GROUP1-18-R-J015 1 Revision 0002

ADDENDUM TO THE STANDARD FORM 1442

REVISION 0002, Dated 14 May 2020

Coastal Storm Risk Management Project, South Ponte Vedra and Vilano Beach, St.

Johns County, Florida

NOTICE OF INTENT TO ORDER: THIS OPPORTUNITY IS AVAILABLE ONLY TO THE

FOLLOWING CONTRACTORS AWARDED A CONTRACT UNDER SOLICITATION

NUMBER W912EP18R0029, GROUP 1 - UNRESTRICTED:

Callan Marine, Ltd. (W912EP19D0023); Cashman Dredging & Marine Contracting Co., LLC (W912EP19D0024); Cavache Inc. (W912EPD0025); Continental Heavy Civil Corp (CHC) (W912EP19D0026); Cottrell Contracting Corporation (W912EP19D0027); Great Lakes Dredge & Dock Company, LLC (W912EP19D0028); J.T. Cleary Inc.

(W912EP19D0029); Manson Construction Co. (W912EP19D0030); Marinex Construction, Inc. (W912EP19D0031); Norfolk Dredging Company (W912EP19D0032); Orion Marine Construction, Inc. (W912EP19D0033); Southern Dredging Co., Inc. (W912EP19D0034);

The Dutra Group (W912EP19D0035); Waterfront Property Services, LLC dba Gator Dredging (W912EP19D0036); Weeks Marine, Inc. (W912EP19D0037).

PROPOSALS WILL NOT BE CONSIDERED FROM ANY ENTITY OTHER THAN THE

PREVIOUSLY LISTED FIRMS INCLUDED IN THE GROUP 1 - UNRESTRICTED DREDGING

MATOC POOL.

A Virtual Site Visit will take place via Webinar on 7 May 2020 @ 10:00 am, Local Time.

The webinar address is:

https://usace.webex.com/meet/jason.s.harrah

The Participant Audio Conference Access Information is:

USA Toll-Free: (877) 336-1280 USA Caller Paid/International Toll: (404) 443-6393 Access Code: 7256138

A Pre-Proposal Conference will be held on 12 May 2020 @ 10:00 am, Local Time via teleconference. The call-in number is: 877-336-1839, the Access Code is: 7686743, and the Security Code is: 1234. It is requested that an email be sent to brian.j.kilpatrick@usace.army.mil to confirm attendance by your organization.

EVALUATION: The award will be made based on the best overall (i.e., best value) proposal that is determined to be the most beneficial to the Government, with appropriate consideration given to the three evaluation factors: Technical Merit, Past Performance and Price. To receive consideration for award, a rating of no less than https://usace.webex.com/meet/jason.s.harrah mailto:brian.j.kilpatrick@usace.army.mil

GROUP1-18-R-J015 4 Revision 0002

"Acceptable" must be achieved for the Technical Merit Factor and Past Performance Factor.

Offerors are cautioned that award may not necessarily be made to the lowest price offeror or the highest technically rated offeror.

FACTOR 1 – Technical Merit FACTOR 2 - Past performance FACTOR 3 – Price

SUBMISSION REQUIREMENTS:

See Section 00100A -- Solicitation Provisions, for detailed submission requirements.

THE FOLLOWING INFORMATION IS APPLICABLE ONLY TO THIS TASK ORDER:

Block 7. ISSUED BY:

USA ENGINEER DISTRICT, JACKSONVILLE CONTRACTING DIVISION 701 SAN MARCO

BLVD JACKSONVILLE FL 32207-8175

Block 9 -- For additional information contact:

A. Name: Brian Kilpatrick

B. Email Address: brian.j.kilpatrick@usace.army.mil

C. Telephone No.: (904) 232-1792

Block 10 – THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED

IN THESE DOCUMENTS:

The work includes nourishing approximately 3.0 miles of shoreline along a portion of South Ponte Vedra and Vilano Beach in St. Johns County, Florida, between FDEP Range Monuments R-102.5 and R-117.5. The northernmost and southernmost approximate 1,000 feet of the fill area includes a taper transitioning the berm template back to the existing shoreline. The project includes construction of both a dune and beach berm. The landward portion of the beach berm will be flat and has a berm elevation of +8.0 feet North Atlantic Vertical Datum of 1988 (NAVD88). The seaward 80 feet of the berm will have a seaward slope of 1V:40H to an elevation of +6.0 NAVD88. The foreshore slope of the berm will be 1V:10H until it ties into existing grade. The width of the berm varies from the Construction Baseline as shown on the drawings. The dune crest varies in height between +15.0 feet and +18.0 feet NAVD88, as shown on the drawings reflecting the average elevation of the natural dune. The slope of the seaward face of the dune is 1V:3H. Planting of dune vegetation will take place following completion of constructed segments.

Sand for the project will be dredged from the Flood Shoal Complex. Project work also includes, but is not limited to, beach tilling/vibration, monitoring, turbidity monitoring, and environmental species monitoring.

DESCRIPTON OF WORK: Refer to Section 01 11 00 for complete description.

MAGNITUDE OF CONSTRUCTION: Between $20,000,000 and $30,000,000.

mailto:brian.j.kilpatrick@usace.army.mil

GROUP1-18-R-J015 5 Revision 0002

THIS SOLICITATION IS FOR GROUP 1 – UNRESTRICTED MATOC POOL

You must be registered in the System for Award Management (SAM) in order to receive an award from this Notice of Intent. The SAM website is located at www.sam.gov.

The NAICS Code for this Notice of Intent is: 237990 and the Small Business Size Standard is:

$27.5 million.

Block 11 -- The Contractor shall begin performance within 60 calendar days and complete it within 310 calendar days after receiving notice to proceed. This performance period is mandatory. (See FAR Clause 52.211-10 in Section 00700).

Block 12A. The Contractor must furnish any required Performance and Payment Bonds: Yes

Block 12B. Performance and Payment Bonds are due within 10 calendar days after award.

Block 13 ADDITIONAL SOLICITATION REQUIREMENTS:

A. Offers to perform the required work are due electronically at the following email address by 2:00 PM, local time on May 27, 2020: brian.j.kilpatrick@usace.army.mil and a carbon copy (cc) shall be sent to tedra.n.thompson@usace.army.mil and griselle.gonzalez@usace.army.mil

The Offeror’s proposal shall be submitted electronically, as described below. The use of hyperlinks in the proposal is prohibited. The offeror’s proposal is due no later than 2:00 PM, local time on 27 May 2020.

NOTE: The only authorized transmission method of proposals in response to the subject solicitation is electronically via SAFE online submission. No other transmission methods (Email, Facsimile, Regular mail, Hand carried, etc.) will be accepted.

The Offeror’s proposal must be received by the Government no later than the date/time specified in the solicitation and cited above. Offerors shall submit their proposal using the following link:

https://safe.apps.mil/

Please submit proposals utilizing the link above to Contract Specialist, Brian Kilpatrick at Brian.J.Kilpatrick@usace.army.mil and Contracting Officer, Tedra Thompson at Tedra.N.Thompson@usace.army.mil.

Instructions for submitting electronic proposals:

In an effort to reduce paperwork and cost, all proposals shall be submitted electronically through the SAFE site. You are limited to five (5) maximum files per upload (total size cannot exceed 2GB). If you have a large number of files, it is recommended that you combine or ZIP your files before uploading to the SAFE site. Offerors may use compression utility software such as WinZip or PKZip to reduce file size and facilitate transmission.

Request for upload code:

Offerors must email Contract Specialist, William Wallace at william.j.wallace@usace.army.mil and to Contracting Officer, James Tracy at james.t.tracy@usace.army.mil Contract Specialist http://www.sam.gov/ mailto:brian.j.kilpatrick@usace.army.mil mailto:tedra.n.thompson@usace.army.mil mailto:griselle.gonzalez@usace.army.mil https://safe.apps.mil/ mailto:Brian.J.Kilpatrick@usace.army.mil mailto:Tedra.N.Thompson@usace.army.mil mailto:william.j.wallace@usace.army.mil mailto:william.j.wallace@usace.army.mil mailto:james.t.tracy@usace.army.mil

GROUP1-18-R-J015 6 Revision 0002

Brian Kilpatrick at brian.j.kilpatrick@usace.army.mil and Contracting Officer, Tedra Thompson at tedra.n.thompson@usace.army.mil no later than five (5) working days prior to the bid due date to receive a request code which will allow for file uploads via the SAFE site. Offerors that fail to email for request a code five (5) working days before bid submission date may not be able to receive a request code in time to upload their submission.

File Description:

To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention. Each file name shall begin with the solicitation number, followed by the word “RESPONSE”, followed by your firm’s name and finally a brief file description.

EXAMPLES:

(1) “W912HP20R0020 RESPONSE Firm name Volume I.pdf”

(2) “W912HP20R0020 RESPONSE Firm name Volume II .pdf”

File Organization, Formatting and other instructions. Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 or larger.

Pages shall be letter sized--larger page sizes (such as 11x17 foldouts, etc.) will be counted as two pages. Offerors shall prepare proposals in the English language. Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized so as to pertain to only the evaluation factor in the section that the information is presented. Information pertaining to more than one evaluation factor should be repeated in the each section for each factor.

Include a “File Description” for each file(s) you upload. The “File Description” will be included in the email notice to each of the recipients you choose to have access your file(s). NOTE: Do NOT enter Privacy Act Data (Personal Identification Information (PII)) in the File Description.)

Upload Completion & Deadline.

Interested parties shall submit responses no later than the date cited above. The time & date of proposal receipt will be the upload completion / delivery time & date recorded within Safe.

Offerors should time their upload effort with prudence by not waiting until the last few minutes— this will allow for unexpected delays in the transmittal process. Submissions after the deadline may be emailed to Contract Specialist Brian Kilpatrick (Brian.J.Kilpatrick@usace.army.mil), but be advised they will be considered late and as such will be processed in accordance with FAR 15.208.

Submission shall be in Adobe PDF format.

Instructions to follow on the SAFE Website:

1. Once at the SAFE website, select the “Drop-off” icon. This allows users without a CAC or users whose computer is not configured to read a CAC the option to access the SAFE site as a guest.

2. After selecting the “Click Here” link you will be prompted to add your personal information, file mailto:brian.j.kilpatrick@usace.army.mil mailto:tedra.n.thompson@usace.army.mil mailto:Brian.J.Kilpatrick@usace.army.mil

GROUP1-18-R-J015 7 Revision 0002 information, recipient (Government representative) information and email settings.

3. When completing your file information for transmittal via the SAFE website, you will be required to enter the email address for all recipients for this solicitation, the recipients are the Contract Specialist and the Contracting Officer. The Contract Specialist for this solicitation is Brian Kilpatrick: Brian.J.Kilpatrick@usace.army.mil and the Contracting Officer is Tedra Thompson: Tedra.N.Thompson@usace.army.mil. The E-Mail address of the Government Employee who initiated the request code will be automatically entered. The Bidder must enter the E-Mail address for both the Contracting Officer and Specialist. The Bidder can enter an additional E-Mail address if desired. After entering the email address, click the ADD button to add the person(s) email to the “Recipients List” of your response. When your bid is submitted, a notification will be sent to the recipients you added.

NOTE: Do NOT send the SAFE site packages to group email accounts.

Even if you successfully upload your bid to the SAFE site, notification will not be sent to the government recipients until you verify your email address. Entering an incorrect email may result in the rejection of your submission for lateness. An Offeror can confirm proper submission by the ‘Drop-Off Completed” screen which generates based on proper file submission.

NOTE: It has been reported that documents may more quickly upload into the SAFE website when using the Firefox web browser. The Government cannot verify that this is true and offers no guarantee that Offerors will have more success utilizing any particular browser.

Receipt of Submission:

For the purposes of establishing whether a proposal submission is considered timely, the Government considers the date and time the submission is completely uploaded into the SAFE website. For proposals larger than the 2GB capacity of the SAFE website and require multiple submissions, the Government will consider the date and time the last submission is completely uploaded into the SAFE website. Do not assume that electronic communication is instantaneous. It can take several minutes or even hours in some cases.

The Government will not be responsible for submissions delivered to any location or to anyone other than those designated to receive proposals. Offerors are responsible for ensuring that bids are submitted so as to reach the designated recipient. Offerors are responsible for allowing sufficient time for the bid to be received in accordance with the instructions provided.

B. An offer guarantee is required. An electronic copy of the bid guarantee shall be submitted with the offer while the Original must be received within two calendar days of the proposal submission date.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the Notice Intent in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

mailto:Brian.J.Kilpatrick@usace.army.mil mailto:Tedra.N.Thompson@usace.army.mil

GROUP1-18-R-J015 8 Revision 0002

NOTICE TO OFFERORS: Offerors are to complete Blocks 14, 15, 16, 17, 19, and 20A- 20D below:

Block 14. NAME AND ADDRESS OF OFFEROR (including Zip Code)

DUNS: CAGE:

Block 15. TELEPHONE NO. (Include area code):

Block 16. REMITTANCE ADDRESS: (Include only if different than Item 14)

Block 17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this Notice of Intent, if this offer is accepted by the Government in writing within 60 calendar days after the date offers are due.

Block 18. The offeror agrees to furnish any required performance and payment bonds.

Block 19. Acknowledgment of Revisions

(The offeror acknowledges receipt of revisions to the notice of intent -- give number and date of each)

REVISION

NO.

DATE

GROUP1-18-R-J015 9 Revision 0002

Block 20A.

NAME AND TITLE OF

PERSON

AUTHORIZED TO

SIGN

OFFER (Type or print)

Block 20B.

EMAIL ADDRESS

Block 20C.

SIGNATURE

Block 20D.

OFFER DATE

Block 26 --This Task Order will be administered by:

North Florida Area Office

Block 27 -- Payment will be made by:

USACE Finance Center 5722 Integrity Drive

ATTN: CEFC-AO-P

Millington, TN 38054-5005

SF 30 CONTINUATION SHEET

COASTAL STORM RISK MANAGEMENT PROJECT SOUTH PONTE VEDRA AND VILANO BEACH,

ST. JOHNS COUNTY, FLORIDA

GROUP1-18-R-J015 1 REVISION 0002

SUMMARY OF CHANGES

1. SPECIFICATIONS:

The text changes have been updated with additions noted by underlined text and deletions noted by line/cross-outs, and pertain only to changes made by this revision. The entire section is replaced if there is any change. The Project Table of Contents and Submittal Register are replaced without underlines and cross-outs if there are changes to these documents. New sections are added without underlines and cross-outs.

Changes to Specifications:

Volume 1 of 2 – Contract Clauses:

N/A

Volume 2 of 2 – Technical Specifications:

DELETE Section 02 22 13 and REPLACE with the attached Section 02 22 13. DELETE Section 35 20 25 and REPLACE with the attached Section 35 20 25.

2. DRAWINGS:

DELETE Drawing C-14 and REPLACE with the attached Drawing C-14.

3. OTHER:

Drone footage of the project site are available via the "Safe.apps.mil" website.

(End of Summary of Changes)

Coastal Storm Risk Management Project South Ponte Vedra and Vilano Beach

SECTION TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

SECTION 02 22 13

VIBRATION MONITORING REQUIREMENTS FOR EXISTING STRUCTURES

PART 1 GENERAL

1.1 SUBMITTALS

1.2 PERSONNEL QUALIFICATIONS

1.2.1 Vibration Control Specialist

1.2.2 Vibration Monitoring Technician(s)

1.2.3 Structural Inspection/Evaluation Engineer

1.2.4 Organizational Changes

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 VIBRATION CONTROL PROGRAM

3.2 PRE-CONSTRUCTION STRUCTURAL SURVEY

3.3 VIBRATION CONTROL PLAN

3.4 DAILY INSTRUMENT LOG

3.5 VIBRATION MONITORING REPORT

3.6 POST-CONSTRUCTION STRUCTURAL SURVEY

-- End of Section Table of Contents --

SECTION 02 22 13 Page 1 GROUP1-18-R-J015 Revision 0002

SECTION 02 22 13

VIBRATION MONITORING REQUIREMENTS FOR EXISTING STRUCTURES

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Vibration Control Specialist ; G, DO

Vibration Control Specialist Alternate ; G, DO

Vibration Monitoring Technician(s) ; G, DO

Structural Inspection/Evaluation Engineer ; G, DO

Within 30 calendar days after Notice to Proceed, submit qualifications for the Vibration Control Specialist and his Alternate; Vibration Monitoring Technician(s); and, Structural Inspection/Evaluation Engineer. Refer to qualifications in paragraph PERSONNEL QUALIFICATIONS below for each person.

Pre-Construction Structural Survey ; G, DO

Within 30 days of Notice to Proceed and prior to mobilization of equipment, submit 3 copies of the Pre-Construction Structural Survey. Refer to requirements in paragraph PRE-CONSTRUCTION STRUCTURAL SURVEY below.

Vibration Control Plan ; G, DO

Within 30 days of Notice to Proceed and prior to mobilization of equipment, submit 3 copies of a Vibration Control Plan. Submit the Vibration Control Plan for compliance with the requirements in paragraph VIBRATION CONTROL PLAN below. The Plan shall include, but not be limited to, the following:

a. List of structures that are susceptible to vibration damage.

b. Number of monitors (seismographs) required for the project and location of monitors that will operate simultaneously in each work area.

c. Calibration data for each seismograph that will be used for the project. Calibrations shall be current, not older than one year, and follow the manufacturer's recommended procedures.

SECTION 02 22 13 Page 2

d. List of methods and procedures to reduce ground vibrations induced by construction activities to below the pre-determined maximum allowable vibration level for the designated vibration sensitive structure(s); i.e., reducing equipment speed, changing fill placement method, reducing equipment size, and using manual labor.

e. Plan for each work area showing the proposed construction equipment in the area, the description of susceptible structure(s) in the work area, monitors in the work area, and the list of methods and procedures in subparagraph d. above.

f. The minimum safe working distance that vibration producing equipment may operate from each vibration sensitive structure(s).

g. The maximum allowable ground vibration level that is permissible without causing threshold damage to each vibration sensitive structure(s).

h. Frequency of instrument maintenance/inspection by the Vibration Control Specialist. Frequency shall not be greater than every 48 hours.

SD-06 Test Reports

Vibration Monitoring Report

Submit a Vibration Monitoring Report every 2 weeks for compliance with the requirements in paragraph VIBRATION MONITORING REPORT below. Submit the Vibration Monitoring Report and the Daily Instrument Logs concurrently.

Daily Instrument Logs

Submit the Daily Instrument Logs every 2 week for compliance with the requirements in paragraph DAILY INSTRUMENT LOGS below.

Submit the Daily Instrument Logs and the Vibration Monitoring Report concurrently.

Post-Construction Structural Survey ; G|DO

Submit 3 copies of the Post-Construction Structural Survey within 15 calendar days after completion of the inspection.

Submit the Post-Construction Structural Survey for compliance with the requirements in paragraph POST-CONSTRUCTION STRUCTURAL SURVEY below.

1.2 PERSONNEL QUALIFICATIONS

1.2.1 Vibration Control Specialist

The Vibration Control Specialist shall have a background in structural and/or geotechnical engineering, have a minimum of three years of demonstrated experience in vibration monitoring and related work, and be a registered professional engineer or registered professional geologist.

The alternate may serve in the event of the Vibration Control Specialist's absence. Periods of absence shall not exceed one week at any one time and not more than fifteen workdays during a calendar year. The requirements

SECTION 02 22 13 Page 3 for the alternate are the same as for the Vibration Control Specialist.

The Vibration Control Specialist shall be designated in the Vibration Control Plan.

1.2.2 Vibration Monitoring Technician(s)

Personnel responsible for operation, maintenance and calibration of seismographs shall have a minimum of three years of demonstrated experience in vibration monitoring and related work.

1.2.3 Structural Inspection/Evaluation Engineer

Structural inspections shall be performed by professional structural engineers registered in the State of Florida with a minimum of three years of demonstrated experience in structural condition inspections. The Structural Inspection Engineer shall have responsibility for pre-construction and post-construction structural surveys. The Structural Inspection Engineer shall be designated in the Vibration Control Plan.

1.2.4 Organizational Changes

When it is necessary to make changes to personnel, resubmit qualifications in accordance with paragraph SUBMITTALS above.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 VIBRATION CONTROL PROGRAM

Implement a program that protects existing structures from damages that result from construction equipment operations and vibrations. The purpose of the program is to avoid damages and potential claims that allege damages were caused by construction activities. The Contractor is responsible to document pre-existing conditions, to avoid damaging existing structures that were determined to be susceptible to vibration damage, and to avoid damaging existing structures that were not determined to be susceptible to vibration damage; related responsibilities include inspection, damage claims, and work stoppage that results from monitoring.

The Contractor's attention is called to Clauses PERMITS AND RESPONSIBILITIES and PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES AND IMPROVEMENTS of Section 00700 CONTRACT CLAUSES in Volume 1 of this contract that define the Contractor's responsibilities.

The Contractor shall process any claim arising from his operation; in particular, all property damage claims shall be acknowledged by the Contractor (or his agent) immediately, and the claimed damage inspected within 30 calendar days following initial notification, and processed to a conclusion (honored, denied, or compromised) within 90 calendar days after completion of the contract; but, in no case shall the claim(s) remain unresolved for a period exceeding six months.

3.2 PRE-CONSTRUCTION STRUCTURAL SURVEY

Inspect existing structures within 200 feet from the beach fill limit as to their potential susceptibility to vibration damage from construction equipment induced ground vibration. Visible structural and/or cosmetic damage to buildings, exterior walls, foundations, decks, walkovers, staircases, revetments , pools, bulkheads and seawalls shall be documented

SECTION 02 22 13 Page 4 by photographs, sketches, and field notes.

Factors to consider in determining potential susceptibility shall include but not be limited to: foundation design; foundation conditions; soils testing data; changes in structural loads and local water levels due to beach fill placement; structural condition including construction materials; past damage history and existing stresses, magnitude, frequency, and duration of predicted vibrations from construction equipment and distance from fill placement.

Inspect all existing structures that are determined to be vibration sensitive. Any damage found shall be documented thoroughly by photographs (supplemented with video as necessary), sketches of visible structural and/or cosmetic damage, and field notes. Photographs shall be at least 3-by 5-inch (or digital) and shall provide a detailed visual explanation of the damage. Include a reference scale in each close-up photograph.

Sketches shall show the general damage location and extent. All inspection items shall be indexed and cross-referenced and shall use the stationing and locations shown on the contract drawings. Include hotel/motel names and addresses where applicable. Structural damage shall be additionally documented by measuring crack or damage size, width, and length. Every effort shall be made to inspect and document the condition of the building's interior where the building has been determined to be extremely susceptible to vibration damage. Structure(s) determined not to be susceptible to vibration damage shall be noted as such.

3.3 VIBRATION CONTROL PLAN

Use the results of the Pre-Construction Structural Survey to develop the Vibration Control Plan. The Plan shall include procedures to monitor vibration sensitive structures, adjust daily mobilization and demobilization activities, and alter fill placement operations. The Plan shall include the appropriate tolerable ground vibration level for each structure that has been determined to be susceptible to vibration damage.

Should ground vibrations equal or exceed the pre-determined maximum vibration level(s), construction operations shall be halted and corrective measures taken in accordance with the approved Plan.

The minimum safe working distance that vibration producing equipment may operate from each vibration sensitive structure shall be documented in the Plan.

The maximum allowable ground vibration level that is permissible without causing threshold damage to each vibration sensitive structure shall be documented in the Plan. Threshold damage is defined as the occurrence of cosmetic damage.

Each seismograph shall have the capability to measure peak particle velocity and frequency and shall be equipped with an alarm system to alert the Vibration Control Specialist that ground vibrations are approaching the maximum tolerable ground vibration level. Seismographs shall record measurements 24 hours a day, 7 days a week. Seismographs shall be installed and shall be properly working prior any construction activities, including mobilization and demobilization of all construction equipment, and fill placement operations.

The Contractor's personnel responsible for implementation of the Plan is hereinafter called Vibration Control Specialist. The Vibration Control Specialist shall be on site at the active fill location during all fill

SECTION 02 22 13 Page 5 placement operations that can affected vulnerable structures. However, seismographs used for the 24/7 monitoring shall be capable of 24-hour real time notifications capable of being sent directly to the Vibration Control Specialist and Vibration Control Technicians. Ground vibrations shall be kept in allowable levels to avoid damaging existing structures that were determined to be susceptible to vibration damage, and to avoid damaging existing structures that were not determined to be susceptible to vibration damage. Additionally, the Vibration Control Specialist will provide support to the Contractor to best mitigate against direct impacts to structures or indirect impacts to structures due to uncontrolled loading.

3.4 DAILY INSTRUMENT LOG

The Contractor's personnel responsible for implementation of the Plan is hereinafter called Vibration Control Specialist. The Vibration Control Specialist shall be on the site during mobilization and demobilization of all construction equipment; and during the fill placement operations that can affect the vibration sensitive structures (as defined in paragraph PRE-CONSTRUCTION STRUCTURAL SURVEY above). When the construction activities do not involve any vibration sensitive structure, the Vibration Control Specialist may choose not to be on site. However, seismographs used for the 24/7 monitoring shall be capable of 24-hour real time notifications capable of being sent directly to the Vibration Control Specialist and Vibration Control Technicians. Ground vibrations shall be kept in allowable levels to avoid damaging existing structures that were determined to be susceptible to vibration damage, and to avoid damaging existing structures that were not determined to be susceptible to vibration damage.

3.5 VIBRATION MONITORING REPORT

The monitoring report shall detail the daily activities of the vibration monitoring program. This report shall include, but not be limited to, locations of monitoring equipment; instrument serial number; date and times of readings; magnitude of vibration levels; a sketch and photograph (3- by 5-inch) of each monitoring station showing the relationship of the monitor to vibration sensitive structures; daily instrument logs;

instructions transmitted to the Contractor's personnel regarding the modification or stoppage of work operations to keep vibrations below the allowable levels; description of complaint(s); and, any other information pertinent to the vibration monitoring program.

3.6 POST-CONSTRUCTION STRUCTURAL SURVEY

Immediately after completion of work, conduct a post-construction inspection of the structures previously inspected under the Pre-Construction Structural Survey. Documentation procedures shall be identical to those performed under the Pre-Construction Structural Survey. Changes or deviations from the pre-construction inspection conditions in any structure shall be identified and described in the inspection documentation. All citizen complaints and remedies that occurred during the placement of beach fill shall be summarized and included in the report.

-- End of Section --

SECTION 02 22 13 Page 6

SECTION TABLE OF CONTENTS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

SECTION 35 20 25

BEACH FILL

PART 1 GENERAL

1.1 SUMMARY

1.2 REFERENCES

1.3 DEFINITIONS

1.3.1 Acceptance Sections

1.3.2 Compensating Slopes

1.3.3 Construction Baseline (CBL)

1.3.4 Maximum Dredging Depth

1.3.5 Target Depth

1.3.6 Work Area

1.4 SYMBOL AND ACRONYM USE

1.5 SUBMITTALS

1.6 PROJECT SCOPE

1.6.1 Project Order of Work

1.6.2 Project Coordination

1.6.3 Project Work Permits and Responsibilities

1.6.3.1 Project Traffic and Navigation

1.6.4 Protection of Existing Structures from Construction Activity

1.6.4.1 Protection of Existing Utilities from Construction Activity

1.6.4.2 Damages to Adjacent Property and Structures

1.6.5 Project Work Violations

1.6.6 Project Final Cleanup

1.7 ENVIRONMENTAL PROTECTION

1.7.1 Pumping of Bilges

1.7.2 Fuel Oil Transfer Operations

1.7.3 Turbidity

1.7.4 Historical Period Shipwreck Sites

1.8 NOTIFICATION OF COAST GUARD

1.8.1 Navigation Aids

1.8.2 Dredging Aids

1.9 WORK AND ACCESS AREA

1.10 SIGNAL LIGHTS

1.11 CRANE AND DRAGLINE SAFETY REQUIREMENTS

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 OVERALL WORK AREA PROVISIONS

3.1.1 Construction Plans and Contract Documents

3.1.2 Staging and Access Areas

3.1.2.1 Existing Conditions Documentation

3.1.3 Public Protection

3.1.3.1 Work Area Signs and Barriers

SECTION 35 20 25 Page 1

3.1.3.2 Dedicated Safety and Flag Person

3.1.4 Noise Control

3.1.4.1 Hauling and Excavating Equipment

3.1.4.2 Booster Pumps Noise Control

3.1.4.3 Sound Pressure Measurements

3.1.5 Buoy and Anchoring Inventory

3.1.6 Protection of Existing Vegetation

3.2 PROTECTION OF CULTURAL RESOURCE AREAS

3.3 EXCAVATION

3.3.1 General

3.3.2 Magnetic Anomalies

3.3.3 Probability of Rock in Borrow Area

3.3.4 Dredge Location Control

3.3.4.1 Other Dredge Type Control

3.3.5 Deduction for Nonconforming Work

3.4 Color-Coded Plot and Dredge Track Drawing Contents

3.5 TRANSPORT OF EXCAVATED MATERIALS

3.5.1 Hopper Dredge/Scow

3.5.1.1 Mis-Dump

3.5.2 Pipeline Transportation

3.5.2.1 Submerged Pipeline

3.5.2.2 Floating Pipeline

3.5.2.3 Upland Pipeline

3.5.2.4 Visual Inspection of Pumpout and Pipeline Locations

3.5.3 Spillage and Leakage

3.5.3.1 Hopper Dredge/Scows

3.5.3.2 Pipeline

3.5.4 Screening and Removal

3.6 BEACH FILL

3.6.1 General

3.6.2 Construction

3.6.2.1 Construction Equipment Limitations

3.6.2.2 Grade Stake Installation and Recovery Operations

3.6.2.3 Control of Fill

3.6.2.4 Longitudinal Dikes

3.6.2.5 Ramps and Walkways

3.6.3 Placement

3.6.3.1 Dressing for Payment

3.6.3.2 Dressing for Final Acceptance

3.6.3.3 Escarpments

3.6.4 Tolerances

3.6.5 Misplaced Materials

3.7 QUALITY CONTROL

3.7.1 Preparatory Inspection

3.7.2 Initial Inspections

3.7.3 Follow-up Inspection

3.8 QUALITY CONTROL FOR BEACH FILL

3.8.1 Compliance Criteria for Beach Fill Material

3.8.2 Beach Fill Observation and Sampling

3.8.3 Determination of Areal Extent of Noncompliant Beach Fill

3.8.4 Remediation

3.8.5 Noncompliant and Unacceptable Material Contingency Plan

3.9 INSPECTION

3.9.1 Quality Assurance Representative (QAR)

3.9.2 Failure to Comply

3.10 CONSTRUCTION FORMS AND DETAILS

-- End of Section Table of Contents --

SECTION 35 20 25 Page 2

SECTION 35 20 25

BEACH FILL

PART 1 GENERAL

1.1 SUMMARY

The project work covered by this section consists of furnishing all plant, labor, equipment, supplies, and material, and of performing all operations in connection with excavating, transporting, and placing beach fill along the project shoreline as indicated on the drawings, as described by applicable permits, and/or as specified herein. Related sections are

01 11 00 SUMMARY OF WORK, 01 57 20 ENVIRONMENTAL PROTECTION, 01 57 25

TURBIDITY AND DISPOSAL MONITORING, and 02 22 13 VIBRATION MONITORING

REQUIREMENTS FOR EXISTING STRUCTURES.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D422 (1963; R 2007) Particle-Size Analysis of Soils

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 Safety and Health Requirements Manual

1.3 DEFINITIONS

1.3.1 Acceptance Sections

Fill placement acceptance sections are defined as the portion of the renourished beach lying between two immediately adjacent pay profile lines.

1.3.2 Compensating Slopes

The allowance for pay volume above the fill tolerance to compensate for foreshore slope vacancies within the fill template due to sediment relocated by natural forces between the time of placement and payment surveys. For details, see plan sheet PAYMENT AND ACCEPTANCE PROFILES.

1.3.3 Construction Baseline (CBL)

To closely resemble the shoreline, a Construction Baseline (CBL) was established. The CBL determines the seaward/gulfward berm crest width and the construction stationing for pre- and post-payment surveys.

1.3.4 Maximum Dredging Depth

The maximum dredge depth is shown on the plans for the borrow area. The

SECTION 35 20 25 Page 3

Contractor cannot remove material below this depth. Contractor will not be penalized for locations in the borrow area which were already deeper than maximum depth prior to dredging. The Florida Department of Environmental Protection (FDEP) designated "disturbance depth" is a 2 foot layer located beneath maximum depth in which material can be agitated but not removed.

1.3.5 Target Depth

The borrow area and each subdivision shall be completely exacavated to the target depth before relocating the dredge to another borrow area or subdivision. The Contracting Officer may permit the Contractor to relocate to another borrow area or subdivision prior to complete clearance to target depth if 1) the remaning quantity is the result of minor side slope sloughing, 2) in isolated areas the remaining sand thickness cannot be efficiently removed after suitable effort by the contractor to clear the entire borrow area or subdivision to target depth, or 3) other reasons determined valid by the Contracting Officer.

1.3.6 Work Area

Work area is defined as the area where Contract work is to be performed, as shown on the contract drawings, impacted by contractor operations, and additional areas agreed by the Contracting Officer.

1.4 SYMBOL AND ACRONYM USE

/ = or b/c = because CBL = Construction Baseline FDEP = Florida Department of Environmental Protection

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Unless otherwise indicated below, Shop Drawings shall be submitted no later than 30 calendar days after Notice to Proceed.

Beach Fill Plan ; G, RO

The Contractor shall submit a Work Plan for review and approval by the Contracting Officer. The work plan shall include but not be limited to the following:

a. Excavation Depth Protection : Provide a detailed description of methods and equipment to be used for each operation, and the sequence of operations, including sketches showing how the Contractor will not excavate below the maximum excavation depth at the borrow area(s) as indicated in the contract drawings.

b. Buoy Log : The Contractor shall develop a method of inventory for all anchors, buoys, and buoy cables used in the

SECTION 35 20 25 Page 4 construction of the project. This record shall be used by the Contractor to recover all buoys and anchoring equipment at the completion of the project

c. Grade Stake Log: The Contractor shall provide a sample Grade Stake Log used on the project and indicate how the log is prepared and maintained to inventory the grade stakes used on the project. The log shall include information concerning the location, installation, and recovery of all grade stakes. During Construction the Contractor shall make this log available for review by the appropriate Government personnel upon request.

d. Staging and Access Area: The Contractor shall indicate if they plan on obtaining additional access or staging areas for their construction operations other than what is shown on the drawings. If the Contractor plans on obtaining additional access/staging areas, submit proposed drawings depicting the areas for Contracting Officer approval.

e. Public Protection: Provide a Contractor's plan for ensuring pedestrian, worker, and vehicular safety at each access location used by the Contractor. Submit means and methods for pedestrian protection during beach fill operations for review and approval by the Contracting Officer. Submit product information and methods of installation for orange safety fencing for crowd control.

Submit methods of staking in place and maintenance of system for duration of construction. Submit off-road trucking operation safety plan.

f. Vibration Control : See Section 02 22 13 VIBRATION MONITORING

REQUIREMENTS FOR EXISTING STRUCTURES.

Progress Maps; G, RO

Provide a progress schedule map of the contractor's design. The progress schedule map shall be a plan view drawing depicting the beach fill site and access areas to be used on the project. The map shall show all access/staging areas, R-monuments, adjacent street names, building names, and pipeline landings anticipated to be used on the project. For each AS, the information shall list the following: Anticipated quantity of material per acceptance section, projected dates for fill to be placed and completed. The map shall provide dates when access areas are to be used and ready for public use. The map will be color coordinated with the following color scheme: Red depicting an area not ready for construction; Orange depicting an area currently being worked, and Green meaning an area accepted by the Contracting Officer and ready for public use. The map shall be updated at least weekly and whenever significant changes occur to the projected dates.

Since the map will be used by the Government for coordination with the public and to track progress, the update shall be provided prior to the weekly project progress meeting.

Relocation of Navigation Aids

Within 7 calendar days following receipt of Notice of Award, the Contractor shall notify the Commander, Seventh Coast Guard . This notification shall be immediately followed by a formal written request with a copy to the Contracting Officer. The Contractor

SECTION 35 20 25 Page 5 shall also contact the U.S. Coast Guard at 305-415-6750 for information concerning the position to which the aids will be relocated.

Construction and Grade Stakes Recovery Plan ; G, RO

The Contractor shall submit a Construction and Grade Stakes Recovery Plan. The plan will outline the steps that the Contractor will implement to recover all the stakes used on the project. This plan will include the use of the Grade Stake Log submitted with the General Work Plan above. A sample plan is on the web site indicated in paragraph CONSTRUCTION FORMS AND DETAILS below, with further information provided in paragraph Grade stake installation and recovery operations.

Rock Removal Plan ; G, DO

The Contractor shall submit to the Contracting Officer a plan detailing the method for removal of rock. The plan shall also include the method for which the quantity of rock removed is measured and the location of rock disposal for acceptance by the Contracting Officer.

Noncompliant and Unacceptable Material Contingency Plan

Submit a Noncompliant Material Contingency Plan as indicated in paragraph QUALITY CONTROL FOR BEACH FILL below.

Electronic Tracking System Charts

The Contractor shall furnish required plotted charts to the Contracting Officer.

Dredge Location Control Color-Coded Plot

The Contractor shall furnish the required color-coded plots to the Contracting Officer with the Daily Report of Operations.

Quality Control for Beach Fill

Beach sediment samples shall be collected and stored a the on-site trailer for inspection. Refer to paragraph QUALITY CONTROL FOR BEACH FILL below for further details on sampling.

Equipment and Performance Data ; G, RO

The Contractor shall furnish proof of electronic positioning equipment calibration to the Contracting Officer.

Grade Stake Recovery ; G, DO

After completion of the project, the Contractor shall provide a letter to the Contracting Officer certifying that all grade stakes have been recovered in accordance with the Contractor's approved Construction and Grade Stake Recovery Plan. With the certification, the Contractor shall also furnish the completed Grade Stake log to the Contracting Officer. Grade stake installation and recovery operation. Refer to paragraph below.

SECTION 35 20 25 Page 6

Placement Plan for work adjacent to structures/seawalls ; G, DO

For government review and in accordance with vibration control and monitoring plan. To included detailed placement method and type of equipment.

Buoy and Anchoring Inventory Recovery ; G, DO

After completion of the project, the Contractor shall provide a letter to the Contracting Officer certifying that all anchors, buoys, buoy cables used in the construction of the project have been recovered in accordance with the Contractor's approved Anchor and Buoy Recovery below. With the certification, the Contractor shall also furnish the completed Buoy and Anchoring Inventory Record.

Notification of Discovery of Historical Period Shipwreck Sites

The Contractor shall immediately notify the Contracting Officer if any shipwreck, artifact, or other objects of antiquity that have scientific or historical value, or are of interest to the public, are discovered, located, and/or recovered.

Daily/Monthly Report of Operations

The Contractor shall prepare on RMS and submit two (2) hard copies of the Daily Report of Operations, using either ENG Form No. 27A or ENG Form No. 4267, for each dredge and/or unloader working. The Daily Report of Operations will include the Dredge Location Control Color-Coded Plot. This report shall be submitted on a daily basis and not in groups (groups = multi-days reports packaged together at one time). In addition to the daily report, the Contractor shall prepare a Monthly Report of Operations for each month or partial month's work on either ENG Form No. 27A or ENG Form No. 4267. The monthly report shall be submitted on or before the 7th of each month, consolidating the previous month's work. Upon completion of the job, the Contractor shall submit a consolidated job report, combining the monthly reports. The Contractor shall distribute one copy of each report to the District Engineer, ATTN: CESAJ-EN-C; U.S. Army Engineer District, Jacksonville, P.O. Box 4970, Jacksonville, Florida 32232-0019.

Reports shall be submitted on a monthly basis with daily reports accompanying the monthly report and job report.

Additionally, one copy of these forms shall be maintained by the Contractor on the dredge(s) for the Contracting Officer's inspection purpose. Further instructions on the preparation of the reports will be furnished at the Preconstruction Conference.

Notice of Misplaced Material

The Contractor shall notify the U.S. Coast Guard Marine Safety Office of any misplaced material as stated in Clause OBSTRUCTION OF NAVIGABLE WATERWAYS of Section 00700 CONTRACT CLAUSES.

Declaration of Inspection

Refer to paragraph FUEL OIL TRANSFER OPERATIONS below for submittal.

SECTION 35 20 25 Page 7

Placement Plan ; G

Pipeline Corridor Plan

Provide a detailed map of the Contractor's placement of pipeline from the Inlet Complex to the project area. Pipeline Corridor Plan shall show all planned sand ramp walkways, R-monuments, adjacent street names, and pipeline landings anticipated to be used. Additionally, provide a detailed description of methods and equipment to be used for operation nearby the Villano Groin.

SD-06 Test Reports

Sound Pressure Measurements ; G, RO

Refer to Paragraph SOUND PRESSURE MEASUREMENTS.

1.6 PROJECT SCOPE

The Contractor shall provide the dredge and support vessels, labor, equipment, supplies, and materials to perform all operations for excavating, transporting, placing, dressing and grading (and possible tilling) beach fill on the beaches as indicated in the drawings and further specified herein. The Contractor shall accomplish the work in such a manner so as to minimize disruption to road and maritime traffic or use of the public beach as well as minimize impacts to existing infrastructure.

1.6.1 Project Order of Work

At the Preconstruction Conference, the Contractor shall propose the order in which the work will be performed, including the anticipated progression excavation of the borrow area(s) and fill placement. The Contractor shall dredge the following borrow areas in any order prior to commencing excavation of the Davis Shoal. The Contractor shall exhaust a borrow area to the target depth prior to requesting permission from the Contracting Officer to use a subsequent borrow area. At a minimum, the Contractor shall exhaust the IWW Widener to the target depth as part of the initial project. The IWW Shoal Borrow Area (north of the Usina Bridge) is included as a sand source, but is not required to be utilized as part of this contract.

IWW Widener Borrow Area North Flood – A Borrow Area North Flood – B Borrow Area

Within each fill placement site, the Contractor shall begin their filling operations at any point along the project beach, but the Contractor shall maintain a continuous filling operation without any intervening gaps.

1.6.2 Project Coordination

Project coordination with the Contracting Officer shall occur during all phases of construction. Coordination also includes but is not limited to coordinating with local officials including police, Public, FDEP, US Coast Guard, and others as agreed during coordination meetings. See paragraph PROJECT COORDINATION of Section 01 30 00 ADMINISTRATIVE PROCEDURES and

SECTION 35 20 25 Page 8

Paragraph COORDINATION MEETING of Section 01 45 05 DREDGING/BEACH FILL

PLACEMENT - CONTRACTOR QUALITY CONTROL.

1.6.3 Project Work Permits and Responsibilities

The Contractor's attention is directed to the Clause PERMITS AND RESPONSIBILITIES of Section 00700 CONTRACT CLAUSES and paragraph PERMITS AND AUTHORIZATIONS of Section 01 57 20 ENVIRONMENTAL PROTECTION. Any other licenses or approvals required for the prosecution of the work shall be secured and paid for by the Contractor. The Contractor shall obtain any and all approvals required to conduct work in the Atlantic Ocean.

1.6.3.1 Project Traffic and Navigation

The Contractor shall so conduct their operations that they shall not close any thoroughfare nor interfere in any way with traffic on railway, highways, or on water, without the written consent of the Contracting Officer. The regulations the Contractor shall adhere to are those established by, but not necessarily limited to, the Department of the Navy, U.S. Coast Guard, Department of the Army, American Bureau of Shipping, Florida Department of Environmental Protection, Florida Department of Transportation, Florida Law Enforcement Agencies, county and municipal.

1.6.4 Protection of Existing Structures from Construction Activity

The Contractor shall be responsible for determining and documenting the pre-construction condition of existing structures within the project area. The Contractor shall take appropriate measures to prevent damage to any structures during construction, and for performing a post-construction verification inspection of those structures previously inspected. Refer to Section 02 22 13 VIBRATION MONITORING REQUIREMENTS FOR EXISTING STRUCTURES for further details and guidelines.

1.6.4.1 Protection of Existing Utilities from Construction Activity

It…