GSA Solicitation No. 47PJ0022R0034
Simplified Acquisition Construction Contract for the repointing of masonry at the Grand Forks CH.
The Agreement
Table of Contents
I. Project Information A. Project Summary B. The Contract C. Period Of Performance D. Work Conditions/Site Requirements E. Authorized Representatives F. Contract Liquidated Damages Rate G. Buy American Exceptions H. Statement of Work, Specifications, Drawings
II. Prices
A. Basis of Pricing B. Contract Price Form
III. General Provisions
A. Commencement, Prosecutions and Completion of Work B. Contractor Responsibilities C. Material and Workmanship D. Project Schedule E. Interpretation of Specifications and Drawings F. Submittals G. Government’s Right to Stop Work for Non-Compliance H. Other Contracts I. Use an Possession Prior to Substantial Completion J. Finality of Contract Modifications K. Liquidated Damages L. Insurance Requirements M. Administrative Matters N. Bonds O. Safeguarding Sensitive Data and Information Technology Resources
IV. Contract Clauses
A. Clauses Incorporated in Full Text
1. FAR 52.222-99 Establishing a Minimum Wage for Contractor (JUL
2014) (DEVIATION)
2. FAR 52.223-2 Affirmative Procurement of Biobased Products Under
Service and Construction Contracts (SEPT 2013)
3. FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (MAY 08)
4. FAR 52.225-9 Buy American—Construction Materials (MAY 2014)
5. FAR 52.228-13 Alternative Payment Protections (July 2000)
6. GSAR 552.204-9 Personal Identity Verification Requirements (JUL 2020)
7. GSAR 552.252-6 Authorized Deviations in Clauses (Deviation FAR
52.252-6) (SEP 99)
8. FAR 52.204-25, Prohibition on Contracting for Certain
Telecommunications and Video Surveillance Services or Equipment
(AUG 2020)
9. FAR 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (DEVIATION APR 2020)
10. FAR 52.228-11, Pledges of Assets (DEVIATION APR 2020)
11. FAR 52.219-14, Limitations on Subcontracting (DEVIATION 2020-19)
12. Additional Clauses
i. FAR 52.222-30, Construction Wage Rate Requirements-Price
Adjustment (None or Separately Specified Method) (Aug 2018)
13. FAR 52.223-99, Ensuring Adequate COVID-19 Safety Protocols for
Federal Contractors (OCT 2021) (DEVIATION)
B. Clauses Incorporated by Reference
I. Project Information
I.A. Project Summary
Repointing (Caulking and Tuckpointing) at the Grand Forks CH.
I.B. The Contract
(1) The Contract consists of the SF1442, the Agreement, the Statement of Work, Specifications, Drawings, Exhibits, Amendments, Modifications, and other Attachments identified herein (collectively, the Contract Documents). The Contract contains the entire agreement of the Parties, and no prior written or oral agreement, express or implied, shall be admissible to contradict or modify any part of the Contract.
(2) The Contractor shall provide and pay for all labor, materials, equipment, tools, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution of the work described in and reasonably inferable from the Contract
Documents (the Work), whether temporary or permanent. In consideration for, and upon condition of, the Contractor's completion of the Work, GSA shall pay the
Contractor the price or prices established in Section II, subject to the terms and conditions set forth in this Contract.
I.C. Period of Performance
(1) Commencement. The Contractor shall commence performance of the Work within 15 days after the Contractor receives the Notice to Proceed (NTP).
(2) Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than 90 calendar days from issuance of Notice to Proceed (NTP).
(3) Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 10 calendar days of Substantial Completion.
I.D. Work Conditions/Site Requirements
Exterior work
I.E. Authorized Representatives
(1) This Contract is between the United States of America, acting by and through the
Administrator of General Services (GSA), and the Contractor (the Parties). References in this Contract to "the Owner" or "the Government" shall be understood to refer to GSA.
The following individual is designated as the only authorized GSA representative under this Contract, unless other warranted contracting officers are designated in writing:
Contracting Officer’s Information
Name: Cody Lee
Address: 657 2nd Ave N Fargo, ND 58102
Telephone: 701-566-6124
Email: cody.lee@gsa.gov
(2) For the applicable authorities and limitations see Section IV of this Agreement, GSAR 552.236-70.
I.F. Contract Liquidated Damages Rate
In accordance GSAR 552.211-12, Liquidated Damages – Construction, in Section IV of this Agreement, liquidated damages shall be calculated at the rate of $ 0 per calendar day.
I.G. Buy American Exceptions
For the applicable Buy American clause and any exceptions, see Section IV of this Agreement.
I.H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments
The following documents are incorporated by reference into this Contract.
(1) Statement of Work for GSA Solicitation No. 47PJ0022R0034, Dated 01/18/22
(2) Construction Drawings for GSA Solicitation No. 47PJ0022R0034
(3) Wage Determination ND20220014, Dated 01/07/22
CONSTRUCTION SCOPE OF WORK
U.S. GENERAL SERVICES ADMINISTRATION, ROCKY MOUNTAIN REGION 8
Date: 1/18/2022 Revision:
Section 1: Project Title
Grand Forks Courthouse Repointing
Section 2: Project Location, Building Name, & Building Number
Ronald N. Davies Federal Building Grand Forks, ND 58203 Building Number: ND0008ZZ
Section 3: Contact List
Contracting Officer (CO) Name: Cody Lee Email: cody.lee@gsa.gov Address: 657 2nd Ave North Fargo, ND 58102 Phone (O): 701 566-6124
Project Manager Name: Jesse Johnson Email: jesse.johnson@gsa.gov Address: 220 East Rosser Ave Bismarck, ND 58501 Phone (O): 701-557-9649 Phone (C): 701-202-9036
Property Manager Name: Shawn Sullivan Email: shawn.sullivan@gsa.gov Address: 102 N 4th St Room 125 Grand Forks, ND 58201 Phone ©: 701-739-3045
Contract Specialists Name: Laura Funk Email: laura.funk@gsa.gov Address: 657 2nd Ave North Fargo, ND 58102 Phone (O): 701-566-6114
Section 4: Project Background & Project Description The intent of this project is to prevent water infiltration and damage from the capstone to the ground level on all four sides of building ND0008ZZ. The contractor will repair caulking and repoint certain areas of the building associated brick, and sandstone.
There are areas where the mortar joints have completely weathered away and need tuckpointing to prevent any further damage to the building. There are two separate areas than need repointing, the brick veneer tuckpointing and sandstone tuckpointing.
Section 5: Project Objectives The contractor shall provide labor, materials, equipment, and supervision necessary to perform:
1) There is approximately 500 SF of brick veneer that need to be repointing up on the roof of the building. (See Pictures)
2) There is approximately 3,500 SF of mortar joints within the sandstone and cap stone that need repointing and re-caulking on the west side of the building. (See Pictures)
3) A staging area will be determined by mutual agreement after contract award.
4) The following information is provided for bidding purposes only. The contractor is advised to conduct a site visit and field-verify the exact information required for use in completing the work and submitting an offer.
5) No asbestos or lead containing materials shall be used.
6) The contractor shall remove and replace existing cracked and/or damaged caulking on the exterior wall areas (to be delineated by Property Manager).
Sealant is to be polyurethane selected per ASTM C1193 Standard Guide for Use of Joint Sealants and suitable for adhesion to concrete and metal, standing water environment and UV resistant.
7) All new mortar and caulking color shall match existing. Submit samples to Property Manager for approval.
8) In areas where old caulking is tarnished, remove old caulking before applying new.
9) Thoroughly inspect the caulking, mortar joints, control joints, brick and surrounding areas for cracks, open joints, caulk not adhering and any other means for water to infiltrate the building. The infiltration appears to increase with the presence of strong winds driving the rain into the building.
10) The contractor is responsible for the protection of all existing building property surfaces from damage due to work performed under this contract. Damages to existing surfaces caused by the performance of this contract shall be repaired as to match the existing surface finish at no additional cost to the Government.
11) The contractor shall remove existing cracked and/or damaged building and masonry joints. Repair cracked masonry grout joints with new grout (approximately 4,000 SF), on west side and on the roof, exterior wall areas (to include lineal areas above and around each side of windows) PLEASE NOTE:
Identify location and area of damaged brick, new replacement brick (if used) shall match existing building brick, this shall be coordinated through the property manager for decisions to be made.
12) Work Area is elevated. Contractor shall provide non-penetrating roof anchoring, roof swing lift, scaffolding or lift to access elevation indicated. Lifts must be capable of reaching from the street level. All equipment shall comply with all applicable regulations.
13) Contractor shall confer with the City of Grand Forks for compliance if sidewalk or street access is to be impaired.
14) The Contractor shall remove all debris generated in the performance of this contract daily.
15) The contractor shall take all necessary precautions to prevent any dust or debris from filtering into other parts of the building including but not limited to mechanical systems. Should dust or debris filter into other parts of the building the contractor shall take immediate steps to clean the area (no equipment or supplies will be furnished by GSA).
16) At the completion of the project, the project area shall be cleaned to building standards as determined by the GSA Property Manager. Should the contractor fail to clean the project limits in a timely manner, GSA will contract for said cleaning and the cost will be deducted from the contract. Ensure that all penetrations are sealed with fire rated approved material as required by the International Building Code.
17) The CO has the right to reject any unsatisfactory or unsuitable material or workmanship
18) The optional bid is for the purpose of adding additional work to the contract.
APPLICABLE PUBLICATIONS
1. Publications listed below form a part of this specification to the extent referenced.
Publications are referenced in the text by basic designation only.
a. American Society for Testing and Materials (ASTM):
b. C67-07 .... Brick and Structural Clay Tile, Sampling and Testing
c. C216-07 .... Facing Brick (Solid Masonry Units Made from Clay or Shale)
d. C270-07 .... Mortar for Unit Masonry
2. International Masonry Institute: Recommended Practices and Guide Specifications for Cold Weather Masonry Construction.
PRODUCTS
REPLACEMENT CAULKING
1. Polyurethane selected per ASTM C1193 Standard Guide for Use of Joint Sealants and suitable for adhesion to concrete and metal, standing water environment and UV resistant.
EXECUTION
REMOVAL OF EXISTING CAULKING
1. Cut out existing damaged or cracked caulking and remove to a depth of 19 mm (3/4-inch), or until sound mortar is reached. Take care to not damage edges of existing masonry units to remain.
2. Remove dust and debris from the joints by brushing, blowing with air or rinsing with water. Do not rinse when the temperature is below freezing.
CUT OUT OF EXISTING MORTAR JOINTS
1. Cut out existing mortar joints (both bed and head joints) and remove by means of a toothing chisel or a special pointer's grinder, to a uniform depth of to 19 mm (3/4-inch), or until sound mortar is reached. Take care to not damage edges of existing masonry units to remain.
2. Remove dust and debris from the joints by brushing, blowing with air or rinsing with water. Do not rinse when the temperature is below freezing.
JOB CONDITIONS
1. Protection: Protect newly pointed joints from rain, until pointed joints are sufficiently hard enough to prevent damage.
2. Cold Weather Protection:
-Repointing may be performed in freezing weather when methods of protection are utilized.
-Comply with applicable sections of "Recommended Practices for Cold Weather Construction" as published by International Masonry Industry All Weather Council.
-Existing surfaces at temperatures to prevent mortar from freezing or causing other damage to mortar.
INSTALLATION OF REPOINTED MORTAR
1. Immediately prior to application of mortar, dampen joints to be repointed. Prior to application of pointing mortar, allow masonry units to absorb surface water.
2. Tightly pack mortar into joints in thin layers, approximately 6 mm (1/4-inch) thick maximum.
3. Allow the layer to become "thumbprint hard" before applying the next layer.
4. Pack final layer flush with surfaces of masonry units. When mortar becomes "thumbprint hard", tool joints.
TOOLING OF JOINTS
1. Tool joints with a jointing tool to produce a smooth, compacted, concaved joint.
2. Tool joints in patch work with a jointing tool to match the existing surrounding joints.
REPLACEMENT OF MASONRY UNITS
1. Cut out mortar joints surrounding cracked and/or damaged masonry units that are to be removed and replaced.
- Units removed may be broken and removed, providing surrounding units to remain are not damaged.
- Once the units are removed, carefully chisel out the old mortar and remove dust and debris.
- If units are located in the exterior wythe of a cavity or veneer wall, exercise care to prevent debris falling into the cavity.
2. Dampen surfaces of the surrounding units before new units are placed.
-Allow existing masonry to absorb surface moisture prior to starting installation of the new replacement units.
-Butter contact surfaces of existing masonry and new replacement masonry units with mortar.
-Center replacement masonry units in opening and press into position.
-Remove excess mortar with a trowel.
-Point around replacement masonry units to ensure full head and bed joints.
-When mortar becomes "thumbprint hard", tool joints.
CLEANING
1. Clean exposed masonry surfaces on completion.
2. Remove mortar droppings and other foreign substances from wall surfaces.
3. First wet surfaces with clean water then wash down with a solution of soap-less detergent specially prepared for cleaning brick.
4. Brush with stiff fiber brushes while washing, and immediately thereafter hose down with clean water.
5. Free clean surfaces from traces of detergent, foreign streaks or stains. Protect materials during cleaning operations including adjoining construction.
6. Use of muriatic acid for cleaning is prohibited.
RUST REMOVAL
1. Existing window lintel paint contains lead. Use proper personal protective equipment.
Properly dispose of lead containing paint debris.
2. Brush, sand or scrape substrate to remove rust and any failing paint
3. Sand or grind existing rust down to bare metal or apply rust removal solution with manufacturer recommended tools on top painted lintel of windows.
4. Remove dust or chemical residue and prepare the surface for paint.
PAINTING
1. Spot prime bare or rusted spots on metal with a rust inhibitive primer
2. New paint shall match existing paint color.
3. Furnish and install 1-2 coats (topcoat) per manufacturer recommendations.
4. Free clean surfaces from traces of remover, primer, paint streaks or stains. Protect existing non-painted surfaces during cleaning operations including adjoining construction.
5. Use of muriatic acid for cleaning is prohibited.
Section 6: Proposal Pricing & Site Walk
1) Pre-proposal Site Visit Meeting:
a) The site visit shall consist of a meeting to review construction requirements followed by a walk-thru of the project site. The meeting shall be attended by the contractor and GSA project personnel, and appropriate sub-contractors.
Contact the Project Manager to schedule a site visit.
b) Review existing conditions of the project area including any field verification.
Review the solicitation/evaluation requirements
2) Cost Proposal Requirements:
a) When submitting a proposal, provide a cost breakdown for each task into the following categories: Materials, equipment, labor hours, subcontractor's quotes, overhead, profit, and bond broken down into shell, tenant improvement (TI) (by tenant), Building- Specific Amortized Capital (BSAC), and environmental (as applicable). Follow P120 guidelines for tier level 3 based on project triage tool. Pricing shall be broken down by Construction Specification Institute (CSI) divisions.
b) Base Bid- For the repointing of the 4000SF (500 + 3,500) area called out above.
c) Optional Bid – Please submit a cost per Lineal Foot, for 100 LF of additional repointing.
Section 7: Period of Performance
Once notice to proceed has been issued, the contractor has 100 calendar days to complete the project. The contractor must also promptly begin the badging process at the time of notice to proceed. Please allow a minimum of 30 days to complete the badging process. Extensions will be granted for unforeseen conditions and other factors outside of the contractor’s control at the Contracting Officer’s discretion.
Section 8: Universal Scope Requirements
• ALL of the requirements in this section are MANDATORY for ALL GSA projects
• See the attached Universal Scope Requirements document for the full details outlining each item
• Failure to comply with any and all of the requirements will result in the project not being accepted as complete
REQUIREMENTS for ALL Projects (Construction, Design & Design/Build)
a. Safety and Health Program
b. Asbestos Containing Materials. To comply with federal and state regulations as well as GSA policy, an asbestos pre-alteration assessment is required for all construction projects as outlined in Section B of the Universal Scope Requirements.
c. Lead Containing Paint / Lead Based Paint
d. Accessibility
e. Green Purchasing
f. Construction Indoor Air Quality (IAQ) Management Plan
g. Construction Waste Diversion
Typical Project Document References
Rebates
The Contractor shall pursue any and all utility rebate and incentive programs and any government grant or incentive programs at the local, state, and federal level. Contractor is responsible for researching, submitting, and ensuring collection of all applicable rebates. Rebate opportunities must be explored for all elements of the project including but not limited to resource-saving equipment, materials, design & services (Commissioning/Recommissioning and other strategies & processes). Submit all rebate checks to:
General Services Administration Attn: Ron Burnett 1961 Stout Street Suite 01-107 Denver, CO 80294
For assistance with the rebate process please contact Doug Baughman, Regional Rebate Coordinator doug.baughman@gsa.gov (303) 941-1306
Section 9: Submittals
1) Contractor shall submit a Method of Procedures (MOP) to the GSA Delivery Project Manager (PM) for approval prior to commencement of work. At a minimum, the MOP shall include:
a) Brief narrative describing method of accomplishment, construction techniques, etc
b) Project schedule (to include critical path, major milestones, long lead time items, mob & de-mob, inspection dates, substantial completion, and occupancy dates)
c) Service/Utility Outages (if necessary)
d) Phasing schedule (if necessary)
e) Any building infrastructure/BAS equipment that may be impacted
2) All new equipment and anything requiring a preventative maintenance plan shall be inputted into Maximo upload template. Information needed from the contractor will be all: Manufacturer, Model Number, Part Number, Serial Number, Any Manufacturer Warranty Information.
3) Manufacturer's specifications, instructions and material specification sheets in original form
4) Submittal register/ log for all products specified to establish a standard of quality to include. Submittal register response by the government shall be (14) calendar days or less.
a) For pricing purposed please assume 1 hard copy of submittals and 1 electronic copy to be sent to the project manager. Distribution list including final quantities will be finalized after receipt of the submittal log/ register by GSA project manager.
5) If product samples are not submitted in a timely fashion, any delays caused by the contractor will not warrant a time extension. After completion of all work, the https://maps.google.com/?q=1961+Stout+StreetSuite+01&entry=gmail&source=g https://maps.google.com/?q=1961+Stout+StreetSuite+01&entry=gmail&source=g mailto:doug.baughman@gsa.gov tel:(303)%20941-1306
Contractor shall submit to the project manager the manufacturer's specifications, instructions and material specification sheets in original form. Additionally, the Contractor shall submit all inventory changes (removals, additions, upgrades, etc., and new condition codes) to the COR.
6) Submittal response by the government shall be (14) calendar days or less.
Section 10: General Requirements
1) Contractor Use of the Premises
a) During the period of the project, the contractor will have access to the site only during business hours of 6:00 am 6:00 pm. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Officer. The contractor will need to coordinate with the Contracting Officer to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to parking lots, any other paved areas, any items that need to be moved during the course of the project, and any areas not included in this scope of work. Any damage caused will be repaired at the contractor’s expense.
b) The contractor may work after hours as long as it is exterior work that doesn’t need access to the building. Weekends are also negotiable.
2) Progress Meetings
a) Progress meetings are not required for this project. The project manager and building team representative shall make daily inspections of the work progress.
3) Equipment The contractor shall provide all equipment associated with the entire project, operate in a safe manner and adhere to all OSHA and GSA standards.
4) Equipment and Material Storage The contractor shall provide and store all equipment, the materials specified above, and any other materials required completing the project. The materials are required to be kept clean and dry throughout the duration of the project.
Contractor to coordinate with building manager for location of storage sheds.
5) Electricity, Water, and Gas GSA will pay for electricity, water, and gas during the course of this project.
The contractor is responsible for making connections to the existing systems.
Temporary electrical work shall meet the requirements of NFPA 70-1996 (NEC), Article 305. When temporary connections are removed, restore existing utility services to their original condition.
6) Fire Watch Contractor shall be responsible for providing fire watch if required per attached GSA fire watch guidelines.
7) Fire Alarm Impairment and Hot Work When a fire suppression or alarm system impairment is required, contractor shall provide written outage request to GSA for approval in advance of impairing any systems. Contractor shall be responsible for having a GSA approved NICET certified fire alarm contractor perform all system impairments. During fire alarm/suppression impairments or hot work procedures, contractor shall provide a fire watch per the GSA Regional Fire Watch Guidelines.
8) Protection of Public The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. The contractor shall illuminate barricades and obstructions at night and maintain safe building access and egress for tenants.
9) Housekeeping The project site shall be kept in a neat, orderly, and safe condition at all times.
The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled. The contractor shall wet down dry materials and rubbish to prevent blowing dust and keep volatile wastes in covered containers.
10) Transportation and Deliveries The contractor shall arrange deliveries of materials in accordance with construction schedules; coordinate with COR to avoid conflict with other tenants and other work conditions at the site. Contractor must make GSA PM & CO aware of any lead times that may affect the project schedule.
11) Cleaning Before scheduling the final inspection, the Contractor shall accomplish six items: (1) Remove all tools, equipment, surplus material, and rubbish; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Remove grease, dirt, stains, foreign materials, and labels from finished surfaces; (4) Thoroughly clean building interiors; (5) Pickup all construction debris from the site; and (6) At time of final inspection, project shall be thoroughly cleaned and ready for use.
12) Protection of the Building The construction contractor is responsible for the protection of all existing building property for damage due to work performed under this contract. Any damage caused by the performance of this contract shall be repaired to match like or better condition at no additional cost to the government
13) Disruptive Work All painting, staining, or other activity which may cause noxious or undesirable fumes and/ or any noisy work that may be disruptive to the tenants/ public must be performed after normal working hours. The use of paint or stain that does not generate odors is preferred and may be required if the space will be occupied the following day with prior written approval from
GSA.
Section 11: Badging & Security
1) Contractor is responsible to follow GSA’s security and badging requirements as detailed in the attached Badging & Security Requirements (Vendor Fitness Determination Training Manual).
2) US Access shared enrollment centers can be found at fedidcard.gov. Travel distances to the nearest center should be accounted for during the badging process.
Section 12: Payments
1) Information regarding payment requests and payment is in the solicitation/ contract. Please contact the CO if you have any questions regarding payments.
Section 13: Substantial Completion & Final Inspection
1) When project, or designated portion of project is complete, request a final inspection. Upon receipt of request that project is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the project from being designated substantially complete.
2) Red-lined drawings and CAD and/or BIM as-built drawings, and field training for Operations and Maintenance (O&M) personnel shall be provided at completion of project. Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions using GSA CAD Standards to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue print. Provide to GSA within timeframe negotiated at time of award.
3) The contractor shall provide O&M manuals. The O&M manuals shall contain the following:
o Executed Warranties (at project completion) o Maintenance and operation manuals
Section 14: Historic Building: The Federal Building in Grand Forks, North Dakota is a
Historic Building and is listed on the National Register of Historic Places (NRID#
83004064 10/1983). As such, projects in the building are required to follow the guidelines set forth in the following publications.
▪ ADM 1020.2 GSA Procedures for Historic Properties
▪ The National Historic Preservation Act of 1966, as amended and Executive
Order 11593.
▪ The Secretary of the Interior's Standards and Illustrated Guidelines for
Rehabilitating Historic Buildings, Revised 1992 (36 CFR 67).
▪ GSA Technical Preservation Guidelines:
http://www.gsa.gov/portal/content/101402
▪ GSA Historic Preservation Technical Procedures:
http://www.gsa.gov/portal/hp/hpc/category/100371/hostUri/portal
▪ National Park Service Preservation Briefs:
http://www.nps.gov/tps/how-to-preserve/briefs.htm
▪ National Park Service Preservation Brief No. 2 Repointing Mortar Joints in Historic Buildings.
https://www.nps.gov/tps/how-to-preserve/briefs/2-repoint-mortar-joints.htm http://fedidcard.gov/ http://www.gsa.gov/portal/content/101402 http://www.gsa.gov/portal/hp/hpc/category/100371/hostUri/portal http://www.nps.gov/tps/how-to-preserve/briefs.htm
Any work that could alter the building’s historic fabric, character, or appearance, both on the interior and exterior must first be approved by the GSA Historic Preservation Officer/Historic Preservation Specialist and the North Dakota State Historic Preservation Office (SHPO) before any actions are to take place.
No construction work can begin until Section 106 of the National Historic Preservation Act (NHPA) is complete.
Section 15: Attachments
1) Universal Scope requirements
2) Badging & Security requirements (Vendor Fitness Determination & Training
Manual)
Roof Pictures
West Side Pictures
Cracks Highlighted ^
Cracks Highlighted^
"General Decision Number: ND20220014 01/07/2022
Superseded General Decision Number: ND20210014
State: North Dakota
Construction Type: Building
County: Grand Forks County in North Dakota.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).
If the contract is entered into on or after January 30, 2022, or the contract is renewed or extended (e.g., an option is exercised) on or after January 30, 2022, Executive Order 14026 generally applies to the contract. The contractor must pay all covered workers at least $15.00 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on that contract in 2022.
If the contract was awarded on or between January 1, 2015 and January 29, 2022, and the contract is not renewed or extended on or after January 30, 2022, Executive Order 13658 generally applies to the contract. The contractor must pay all covered workers at least $11.25 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on that contract in 2022.
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/07/2022
* BOIL0647-006 01/01/2021
Rates Fringes
BOILERMAKER......................$ 40.94 28.44
ELEC1426-007 06/01/2021
Rates Fringes
ELECTRICIAN......................$ 33.04 11.5%+$11.98
IRON0512-006 05/03/2021
Rates Fringes
IRONWORKER, STRUCTURAL...........$ 34.30 31.80
* PLAS0633-003 05/01/2021
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 33.88 16.87
PLASTERER........................$ 25.47 14.88
PLUM0300-020 06/07/2021
Rates Fringes
PIPEFITTER.......................$ 38.19 17.42
SHEE9010-002 06/03/2019
Rates Fringes
SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 30.65 17.60
SUND2012-003 08/18/2014
Rates Fringes
BRICKLAYER.......................$ 23.47 12.34
CARPENTER........................$ 19.16 3.88
DRYWALL FINISHER/TAPER...........$ 21.48 6.66
DRYWALL HANGER AND METAL STUD
INSTALLER........................$ 19.60 4.34
INSULATOR - MECHANICAL
(Duct, Pipe & Mechanical System Insulation)...............$ 15.80 2.60
LABORER: Common or General......$ 12.99 2.81
LABORER: Mason Tender - Brick...$ 15.32 0.00
LABORER: Mason Tender - Cement/Concrete..................$ 14.54 3.41
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 26.00 3.82
OPERATOR: Crane.................$ 26.18 9.39
OPERATOR: Forklift..............$ 23.06 15.47
OPERATOR: Loader................$ 23.75 0.00
PAINTER (BRUSH AND ROLLER),
Excludes Drywall Finishing/Taping.................$ 21.86 8.41
PLUMBER..........................$ 21.64 4.98
ROOFER...........................$ 16.37 2.84
SHEET METAL WORKER, Excludes HVAC Duct Installation...........$ 27.27 7.76
TRUCK DRIVER: Dump Truck........$ 19.81 5.42
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union, which prevailed in the survey for this classification, which in this example would be Plumbers 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Division National Office Branch of Wage Surveys. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"
II. Prices
II.A. Basis of Pricing
(1) Contract Prices. All Contract prices set forth in this Section include all costs necessary to complete the work for which the price is established (e.g., Base Contract, Unit Price, Options) in accordance with the Contract Documents, including, but not limited to, the cost of work performed by subcontractors and consultants, indirect costs, fees, expenses, taxes, and profit.
(2) Knowledge of Conditions Affecting Price. FAR 52.236-3, Site Investigations and Conditions Affecting the Work, is incorporated by reference in this Contract. The Contractor shall be presumed to have established all prices with knowledge of general and local conditions that may affect the cost of Contract performance at the site where the Work is to be performed, to the extent that such information is reasonably obtainable.
(3) Unit Prices and Allowances. If any portion of the Work is to be performed on a unit price basis, the Unit Price shall include all costs of coordinating and incorporating the unit-priced portion of the Work into the Base Contract Work. The Contractor shall only be obligated to perform unit-priced work to the extent that an Allowance has been established. The Contractor shall be obligated to perform such work in excess of a unit quantity for which an Allowance is established only if directed by the Contracting Officer in writing. The Contractor shall be bound to the unit price or prices set forth herein in all equitable adjustments for changes including unit priced work, and no markups shall be applied to such unit prices.
(4) Options. If any portion of the Work is to be performed upon the timely exercise of an Option, the Option Price shall include all costs of coordinating and incorporating the Option-priced portion of the Work into the Base Contract Work. An adjustment to the Contract price for such additional work shall be computed solely on the basis of the Option price or prices set forth herein. Unless otherwise specified, all options may be exercised within 90 days of Contract award.
(5) Bid Rates. If this Contract includes Bid Rates to be used in determination of equitable adjustments (e.g., overhead, profit, daily rates for time-related costs), such rates shall be deemed to include all costs recoverable as components of an equitable adjustment consistent with the requirements, definitions, and exclusions applicable to equitable adjustments set forth in this Contract, and consistent with the Contractor's cost accounting practices. Unless otherwise specified, the bid rates shall be deemed to include only the Contractor's costs, and not the costs of any subcontractors.
II.B. Contract Price Form
Please use SF 1442 and attach price breakdown of offer on separate document.
III. Terms and Conditions
III.A. Commencement, Prosecution, and Completion of Work
FAR 52.211-10, Commencement, Prosecution, and Completion of Work and GSAR 552.211-10, Commencement, Prosecution and Completion of Work is supplemented as follows:
The Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of the Work, as defined in GSAR 552.211-70 Substantial Completion (Mar 2019) and the time specified in Section I (Project Information), “Period of Performance” clause. If the Contract specifies different completion dates for different phases or portions of the Work, the Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of such phases or portions of the Work within the times specified.
III.B. Contractor Responsibilities
GSAR 552.236-71, Contractor Responsibilities is located in Section IV.A. of this Agreement and is supplemented as follows:
(1) The Contractor shall secure and pay for all necessary permits and governmental fees, licenses, and inspections that are customarily secured after award of the Contract and that are legally required at the time of award. The Contractor shall provide a copy of the permits required for execution of the work to the Contracting Officer prior to commencement of any related work.
III.C. Material and Workmanship
All equipment, material, and articles incorporated into the Work shall be new and of the most suitable grade for the purpose intended, unless otherwise specified in this Contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number shall be regarded as establishing a standard of quality and performance and shall not be construed as limiting competition.
Unless specifically directed by the Contracting Officer, the Contractor may use any equipment, material, article, or process that is equal to that named in the specifications, so long as it is of comparable quality and meets specified characteristics, or, if no such characteristics are specified, the relevant performance characteristics of the specified item.
III.D. Project Schedule
(1) The Project Schedule shall be a rational, reasonable and realistic plan for completing the Work, and conform to requirements specified in this clause and elsewhere in this Contract.
(2) The Contractor understands and acknowledges that the preparation and proper management of the Project Schedule is a material component of the Work, and that the Contract price includes all costs of compliance with Project Schedule requirements.
(3) The Project Schedule shall depict all major activities necessary to complete the Work.
(4) Prior to NTP, the Contractor shall submit its Project Schedule to the Contracting Officer. The Contractor shall submit the Project Schedule in PDF and hardcopy print format.
(5) The Project Schedule shall incorporate both major tasks as well as milestone events specified in the Contract, including, as applicable, NTP, Substantial Completion, and milestones related to specified work phases and site restrictions. The Project Schedule shall also include Contractor-defined milestones to identify target dates for critical events, based upon the Contractor's chosen sequence of work and be linked to the tasks that drive those milestones.
(6) Unless a shorter period for updates is specified elsewhere, the Contractor shall update the Project Schedule weekly to reflect its actual progress in completing the Work, and submit the updated Project Schedule to the Contracting Officer.
(7) If the Contractor revises the Project Schedule after initial submission, the Contractor shall provide in writing to the Contracting Officer a narrative describing the substance of the revision, the rationale for the revision, and the impact of the revision on the projected substantial completion date.
(8) If at any time the Contracting Officer finds that the Project Schedule does not comply with any Contract requirement, the Contractor shall, upon written notice of exceptions taken by the Contracting Officer, revise the Project Schedule, adjust activity progress, or provide sufficient information demonstrating compliance.
(9) If the Contractor fails to sufficiently address the Contracting Officer's exceptions to the Project Schedule within # calendar days [CO Note: Include appropriate time frame] of written notice of same, the Contracting Officer may withhold retainage until the Project is Substantially Complete or until such time as the Contractor has complied with Project Schedule requirements.
(10) The Contracting Officer shall be entitled, but not required, to rely upon the Project Schedule to evaluate the Contractor's progress, evaluate entitlement to extensions of time, and determine the criticality or float of any activities described in such Project Schedule.
III.E. Interpretation of Specifications and Drawings
(1) The specifications and drawings shall be interpreted to complement each other. Requirements set forth in the specifications and not shown on the drawings, or shown on the drawings and not set forth in the specifications, shall be of like effect as if shown or set forth in both.
(2) Different requirements within the Contract Documents shall be deemed inconsistent only if compliance with both cannot be achieved.
(3) If a requirement set forth in one location is more restrictive than that set forth elsewhere in the Contract Documents, requirements set forth in specifications shall govern over requirements set forth in drawings; otherwise, the more restrictive shall govern.
(4) In case of inconsistent requirements within the drawings, the following order of precedence shall apply:
(a) Requirements indicated in large-scale drawings shall govern over inconsistent requirements indicated in small-scale drawings.
(b) Requirements indicated in schedules shall govern over inconsistent information shown in drawings.
(5) Unless otherwise noted, the drawings shall be interpreted to provide for a complete construction, assembly, or installation of the Work, without regard to the detail with which material components are shown in the drawings.
(6) If any inconsistency within the drawings or specifications cannot be reconciled by reference to this clause, the Contractor shall promptly request a determination from the Contracting Officer as to which requirement shall govern. Election by the Contractor to follow either requirement without a determination from the Contracting Officer shall be at the Contractor's risk; should the Contracting Officer subsequently determine that the requirement not followed by the Contractor governs, the Contractor shall be responsible for all cost and time required to comply with the Contracting Officer's determination.
III.F. Submittals
(1) The Contractor shall prepare and submit to the Contracting Officer shop drawings, samples, calculations, product information, mockups, GSA Form 184 (associated 184A and 184B as necessary) and other submittals (collectively, "submittals") demonstrating compliance with Contract requirements for all Work components as specified elsewhere in this Contract. If particular submittal requirements are not specified for a component of the Work, the Contractor shall prepare submittals for such Work as directed by the Contracting Officer.
(2) Prior to submission, the Contractor shall review all submittals for accuracy, completeness, compliance with Contract requirements, and coordination between different trades and subcontractors. The Contractor shall indicate its approval on all submittals as evidence of such review and coordination. Submittals submitted to the Contracting Officer without evidence of the Contractor’s approval may be rejected without further review.
(3) The Contractor shall not proceed with work or procure products or materials described or shown in submittals until the Contracting Officer has indicated approval of the submittal.