1100 TONS 3/4 CRUSH GRAVEL, DELIVERED
Solicitation number
140P1424Q0100
Issued by

About this file

This document is a Request for Quote (RFQ) for approximately 1,100 tons of 3/4-inch Grade W road base gravel to be delivered to Grand Teton National Park between August 25, 2024 and December 6, 2024. The gravel must meet specific gradation and aggregate property requirements outlined in the RFQ. The contractor will be responsible for furnishing all equipment, operators, and support functions necessary to deliver the gravel to the specified location. Delivery quantities may vary between 6 and 500 yards per scheduled delivery, with the Government providing a minimum of 24-hours' notice. The contractor must have an approved weed management plan and submit test samples for Government approval prior to delivery. Payment will be made based on actual quantities delivered, not to exceed 1,100 tons.

View the file

Other files

File Type Posted
Wage_Determination.pdf PDF
Airport_Pit_Location.pdf PDF
Sol_140P1424Q0100.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gravel with Delivery Grand Teton National Park

RFQ # 140P1424Q0100

REQUIREMENT

Grand Teton National Park needs to purchase approximately 1100 tons of ¾ inch GRADE W Road Base Gravel for the 2024 construction season. The material must be available for delivery between August 25, 2024, and December 6, 2024.

Delivery Location:

Grand Teton Maintenance Pit (airport pit) located 0.3 miles southeast of Jackson Hole Airport access road (43°35'51.1"N 110°43'16.4"W). See location in map attachment.

Salient Characteristics:

Gravel (3/4” GRADE W)

Specifications:

This is a supply requirement for gravel cover material which shall meet the requirements of the following table of gradations as determined by Wyoming specification: 801.4.4-1 Subbase and Base Grading “W”. Furnish crushed top surfacing Type “W”, including added binder or blending material, meeting Table 803.4.4-1 gradation requirements. Copies of the referenced Wyoming Specifications may be obtained from the Wyoming Department of Transportation 2010 Standard Specifications handbook.

ABLE 803.4.4-1

Gradation Requirements:

Subbase and Base

PERCENTAGE BY WEIGHT PASSING SQUARE MESH SIEVES

Sieve Size Grade J Grade GR Grade L Grade K Grade W 2 inch (50 mm) 100 - - - -

1 1/2 inch (37.5 mm) 90 to 100 - 100 100 100 1 inch (25 mm) - 100 90 to 100 90 to 100 90 to 100

3/4 inch (19 mm) - 90 to 100 - - - ½ inch (12.5 mm) - 65 to 85 60 to 85 - 60 to 85 3/8 inch (9.50 mm) - - - - -

No. 4 (4.75 mm) 35 to 75 50 to 78 35 to 55 40 to 65 45 to 65 No. 8 (2.36 mm) - 37 to 67 25 to 50 30 to 55 33 to 53 No. 30 (600 um) - 13 to 35 10 to 30 - -

No. 200 (0.075 um) 0 to 15 4 to 15 3 to 15 3 to 15 3 to 12

Table 803.4.4-2 Aggregate Properties:

Subbase and Base Properties Subbase Crushed Base Crushed Base (gravel Roads

LA Abrasion Loss, Max., % 50 50 50 Liquid Limit, Max. 25 25 30

Plasticity Index 0 to 6 0 to 3 4 to 12 R‐Value, Min. 60 75 60

Meet the following requirements for crushed top surfacing Type “W”, including added binder or blending material:

A. Dust Ratio: the portion passing the No. 200 sieve cannot exceed two-thirds of the portion passing the No. 30 sieve.

B. The maximum liquid limit and plasticity index for the material passing the No. 30 sieve is 30 and 4-12 respectively.

C. The composite aggregate does not contain adherent films of clay and other matter that prevents thorough coating with bituminous material. Bituminous material must remain adhered to the material upon contact with water.

D. When the aggregate is to be bituminized, both the material source and the composite aggregate must have a volume swell not exceeding 10 percent, and not show cracking or disintegration.

E. Do not remove intermediate sizes from the material during production, unless authorized in writing.

F. Have a wear factor not exceeding 50 percent at 500 revolutions; and G. At least 35 percent by weight of the aggregate retained on the No. 4 sieve must have at least one mechanically fractured face.

The Contractor shall provide all equipment, operating supplies, operators, supervision, and support functions necessary in order to furnish the gravel to the Government including hauling to required location.

Period of Performance:

The period of performance is from August 25, 2024 through December 6, 2024.

Scheduling:

The gravel shall be readily available for delivery during the period of performance, 08/25/2024 – 12/06/2024., Monday through Friday, from 7:00am to 5:30 pm: approximate quantities will range between 6 yards and 500 yards per scheduled delivery. Park point of contact identified at contract award will contact Contractor 24 hours in advance to confirm delivery.

Note: The delivery quantity variation is due in part to uncertainty in weather conditions and availability of equipment (e.g., a change in weather conditions may only allow work for ½ day and/or equipment failures/availability may result in fewer yards of gravel being transported in a day).

The Government will provide a minimum of 24 hours’ notice prior to delivery. Should the Government give less than 24 hours’ notice, the Contractor may elect either to load the trucks as requested or to schedule an alternate day. Delivery days will be scheduled when conditions are favorable and are weather dependent.

Hauling:

A. All dump trucks have and use tarps.

B. The Contractor shall furnish equipment on a fully operated basis that is in good mechanical and operating condition.

C. All vehicles and equipment to be used in Grand Teton National Park shall be thoroughly pressure washed prior to arrival. Only clean equipment shall be permitted into the Park.

Particular attention must be shown to the under carriage and any surface where soil containing exotic weed seeds may exist.

D. Equipment must be operated by competent operators who are experienced in performing similar work. The operators will be experienced in safely operating dump trucks and be thoroughly familiar with their capabilities.

E. The Contractor shall provide all equipment, operating supplies, operators, supervision, and support functions necessary to perform the required work.

F. The Contractor shall adhere to all roadway use regulations and posted speed limits within the Park.

G. The use of engine brakes (either compression or exhaust) in a 3-mile radius of housing areas and campgrounds is prohibited.

Inspection, Testing, &Acceptance:

The Contractor shall have test samples submitted to the Government for suitability evaluation at least two (2) weeks prior to the actual delivery or acceptance of the material. The Government may require additional material testing if specifications are suspect. Material that does not meet contract specifications and requirements following test sample evaluation and Government inspection shall be rejected. The Contractor shall be notified in writing to correct the deficiencies and must produce and acceptable product within five business days. Failure to furnish an acceptable product within five business days may result in the termination of the Contractor’s right to proceed.

Vegetation Management: The control of noxious weeds shall be achieved through a weed management plan. All parties submitting offers for gravel must have a current weed management plan that has been approved by the local county weed board and Grand Teton National Park. All plans require one annual inspection by Park staff during the growing season (June – August) prior to sale of material. Parties submitting offers must provide proof of the most recent weed inspection by Park staff.

The weed inspection will designate a pit in one of three rating categories: acceptable, conditionally acceptable, or unacceptable. Gravel from a pit designated as unacceptable can be used if the material is heat treated to 300 degrees Fahrenheit and promptly transported from the quarry to the Park or a pre-approved weed free storage area to prevent possible weed contamination. A list of weeds of concern can be obtained from Grand Teton National Park. The control of noxious weeds shall be achieved by a method approved by the Contracting Officer.

Submittals: At the time of delivery, and with each invoice, the Contractor shall provide truck scale weight tickets to the Government, which shall serve as contractor certification as to the number of tons delivered.

Measurement and Payment/Method of Measurement:

The contractor shall furnish truck scale weight tickets from state certified scales for each delivery made to the Government. Payment will be made on actual quantities delivered and shall not exceed 1100 tons.

ABLE 803.4.4-1