General Conditions.pdf
PDF 403 KB Posted
- Solicitation number
- RFP-PRL-25-587
- Issued by
- Jefferson County, Weston CDP, Colorado
About this file
This document is the General Conditions to the Construction Contract for the City of Westminster, Colorado, which establishes the comprehensive legal and procedural framework governing a construction project. The document outlines the rights, responsibilities, and expectations of both the Owner (City of Westminster) and the Contractor, covering all aspects of project execution from contract initiation through completion, including provisions for project management, payment procedures, work performance standards, safety requirements, insurance obligations, and potential contract termination scenarios.
The General Conditions specify detailed requirements for contractor performance, including mandatory insurance coverages (workers' compensation, commercial general liability, automobile liability, and umbrella liability), with specific minimum coverage limits and endorsement conditions. Financial terms include a five percent (5%) retainage on progress payments, provisions for progress and final payments, and mechanisms for addressing change orders and potential contract disputes. The document also establishes strict protocols for work quality, correction of defective work, test and inspections, and compliance with equal employment opportunity standards. Critical provisions include the contractor's obligations for workplace safety, underground utility protection, and comprehensive documentation and reporting requirements throughout the project lifecycle.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT B TO INVITATION FOR BIDS
GENERAL CONDITIONS TO THE CONSTRUCTION CONTRACT
TABLE OF CONTENTS
ARTICLE 1 GENERAL PROVISIONS
1.1 Definitions
1.2 Execution, Correlation and Intent
1.3 Ownership and Use of Documents
ARTICLE 2 OWNER
2.1 Information and Services Required of the Owner
2.2 Owner’s Right to Stop the Work
2.3 Owner’s Right to Carry Out the Work
ARTICLE 3 CONTRACTOR
3.1 Review of Contract Documents and Field Conditions by Contractor
3.2 Supervision and Construction Procedures
3.3 Labor and Materials
3.4 Reserved
3.5 Warranty
3.6 Taxes
3.7 Permits, Fees and Notices
3.8 Allowances
3.9 Superintendent
3.10 Contractor's Construction Schedule
3.11 Documents and Samples at the Site
3.12 Shop Drawings, Product Data and Samples
3.13 Use of Site
3.14 Cutting and Patching of Work
3.15 Cleaning Up
3.16 Communications
3.17 Royalties and Patents
3.18 Indemnification
3.19 Attorneys Fees
ARTICLE 4 ADMINISTRATION OF THE CONTRACT
4.1 Project Manager
4.2 Project Manager’s Administration of the Construction Contract
4.3 Claims and Disputes
4.4 Resolution of Claims and Disputes
ARTICLE 5 SUBCONTRACTORS
5.1 Award of Subcontracts and Other Contracts for Portions of the Work
5.2 Subcontractual Relations
5.3 Contingent Assignment of Subcontracts
ARTICLE 6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
6.1 Owner's Right to Perform Work and to Award Separate Contracts
6.2 Mutual Responsibility
6.3 Owner's Right to Clean Up
ARTICLE 7 CHANGES IN THE WORK
7.1 Changes
7.2 Change Orders
7.3 Construction Change Directives
7.4 Minor Changes in the Work
ARTICLE 8 TIME
8.1 Date of Commencement of the Work
8.2 Progress and Completion
8.3 Delays and Extensions of Time
ARTICLE 9 PAYMENTS AND COMPLETION
9.1 Contract Sum
9.2 Schedule of Values
9.3 Applications for Payment
9.4 Certificates for Payment
9.5 Decisions to Withhold Certification
9.6 Progress Payments
9.7 Failure of Payment
9.8 Substantial Completion
9.9 Partial Occupancy or Use
9.10 Final Completion and Final Payment
ARTICLE 10 PROTECTION OF PERSONS AND PROPERTY
10.1 Safety Precautions and Programs
10.2 Safety of Persons and Property
10.3 Emergencies
10.4 Use of Explosives, Driving or Removal of Piles, Wrecking, Excavation Work or Other Similar and Potentially Dangerous Work
10.5 Underground Utilities
ARTICLE 11 INSURANCE REQUIREMENTS
11.1 Contractor's Insurance
11.2 Additional Named Insured
11.3 Builder’s Risk/Property Insurance
11.4 General Requirements
ARTICLE 12 UNCOVERING AND CORRECTION OF WORK
12.1 Uncovering of Work
12.2 Correction of Work
12.3 Acceptance of Defective or Non-Conforming Work
ARTICLE 13 MISCELLANEOUS PROVISIONS
13.1 Governing Law
13.2 Successors and Assigns
13.3 Written Notice
13.4 Claims for Damages
13.5 Performance and Payment bond
13.6 Rights and Remedies
13.7 Tests and Inspections
13.8 Litigation and Work Progress
13.9 Equal Employment Opportunity
13.10 Commercial Driver’s License Substance Screening
ARTICLE 14 TERMINATION OF THE CONTRACT
14.1 Termination by the Contractor
14.2 Termination by the Owner for Cause
14.3 Suspension by the Owner for Convenience
ARTICLE 1
GENERAL PROVISIONS
1.0 This Construction Contract is expressly contingent upon the approval of the City of
Westminster's City Council of all of the terms set forth herein. In the event this Construction
Contract is not approved in its entirety by City Council neither Party shall be bound to the terms of this Construction Contract.
1.1 DEFINITIONS
1.1.1 “Application for Payment” means the Contractor’s request for payment submitted to the Project Manager according to the process set forth in paragraphs 9.3.1- 9.3.4.
1.1.2 “Bidding Documents” means the Bid Packet including its Bid Notice, Invitation to Bid, Instructions to Bidders, Bid Form, Non-Collusion Affidavit of Prime Bidder, Bidder’s Certification, Bid Bond, and any attachments and exhibits to the Bid Packet.
1.1.3 “Certificate for Payment” means the amount approved for payment by the Project Manager after the receipt of the Contractor’s Application for Payment, as more fully defined in paragraph 9.4.1.
1.1.4 “Change Order” means a written order to the Contractor, signed by the Contractor and the Owner stating their agreement upon a change in the Work; the amount of the adjustment in the Contract Sum, if any; or the extent of the adjustment in the Contract Time, if any, as more fully defined in paragraph 7.2.
1.1.5 “Claim” means a demand or assertion by one of the parties seeking, as a matter of right, adjustment of contract terms, payment of money, extension of time, or other relief with respect to the terms of the Construction Contract, or other disputes between the Owner and Contractor arising out of or relating to the Construction Contract.
1.1.6 “Construction Change Directive” means a written order directed to the Contractor and signed by the Owner, directing a change in the Work and stating a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both, as defined more fully in paragraphs 7.3.1-7.3.9.
1.1.7 “Construction Contract” or “Contract” means the entire and integrated agreement between the parties hereto, evidenced by the Contract Documents, which supersedes all prior negotiations, representations, or agreements, either written or oral, subject only to amendment or modification as permitted by Article 7.
1.1.8 “Contract Documents” means the Construction Contract, the Conditions of the Contract (General, Special, Supplementary and other Conditions), the Drawings, the Specifications, all Addenda issued prior to and all Modifications issued after execution of the Contract, and all other documents listed in the Contract, including the Bidding Documents, the Notice of Award, Notice to Proceed; Performance Bond;
Payment Bond; Certificates of Insurance; and Tax-Exempt Certificates. Nothing contained in the Contract Documents creates any contractual relationship between the Owner any subcontractor, sub-subcontractor, or supplier of equipment or materials (except as provided in paragraph 5.4 hereof).
1.1.9 “Contract Sum” means the amount stated in paragraph 2.01 of the Construction Contract and, including authorized adjustments thereto, is the total amount payable by the Owner to the Contractor for the performance of the Work under the Contract Documents.
1.1.10 “Contract Time” means the period of time allotted in the Contract Documents for Substantial Completion of the Work, including authorized adjustments thereto.
1.1.11 “Contractor” means the person or entity identified as such in the Construction Contract or an authorized representative thereof.
1.1.12 “Date of Commencement of the Work” is the date established in the Notice to Proceed. If there is no Notice to Proceed, it shall be the date of the Construction Contract or such other date as may be established therein.
1.1.13 The “Date of Substantial Completion” is the date certified by the Project Manager in accordance with paragraph 9.8.
1.1.14 “Day” as used in the Contract Documents shall mean calendar day unless otherwise specifically designated.
1.1.15 “Drawings” are the graphic and pictorial portions of the Contract Documents, wherever located and whenever issued, showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedules, and diagrams.
1.1.16 “Final Completion” means the finding by the Project Manager that the final Certificate for Payment should be issued based on his knowledge, information and belief that the Work has been completed in accordance with the terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor, and noted in said final Certificate for Payment, is due and payable, as more fully defined in paragraph 9.10.1.
1.1.17 “Modification” means (1) a written amendment to the Construction Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive, or (4) a written Order for a Minor Change in the Work approved by the Owner pursuant to paragraph 7.4.
1.1.18 “Notice to Proceed” means the form issued by the City and accepted in writing by the Contractor that notifies Contractor to begin work on or before a date certain, establishes an end date, and returns bid security.
1.1.19 “Order for a Minor Change in the Work” means an order issued by the Project Manager adjusting the Contract Sum or extending the Contract Time as permitted by paragraph 7.4.1.
1.1.20 “Owner” means the person or entity identified as such in the Construction Contract or an authorized representative thereof. The term “City” may be used interchangeably with the term “Owner.”
1.1.21 “Project” means the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner or by separate contractors.
1.1.22 “Project Manager” means the City representative identified as such in Part 5 of the Contract.
1.1.23 “Project Manual” means the volume usually assembled for the Work which may include the bidding requirements, sample forms, conditions of the Contract, and Specifications.
1.1.24 “Specifications” or “Project Specifications” are that portion of the Contract Documents consisting of the written requirements for materials, equipment, construction systems, standards, and workmanship for the Work, and performance of related services.
1.1.25 “Subcontractor” means a person or entity who has a direct contract with the Contractor to perform any of the Work at the site or an authorized representative thereof. "Subcontractor" does not include any separate contractor or his subcontractor.
1.1.26 “Substantial Completion” means the stage in the progress of the Work when the Work (or designated portion thereof that the Owner agrees to accept separately) is sufficiently complete in accordance with the Contract Documents so the Owner can occupy or use the Work for its intended use as more fully explained in paragraph 9.8.1.
1.1.27 “Sub-subcontractor” means a person or entity who has a direct or indirect contract with a subcontractor to perform any of the Work at the site or an authorized representative thereof.
1.1.28 “Underground Utilities” means any below ground line, structure, facility or installation used by a utility or service provider including, but not limited to, telephone company lines, cable and conduit; cable television lines, cable and conduit; internet lines, cable and conduit; sewer lines and water lines, including individual sewer and water service lines; stormwater lines; gas lines; electrical lines, cables and conduit;
and traffic signal lines, cable and conduit.
1.1.29 “Work” means the construction and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor's obligations for the completed construction required by the Contract Documents. The Work may constitute the whole or a part of the Project.
1.2 EXECUTION, CORRELATION AND INTENT
1.2.1 The Contract Documents shall be signed in not less than triplicate by the Owner and Contractor and shall be maintained by the Project Manager.
1.2.2 By executing the Contract, the Contractor represents that he has visited the site, familiarized himself with the local conditions under which the Work is to be performed, and correlated his observations with the requirements of the Contract Documents.
In connection with the foregoing, and having carefully examined all Contract Documents, as aforesaid, and having visited the Site, and having familiarized himself with the urban site construction circumstances of the Project, the Contractor acknowledges and declares that it has no knowledge of any discrepancies, omissions, ambiguities, or conflicts in said Contract Documents and that if it becomes aware of any such discrepancies, omissions, ambiguities, or conflicts, it will promptly notify Owner and Project Manager of such fact.
1.2.3 The Contract Documents include all items necessary for the proper execution and completion of the Work by the Contractor. The Work shall consist of all items specifically included in the Contract Documents as well as all additional items of work which are reasonably inferable from that which is specified in order to complete the Work in accordance with the Contract Documents. The Contract Documents are complementary, and what is required by any one Contract Document shall be as binding as if required by all. Any differences between the requirements of the Drawings and the Specifications or any differences within the Drawings themselves or within the Specifications themselves have been referred to the Owner by Contractor prior to the submission of bids and have been clarified by an Addendum issued to all Bidders.
If any such differences or conflicts were not called to the Owner’s attention prior to submission of bids, the Project Manager shall decide which of the conflicting requirements will govern based upon the most stringent of the requirements, and subject to the approval of the Owner, the Contractor shall perform the work at no additional cost or time to the Owner in accordance with the Project Manager’s decision.
Work not covered in the Contract Documents will not be required unless it is consistent therewith and is reasonably inferable therefrom as being necessary to produce the intended results.
1.2.4 The organization of the Specifications into divisions, sections and articles, and the arrangement of Drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade.
1.2.5 Unless otherwise stated in the Contract Documents, words and abbreviations which have well-known technical or trade meanings are used in the Contract Documents in accordance with such recognized meanings.
1.2.6 In the interest of brevity, the Contract Documents frequently omit modifying words such as “all” and “any” and articles such as “the“ and “an.” The fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement.
1.2.7 Interpretation of Contract Documents - masculine includes both the masculine and the feminine;
singular includes the singular and the plural; headings are for reference only and are not substantive
1.3 OWNERSHIP AND USE OF DOCUMENTS
1.3.1 The Drawings, Specifications, and other similar or related documents and copies thereof are furnished to the Contractor for the purpose of performing the Work and are, and shall remain, the property of the Owner. The Contractor may retain one record set. Neither the Contractor nor any subcontractor, sub-subcontractor or material or equipment supplier shall own or claim a copyright in the Drawings, Specifications and other similar or related documents, and Owner will retain all common law, statutory, and other reserved rights, in addition to the copyright (including, without limitation, the right to create derivative works therefrom). All copies of such documents shall be returned to the Owner upon completion of the Work. The Drawings, Specifications, and other similar or related documents and copies thereof furnished to the Contractor, are for use solely with respect to this Project. They are not to be used by the Contractor or any subcontractor, sub-subcontractor or material or equipment supplier on other projects or for additions to this Project outside the scope of the Work without the specific written consent of the Owner. The Contractor, subcontractors, sub-subcontractors and material or equipment suppliers are granted a limited license to use and reproduce applicable portions of the Drawings, Specifications and other documents appropriate to and solely for use in the execution of their Work under the Contract Documents. All copies made under this license shall bear the statutory copyright notice, if any, shown on the Drawings, Specifications and other documents. Submittal or distribution to meet official regulatory requirements or for other purposes in connection with this Project is not to be construed as publication in derogation of any copyright or other reserved rights.
ARTICLE 2
OWNER
2.1 INFORMATION AND SERVICES REQUIRED OF THE OWNER
2.1.1 The Owner shall furnish surveys describing the physical characteristics, legal limitations and utility locations, if such utilities are the property of Owner, for the site of the Project, and a legal description of the site, if necessary. The Contractor shall undertake such further investigations and studies as may be necessary or useful to determine site characteristics and conditions. In connection with the foregoing, Contractor shall locate prior to performing any work, all Underground Utilities. If utility locate services are provided in the field by utility owners, Contractor nonetheless remains solely responsible to determine the actual location of all Underground Utilities.
2.1.2 Except for permits and fees which are the responsibility of the Contractor under the Contract Documents, the Owner shall secure and pay for necessary approvals, easements, assessments and charges required for the construction, use or occupancy of permanent structures or for permanent changes in existing facilities. Such approvals and the like shall be provided by Owner within a time and in a manner as to avoid any unreasonable delays in the Work or schedule of Contractor and shall include only such approvals for permanent facilities which are necessary to perform the Work as set forth in the Contract Documents.
2.1.3 Information or services required to be furnished by Owner shall be furnished by the Owner with reasonable promptness to avoid unreasonable delay in the orderly progress of the Work.
2.1.4 Unless otherwise provided in the Contract Documents, the Contractor will be furnished, free of charge, all copies of Drawings and Specifications reasonably necessary for the execution of the Work.
2.1.5 The Owner shall forward all instructions to the Contractor through the Project Manager.
2.1.6 The foregoing are in addition to other duties and responsibilities of the Owner enumerated herein and especially those in respect to Work by Owner or by Separate Contractors, Payments and Completion, and Insurance in Articles 6, 9, and 11 respectively.
2.2 OWNER'S RIGHT TO STOP THE WORK
2.2.1 If the Contractor fails to correct defective Work as required by Paragraph 12.2 or fails to carry out the Work in accordance with the Contract Documents, or fails or refuses to provide a sufficient amount of properly supervised and coordinated labor, materials, or equipment so as to be able to complete the Work within the Contract Time, or fails to remove and discharge (within ten days) any lien filed upon Owner’s property by anyone claiming by, through, or under Contractor, or disregards the instructions of the Project Manager or Owner when based on the requirements of the Contract Documents, the Owner or the Project Manager, by a written order, may order the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of the Owner and the Project Manager to stop the Work shall not give rise to any duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity.
2.3 OWNER'S RIGHT TO CARRY OUT THE WORK
2.3.1 If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a seven-day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, or fails within such seven-day period to eliminate (or diligently commence to eliminate) the cause of any stop work order issued under paragraph 2.3.1 hereof, the Owner may, without prejudice to other remedies the Owner may have, correct such deficiencies. In such case an appropriate Change Order shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies, including compensation and additional services and expenses made necessary by such default, neglect or failure. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner.
ARTICLE 3
CONTRACTOR
3.1 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR
3.1.1 In addition to and not in derogation of Contractor’s duties under paragraphs 1.2.2 and 1.2.3 hereof, Contractor shall carefully study and compare the Contract Documents and shall at once report to the Owner any error, inconsistency or omission discovered. The Contractor shall not be liable to the Owner for any damage resulting from any such errors, inconsistencies or omissions in the Contract Documents hereof unless the Contractor recognized or reasonably should have recognized such error, inconsistency or omission and failed to report it to the Owner. If the Contractor performs any construction activity involving an error, inconsistency or omissions in the Contract Documents that Contractor recognized or reasonably should have recognized, without such notice to the Owner, the Contractor shall assume complete responsibility for such performance and shall bear the full amount of the attributable costs for correction. The Contractor shall perform no portion of the Work at any time without Contract Documents or, where required, approved Shop Drawings, Product Data or Samples for such portion of the Work.
3.1.1.1 If any errors, inconsistencies, or omissions in Contract Documents are recognized or reasonably should have been recognized by the Contractor, any member of its organization, or any of its subcontractors, the Contractor shall be responsible for notifying the Owner in writing of such error, inconsistency, or omission before proceeding with the Work. The Owner will take such notice under advisement and within a reasonable time commensurate with job progress, render a decision. If Contractor fails to give such notice and proceeds with such work, it shall correct any such error, inconsistency, or omission at no additional cost to Owner.
3.1.2 In addition to and not in derogation of Contractor's duties under paragraphs 1.2.2 and 1.2.3 hereof, the Contractor shall take field measurements and verify field conditions and shall carefully compare such field measurements and conditions and other information known to the Contractor with the Contract Documents before commencing activities. Errors, inconsistencies or omissions discovered shall be reported to the Project Manager at once.
3.1.3 The Contractor shall perform the Work in accordance with the Contract Documents and submittals approved pursuant to paragraph 3.12.
3.2 SUPERVISION AND CONSTRUCTION PROCEDURES
3.2.1 The Contractor shall supervise and direct the Work, using his best skill and attention. The Contractor shall be solely (subject to the terms and provisions of Article 4 hereof), responsible for and have control over all construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless Contract Documents give other specific instructions concerning these matters.
The Contractor shall review any specified construction or installation procedure, including those recommended by manufacturers, and shall advise the Owner if the specified procedure deviates from good construction practice or if following the procedure will affect any warranties, and may propose any alternative procedure which the Contractor will warrant.
3.2.2 The Contractor shall be responsible to the Owner for the acts and omissions of his employees, subcontractors and their agents and employees, and other persons performing any of the Work under a contract or other arrangements with the Contractor. It is understood and agreed that the relationship of Contractor to Owner shall be that of an independent contractor. Nothing contained herein or inferable herefrom shall be deemed or construed to (1) make Contractor the agent, servant, or employee of the Owner, or (2) create any partnership, joint venture, or other association between Owner and Contractor.
Any direction or instruction by Owner in respect of the Work shall relate to the results the Owner desires to obtain from the Work, and shall in no way affect Contractor's independent contractor status as described herein.
3.2.3 The Contractor shall not be relieved from his obligations to perform the Work in accordance with the Contract Documents either by the activities or duties of the Project Manager in his administration of the Contract, or by inspections, tests or approvals required or performed under Paragraph 13.7 by persons other than the Contractor.
3.2.4 The Contractor shall be solely responsible for locating all existing underground installations, including Underground Utilities and their service connections, in advance of excavating or trenching, by contacting the owners thereof and prospecting. Notwithstanding utility locate services that may be provided in the field by utility owners, Contractor remains ultimately responsible to determine the actual location of all Underground Utilities, facilities, structure, or installations. The Contractor shall use his own information and shall not rely upon any information shown or not shown on the plans or on field locates provided by the utility owner concerning existing Underground Utilities, facilities, structure, or installations. Any delay, additional work, or extra cost to the Contractor caused by existing Underground Utilities, facilities, structures or installations shall not constitute a claim for extra work, additional payment, or damage.
3.2.5 The Contractor has the responsibility to ensure that all equipment and material suppliers and subcontractors, their agents, and employees adhere to the Contract Documents, and that they order material and equipment on time, taking into account the current market and delivery conditions and that they provide equipment and materials on time. The Contractor shall coordinate its Work with that of all others on the Project, including deliveries, storage, installations, and construction utilities. The Contractor shall be responsible for the space requirements, locations, and routing of its equipment. In areas and locations where the proper and most effective space requirements, locations, and routing cannot be made as indicated, the Contractor shall meet with all others involved, before installation, to plan the most effective and efficient methods of overall installation.
3.2.6 The Contractor shall establish and maintain bench marks and all other grades, lines, and levels necessary for the Work, report errors or inconsistencies to the Owner before commencing work, and review the placement of the structure(s) and permanent facilities on the site with the Owner after all lines are staked out and before foundation work is started. Contractor shall provide access to the Work for the Owner, the Project Manager, other persons designated by Owner, and governmental inspectors. Any encroachments, as revealed by an improvement survey, made by Contractor or its subcontractors (of any tier) on adjacent properties due to construction, except for encroachments arising from errors or omissions not reasonably discoverable by Contractor in the Contract Documents, shall be the sole responsibility of the Contractor and Contractor shall correct such encroachments within thirty (30) days of the improvement survey (or as soon thereafter as reasonably possible), at Contractor’s sole expense, either by the removal of the encroachment (and subsequent reconstruction on the project site) or agreement with the adjacent property owner(s) (in form and substance satisfactory to Owner in its sole discretion) allowing the encroachments to remain.
3.3 LABOR AND MATERIALS
3.3.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work.
3.3.2 The Contractor shall at all times enforce strict discipline and good order among his employees and shall not employ on the Work any unfit person or anyone not skilled in the task assigned to him.
3.4.3 Materials shall conform to manufacturer's standards in effect at the date of execution of the Construction Contract and shall be installed in strict accordance with manufacturer's directions. The Contractor shall, if required by the Owner, furnish satisfactory evidence as to the kind and quality of any materials. All packaged materials shall be shipped to the site in the original containers clearly labeled, and delivery slips shall be submitted with bulk materials identifying thereon the source, and warranting quality and compliance with Contract Documents.
3.3.4 When the Contract Documents require the Work, or any part of same, to be above the standards required by applicable laws, ordinances, rules, regulations, and other statutory provisions pertaining to the Work, such Work shall be performed and completed by the Contractor in accordance with the Contract Documents.
3.4 RESERVED
3.5 WARRANTY
3.5.1 The Contractor warrants to the Owner that all materials and equipment furnished under this Contract will be of good quality and new unless otherwise required or permitted by the Contract Documents, and that all Work will be of good quality, free from faults and defects and in conformance with the Contract Documents. All Work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered defective. If required by the Owner, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment.
3.5.2 Experienced manufacturer's representatives shall be used to supervise the installation of equipment as may be required by the Owner. Any special tools or equipment which may be required for first class work shall be provided by the Contractor.
3.5.3 The acceptance at any time of materials or equipment by or on behalf of the Owner shall not be a bar to future rejection if they are subsequently found to be defective, inferior in quality or uniformity, to the material or equipment specified, or are not as represented to the Owner.
3.5.4 In the absence of detailed specifications, all materials shall conform to the latest standards of the American Society for Testing Materials (ASTM) available at the time notice inviting Contractors to bid is published unless otherwise indicated.
3.5.5 Any reference to standard specifications in any of the Contract Documents shall always imply the latest edition of such standard specifications or specifications available at the time notice inviting contractors to bid is published unless otherwise indicated.
3.5.6 Within one year after the date of Final Completion of the Work or within such longer period of time as may be prescribed by law or by the terms of any applicable special warranty required by the Contract Documents, the Contractor shall make all needed repairs arising out of defective workmanship or materials, or both, which in the judgment of the Owner shall become necessary during such period. If within ten (10) days after the mailing of a notice in writing to the Contractor or his agent, the Contractor shall neglect to make, or undertake with due diligence to make the aforesaid repairs, the Owner is hereby authorized to make such repairs at the Contractor's expense. In case of an emergency, the Contractor will be notified and shall correct and make repairs within the necessary time constraints. Failure of the Contractor to respond to the notification shall result in the Owner making the necessary repairs at the Contractor's expense. This obligation shall survive termination of the Contract.
3.5.7 Should the Owner claim by written communication before the warranty period expires that certain defects exist and that these require repair or replacement, the warranty period and applicable surety shall be automatically extended for as long as these defects remain unremedied.
3.6 TAXES
3.6.1 All sales of construction and building materials to contractors and subcontractors for use in the building, erection, alteration or repair of structures, highways, roads, streets and other public works owned and used by the Owner are exempt from State and other State-collected sales and use taxes and from Westminster sales and use taxes. However, such materials may be subject to sales and use taxes imposed by other local taxing authorities.
3.6.2 Prior to City’s issuance of the Notice to Proceed and start of work, the Contractor shall deliver to the Project Manager two copies of the completed and executed "Application for Exemption Certificate" with the approval of the Department of Revenue, State of Colorado, affixed. These certificates will serve as an indication to the Owner that the Contractor has acquired the necessary exemption for State and other State-collected sales and use taxes. The Contractor also agrees to make the same requirement, as contained above, of the material suppliers and subcontractors on this project.
3.6.3 Westminster use tax will be due on construction tools and equipment used on the Project if a legally imposed local sales or use tax was not paid on the full purchase price of these items. If such local sales or use tax was less than that of the City of Westminster, Contractor, equipment suppliers, and subcontractors shall pay to Westminster the difference between such local sales or use tax and the tax imposed by Westminster. Any sales or use tax due Westminster may be prorated according to the time the tools or equipment are located within the City, providing an equipment declaration form is properly filed with the City. This paragraph 3.6.3 shall apply to all construction tools and equipment which had a purchase price of $2,500 or more.
3.6.4 All books and records pertaining to the Project that will allow the accurate determination of any tax due must be retained and be kept available for inspection by the City for three years after the completion of the Project.
3.6.5 All applicable taxes are to be paid by Contractor and are to be included in appropriate bid items;
except that, the Contractor shall not be reimbursed for any State or other sales or use taxes incurred as a result of failure to obtain an exemption certificate prior to City’s issuance of the Notice to Proceed.
3.6.6 A copy of the Construction Equipment Declaration for Proration of Municipal Use Tax form shall be obtained from the City's Finance Department.
3.7 PERMITS, FEES AND NOTICES
3.7.1 Unless otherwise provided in the Contract Documents, the Contractor shall obtain any necessary building permits and applicable inspections and shall secure and pay for all other permits and governmental fees, licenses and inspections, including but not limited to City right-of-way permits and street cut impacts fees, necessary for the proper execution and completion of the Work, which are customarily secured after execution of the Contract and are legally required. Contractor shall secure and pay for such permits, fees, licenses, and inspections as may be required for the Work by any jurisdiction.
3.7.2 The Contractor shall give all notices and comply with all laws, ordinances, rules, regulations and lawful orders of any public authority bearing on the performance of the Work.
3.7.3 It is not the responsibility of the Contractor to make certain that the Contract Documents are in accordance with applicable laws, statutes, building codes and regulations. If the Contractor observes or in the exercise of due care should observe that any of the Contract Documents are at variance therewith in any respect, he shall promptly notify the Project Manager in writing, and any suggested changes shall be made to the Owner. The Contractor shall notify the Project Manager of all conflicts between the Drawings and Specifications and any laws, ordinances, rules, regulations, or restrictions that come to the Contractor's attention or should have come to his attention in the exercise of due care.
3.7.4 It is the responsibility of the Contractor to make certain that all his Work is done in accordance with applicable laws, statutes, building codes and regulations, and the Contractor shall bear any costs related to his failure to do so.
3.7.5 If the Contractor performs Work, including without limitations, the installation of any materials or equipment that it knows, or reasonably should know, would be contrary to laws, statutes, ordinances, building codes, rules, and regulations, the Contractor shall assume full responsibility for such work and shall bear all costs attributable to the correction thereof or related thereto, including all fines and penalties.
3.8 ALLOWANCES
3.8.1 The Contractor shall include in the Contract Sum all allowances stated in the Contract Documents. Items covered by these allowances shall be supplied for such amounts and by such persons as the Owner may direct, but the Contractor will not be required to employ persons against whom he makes a reasonable objection.
3.8.2 Unless otherwise provided in the Contract Documents:
.1 materials and equipment under an allowance shall be selected promptly by the Owner to avoid unreasonable delay in the Work;
.2 these allowances shall cover the cost to the Contractor, less any applicable trade discount, of the materials and equipment required by the allowance delivered at the site, and all applicable taxes;
.3 the Contractor's costs for unloading and handling on the site, labor, installation costs, overhead, profit and other expenses contemplated for the original allowance shall be included in the Contract Sum and not in the allowance;
.4 whenever the cost is more than or less than the allowance, the Contract Sum shall be adjusted accordingly by Change Order, the amount of which will recognize changes, if any, in handling costs on the site, labor, installation costs, overhead, profit and other expenses.
3.9 SUPERINTENDENT
3.9.1 The Contractor shall employ a competent Superintendent and necessary assistants who shall be in attendance at the Project site during the progress of the Work. The Superintendent shall represent the Contractor and all communications given to the Superintendent shall be as binding as if given to the Contractor. Important communications shall be confirmed in writing. Other communications shall be so confirmed on written request in each case.
3.9.2 Contractor shall assign a person to be and remain the Superintendent to generally and directly supervise and coordinate the performance of the Work. The naming of such person is and was a material inducement to Owner to enter into the Contract. If such person is not the Superintendent or does not remain the Superintendent for any reason whatsoever, the Owner reserves the right to review and approve or disapprove said Superintendent's replacement, in Owner's sole discretion. If said replacement is disapproved, the Contract may, at Owner's option, be terminated for cause.
3.9.3 Owner shall have the right, upon notice, to demand that the Superintendent or other key personnel retained by Contractor be replaced by Contractor. In the event of such demand, Contractor shall, within seven (7) days after notification thereof, replace said individual(s) with an individual satisfactory to Owner, in Owner's sole discretion. If said replacement is disapproved, the Contract, may, at Owner's option, be terminated for cause.
3.10 CONTRACTOR'S CONSTRUCTION SCHEDULE
3.10.1 A preconstruction conference shall be scheduled at the time the Notice of Award is issued. The Contractor, at the preconstruction conference, shall prepare and submit for the Owner's review and approval a Contractor's construction schedule for the Work, in such form and detail as Owner may require. The schedule shall not exceed time limits current under the Contract Documents, shall be revised as required herein and at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work. The schedule shall indicate the proposed starting and completion dates for the various subdivisions of the Work as well as the totality of the Work. The schedule shall be updated every thirty (30) days and submitted to the Project Manager with Contractor's applications for payment. Each schedule shall contain a comparison of actual progress with the estimated progress for such time stated in the original schedule. If any schedule submitted sets forth a date for Substantial Completion for the Work or any phase of the Work beyond the date(s) of Substantial Completion established in the Contract (as the same may be extended as provided in the Contract Documents), then Contractor shall submit to the Owner for its review and approval, a narrative description of the means and methods which Contractor intends to employ to expedite the progress of the Work to ensure timely completion of the various phases of the Work as well as the totality of the Work.
To ensure such timely completion, Contractor shall take all necessary action including, without limitation, increasing the number of personnel and labor on the Project and implementing overtime and double shifts (with hours of work approved by the Project Manager). In that event, Contractor shall not be entitled to an adjustment in the Contract Sum or the Schedule.
3.10.2 The Contractor shall prepare and keep current, for the Project Manager’s approval, a schedule of submittals which is coordinated with the Contractor's construction schedule and allows the Project Manager reasonable time to review submittals.
3.10.3 The Contractor shall conform to the most recent schedules.
3.11 DOCUMENTS AND SAMPLES AT THE SITE
3.11.1 The Contractor shall maintain at the site for the Owner one record copy of all Drawings, Specifications, Addenda, Change Orders and other Modifications, in good order and marked currently to record all changes and selections (all changes and selections to be approved by the Owner in advance) made during construction, and approved Shop Drawings, Product Data and Samples and similar required submittals. These shall be available to the Project Manager and shall be delivered to him for the Owner upon completion of the Work.
3.11.2 At the date of Substantial Completion and as a condition precedent to Final Payment, the Contractor shall furnish the following documents (unless directed otherwise by Owner) to the Project Manager for submittal to the Owner: record drawings showing the field changes and selections affecting the general construction, mechanical, electrical, plumbing, and all other work, and indicating the Work as actually installed. These shall consist of carefully drawn markings on a set of reproducible prints of the Drawings. The Contractor shall maintain at the job site one (1) set of Drawings and indicate thereon each field change as it occurs.
3.11.3 All documents and records required to be prepared or maintained by Contractor for eventual delivery to the Owner shall be maintained and delivered in hard copy and in an electronic/digital format acceptable to the Owner.
3.12 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
3.12.1 Shop Drawings are drawings, diagrams, schedules and other data specifically prepared for the Work by the Contractor or any subcontractor, sub-subcontractor, manufacturer, supplier or distributor to illustrate some portion of the Work.
3.12.2 Product Data are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate a material, product or system for some portion of the Work.
3.12.3 Samples are physical examples which illustrate materials, equipment or workmanship and establish standards by which the Work will be judged.
3.12.4 The Contractor shall review, approve and submit to the Owner, with reasonable promptness and in such sequence as to cause no delay in the Work or in the work of the Owner or any separate contractor, all Shop Drawings, Product Data, Samples and similar submittals required by the Contract Documents.
Submittals made by the Contractor that are not required by the Contract Documents may be returned without action.
3.12.5 The Contractor shall not perform any portion of the Work requiring submittal and review of shop drawings, product data, samples, or similar submittals until the respective submittal has been approved by the Owner. Such Work shall be in accordance with approved submittals.
3.12.6 By approving and submitting Shop Drawings, Product Data, Samples, and similar submittals, the Contractor represents that he has determined and verified all materials, field measurements, and field construction criteria related thereto, or will do so, and that he has checked and coordinated the information contained within such submittals with the requirements of the Work and of the Contract
Documents.
3.12.7 The Contractor shall not be relieved of responsibility for any deviation from the requirements of the Contract Documents by the Owner’s or Project Manager’s approval of Shop Drawings, Product Data, Samples, or similar submittals unless the Contractor has specifically informed the Owner in writing of such deviation at the time of submission and the Owner has given written approval to the specific deviation. The Contractor shall not be relieved from responsibility for errors or omissions in the Shop Drawings, Product Data, Samples or similar submittals by the Owner’s approval thereof.
3.12.8 The Contractor shall direct specific attention, in writing, on resubmitted Shop Drawings, Product Data, Samples, or similar submittals to revisions other than those required by the Owner on previous submittals.
3.12.9 When professional certification of performance criteria of materials, systems, or equipment is required of the Contractor by the Contract Documents, the Owner shall be entitled to rely in a reasonable and professional fashion upon the accuracy and completeness of such calculations and certifications. If any or all such calculations or certifications are found to be inaccurate or incomplete, Contractor shall assume full responsibility and bear all costs attributable or related thereto, including, without limitation, the expense of Owner’s additional services associated with the verification of such calculations or certifications, and the expense of Owner’s additional services made necessary by the failure of such calculations or certifications to be accurate or complete.
3.12.10 Contractor shall furnish Owner with copies of all operator's instructions, service and parts manuals, and all other literature received by Contractor from the manufacturer or supplier of equipment furnished under the Contract. All operator's instructions, service and parts manuals, and all other such literature shall be bound in permanent binders satisfactory to the Project Manager.
3.12.11 Copies of any manufacturer's guaranty or certificate as may be required by the Contract Documents or normally included with the product, shall be submitted to the Owner through the Project Manager prior to Substantial Completion of the Work issued by the Owner.
3.12.12 Throughout the progress of construction, the Contractor shall maintain a careful up-to-date record of all changes on the plans and drawings during actual construction. Upon completion of Work, and prior to Substantial Completion issued by the Owner, the Contractor shall file with the Project Manager one set of complete drawings with all changes and Contractor's field construction notes neatly and legibly recorded thereon. Such drawings shall indicate in part the exact routing, if changed from drawing location, of Underground Utilities, oxygen supply, condenser water lines, fuel oil tanks and lines, fire protection lines and any other major buried utility lines, and routing of conduit runs which are buried or concealed in concrete slabs. Such information may be used to prepare record drawings for the Owner.
3.12.13 All documents and records required to be prepared or maintained by Contractor for eventual delivery to the Owner shall be maintained and delivered in hard copy and in an electronic/digital format acceptable to the Owner.
3.13 USE OF SITE
3.13.1 The Contractor shall confine his construction operations to the immediate vicinity of the location shown on the plans and shall use due care in placing construction tools, equipment, excavated materials, materials and equipment for installation and supplies, so as to cause the least possible damage to property and interference with traffic. The placing of such tools, equipment, and materials shall be subject to the approval of the Project Manager. If it is necessary or desirable that the Contractor use land outside the
Owner's right-of-way, the Contractor shall obtain consent from, and shall execute a written agreement with, the owner and tenant of the land and shall be responsible for all associated costs, including clean-up and restoration.
3.13.2 The Contractor shall protect, shore, brace, support and maintain all Underground Utilities, drains, and underground construction uncovered or otherwise affected by the construction work performed by him.
3.14 CUTTING AND PATCHING OF WORK
3.14.1 The Contractor shall be responsible for all cutting, fitting or patching that may be required to complete the Work or to make its several parts fit together properly.