Gilcher-Crissman Park Pavilion - Bid Book.pdf

PDF 20 MB Posted

Attached to
Gilcher-Crissman Park Pavilion
Solicitation number
20408.01A
Issued by
Macomb County, Michigan

About this file

The document is a comprehensive bid package for the Gilcher-Crissman Park Pavilion project, issued by the Washington, Bruce and Romeo Parks and Recreation Commission in Macomb County, Michigan. The project involves constructing a 5,040 square foot open-air pavilion with associated concrete pavement, footings, and electrical work at Gilcher-Crissman Park. Sealed bids will be received until 2:00 PM on Monday, May 5, 2025, with a bid opening scheduled for the same day. The contract will be awarded as a single prime contract on a lump sum and unit price basis, with a substantial completion date of Monday, December 15, 2025, and final completion by Thursday, April 30, 2026.

The project has unique environmental considerations, as the site is officially recognized as a "facility" with historical contamination from orchard operations. No excavated material can be used offsite, and a one-foot clean topsoil cap must be maintained above contaminated fill. The bid includes various line items such as mobilization, non-hazardous material handling, clean fill, erosion control, and a cash allowance for permits. The estimated contract value will be determined through unit pricing, with bidders required to provide a bid bond and meet specific insurance and bonding requirements. Contractors must also submit qualifications, including experience, financial data, and evidence of ability to perform the work, with bids to be evaluated based on responsiveness, responsibility, and lowest price.

View the file

Other files

File Type Posted
Gilcher-Crissman Park Pavilion - Bid Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

#20408.01

Prepared By

Gilcher-Crissman Park Pavilion

Washington Township Macomb County, Michigan

Issued for Bids:

April 15, 2025

361 Morton St. Romeo MI 48065

6303 26 Mile Road, Suite 100 Washington Township, MI 48094

BID SET

BIDDING DOCUMENTS:

#20408.01 Washington, Bruce and Romeo Parks and Recreation Commission Gilcher-Crissman Park Pavilion

Giffels Webster 00 01 10-1 Table of Contents

Washington, Bruce and Romeo Parks and Recreation Commission

BIDDING AND CONTRACT DOCUMENTS

Gilcher-Crissman Park Pavilion

GIFFELS WEBSTER PROJECT NO ...................................................... 20408.01

TABLE OF CONTENTS

Procurement and Contracting Requirements Group

Division 00 - Procurement and Contracting Requirements Section Pages Project Title Page ............................................................................................................. 00 01 01 1 Table of Contents ............................................................................................................ 00 01 10 2 Advertisement for Bids .................................................................................................... 00 11 13 2 Instructions to Bidders .................................................................................................... 00 21 13 10 Preliminary Schedules ..................................................................................................... 00 31 13 1 Geotechnical Data ........................................................................................................... 00 31 32 50 Permits ............................................................................................................................. 00 31 46 1 Bid Form - Unit Price (Single-Prime Contract) ................................................................. 00 41 43 6 Bid Security Form............................................................................................................. 00 43 13 2 Bidder's Qualifications ..................................................................................................... 00 45 13 11 Agreement Form - Stipulated Sum .................................................................................. 00 52 13 8 Performance Bond Form ................................................................................................. 00 61 13.13 2 Payment Bond Form ........................................................................................................ 00 61 13.16 2 Maintenance Bond Form ................................................................................................. 00 61 19 3 Application for Payment Form ........................................................................................ 00 62 76 1 Request for Interpretation Form ..................................................................................... 00 63 13 1 Field Order Form.............................................................................................................. 00 63 36 1 Work Change Directive Form .......................................................................................... 00 63 49 1 Change Order Form ......................................................................................................... 00 63 63 1 Certificate of Completion Form ....................................................................................... 00 65 19 1 General Conditions .......................................................................................................... 00 72 00 65 Supplementary Conditions .............................................................................................. 00 73 00 12 Addenda .......................................................................................................................... 00 91 13 2

Specifications Group

Division 01 - General Requirements Section Pages General Requirements ..................................................................................................... 01 00 00 61

Division 02 - Division 30 NOT USED

Division 31 - Earthwork Section Pages Soils for Earthwork .......................................................................................................... 31 05 13 2 Aggregates for Earthwork ................................................................................................ 31 05 16 2 Earth Moving ................................................................................................................... 31 20 00 7 Grading ............................................................................................................................ 31 22 00 8 Trenching ......................................................................................................................... 31 23 16.13 4 Backfill.............................................................................................................................. 31 23 23.13 3

Division 32 - Exterior Improvements Section Pages

Giffels Webster 00 01 10-2 Table of Contents

Selective Demolition for Exterior Improvements ............................................................ 32 05 05 5 Aggregate Base Courses .................................................................................................. 32 11 23 2 Concrete Paving ............................................................................................................... 32 13 13 8 Soil Preparation ............................................................................................................... 32 91 13 3 Seeding ............................................................................................................................ 32 92 19 3 Plants ............................................................................................................................... 32 93 00 7

Division 33 - Division 49 NOT USED

Additional Materials Section Pages A Contractors Guide to Storm Water Pollution Prevention ............................................ N/A 2

Special Provisions Related to the 2020 MDOT Standard Specifications Date 2057021 Subgrade Undercutting, Type II, Modified ....................................................... 4/11/2025 20SP-205A-01 Non-Hazardous Contaminated Material Handling and Disposal ............. 3/2/2020

List of Drawing Sheets Cover Sheet...................................................................................................................... CP-01 General Notes & Legend .................................................................................................. CP-02 Existing Conditions .......................................................................................................... CP-03 Site Plan ........................................................................................................................... CP-04 Details .............................................................................................................................. CP-05 Soil Erosion & Sediment Control Notes & Details ........................................................... CP-06

EJCDC® C-111, Suggested Advertisement for Bids for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 11 13-1 Advertisement for Bids

WASHINGTON, BRUCE AND ROMEO PARKS AND RECREATION COMMISSION

MACOMB COUNTY, MICHIGAN

GILCHER-CRISSMAN PARK PAVILION

(#20408.01)

ADVERTISEMENT FOR BIDS

Sealed Bids for the Gilcher-Crissman Park Pavilion Project (#20408.01) will be received, by the Washington, Bruce and Romeo Parks and Recreation Commission at the Bruce Township offices at 223 East Gates Street Romeo, MI 48065, until 2:00PM local time on a Bid Opening date of Monday, May 5, 2025, at which time the Bids received will be publicly opened and read. Any Bids received after said Bid Opening date and time will not be valid or opened and will be returned to the Bidder.

The Project consists of constructing a 5040 square foot open air pavilion at Gilcher-Crissman Park with associated concrete pavement, footings, and electrical. The contractor is responsible for jobsite cleanup and for hauling any debris created as a result of the project to an approved disposal facility (assuming Type II Landfill) per the environmental documents dated April 20, 2002, September 23, 2003, February 14, 2025 (attached). This site has been officially recognized as a “facility” in the attached environmental documents so no excavated material can be used offsite and there must be a one-foot clean topsoil cap above any contaminated fill.

Bids will be received for a single prime Contract on a lump sum and unit price basis. The Issuing Office for the Bidding Documents is as follows:

Washington, Bruce and Romeo Parks and Recreation Commission 361 Morton St. Romeo MI 48065

For any specific questions regarding this advertisement, please contact Parks and Recreation Director Clara Russell at (586) 752-6543 or russellc@rwbparksrec.org by 5:00PM Monday, April 28, 2025.

Questions received after this time will not be answered. Prospective Bidders may obtain copies of the Bidding Documents from the Issuing Office as described below.

All Bidding Documents and addenda will be available on the internet starting April 15, 2025 where they can be viewed and downloaded electronically.

Bid Documents are available through the following organization(s):

Michigan Inter-governmental Trade Network https://www.bidnetdirect.com/mitn

Distribution of the Bid Documents through any means of delivery should be coordinated by the Bidder at their own cost. The date that the Bidding Documents are transmitted from the above organization(s) will be considered the Bidder’s date of receipt of the Bidding Documents. Partial sets of the Bidding Documents will not be available.

Sealed Bids shall be submitted on the forms provided in the Bid Documents. Bid security shall be furnished in accordance with the Instructions to Bidders, payable to the Washington, Bruce and Romeo Parks and Recreation Commission.

Each Bidder agrees to waive any claim it has or may have against the Owner, Engineer, and their respective Employees, arising out of or in connection with the administration, evaluation, or recommendation of any Bid.

EJCDC® C-111, Suggested Advertisement for Bids for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 11 13-2 Advertisement for Bids

The Owner reserves the right to accept or reject any or all base or alternative Bid items of work, in whole or in part, and to waive any informalities, therein when such waiver is in the interest of the Owner, and to award the Contract to other than the low Bidder.

Bids shall remain firm for a period of 120 days.

Owner: Washington, Bruce, and Romeo Parks and Recreation Commission

By: Clara Russell

Title: Parks and Recreation Director

Date: April 15, 2025

+ + END OF ADVERTISEMENT FOR BIDS + +

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-i Instructions to Bidders

INSTRUCTIONS TO BIDDERS

TABLE OF CONTENTS

Page

ARTICLE 1 – Defined Terms

ARTICLE 2 – Copies of Bidding Documents

ARTICLE 3 – Qualifications of Bidders

ARTICLE 4 – Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

ARTICLE 5 – Bidder’s Representations

ARTICLE 6 – Pre-Bid Conference

ARTICLE 7 – Interpretations and Addenda

ARTICLE 8 – Bid Security

ARTICLE 9 – Contract Times

ARTICLE 10 – Liquidated Damages

ARTICLE 11 – Substitute and “Or-Equal” Items

ARTICLE 12 – Subcontractors, Suppliers, and Others

ARTICLE 13 – Preparation of Bid

ARTICLE 14 – Basis of Bid

ARTICLE 15 – Submittal of Bid

ARTICLE 16 – Modification and Withdrawal of Bid

ARTICLE 17 – Opening of Bids

ARTICLE 18 – Bids to Remain Subject to Acceptance

ARTICLE 19 – Evaluation of Bids and Award of Contract

ARTICLE 20 – Bonds and Insurance

ARTICLE 21 – Signing of Agreement

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-1 Instructions to Bidders

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office – The office from which the Bidding Documents are to be issued.

B. Owner – One who the bid is submitted to, Washington, Bruce and Romeo Parks and Recreation Commission.

C. Bidder – One who submits the Bid directly to the Owner as distinct from a sub-bidder, who submits a bid to a Bidder.

D. Successful Bidder – The lowest, responsible, and responsive Bidder to whom the Owner (on the basis of the Owner’s evaluation as herein provided) makes an award.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office in the number and format stated in the advertisement or invitation to bid.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, Bidder shall submit with its Bid (a) written evidence establishing its qualifications such as financial data, previous experience, and present commitments, and (b) the following additional information:

A. Evidence of Bidder’s authority to do business in the state where the Project is located.

B. Bidder’s state or other contractor license number, if applicable.

C. Subcontractor and Supplier qualification information; coordinate with provisions of Article 12 of these Instructions, “Subcontractors, Suppliers, and Others.”

D. Other required information regarding qualifications.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-2 Instructions to Bidders

ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

4.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

4.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify:

a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.

b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

c. reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings. These reports and drawings, if they exist, are available by request only.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site are set forth in the Contract Documents and are based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.

C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-3 Instructions to Bidders

4.03 Site Visit and Testing by Bidders

A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.

B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

C. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.

D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

4.04 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. As the General Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary Conditions.

4.05 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 5 – BIDDER’S REPRESENTATIONS

5.01 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;

B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;

C. become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;

D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-4 Instructions to Bidders

Conditions, if any, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings;

E. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, if any, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;

F. agree, based on the information and observations referred to in the preceding paragraph, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;

G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;

H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;

I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work;

and

J. agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

ARTICLE 6 – PRE-BID CONFERENCE

6.01 A pre-Bid conference will be held with details given in Section 00 31 13 Preliminary Schedules.

Bidders are encouraged to submit any questions or comments in writing to the contact person indicated on the Advertisement for Bids.

ARTICLE 7 – INTERPRETATIONS AND ADDENDA

7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer in writing. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all parties recorded as having received the Bidding Documents. Questions received less than five days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding.

Oral and other interpretations or clarifications will be without legal effect.

7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents as deemed advisable by the Owner or Engineer.

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-5 Instructions to Bidders

ARTICLE 8 – BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of five percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a certified check, bank money order, or a Bid bond (on the form included in the Bidding Documents) issued by a surety meeting the requirements of Paragraphs 6.01 and 6.02 of the General Conditions.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within fifteen (15) days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Contract or 91 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within seven days after the Bid opening.

ARTICLE 9 – CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be substantially completed and ready for final payment are set forth in the Agreement.

ARTICLE 10 – LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS

11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.

11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-6 Instructions to Bidders

ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS

12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals or entities for the performance of the Work if required by the Bidding Documents (most commonly in the Specifications) to do so. If a prospective Bidder objects to retaining any such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or Contractor to retain any Subcontractor, Supplier, or other individual or entity against which Contractor has reasonable objection.

12.03 The apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work: Pavilion Building

If requested by Owner, such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder shall submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

12.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.

ARTICLE 13 – PREPARATION OF BID

13.01 The Bid Form is included with the Bidding Documents; additional copies may be obtained from the Engineer.

A. All blanks on the Bid Form shall be completed in ink or typed and the Bid Form signed in ink. Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate seal shall be affixed and attested by the corporate secretary or an assistant corporate secretary. The corporate address and state of incorporation shall be shown.

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-7 Instructions to Bidders

A. A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership shall be shown below the signature.

13.03 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown.

13.04 A Bid by an individual shall show the Bidder’s name and official address.

13.05 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown.

13.06 All names shall be typed or printed in ink below the signatures.

13.07 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

13.08 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.

13.09 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.

ARTICLE 14 – BASIS OF BID

14.01 Lump Sum

A. Bidders shall submit a Bid on a lump sum basis as set forth in the Bid Form.

14.02 Unit Price

A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

14.03 Allowances

A. For cash allowances the Bid price shall include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-8 Instructions to Bidders

ARTICLE 15 – SUBMITTAL OF BID

15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 7 of the Bid Form.

15.02 A Bid shall be received no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid and shall be enclosed in a plainly marked package with the Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted), the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid shall be addressed to the location indicated in the advertisement or invitation to bid.

15.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID

16.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.

16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.

ARTICLE 17 – OPENING OF BIDS

17.01 Bids will be opened publically. A Bid tabulation of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that Owner believes would not be in the best interest of the Project to make an award to that bidder

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-9 Instructions to Bidders or finds, after reasonable inquiry and evaluation, to not be responsible whether, including without limitation, because the Bid is not reasonable, the Bidder is unqualified or of doubtful financial ability to meet any other pertinent standard, or criteria established by the Owner. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive; provided that Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work and to negotiate contract terms with the bidder.

19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid whose evaluation by the Owner indicates to the Owner that the award will be in the best interests of the Project. Bid alternates will be considered in making this evaluation and shall be a mandatory requirement for a responsive Bidder. The Township reserves the right to accept or reject any or all base or alternative Bid items of work, in whole or in part, and to waive any informalities, therein when such waiver is in the interest of the Owner, and to award the contract to other than the low Bidder.

19.03 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.

19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidders, whether or not the bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award and may consider the qualifications and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other persons and organizations must be submitted as provided in the Bidding Documents. Owner also may consider the operating costs, maintenance requirements, performance data, and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award.

19.05 Owner may conduct such investigations as Owner deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors, Suppliers, and other persons and organizations to perform and furnish the Work in accordance with the Contract Documents to Owner’s satisfaction within the prescribed time.

ARTICLE 20 – BONDS AND INSURANCE

20.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to insurance. When the Successful Bidder delivers the Agreement (executed by Successful Bidder) to Owner, it shall be accompanied by required insurance documentation.

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts. Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Giffels Webster 00 21 13-10 Instructions to Bidders

ARTICLE 21 – SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder shall execute and deliver the required number of counterparts of the Agreement (and any bonds and insurance documentation required to be delivered by the Contract Documents) to Owner. Within 10 days thereafter, Owner shall deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents, including a complete set of Drawings with appropriate identification as stated in Paragraph 2.02 of the General Conditions.

Giffels Webster 00 31 13-1 Preliminary Schedules

PRELIMINARY SCHEDULES

Start site work after receiving the Notice to Proceed. The date indicated on the Notice to Proceed is the date at which Contract times commence. In no case shall site work be commenced prior to receipt of a formal Notice to Proceed by the Owner.

The tentative scheduled dates of activity are as follows:

Tuesday, April 15, 2025 Bid Package available for pickup (Bid issue date)

Monday, April 28, 2025 Pre-Bid opening questions due to issuing office by 5:00PM

Monday, May 5, 2025 Bids due; Bid Opening at 2:00PM

Thursday, May 15, 2025 Owner awards Contract and issues Notice of Award

Monday, May 19, 2025 Owner delivers three unsigned books to Bidder for review and signature

Tuesday, June 3, 2025 Contractor delivers bonds, insurance, and signed books to Owner

Friday, June 13, 2025 Owner signs Contract (Effective Date of the Contract), delivering one Project Manual to Contractor and one to Engineer

Friday, June 20, 2025 Pre-Construction Meeting: Owner issues Notice To Proceed stating date of Contract Time Commencement

Friday, June 20, 2025 Contract Times Commence

Monday, December 15, 2025 Substantial Completion Date

Thursday, April 30, 2026 Final Completion Date

Perspective Bidders will be required to participate in the pre-construction and (if applicable) pre-bid meetings with Owner and Engineering representatives to discuss a detailed Progress Schedule. The Owner will arrange the time and place for the meetings. The Progress Schedule shall include, at a minimum, the controlling work items for the completion of the project, the planned dates that these work items will be controlling operations, and the dates of Substantial and Final Completion.

Note that the above tentative schedule does not preclude the Owner from utilizing other requirements of the project related to timing in the Instructions to Bidders and General Conditions. Furthermore, Contractors shall coordinate all work with the Owner to ensure conflicts between this project and any other concurrent projects are avoided. Failure on the part of the Contractor to carry out provisions of this section as established may be sufficient cause to prevent bidding on future projects with the Owner.

#20408.01 Charter Township of Washington

Giffels Webster 00 31 32-1 Geotechnical Data

GEOTECHNICAL DATA

The following reports should be used by the contractor to determine environmental safety procedures during construction:

1. Stratford Park BEA prepared by McDowell & Associates on April 20, 1999 (8 pages).

2. Stratford Park Section 7a Compliance Analysis prepared by McDowell & Associates on April 20, 1999 (4 pages).

3. Letter of Determination prepared by The Michigan Department of Environmental Quality (now Environment, Great Lakes, and Energy) on July 22, 1999 (2 pages).

4. Status Letter prepared by McDowell & Associates on October 17, 2002 (2 pages).

5. Letter of Land Acquisition Recommendation with Enclosures prepared by Professional Engineering Associates, Inc (now PEA Group) on September 23, 2003 (20 pages).

6. Risk Mitigation Plan for Construction Activities prepared by Atlas Technical Consultants, LLC on February 14, 2025 (12 pages).

e

RISK MITIGATION PLAN

GILCHER-CRISSMAN PARK CONSTRUCTION

240VAP2502

6859 29 Mile Road

Washington, MI 48095

PREPARED FOR:

WBR Parks and Recreation Commission and Mr. Brent Kraft, PE Giffels Webster 6303 26 Mile Road, Suite 100 Washington, MI 48094

PREPARED BY:

Atlas Technical Consultants LLC 46555 Humboldt Drive, Suite 100 Novi, MI 48377 February 14, 2025

Copyright Protected Photograph Property of RWB Parks & Recreation

Page | 1

46555 Humboldt Drive, Suite 100 Novi, MI 48377

(248) 669-5140 | oneatlas.com

February 14, 2025 Atlas No. 240VAP2502

MR. BRENT KRAFT, PE

GIFFELS WEBSTER

6303 26 MILE ROAD, SUITE 100

WASHINGTON, MI, 48094

Subject: Risk Mitigation Plan

Reference: Risk Mitigation Plan for Construction Activities at Gilcher-Crissman Park

Dear Mr. Kraft:

Atlas is pleased to present this Risk Mitigation Plan (RMP) outlining the procedures to be followed to ensure the health and safety of construction workers during construction activities at Gilcher-

Crissman Park in Washington, Michigan.

If you have any questions, please do not hesitate to contact us.

Respectfully submitted, Atlas Technical Consultants LLC

Nate Wanner, CPG Joshua Schuyler Senior Project Manager Regional Operations, Area Manager, MI Direct: 614-917-8406 Direct: 248-863-2666 Email: nate.wanner@oneatlas.com Email: joshua.schuyler@oneatlas.com mailto:nate.wanner@oneatlas.com mailto:ron.santos@oneatlas.com

Atlas No. 240VAP2502 Gilcher-Crissman Park Risk Mitigation Plan

Page | i

CONTENTS

EXECUTIVE SUMMARY

1. PURPOSE OF THE RISK MITIGATION PLAN

2. IMPLEMENTING THE RISK MITIGATION PLAN

3. POTENTIAL HEALTH RISKS

3.1 Arsenic

3.2 Lead

4. PRECAUTIONS AGAINST EXPOSURES

5. ACTIONS TO BE TAKEN IF SIGNIFICANT EXPOSURES OCCUR

6. HANDLING CONTAMINATED ENVIRONMENTAL MEDIA

7. NOTICE TO CONTRACTORS AND WORKERS

8. RECORD KEEPING AND REPORTING

9. MODIFICATION AND TERMINATION CRITERIA

APPENDICES

Risk Migitation Plan Acknowledgement Form

EXECUTIVE SUMMARY

Based upon the historical documents provided to Atlas, soils at the Property were contaminated with arsenic during historical operation as an orchard. Detected concentrations ranged from 1.8 mg/kg to 62 mg/kg and exceeded Residential Direct Contact criterion (7.6 mg/kg), Site-Specific

Background Levels (16 mg/kg), and Non-Residential Direct Contact criterion (37 mg/kg). The orchard area was subsequently capped with approximately one (1) foot of topsoil. This clean soil cap serves as an exposure barrier to prevent direct contact with contaminated soils.

Concentrations of arsenic in cap materials ranged from 2.7 mg/kg to 10 mg/kg (below Site-

Specific Background Levels).

Because contaminated soils remain in place, care must be taken to mitigate or eliminate human exposure to the contaminants during construction activities which may expose the contaminated soil. This includes:

1. Informing construction workers of health and safety measures to be followed.

2. Restricting public access to the construction site with fencing.

3. Employing dust control measures during construction, as necessary.

4. Appropriate handling of all excavated and disturbed soil.

5. Appropriate characterization and disposal of any excavated soil that will be removed from the…