNet as soon as the comment/question entering period is over and all answers are all finalized.

The Solicitation Number is: GROUP4-10-R-J037

The Bidder Inquiry Key is: 2628VJ-V93URM

Specific Instructions for ProjNet Bid Inquiry Access from ProjNet home page:

1. Identify the Agency. This should be marked as USACE.

2. Email. Enter the email address you would like to use for communication.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

5. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret

Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

6. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access from ProjNet home page:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. Identify the Agency. This should be marked as USACE.

3. Email. Enter the email address you used to register previously in ProjNet.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

6. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

THE FOLLOWING PAGES CONTAIN ADDENDUMS TO SPECIFIC SECTIONS OF THE

ORIGINAL SOLICITATION NUMBER W912EP-10-R-0026

THESE ADDENDUMS ARE ONLY APPLICABLE TO THIS

SPECIFIC TASK ORDER

REQUEST FOR PROPOSAL NUMBER: GROUP4-10-R-J037

TASK ORDER PROJECT TITLE:

Tampa Harbor, Maintenance Dredging, 34 and 43-Foot Project, Hillsborough Bay (HB), Ybor Channel, Upper and Lower Sparkman, Port Sutton and East Bay, and St. Petersburg Harbor, Maintenance Dredging, 24-Foot Project, Entrance Channel and Turning Basin, Hillsborough and Pinellas Counties, Florida

NOTICE TO OFFERORS: The information on the following pages is provided for the various clauses and/or paragraphs which require information to be filled in (when applicable) on each Request for Proposal for Task Orders issued under the awarded contracts. All applicable clauses, terms and conditions contained in the original solicitation and subsequently awarded contracts become part of each Task Order.

GROUP-10-R-J037 Clause Addendum-1

ADDENDUM TO SECTION 00100, INSTRUCTIONS TO OFFERORS

THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00100 ARE HEREBY PROVIDED:

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

17.9% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Hillsborough and Pinellas Counties, Florida.

(End of provision)

GROUP4-10-R-J037 00100-A1

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) (ALTERNATE I) (FEB 1995) (CESAJ

ADAPTATION)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for – 13 Jul 2017 at 9:00 AM Local Time.

(c) Participants will meet at -- (Location will be provided by the contract administration office via telephone. See (d) below.)

(d) Participants should call Andy Cummings at 813-348-0690 (office) or 813-503-1362 (cell) on or before Jul 10, 2017 to make arrangements.

(e) Core borings are available. (If available, follow the instructions in the Physical Data paragraph in Section 00 11 00 and 00 31 32 of individual request for proposals issued for task orders under this contract to make arrangements to inspect the borings. Failure to follow the instructions may result in a delay ranging in duration from one hour to 4 days.)

(f) After the site visit, a memorandum summarizing the visit may be posted to the appropriate website under the solicitation number. This posting will be strictly for informational purposes only.

The memorandum will not become a part of the solicitation. If the solicitation needs to be changed as a result of information obtained during the site visit, a written amendment will be made available to all registered vendors. Questions regarding any information given in the memorandum must be directed to the person whose name appears in item 9 of the Addendum to the Standard Form 1442.

(End of provision)

GROUP4-10-R-J037 00100-A2

ADDENDUM TO SECTION 00700, CONTRACT CLAUSES

THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00700 ARE HEREBY PROVIDED:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract immediately upon receipt of the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than * calendar days after the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

* The total completion time of 180 calendar days includes the following:

Base 110 calendar days

Option A 10 calendar days

Option B 50 calendar days

Option C 6 calendar days

Option D 4 calendar days

(End of clause)

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,559.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

GROUP4-10-R-J037 00700-A1

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general—

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title File Drawing Index No.

Tampa Harbor GROUP4-10-R-J037 G-02 Project, Hillsborough and Pinellas Counties, Florida

GROUP4-10-R-J037 00700-A2

ADDENDUM TO SECTION 00800, SPECIAL REQUIREMENTS

THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00800 ARE HEREBY PROVIDED:

LIMITATIONS ON SUBSTITUTIONS FOR CERTAIN POSITIONS AND/OR

SUBCONTRACTORS

The award decision for this contract was based, in part, on an evaluation of the personnel and/or subcontractors the Contractor included in its proposal for the positions and/or items of subcontracted work identified at the end of this paragraph. The Contractor agrees these personnel and/or subcontractors will be employed as described in its proposal and no substitutes will be employed without prior written approval of the Contracting Officer or Administrative Contracting Officer. The Contractor further agrees that any proposed substitutes shall meet or exceed the qualifications of the original personnel and/or subcontractors. If the Contractor’s proposal did not name a subcontractor for an identified item of work, the Contractor will not be allowed to subcontract that item of work without prior approval of the Contracting Officer or Administrative Contracting Officer. The limitations described herein shall apply to the following:

plant and equipment.

(End of paragraph number 999.215-4001)

GROUP4-10-R-J037 00800-A1

SECTION 00800A

WAGE DETERMINATIONS & OTHER ATTACHMENTS

LIST OF CONSTRUCTION CONTRACT ATTACHMENTS

NO. TITLE DATE NO. OF PAGES

1 NOTE 1

2 General Decision Number FL170002 02/03/2017 5 3 General Decision Number FL170003 01/06/2017 4 4 General Decision Number FL170159 01/06/2017 5

00800A-

NOTE NOTE NOTE

THIS PROJECT INCORPORATES STATEWIDE HEAVY DREDGING AND HOPPER

DREDGING WAGE DETERMINATIONS AS WELL AS THE HEAVY CONSTRUCTION

WAGE DETERMINATION FOR HILLSBOROUGH COUNTY, FL

THE HEAVY CONSTRUCTION WAGE DECISION MAY ONLY BE APPLIED TO

OPERATIONS OCCURRING ON LAND

EXECUTIVE ORDER (EO) 13658 ESTABLISHES AN HOURLY MINIMUM WAGE OF

$10.20 FOR 2017 THAT APPLIES TO ALL CONTRACTS SUBJECT TO THE DAVIS-

BACON ACT FOR ALL HOURS PERFORMED ON THE CONTRACT IN CALENDAR

YEAR 2017.

IF YOU HAVE ANY QUESTIONS CONCERNING THE APPLICATION OF THE WAGE

DECISIONS FURNISHED FOR THIS PROJECT, PLEASE CONTACT:

FRAN RUSSELL, OFFICE OF COUNSEL, JACKSONVILLE DISTRICT, U.S. ARMY

CORPS OF ENGINEERS AT 904-232-3761.

General Decision Number: FL170002 02/03/2017 FL2

Superseded General Decision Number: FL20160002

State: Florida

Construction Type: Heavy Dredging

Counties: Florida Statewide.

Dredging Construction Projects FLORIDA (Excluding West of the Aucilla River and its tributary waterways)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.

The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017 1 02/03/2017

* ENGI0025-002 10/01/2016

Rates Fringes

Dredging : (Hydraulic Dredges Over 20") CLASS A.....................$ 37.25 13.28+a CLASS B1....................$ 32.21 12.88+a CLASS B2....................$ 30.33 12.73+a CLASS C1....................$ 29.50 12.41+a CLASS C2....................$ 28.54 12.33+a CLASS D.....................$ 23.71 11.70+a Hydraulic Dredges Under 20" Cook........................$ 8.11 1.73+b Deckhand....................$ 7.77 1.73+b Engineer....................$ 9.59 1.73+b Launchman...................$ 8.19 1.73+b Leverman....................$ 10.03 1.73+b Mate........................$ 8.82 1.73+b Mess Cook...................$ 7.71 1.73+b Messman & Janitor...........$ 7.53 1.73+b Oiler & Fireman.............$ 8.11 1.73+b Shoreman....................$ 7.82 1.73+b Spider Barge Operator.......$ 8.68 1.73+b Spill Barge Operator........$ 8.68 1.73+b Welder......................$ 9.79 1.73+b

CLASSIFICATIONS:

CLASS A: Leverman, Operator.

CLASS B1: Licensed Tug Operator over 1000 HP, Derrick Operator, Spider/Spill Barge Operator, Timber Fork Operator, Dozer Operator, Engineer, Blaster/Driller, Fill Placer, Electrician.

CLASS B2: Licensed Boat Operator, Certified Welder.

CLASS C1: Mate, Drag Barge Operator, Welder, Assistant Fill Placer, Steward.

CLASS C2: Boat Operator.

CLASS D: Shoreman, Deckhand, Rodman, Scowman, Cook, Messman, Oiler, Janitor.

PREMIUMS: Additional 20% for hazardous material work

FOOTNOTE APPLICABLE TO ABOVE CRAFTS:

a. New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.

Vacation Contribution of 8% of straight time rate multiplied by the total hours worked.

b. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day. Plus Vacation contribution of 8% of straight time pay for all hours worked.

INCENTIVE PAY : (Add to Hourly Rate)

Operator (NCCCO License/Certification) $0.50; Licensed Tug Operator over 1000 HP (Assigned as Master) USCG licensed Master of Towing Vessels (MOTV) $1.00; Licensed Boat Operator (assigned as lead boat captain) USCG licensed boat operator $0.50; Engineer (QMED and Tankerman endorsement or licensed engineer (USCG) $0.50; Oiler QMED and Tankerman endorsement (USCG) $0.50; All classifications Tankerman endorsement only (USCG) $0.50; Deckhand or Mater AB w/Lifeboatman only (USCG) $0.25; Welder (ABS certification) $0.50

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210 dvb

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

General Decision Number: FL170003 01/06/2017 FL3

Superseded General Decision Number: FL20160003

State: Florida

Construction Types: Heavy Dredging

Counties: Florida Statewide.

HOPPER DREDGE CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017. The EO minimum wage rate will be adjusted annually.

Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017

SUFL1993-010 05/24/1993

Rates Fringes

Self-Propelled Hopper Dredge Drag Tenders................$ 8.21

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4/7/2017

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

General Decision Number: FL170159 01/06/2017 FL159

Superseded General Decision Number: FL20160159

State: Florida

Construction Type: Heavy

County: Hillsborough County in Florida.

HEAVY CONSTRUCTION PROJECTS (Including Sewer and Water Lines)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017. The EO minimum wage rate will be adjusted annually.

Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017

* ELEC0915-003 12/05/2016

Rates Fringes

ELECTRICIAN......................$ 27.46 37.2%

ENGI0925-010 06/01/2013

Rates Fringes

POWER EQUIPMENT OPERATOR:

Crawler Cranes; Truck Cranes; Pile Driver Cranes; Rough Terrain Cranes; and Any Crane not otherwise described below...$ 29.61 11.50 Drill.......................$ 29.61 11.50 Hydraulic Cranes Rated 100 Tons or Above but Less Than 250 Tons; and Lattice Boom Cranes Less Than 150 Tons if not described below.$ 30.61 11.50 Lattice Boom Cranes Rated at 150 Tons or Above;

Friction Cranes of Any Size; Mobile Tower Cranes or Luffing Boom Cranes of Any Size; Electric Tower Cranes; Hydraulic Cranes Rated at 250 Tons or Above; and Any Crane Equipped with 300 Foot or

More of Any Boom Combination.................$ 31.61 11.50 Oiler.......................$ 22.91 11.50

IRON0397-006 07/01/2016

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 29.10 15.39

LABO0517-002 05/01/2014

Rates Fringes

LABORER: Grade Checker..........$ 18.35 6.45

PAIN0088-008 08/01/2014

Rates Fringes

PAINTER: Brush, Roller and Spray............................$ 19.50 8.83

SUFL2009-155 06/24/2009

Rates Fringes

CARPENTER........................$ 14.95 2.92

CEMENT MASON/CONCRETE FINISHER...$ 14.77 3.50

LABORER: Common or General......$ 10.06 0.00

LABORER: Landscape..............$ 7.25 0.00

LABORER: Pipelayer..............$ 11.33 0.00

LABORER: Power Tool Operator (Hand Held Drills/Saws, Jackhammer and Power Saws Only)............................$ 10.63 2.20

OPERATOR: Asphalt Paver.........$ 11.59 0.00

OPERATOR: Backhoe Loader Combo............................$ 16.10 2.44

OPERATOR: Backhoe/Excavator.....$ 16.00 0.00

OPERATOR: Bulldozer.............$ 17.00 0.00

OPERATOR: Grader/Blade..........$ 16.00 2.84

OPERATOR: Loader................$ 17.00 0.00

OPERATOR: Mechanic..............$ 14.32 0.00

OPERATOR: Roller................$ 10.76 0.00

OPERATOR: Scraper...............$ 11.00 1.74

OPERATOR: Trackhoe..............$ 20.92 5.50

OPERATOR: Tractor...............$ 10.54 0.00

TRUCK DRIVER, Includes Dump Truck............................$ 11.00 0.00

TRUCK DRIVER: Lowboy Truck......$ 12.73 0.00

TRUCK DRIVER: Off the Road Truck............................$ 12.21 1.97

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .