This is a Task Assignment Amendment scope of work document for professional stormwater and environmental engineering services between Geosyntec Consultants, Inc. and Volusia County, Florida for post-design construction support services related to the Lantern Park Stormwater Pond project. The project addresses flooding mitigation at Lantern Park, a 168-home subdivision in South Daytona that experienced significant damage during Hurricanes Ian and Milton due to an overwhelmed stormwater pond. Geosyntec will provide comprehensive post-design construction support services including bid support with addendum preparation, pre-construction meeting coordination, contractor requests for information (RFI) review and response within five working days, shop drawing review and approval within five working days, plan sheet revisions, construction observation visits with documentation (estimated at six visits), attendance at up to nine progress meetings, work change directive support, substantial and final completion inspections with punch list development, and final record drawing review and certification. The estimated project schedule is 12 months for completion.
Geosyntec proposes a lump sum fee of $41,591.52 based on an estimated 214 total manhours distributed across multiple pay grades ranging from $58 to $244 per hour, with an expenses allowance of 2 percent of labor fees ($815.52). The project is funded through a U.S. Department of Housing and Urban Development Community Development Block Grant for Disaster Recovery (CDBG-DR) administered by Volusia County's Office of Recovery and Resiliency (ORR). Billing will be structured on a lump sum task percent complete basis with invoices detailing accomplished work, budget invoiced, overall budget expended, and budget remaining, accompanied by narrative status reports. All deliverables will be provided via email in PDF format where applicable, and Geosyntec will maintain logs of all RFIs and submittals throughout the construction phase.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11301 Corporate Blvd., Suite 155 Orlando, Florida 32817
PH 407.321.7030
www.geosyntec.com
June 12, 2026
Jane Dai, PE CFM Volusia County Public Works 123 W Indiana Avenue, Suite 402 DeLand, FL 32720
Subject: Task Assignment Amendment for Lantern Park Stormwater Pond Post Design Construction Support
Services Professional Stormwater and Environmental Engineering Services - Contract No. 24-SQ-101KW Volusia County, Florida
Dear Ms. Dai:
Geosyntec Consultants, Inc. (Geosyntec) is pleased to provide this proposal for providing our services for the above referenced project.
BACKGROUND
Lantern Park is a 168-home subdivision located off of Reed Canal Road in South Daytona. The subdivision was constructed in the 1960s without a stormwater pond. Prior to Hurricane Ian in 2022, the City purchased a 1.42 acre vacant track at the front of the subdivision and constructed a stormwater pond. The pond has a pump station that conveys water into Reed Canal before, during, and after a storm. During Hurricane Ian, the pond became overwhelmed and the majority of the homes located here flooded. During Hurricane Milton, the pond once again became overwhelmed and most of the homes flooded yet again.
Geosyntec recently completed a stormwater improvement design aimed at mitigating flooding in the Lantern Park subdivision. The County has asked Geosyntec to prepare this scope of work for post design construction support services. This scope of work includes the tasks necessary to support the County during the construction phase of the stormwater improvements.
SCOPE OF WORK
The consultant shall perform the following scope of services to meet the goals of the project. Estimated costs to perform these services are provided in Attachment A.
1. TASK 1: Post Design Construction Support Services – Geosyntec will assist the County with the following post design construction support services.
Bid Support – Geosyntec will answer design related questions from potential bidders and provide addendum support if necessary.
Pre-Construction Meeting and Meeting Summary – Geosyntec will attend a pre-construction meeting and answer questions from the Contractor and Subcontractors. Geosyntec will prepare an agenda and submit a meeting summary via email to the County Project Manager including a summary of the questions and responses during the pre-construction meeting.
Contractor Requests for Information (RFIs) – Geosyntec will review and process all Requests for Interpretation/Information (RFI) by providing technical interpretation of the plans/drawings and specifications;
evaluate requested deviation from the approved design or specification; review and respond to RFIs. Responses to Contractor RFIs will be provided to the County Project Manager via email within five (5) working days of receipt. Geosyntec will maintain a RFI log of all RFIs submitted to Geosyntec.
Contractor Shop Drawing Submittals – Geosyntec will review and process all Contractors’ submittals concerning product data, shop drawings and other submissions as required for general conformance with design concept of this Project and the Contract Documents in consultation with the County Project Manager. All
Lantern Park Stormwater Pond Post Design Construction Support Services Volusia County, Florida June 2026 approved Contractor‘s submittals will bear the Geosyntec stamp and be delivered to the County Project Manager via email within 5 working days of receipt. Geosyntec will maintain at all times a Submittal log of all submittals sent to Geosyntec.
Plan Sheet Revisions – Geosyntec will prepare supplementary sketches as may be necessary for clarification of construction plans and assist in resolving actual field conditions encountered.
Construction Observation Visits and Progress Meetings – Geosyntec will conduct construction site visit observations concerning the installation of the work to observe the progress and quality of the work and to determine, in general, if the work is proceeding in accordance with the intent of the Contract Documents. Each construction observation will be documented in a Construction Observation Report that is forwarded via email to the County Project Manager. Geosyntec will route all job correspondence to the Contractors through the County Project Manager.
The number of Construction Observation Visits and Reports will be dependent on the Contractor’s construction schedule, which is currently not known. It is assumed for budgetary purposes that six (6) Construction Observation Visits and Reports are proposed.
Geosyntec will attend up to nine (9) progress construction meetings with the County Project Manager and staff to discuss project progress and status, technical issues, and upcoming events and activities. Geosyntec will prepare and distribute a meeting summary via email following each of these meetings.
Work Change Directives Support – Geosyntec will support the County by providing design related input should work change directives be required during the construction process.
Substantial Completion and Final Completion Inspections and Punch Lists – Geosyntec will attend the Substantial and Final Completion Inspections. Geosyntec will assist the County Project Manager in verifying the completion of the construction contract and provide input to the County Project Manager to develop Substantial and Final Punch Lists.
Final Record Drawings – Geosyntec will review the final record drawings / as-builts provided by the Contractor. Geosyntec will provide review comments to the County Project Manager outlining any substantial deviations in the as-builts from the Contract Documents. Upon final approval, Geosyntec will certify that construction has been completed in accordance with the Contract Documents.
2. TASK 2: Project Management - consisting of the following tasks: project administration setup, management of project staff, project tracking, schedule updates, miscellaneous project meetings, status reports, etc.
DELIVERABLES
a) Bid support answers via email.
b) Pre-construction meeting agenda and summary via email.
c) Responses to Contractor RFI and shop drawings via email.
d) Construction observation reports in PDF format via email.
e) Work change directives support via email.
f) Substantial and final punch list items, if necessary, via email.
g) Review of final record drawings / as-builts via email.
SCOPE ASSUMPTIONS
i. The County will make all pertinent data available to Geosyntec, including copies of all scanned documents.
Hard copy documents will be made available for scanning.
ii. This scope of services has assumed that the consultant will not be involved in any public involvement meetings during the duration of the project.
iii. The scope does not include the preparation of any permit documents for construction.
BUDGET ESTIMATE
Geosyntec proposes to provide the services discussed herein for $41,591.52 on a lump sum basis, in accordance with the terms and conditions specified herein and pursuant to Contract No. 24-SQ-101KW. The lump sum amount is based on our estimated budget for performing these services, which includes the labor and other direct costs necessary to complete the work scope described in the proposal, as detailed in Attachment A.
Project efforts will be billed to the County on a lump sum task percent complete basis, based on the major tasks defined in the cost build‐up spreadsheet in Attachment A. Combined other direct costs will likewise be billed lump sum based on a percent complete basis. Invoices will be structured to list project tasks (and combined other direct costs) with accomplished percent complete, then corresponding budget invoiced, overall budget expended and overall budget remaining. A separate status report will be provided to the County’s project manager providing a narrative of work accomplished supporting the invoice.
SCHEDULE
The estimated project schedule is completion in 12 months.
CLOSURE
We appreciate the opportunity to work with the County on this project. Should you have any questions or comments regarding this proposal, please do not hesitate to contact us at (407) 321-7030.
Sincerely, Geosyntec Consultants, Inc.
Mark W. Ellard, PE, CFM, BC.WRE, ENV SP Nick Hartshorn, PE Senior Principal Water Resources Engineer mellard@geosyntec.com nhartshorn@geosyntec.com
Attachments A – Manhour and Fee Estimate mailto:mellard@geosyntec.com mailto:nhartshorn@geosyntec.com
ATTACHMENT A
MANHOUR AND FEE ESTIMATE
EXHIBIT A1 - FEE ESTIMATE
Task Assignment Amendment for Lantern Park Stormwater Pond Post Design Construction Support Services Date:
Volusia County, Florida Contract:
Basic Man-hours Average
Rate = $244.00 Rate = $224.00 Rate = $175.00 Rate = $154.00 Rate = $132.00 Rate = $110.00 Rate = $58.00 Activity by Hourly Activity Manhours Cost Manhours Cost Manhours Cost Manhours Cost Manhours Cost Manhours Cost Manhours Cost Amount Activity Rate
1 Post Design Construction Support Services Post Design Construction Support Services 14 $3,416.00 48 $10,752.00 28 $4,900.00 96 $14,784.00 $0.00 24 $2,640.00 4 $232.00 $36,724.00 214 $171.61
SUBTOTAL 14 $3,416.00 48 $10,752.00 28 $4,900.00 96 $14,784.00 0 $0.00 24 $2,640.00 4 $232.00 $36,724.00 214 $171.61 2 Project Management
Project Management 6 $1,464.00 10 $2,240.00 $0.00 $0.00 $0.00 $0.00 6 $348.00 $4,052.00 22 $184.18 SUBTOTAL 6 $1,464.00 10 $2,240.00 0 $0.00 0 $0.00 0 $0.00 0 $0.00 6 $348.00 $4,052.00 22 $184.18
SUB-TOTAL (LUMP SUM FEE): 14 $3,416.00 48 $10,752.00 28 $4,900.00 96 $14,784.00 0 $0.00 24 $2,640.00 4 $232.00 $40,776.00 214
(1) Salary Cost (from above) = $40,776.00
(1) (2) Expenses Allowance (2% of labor fees) + $815.52
(3) (3) Subtotal (Consultant's Fees) [(1)+(2)] = $41,591.52
(2) (4) Subconsultant's Fees (from left) + $0.00
Total Subconsultant Fees: 0.0%
Proposed Total Lump Sum Fee [(3)+(4)] = $41,591.52
06/12/26
24-SQ-101KW
Principal Engineer Senior Professional Engineer Senior Staff Engineer Staff Engineer Drafter/CAD Operator ClericalProfessional Engineer
Task
PercentageAmount
SUBCONSULTANTS TOTAL LUMP SUM FEE COMPUTATIONS
Name
$0.00
Exhibit A1 - Page 1 of 1
| SCOPE ASSUMPTIONS |
| BUDGET ESTIMATE |