About this file
This is an Industry Day presentation for Grand Canyon National Park outlining multiple federal construction contract opportunities totaling over $200 million in magnitude. The presentation covers four major projects at North Rim and one at South Rim, all involving utilities infrastructure restoration and replacement work following the Dragon Bravo fire and general system modernization needs.
North Rim Utilities (GRCA 317819) is a Design-Bid-Build project exceeding $100 million in magnitude, using full and open competition with one firm-fixed-price contract. Anticipated solicitation is expected in August 2026 (posted for 90 days) with award in early 2027 and a 4-year performance period. Project scope includes water system improvements (Roaring Springs Pumphouse rehabilitation, raw and finished water pipelines, water treatment plant modernization with membrane filtration technology), wastewater collection system replacement, and power system upgrades including additional diesel fuel storage, standby generators, transformer replacements, overhead and underground power replacements, fiber communications upgrades, and solar power system replacement. A critical component involves two boreholes (9,260 feet long, 8-26 inch diameter) directionally drilled from North Rim to Roaring Springs using vertical directional drilling technology. Temporary WWTP (GRCA 317819) is a $5-10 million small business set-aside, Design-Bid-Build project with solicitation expected June 12, 2026, onsite pre-bid meeting June 23, 2026, and award in August 2026, performing through June 1, 2027. This project installs a temporary 90,000 gpd packaged wastewater treatment plant using Cloacina membrane bioreactor technology with two 45,000 gpd MBR treatment units. Permanent WWTP (GRCA 317819) is a $50-100 million Design-Bid-Build project with sources sought in summer 2027, solicitation in fall 2027, and award in early spring 2028, performing for 3 years. The permanent facility uses MBR technology with 127,000 gpd capacity across three building configuration and provides Class A+ reclaimed water and Class B biosolids.
North Rim Critical Utility Restoration (GRCA 352119) is valued between $1-5 million as a 100% Indian Small Business Economic Enterprises (ISBEEs) set-aside using Bureau of Indian Affairs Construction Multiple Award Contract (C-MAC), with Performance Work Statement contract documents. Solicitation is expected early July 2026 with award in late August 2026, emphasizing fall 2026 completion with final completion in spring 2027. Work includes testing and repair of electrical power distribution systems, wastewater collection system restoration, water distribution system restoration, and SCADA/communications infrastructure restoration. North Rim Heavy Equipment Facility (GRCA 353101) is anticipated at $10-50 million using Design-Build Program of Requirements methodology with one firm-fixed-price contract. Sources sought, solicitation, and award are all expected during 2027 with period of performance and procurement method to be determined. The facility requires 12-14 vehicle bays, vehicle maintenance shop with lift, welding shop, and interior conditioned space for offices and break rooms to support operation and maintenance of snow removal equipment, over-snow equipment, and heavy construction equipment.
Replace South Rim Wastewater Treatment Plant (GRCA 257282) exceeds $100 million as a Design-Bid-Build full and open competition project with one firm-fixed-price contract. Sources sought posting was completed in 2025, solicitation expected summer 2026 (posted 90 days), and award expected first quarter 2027 with approximately 36 months performance. The project replaces the 1970s WWTP with MBR technology-based treatment designed for 0.65 MGD maximum monthly flow and 1.2 MGD peak hour flow, producing Class A+ reclaimed water and Class B biosolids with small Class A composting stream. Scope includes new administration, laboratory, maintenance facilities, electrical service, emergency generator, phased construction maintaining existing plant operations, demolition of existing structures, and construction of new paved access road. ADEQ permit has been issued.
All projects will utilize Construction Management Representative Services through call orders against standing Blanket Purchase Agreements for GRCA. Contracting officers and specialists are identified for each opportunity, with questions directed in writing to the Design Support Center contracting office. All interested parties must review specific solicitation requirements posted to Notice ID 140P2026R0080.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GRCA_Attendance_List_06_11_26_3.pdf | ||
| SURVEY_GRCA_Projects_3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NPS ● 2025
NORTH RIM UTILITIES
NPS PMIS# GRCA 317819
NORTH RIM CRITICAL UTILITY RESTORATION
NPS PMIS# GRCA 352119
NORTH RIM HEAVY EQUIPMENT MAINTENANCE FACILITY
NPS PMIS# GRCA 353101
REPLACE SOUTH RIM WASTEWATER TREATMENT PLANT
NPS PMIS #: GRCA 257282
June 11, 2026
THIS MEETING WILL NOT BE RECORDED
INDUSTRY DAY
GRAND CANYON NATIONAL PARK
Notice ID: 140P2026R0080
AGENDA
• Introductions and Welcome - Jim Waller, Contracting Officer
• North Rim Utilities (Post-Fire) – Mike Luecker, Project Manager
• North Rim Utilities (Temp WWTP)
• North Rim Utilities (Permanent WWTP)
• North Rim Critical Utility Restoration (Post-Fire) – Doug Denk, Project Manager
• North Rim Heavy Equipment Maintenance Facility
• Replace South Rim WWTP
• Closing Remarks & Survey Request - Jim Waller, Contracting Officer
GRCA - 317819 North Rim Utilities – Post-Fire
• Location: Grand Canyon National Park, Arizona
• Magnitude of Construction: Greater Than $100M
• Design & Construction Method: Design – Bid – Build
• One firm-fixed-price
• Procurement Method: Full & Open
• Anticipated Dates (Approximate):
• Sources Sought Posting: (completed April 2026)
• Solicitation: Expected August 2026 (posted 90 days)
• Award: Expected Early 2027
• Period of Performance: 4 years
• Construction Management Representative Services: Call
Order against standing Blanket Purchase Agreement for
GRCA.
Impacts of Dragon Bravo Fire to Design
Fire Impacts to DesignDescriptionVol
No impacts, use admin area for staging/camps
Construction camps and staging
No impactsNew NR pipeline and access road
No impactsBore – Pipeline NR to RSPH2 No impactsPipeline - NR to Supai3 No impactsRS Cave Pipeline4 No impactsRSPH5 No impactsNR Water Treatment Plant6 Redesign requiredNR WW Treatment Plant7 Remove Historic District; no impact to other regions
NR Collections8
Remove Historic District; no impact to other regions
NR Power9
No impactsOverhead Power10 No impactsPower to Manzanita11 No impactsPower at Cottonwood12
Pre-Fire Industry Day – June 2025
Impacts of Dragon Bravo Fire to Design – June 2025 Industry Day
Refer to Prior Industry Day (June 2025) Attachments:
• SR WWTP information is still valid to provide draft concepts and scope of work.
• NR Utilities information is still valid to provide draft concepts and scope of work, with following post-fire changes:
• Volume VII WWTP will be removed
• Volume VIII Collections – Historic District removed
• Volume IV Power - Historic District removed
Refer to Prior Industry Day (June 2025 – Notice ID 140P2025R0075) Focused on:
• SR WWTP (GRCA 257282)
• NR Utilities (GRCA 318719) – Pre-Fire, Volumes
1-12)
North Rim Utilities – Project Overview
Water System Improvements
• Rehabilitation to the Roaring Springs
Pumphouse (RSPH) to supply raw water from the Roaring Springs source
• Raw and finished water pipelines between the North Rim water storage tanks (Tank Farm) and Roaring Springs Pumphouse for improved reliability and reduced repairs
• Rehabilitation of raw water pipeline between Roaring Springs Cave and the
RSPH
This project will address critical system deficiencies associated with water, wastewater, electrical, and communication systems, along with their associated equipment, components, and support structures. Infrastructure includes water (raw water, treatment, and distribution), wastewater conveyance, power and communications (standby power, overhead power, solar power, fiber communications).
Project Scope Includes:
North Rim Utilities – Project Overview - Water
Water Treatment Plant Modernization
• Replacement of the North Rim
Water Treatment Plant (NRWTP) to meet current health and safety standards
• Membrane filtration-based potable water treatment process
• Construction of:
• New raw water storage tank
• Filtration and chemical treatment systems
• Clearwell for disinfected water storage
• Backup generator and full
SCADA integration
This project will address critical system deficiencies associated with water, wastewater, electrical, and communication systems, along with their associated equipment, components, and support structures. Infrastructure includes water (raw water, treatment, and distribution), wastewater conveyance, power and communications (standby power, overhead power, solar power, fiber communications).
Project Scope Includes:
NPS ● 20258
North Rim Utilities – Project Overview - Water
North Rim Utilities – Project Overview – Wastewater & Power Wastewater System
• Replacement of the sewer collection system
Power System
• Additional diesel fuel storage at Power
Distribution Center to receive full deliveries and provide for longer outages
• Addition of fourth standby generator at Power Distribution Center
• Replacement of transformers which have exceeded life cycle at Power Distribution Center and throughout North Rim campus
• Replacement of junction boxes and shunt reactors in poor condition throughout North Rim campus
• Replacement of overhead power from North Rim to RSPH to increase life expectancy and reliability
• Replacement of underground power from RSPH to Manzanita
• Replacement of fiber communications from RSPH to Manzanita
• Replacement of defunct solar power system at Cottonwood Campground
North Rim Utilities – Project Overview –Power
North Rim Utilities – Project Overview – Water/Borehole
Bore Installation (Vertical Directional Drilling - VDD)
Includes:
• Bore pit preparation and staging at the North Rim
• VDD execution with telescoped casing and fiber optic installation
• Receiving pit setup and spoil containment at Roaring Springs
• All mobilization and helicopter-supported logistics for Inner Canyon access
A key project component includes new boreholes to be directionally drilled from the North Rim to Roaring Springs Pump House with carrier pipes to include raw and potable waterlines. Two approximately 8-to-26-inch diameter, 9,260-feet-long boreholes will be drilled sequentially using vertical direction drilling, extending from the drill site (i.e., bore entry site) at the North Rim ballfield to the bore exit site just west of Roaring Springs Pumphouse in the inner canyon, where the borehole would daylight. The planned boreholes have a vertical length of 3,310 feet, a total measured length of 9,260 feet, and will be drilled through several Paleozoic geologic units of variable lithology with the potential for a variety of geologic risks
Project Scope Includes: “Ballfield”
Entry Site – Ballfield
Includes: 2 boreholes
Exit Site – Roaring Springs Pump House
NPS ● 202513
North Rim Utilities – Bore Profile
GRCA - 317819 North Rim Utilities – Temporary WWTP
• Location: Grand Canyon National Park, Arizona
• Magnitude of Construction: $5-10M
• Design & Construction Method: Design – Bid – Build
• One firm-fixed-price
• Procurement Method: Small Business Set-Aside
• Anticipated Dates (Approximate):
• Sources Sought Posting: (completed April 2026)
• Solicitation: Expected June 12, 2026
• Onsite Pre-Bid Meeting: June 23, 2026 @ 10am
• Award: Expected August 2026
• Period of Performance: June 1, 2027 (ultimate completion)
• Construction Management Representative Services: Call Order against standing Blanket Purchase Agreement for
The proposed project would install a temporary, packaged, 90,000 gallon per day (gpd) WWTP along the existing south fenceline of the WWTP (adjacent to the sludge drying beds) until a permanent WWTP can be constructed. The temporary packaged WWTP will include headworks, two 45,000 gpd MBR treatment units, an equalization tank with aeration and pumping system to the MBR units, and a treated effluent break tank and ultraviolet (UV) disinfection system.
Temporary storage units would be installed for chemical storage and laboratory functions. On site utilities (yard piping/cabling) would be installed and connect to existing utilities.
WW Treatment System: Turn-Key Package Integrated System o Basis of Design Manufacture: Cloacina (CA, UT) o System Includes
• Equalization Tank, Two MBR Treatment Units, UV Skid Disinfection
• Each MBR Treatment Unit Independently Operates with Own HMI/PLC
• Integrated EQ Tank Pumping System to the MBR Treatment Units
• Gravity Flow to Break Tank – Gravity Flow Thru UV Treatment to Outfall
Sanitary Sewer to Equalization (EQ) Tank o Components Process Flow
• Diversion from SS to Septage Receiving Manhole
• Mechanical Screening Unit with Bypass Bar Screen
• Package Lift Station (Influent LS) Pumps to EQ Tank
• Influent Lift Station Overflow to SS to Large Septic Tank
• EQ TankAerates for Oder Control and Pumps to MBR Units
Generation 2
Site o Concrete Pads: MBR Tanks, EQ Tank, Break Tank & UV Skid o Crushed Rock for Drainage o Security Fence with Multiple Gate Access
Chemicals o Conditioned Shipping Containers, Two Units, Two Rooms/Unit o Three Rooms: Chemicals, One Room: Spare Parts Storage, Winter Storage o System Includes
• Three Chemical Rooms, Eyewash Stations
• On Spare Parts Storage and Winter Equipment Storage Room
Portable Certified Wastewater Lab o 8ft x 40ft Portable Container
• Conditioned Space with Lab Mechanical Equipment (Hood Vent)
• Power, Sewer, Water
SCADA
o No Remote Monitoring Until LRF Project SCADA Work is Completed
• Install Fiber WWTP to Water Treatment Plant for Back Communication thru RSPH to SR o Location Control, Observation, Alarm HMI/PLCs at Each MBR Unit
• Housing Area for Operators is Walking Distance
EQ Tank
Break Tank UV Skid
Package Pump
Station
Overview of Scope
Treatment System
Containers Site Utilities
Storage Units
Two 40’ Connex Trailers o Sodium Hypochlorite Room & Caustic Room o Citric Acid Room & Parts/Eqp. Storage Room
Trailers will be modified to include separate rooms, HVAC, plumbing, and electrical components.
Chemical Storage
Chemical Parts-Winter Storage
Interior Insulation
Construction Sequencing Phase I – Fall 2026
1 Grading - Utilities Phase II – Spring 2027
Units – Storage - Fence
GRCA - 317819 North Rim Utilities – Permanent WWTP
• Location: Grand Canyon National Park, Arizona
• Magnitude of Construction: $50-100M
• Design & Construction Method: Design – Bid – Build
• One firm-fixed-price
• Procurement Method: To be determined
• Anticipated Dates (Approximate):
• Sources Sought Posting: Summer 2027
• Solicitation: Fall 2027
• Award: Early Spring 2028
• Period of Performance: 3 years
• Construction Management Representative Services: Call
Order against standing Blanket Purchase Agreement for GRCA
GRCA - 317819 North Rim Utilities – Permanent WWTP
Treatment Technology: MBR (Membrane Bioreactor)
• Total Treatment Capacity: 127,000 gpd Three Building Configuration:
• New combined Control and Secondary
Treatment Building, New Headworks Building, New Solid Digestion Building
• Digesters in separate structure to reduce
O&M power load from classified space
Project Scope Includes: 30% Schematic Design Concept
GRCA 352119 North Rim Critical Utility Restoration
• Location: Grand Canyon National Park, Arizona
• Magnitude of Construction: Between $1M and $5M
• Design & Construction Method: Performance Work Statement
(PWS) contract documents
• One firm-fixed-price construction contract
• Procurement Method: 100% set-aside for Indian Small Business Economic Enterprises (ISBEEs) via Bureay of Indian Affairs Construction – Multiple Award Contract (C-MAC)
• Anticipated Dates (Approximate):
• Sources Sought Posting: (completed Mar 2026)
• Solicitation: Expected early-July 2026
• Award: Expected late-Aug 2026
• Period of Performance: To Be Determined; emphasis on Fall 2026 with final completion in Spring 2027
• Construction Management Representative Services: Call Order against standing Blanket Purchase Agreement for GRCA.
North Rim Critical Utility Restoration – Project Overview
Project Scope Includes:
Repair and Restore Electrical Power Distribution System:
• Removal of transformers
• Testing of generators, generator stand-by system
(multiple generators on ATS,) medium voltage cables, & transformers
• Replacing system components
• Re-energizing Distribution System (confirm power supply to lift stations/pumps prior to initiating wastewater/water system work)
This project will test, repair, restore, and place into operational service existing wastewater, potable water and electrical power utility systems in the North Rim developed area to support the NPS goal of opening portions of the North Rim to the public and providing limited visitor services and amenities starting in 2026 to the extent possible, where possible and when possible, as it is safe to do so. Work includes restoration of applicable system supervisory control and data acquisition systems (SCADA)/radio/communications infrastructure.
Project Scope Includes:
Repair and Restore Wastewater Collection System:
• Repair damaged infrastructure.
• Inspect manholes to remain in service and remove debris.
• Abandon lines and services.
• Return lift stations to service
• Flush sewer pipes
• CCTV inspect sewer pipes
Project Scope Includes:
Repair and Restore Water Distribution System:
• Repair damaged infrastructure
• Install system improvements
• Fill and repressurize system
• Flush System
GRCA 353101 North Rim Heavy Equipment Facility
• Location: Grand Canyon National Park, Arizona
• Magnitude of Construction: Between $10M and
$50M
• Design & Construction Method: Design-Build
Program of Requirements (anticipated)
• One firm-fixed-price contract
• Procurement Method: TBD
• Anticipated Dates (Approximate):
• Sources Sought Posting: Expected early CY 2027
• Solicitation: Expected CY 2027
• Award: Expected CY 2027
• Period of Performance: TBD
• Construction Management Representative
Services: TBD
North Rim Heavy Equipment Facility – Project Overview
Project Scope Includes:
Design-Build of a new Heavy Equipment Facility to be located in the North Rim Developed area with the following requirements:
• House and support the operation and maintenance of various types of vehicles and heavy equipment including snow removal equipment, over-snow equipment, road maintenance and construction equipment and various specialized NPS vehicles.
• Support 12 - 14 vehicle bays plus a vehicle maintenance shop with a vehicle lift, a welding shop to support vehicle and equipment maintenance, and a limited amount of interior conditioned space to support functions such as NPS staff offices, employee restrooms, a break room, and similar spaces.
This project will replace certain facilities lost in the Dragon Bravo fire in order to resume safe, efficient and effective administration and operations on the North Rim. Due to the North Rim’s climate, snow removal and over-snow equipment is an essential part of North Rim operations and the housing and maintenance of that and similar equipment is critical to the park.
GRCA 257282 Replace South Rim Wastewater Treatment Plant
• Location: Grand Canyon National Park, Arizona
• Magnitude of Construction: Greater Than $100M
• Design & Construction Method: Design – Bid – Build
• One firm-fixed-price contract with a single period of performance
• Procurement Method: Full & Open
• Anticipated Dates (Approximate):
• Sources Sought Posting: (completed 2025)
• Solicitation: Expected Summer 2026 (posted 90days)
• Award: Expected 1Q CY 2027
• Solicitation #: TBD
• NAICS: 237990
• Period of Performance: Approximately 36 months
• Construction Management Representative Services: Call
Order against standing Blanket Purchase Agreement for
South Rim WWTP – Project Overview This project will replace the 1970s WWTP to improve treatment efficiency & meet current standards.
Project Scope Includes:
• The wastewater processes will be designed for a for a 0.65 MGD max monthly flow and 1.2 MGD peak hour flow
• Treatment based on MBR technology
• Class A+ reclaimed water
• Class B biosolids w/ small Class A biosolids stream (composting)
• Construction of new admin, laboratory and maintenance facilities
• Construction of new electrical service and new emergency generator
• Construction and phasing of new facilities, while maintaining uninterrupted operation of the existing plant throughout construction and commissioning period
• Completion of tie-ins to existing wastewater influent manhole and effluent discharge
• Demolition of all existing structures including process structures, buildings, and all supporting systems
• Construction of a new paved access road generally following the route of an existing two-track dirt road.
• The road will be used as the primary contractor route to the SR WWTP and adjacent staging area (constructed as part of this project).
• ADEQ Permit has been issued.
WWTP – Existing Facilities
WWTP – Demolition / Relocation / Site Prep
Demolish / Relocate
Remove Vegetation, Clear & Grub
WWTP – Phase 1 of 4 - Construction of New Facilities
WWTP – Phase 2 of 4 - Commissioning, Demonstration Testing and Transition of Operation to New Facilities
WWTP – Phase 3 of 4 - Demolition of Existing WWTP
WWTP – Phase 4 of 4 - Construction of Remaining New Facilities
WWTP – Overall Site Plan – Completed Project
Headworks
Process Building (Blowers / RAS Pumps/ UV / Chemical Storage / RW PS / Plant Water
Aerobic Digestion
Reclaimed Water Storage
Septage Receiving
Composting
Odor Control
Drying Beds
Bioreactors & Flow Equalization
Maintenance Building
Administration Building & Laboratory
Questions & Survey Request
• Direct all questions to the DSC Contracting Office in writing following the event.
• Points of Contact
• NR Utilities (GRCA 318719):
• Contracting Officer: Jim Waller; james_waller@ios.doi.gov
• Contracting Specialist: Kristin Tauber; kristin_tauber@ios.doi.gov
• NR Critical Utilities Restoration (GRCA 352119):
• Contracting Officer: Jason Longshore; jason_longshore@ios.doi.gov
• NR Heavy Equipment Maintenance Facility (GRCA 353101):
• Contracting Officer: Jason Longshore; jason_longshore@ios.doi.gov
• SR WWTP (GRCA 257282):
• Contracting Officer: Tim Burger; timothy_burger@ios.doi.gov
• Contracting Specialist: Kristin Tauber; kristin_tauber@ios.doi.gov
• Survey Request:
• DSC Contracting Office is requesting survey response from all potential Contractors and Sub-Contractors.
• FEEDBACK provided to NPS will be considered confidential and not shared outside of DSC Design Team. A formal survey request will be included in a special notice posted to 140P2026R0080
Interested parties must review the requirements as posted in each solicitation.
Thank you