This is an Invitation to Bid (ITB #26-17) issued by the Walton County Board of County Commissioners, Florida, for Gasoline and Diesel Fuel Supply Services. The project consists of installing fuel tank monitoring systems at all County fuel sites and providing on-demand delivery of unleaded gasoline and diesel fuel to eight delivery locations throughout the county. The Vendor shall monitor fuel levels and deliver fuel when tanks reach approximately 20% capacity or within twenty-four hours of a County request, with the Public Works Director serving as the primary point of contact. Fuel specifications include unleaded gasoline (minimum 87 octane, per ASTM D4814) and Grade No. 2 Ultra Low Sulfur diesel fuel (per ASTM D975), delivered via tank wagon or bulk transport as specified. The county maintains eight fuel distribution points with combined storage capacities ranging from 6,000 to 17,000 gallons, with delivery hours of 6:00 a.m. to 4:00 p.m. Monday through Thursday (with the exception of one location open Sunday through Saturday). The question submission deadline is April 27, 2026, at 12:00 p.m., and sealed bids are due May 13, 2026, at 3:00 p.m. via the County's e-Procurement Portal, with public bid opening immediately following. The contract term is one year from the date of complete execution, with potential renewal for up to four additional one-year periods at the sole discretion of the County.
Pricing shall be based on OPIS Pensacola rack average pricing on the date of delivery plus a fixed markup per gallon (in cents or percentage) submitted by the bidder, with the markup remaining firm for the contract duration. All fuel deliveries shall be temperature-adjusted to 60 degrees Fahrenheit for billing purposes, with applicable state inspection fees and taxes added to invoices as required. The County offers local vendor preference in accordance with Walton County Purchasing Policies and Procedures (PP017), allowing qualified local vendors to apply for preference consideration. Bid security is not required; however, bids remain valid and subject to acceptance for forty-five calendar days following the bid opening date. The successful bidder must execute the contract and provide all required Certificates of Insurance (demonstrating A.M. Best Financial Strength Rating of A-, Class VII or better) within ten business days of the Notice of Award. The County reserves the right to reject any or all bids, to conduct investigations into bidder qualifications and past performance, and to value engineer the scope of services if the apparent low bid exceeds the County's available budget. Failure to maintain timely fuel deliveries as specified may result in contract cancellation, and the County reserves the right to withhold payment for delivery tickets lacking proper stick/dial readings or authorized signatures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Contract_No._26-17.pdf | ||
| CONSTRUCTION_CONTRACT.doc | DOC document | |
| Public_Construction_Bond_(25).doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For more information, please visit our online supplier portal, located at https://procurement.opengov.com/portal/waltoncountyfl
Walton County
INVITATION TO BID
26-17
GASOLINE AND DIESEL FUEL SUPPLY SERVICES
RELEASE DATE: April 13, 2026
RESPONSE DEADLINE: May 13, 2026, 3:00 pm
Please refer to the project timeline in this document for all important deadlines.
Invitation To Bid #26-17 Title: Gasoline And Diesel Fuel Supply Services
Table of Contents
1. Invitation to Bid
2. Instruction to Bidders
3. Scope of Services
4. Bid Schedule
5. Vendor Submissions
6. Attachments
Attachments:
A - Contract No. 26-17
1. Invitation to Bid
BOARD OF COUNTY COMMISSIONERS,
WALTON COUNTY, FLORIDA
Gasoline And Diesel Fuel Supply Services
26-17
Sealed bids for the Gasoline And Diesel Fuel Supply Services Project will be received by the Walton County
Board of County Commissioners, hereinafter referred to as "County" until 3:00 pm LOCAL TIME on
Wednesday, May 13, 2026, for furnishing labor and materials and performing all work set forth in the Bidding
Documents prepared by Walton County. IMMEDIATELY FOLLOWING the scheduled closing time for the reception of bids, all bids which have been submitted in accordance with the conditions of the Bidding
Documents issued in relation to this Project will be publicly opened and read aloud.
Bidder is responsible for the submission of its bid.
Bids received after the specified day and time will not be opened.
The proposed project, hereinafter referred to as the “Project,” consists of the installation of fuel tank monitoring systems at all County fuel sites and the provision of on-demand delivery of unleaded gasoline and diesel fuel. The Vendor shall monitor fuel levels and ensure deliveries are made when tanks reach approximately 20% capacity or within twenty-four (24) hours of a County request, with the Public Works
Director or designee serving as the primary point of contact. The Vendor shall furnish all required fuel in accordance with applicable ASTM standards and State of Florida regulations, provide delivery via tank wagon or transport as specified, and supply delivery tickets reflecting OPIS-based pricing. All fuel deliveries shall be temperature-adjusted to 60°F for billing purposes, with applicable taxes and fees added to invoices as required.
Contract Term: The term of this agreement shall be ONE (1) Year from the date of its complete execution and may be renewed for up to FOUR (4) additional periods of ONE (1) Year each at the sole discretion of the
County.
AWARD OF THE CONTRACT FOR THIS PROJECT SHALL BE SUBJECT TO LOCAL VENDOR PREFERENCE IN
ACCORDANCE WITH WALTON COUNTY PURCHASING POLICIES AND PROCEDURES (PP017).
Application for Local Preference is available in the Vendor Submissions section of this Invitation to Bid.
Advertisement Date: April 13, 2026
Question Submission Deadline: April 27, 2026, 12:00pm https://procurement.opengov.com/portal/waltoncountyfl/projects/247698/document?section=2366340
Bid Closing Deadline: May 13, 2026, 3:00pm
In-Person Bid Opening:
Office of Central Purchasing 176 Montgomery Circle DeFuniak Springs, Florida 32435
OR
Bidders may also attend the bid opening meeting via teleconference by dialing 850- 635-0655 ext. 261217
All responses must be submitted electronically via the County e-Procurement Portal:
https://procurement.opengov.com/portal/waltoncountyfl/projects/247698.
Through the e-Procurement Portal, responses will be securely locked and digitally encrypted until the submission deadline passes.
Should you encounter any technical difficulties or require assistance with the e-Procurement Portal, please reach out to our technical support team via the blue chat bubble on the bottom right or via email at procurement-support@opengov.com
All subcontractors, if any, and suppliers shall be declared on the prescribed Subcontractors and Suppliers
Declaration form.
Each Bidder’s submittal shall include all the items listed in the Vendor Submissions section.
All required insurance policies and certificates of insurance shall be issued by an insurance company authorized to do business in the State of Florida and possessing a current A.M. Best Financial Strength Rating of A-, Class VII or better.
Certificates of Insurance shall be executed by a licensed insurance agent or authorized representative of the insurer and shall demonstrate compliance with the insurance requirements set forth in the Contract
Documents.
The Successful Bidder shall maintain all required insurance coverage for the duration of the Agreement and shall provide updated certificates upon renewal or upon request by Walton County. Failure to maintain the required insurance coverage may result in suspension of services or termination of the Agreement in accordance with the Contract.
The bid may be withdrawn without penalty prior to the date and time of bid opening. Bids shall remain open and subject to acceptance for a period of forty-five (45) calendar days after the date of bid opening. No Bidder may withdraw its bid for a period of forty-five (45) calendar days after the date of bid opening.
https://procurement.opengov.com/portal/waltoncountyfl/projects/247698 mailto:procurement-support@opengov.com
The County will award the bid to the lowest, most Responsible and Responsive Bidder that is most qualified to perform the job according to the specifications and qualifications listed in the Invitation to Bid. Bidders shall provide documentation demonstrating their ability to perform the required services, including references and examples of past or current contracts of a similar nature., along with references. Failure to provide said documentation will result in a bid being found non-responsive.
Before a contract will be awarded for the Project contemplated herein, the County will conduct such investigations as is necessary to determine the performance record and ability of the apparent low Bidder to perform the scale and type of services specified under the Contract. The County reserves the right to reject bids from Bidders whose past work performance with the County and other governmental agencies, including timeliness of completion of projects and history of payment to subcontractors or materialmen is deemed by the County to be unsatisfactory. The Bidder shall submit with its bid detailed written evidence of experience and current commitments necessary to allow the County to evaluate the bidder's qualifications. Failure to do so will result in bid being found non-responsive.
IIn the event the apparent low bid submitted by a Responsible and Responsive Bidder exceeds the County’s available budget, the County reserves the right to value engineer the published scope of services in order to effect deductive cost changes with the lowest responsive and responsible Bidder. In light of the modified scope of work, the County shall review the three lowest bids submitted by Responsible and Responsive
Bidders in order to select one Bidder to whom to award the Contract.
The County reserves the right to reject any or all bid(s), and may postpone the award of the Contract for a period of time which shall not extend beyond forty-five (45) calendar days from the bid opening date.
A person or an affiliate who has been placed on the convicted vendor list following a conviction for public entity crime may not submit a bid on a contract to provide any goods or services to a public entity, may not submit a bid on a contract with a public entity for the construction or repair of a public building or public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity, and may not transact business with any public entity in excess of the threshold amount provided in Section 287.017, Florida
Statutes, for CATEGORY TWO for a period of thirty-six (36) months from the date of being placed on the convicted vendors list.
Walton County, as a political subdivision of the State of Florida, shall comply with Executive Order Number 11-
02, dated January 4, 2011, and shall require that contractors utilize the U.S. Department of Homeland
Security’s E-Verify system to verify the employment eligibility of: (a) all persons employed during the contract term by the contractor to perform employment duties within Florida; and (b) all persons (including subcontractors) assigned by the contractor to perform work pursuant to the Contract with the County.
Pursuant to §287.05701, Florida Statutes, the County may not request documentation of or consider a contractor's social, political, or ideological interests when determining if the contractor is a responsible contractor. Further, the County may not give preference to a contractor based on the vendor's social, political, or ideological interests.
2. Instruction to Bidders
2.1 DEFINED TERMS
The term "Bidder" shall mean one who submits a bid directly to the County, as distinct from a sub-bidder, who submits a bid to a Bidder. The term "Responsible and Responsive Bidder" means a person or entity who has submitted a bid which conforms in all material respects to the requirements set forth in the Bidding
Documents and has the capability, in all respects, to perform fully the contract requirements, and the tenacity, perseverance, experience, integrity, reliability, capacity, facilities, equipment, and credit which will assure good faith performance. The term “Successful Bidder” means the most Responsible and Responsive Bidder with the lowest bid who has been selected for award of the Contract. The term “Contract” shall mean the agreement between the Successful Bidder and the County resulting from this ITB. The term “Contract
Documents” include the Service Agreement, Scope of Work, Bid Schedule, and all addenda issued for this solicitation, consisting of information provided in Scope of Work and Attachments sections. The term "Bidding
Documents" includes the Invitation to Bid, Instruction to Bidders, Contract Documents and the Bid Form
(including all addenda issued prior to receipt of bids). The term “Notice of Award” shall mean the form issued by the Purchasing Department awarding the Contract to the Successful Bidder. The term “Notice to Proceed” shall mean the letter issued by the Purchasing Department notifying Successful Bidder to commence work on the Project.
2.2 COPIES OF BIDDING DOCUMENTS
A. Complete sets of Bidding Documents must be used in preparing bids; neither the County nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of
Bidding Documents.
B. The County and Engineer in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining bids on the Project and do not confer a license or grant for any other use.
2.3 QUALIFICATIONS OF BIDDERS
To demonstrate qualifications to perform the Project, each Bidder shall submit with their bid detailed written evidence of experience completing projects of the nature and scope similar to the project described in this
Invitation to Bid, documentation of current commitments, a copy of all applicable occupational and state contractor licenses, and such information as is required in the Vendor Submissions section. Each Bidder must also be prepared to submit within FIVE (5) business days of the County's request, written evidence, such as licenses, financial data, previous experience, present commitments, and other such data as may be requested by the County. Each bid must contain evidence of Bidder's qualification to do business in the State of Florida.
Specifically, the Bidder shall have all licenses and permits required by federal, state, and local statutes, regulations, and ordinances.
2.4 EXAMINATION OF CONTRACT DOCUMENTS AND SITE
https://procurement.opengov.com/portal/waltoncountyfl/projects/247698/document?section=2366342 https://procurement.opengov.com/portal/waltoncountyfl/projects/247698/document?section=2366343 https://procurement.opengov.com/portal/waltoncountyfl/projects/247698/document?section=2366340
A. It is the responsibility of each Bidder before submitting a bid, to (a) examine the Contract Documents thoroughly, (b) visit the Project site to become familiar with local conditions that may affect cost, progress, performance, or completion of the Project, including the time and cost in obtaining any necessary fee or permit, (c) consider federal, state, and local laws and regulations that may affect cost, progress, performance, or completion of the Project, (d) study and carefully correlate Bidder's observations with the Contract Documents, (e) notify the County of any conflicts, errors, or discrepancies in the Contract Documents, and (f) attend any mandatory pre-bid meeting. The County does not assume responsibility for the accuracy or completeness of the Contract Documents or for any additional reports, drawings, and specifications that may be made available for viewing by the County to any Bidder on request.
B. Before submitting a bid, each Bidder will, at the Bidder's own expense, make or obtain any additional information and data which pertain to the physical conditions (surface, subsurface, underground facilities) at or contiguous to the site which may affect cost, progress, performance, or completion of the Project and which Bidder deems necessary to determine its bid for performing and completing the
Project in accordance with the time, price, and other terms and conditions of the Contract Documents.
C. Upon request, in advance, the County will provide each Bidder access to the Project site to conduct such explorations and tests as each Bidder deems necessary for submission of a bid. Bidder shall fill all holes, clean up, and restore the site to its former condition upon completion of such explorations.
D. Temporary construction facilities and storage of materials and equipment will be provided by Bidder.
E. The submission of a bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of these Instructions to Bidders including visiting the Project site to become familiar with local conditions that may affect the cost, progress, performance, or completion of the Project; that without exception the bid is premised upon performing and furnishing of the labor, services, equipment, and materials required by the Contract Documents in accordance with such means, methods, techniques, sequences, or procedures of construction as may be indicated in or required by the Contract Documents; and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and completion of the Project.
2.5 INTERPRETATIONS AND ADDENDA
A. All questions about the meaning or intent of the Contract Documents are to be posted on the County's e-Procurement portal accessible via the following link;
https://procurement.opengov.com/portal/waltoncountyfl.
B. Addenda may be issued to modify the Bidding Documents as deemed appropriate by the County.
https://procurement.opengov.com/portal/waltoncountyfl
DIRECTING QUESTIONS TO ANY OTHER COUNTY COMMISSIONER, COUNTY EMPLOYEE, PROJECT ENGINEER, OR ANY OTHER PERSON IS PROHIBITED AND WILL RESULT IN A BID BEING DISQUALIFIED. QUESTIONS MUST
BE SUBMITTED ON THE COUNTY'S E-PROCUREMENT PORTAL AT
https://procurement.opengov.com/portal/waltoncountyfl NO LATER THAN 12:00 pm ON Monday, April 13, 2026. Interpretations or clarifications considered necessary by the County in response to such questions will be issued by Addenda on the County’s e-Procurement portal. Only questions answered by formal written
Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
2.6 BLACKOUT PERIOD
The period between the beginning of the advertisement for the Invitation to Bid, and the contract award, or any resulting bid protest is resolved, or the solicitation is otherwise canceled is referred to as the blackout period. During the blackout period any communication regarding the aforementioned solicitations is prohibited between the Bidder (or its agents or representatives) and any other entity with the potential for a financial interest in the award (or their respective agents or representatives) regarding such competitive solicitation, and any County Commissioner or County employee, selection committee member, or other persons authorized to act on behalf of the County including the County’s architect, engineer, or their sub consultants, or anyone designated to provide a recommendation to award a particular contract, other than
Purchasing Division staff. Each competitive solicitation shall provide notice of the blackout period.
Exceptions to the Blackout Period. The blackout period shall not apply to:
A. Communications at any public proceeding or meeting, including pre-bid conferences, selection committee presentations, or pre-award meetings.
B. Communications during contract negotiations between designated County employees and the contract awardee.
C. Communication with a vendor initiated by a Purchasing Division employee following the bid opening to clarify the vendor’s bid or intended scope of services.
D. Communication following the filing of a protest between the protesting party and the Purchasing
Division, County Administrator’s Office, and the County Attorney’s Office, during the dispute resolution process.
E. Purchases exempt from competitive selection, sole source procurements, single source procurements, and emergency procurements, as defined in Walton County Board of County Commissioners
Purchasing Policy and Procedure Manual.
F. Communications with existing vendors in the performance of existing contracts.
2.7 BID SECURITY
A. Bid security shall not be required for this solicitation.Bids submitted in response to this Invitation to Bid shall remain valid and subject to acceptance by Walton County for a period of forty-five (45) calendar athttps://procurement.opengov.com/portal/waltoncountyfl athttps://procurement.opengov.com/portal/waltoncountyfl days following the bid opening date.The Successful Bidder shall execute the Contract and provide all required Certificates of Insurance within ten (10) business days after issuance of the Notice of Award, unless otherwise approved in writing by Walton County.If the Successful Bidder fails to execute the
Contract or provide the required Certificates of Insurance within the specified time, Walton County reserves the right to withdraw the Notice of Award and award the Contract to the next lowest responsive and responsible Bidder, or to re-solicit the services if deemed to be in the best interest of the County.Failure of a Bidder to honor the terms of its bid during the bid validity period may result in the Bidder being deemed non-responsible for the purposes of this solicitation or future County solicitations.
2.8 SUBSTITUTE OR "OR-EQUAL" ITEMS
The use of brand names is for the purpose of describing the standard of quality, performance, and characteristics desired and is not intended to limit or restrict competition. Equipment or materials determined by the County to be substantially equivalent to that equipment or materials specified by brand name will be considered for award.
2.9 BID FORM
A. The Bidder shall use the Bid Form included with the Bidding Documents. Failure to use the Bid Form shall result in the bid being declared un-responsive. All blanks on the Bid Form must be completed in ink by hand or typewritten.
B. Bids by corporations must be executed in the corporate name by the president or a vice-president (or other corporate officer accompanied by evidence of authority to sign), and the corporate seal must be affixed and attested. The corporate address and state of incorporation must be shown below the signature.
C. Bids by partnerships must be executed in the partnership name and signed by a partner, whose title must appear under the signature, and the official address of the partnership must be shown below the signature.
D. All bids shall be notarized and names must be typed or printed below the signature. The bid shall contain an acknowledgement of receipt of all addenda via County’s e-Procurement Portal. The contact person's name, address and telephone number, for communications regarding the bid must be provided.
E. Each Bidder’s submittal shall include all the items listed in the Vendor Submissions section.
2.10 SUBMISSION OF BIDS
All bids submitted on e-Procurement Portal will be securely locked and digitally encrypted until the submission deadline passes. Please note that all bids must be submitted prior to 3:00 pm on Wednesday, May 13, 2026.
In order to perform work on public contracts, the successful Bidder shall have all licenses and permits required by federal, state, and local statutes, regulations and ordinances.
Ensure that all required documents and information are complete and accurately provided before submission.
Upon successful submission through the e-Procurement Portal, you will receive a confirmation email acknowledging receipt of your bid.
Bids received after the specified deadline will not be considered.
Thank you for your attention to these submission instructions. Should you have any questions regarding the bidding process or requirements, feel free to contact the Purchasing Department at purchasing@co.walton.fl.us or call 850.892.8176.
2.11 MODIFICATION AND WITHDRAWAL OF BIDS
A. Bids may be modified or withdrawn by the Bidder by clicking on “Unsubmit Proposal” via County’s e-
Procurement Portal. Bids can be re-submitted at any time prior to the opening of bids.
B. Bids may not be withdrawn for a period of FORTY-FIVE (45) calendar days after the date of bid opening.
2.12 BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE
All bids shall remain open and subject to acceptance for a period of forty-five (45) calendar days after the date of bid opening, but the County at its sole discretion may release any bid and return the bid security prior to that date.
2.13 AWARD OF CONTRACT
A. The County reserves the right to reject any and all bids for any reason or for no reason as may be deemed necessary by the County to be in its best interest, including but not limited to bids from any contractor who has failed to successfully complete a previous project to the satisfaction of the County.
The County further reserves the right to waive any and all informalities, and reserves the right to reject all nonconforming, unresponsive, unbalanced, or conditional bids. PLEASE NOTE: ANY TERMS, CONDITIONS, OR EXCEPTIONS SUBMITTED WITH A BID SHALL BE DISREGARDED AND HAVE NO
EFFECT UPON THE CONTRACT RESULTING FROM THIS SOLICITATION. The County reserves the right to reject the bid of any Bidder if the County believes that it would not be in the best interest of the
Project to make an award to that Bidder, because the bid is not responsive or responsible, or the
Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by the County. The County also reserves the right to enter into contract negotiations with a Responsible and Responsive Bidder who submits the lowest bid. If the County and the low Bidder cannot negotiate a successful contract, the County may terminate such negotiations and begin negotiations with a Responsible and Responsive Bidder who submits the next lowest bid. No
Bidder shall have any rights against the County arising from such negotiations. Discrepancies in the mailto:purchasing@co.walton.fl.us multiplication of units of work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Where numeric data is given both in Arabic numerals and in written language, and where there exists a discrepancy between an Arabic numeral and written language, the written language shall be presumed to be correct and the Arabic numeral presumed incorrect.
B. In the event the apparent low bid submitted by a Responsible and Responsive Bidder exceeds the
County's budget for the Project, the County reserves the right to value engineer the published scope of work in order to effect deductive cost changes. In light of the modified scope of work, the County shall review the three lowest bids submitted by Responsible and Responsive Bidders in order to select one
Bidder to whom to award the contract.
C. The County reserves the right to delete any bid items, and the total bid shall be determined as the sum of the bid items awarded. In evaluating bids, the County will consider the qualifications of the Bidders, whether or not the bids comply with the prescribed requirements, time of completion, and other data, as may be requested in the Bid Form or prior to the Notice of Award. The County may conduct such investigations as the County deems necessary to assist in the evaluation of any bid and to establish the responsibility, qualifications and financial ability of Bidders, proposed Subcontractors, Suppliers, and other persons and organizations to perform and complete the Project in accordance with the contract
Documents to the County's satisfaction within the prescribed time. The County may consider the operating costs, maintenance requirements, performance data, and guarantees of major items of materials and equipment proposed for incorporation in the Project when such data is required to be submitted prior to Notice of Award.
If the contract is to be awarded, it will be awarded to the Responsible and Responsive Bidder submitting the lowest bid whose evaluation by the County indicates to the County that the award will be in the best interest of the Project. The Notice of Award shall be issued only after approval by the Walton County Board of County
Commissioners and upon completion of all required award documentation.
No contractual obligation shall exist until the contract has been approved and executed by the Board.
2.14 BID PROTEST
Any person or entity whose bid is rejected, in whole or in part, or who submits a bid but is not awarded the contract, may protest such decision. Written notice of intent to file a bid protest must be submitted with the
Purchasing Department or Chief Financial Officer within twenty-four (24) hours after the Board’s declaration of its intention with regard to an award. Written protest must be submitted to Purchasing Director or Chief
Financial Officer within ten (10) calendar days after filing written notice of intent.
Each written protest must be accompanied by a bid protest bond in the form of a certified check, cashier’s check, or money order made payable to the Walton County Board of County Commissioners, in an amount equal to 1% of the protestor’s bid received by the County, but in no case less than $500.00.
The condition of the protest bond shall be that, should the protest be determined to be without merit and non-valid, the bond shall be forfeited to the County in its entirety.
2.15 PUBLIC ENTITY CRIMES
A person or an affiliate who has been placed on the convicted vendor list following a conviction for public entity crime may not submit a bid on a contract to provide any goods or services to a public entity, may not submit a bid on a contract with a public entity for the construction or repair of a public building or public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity, and may not transact business with any public entity in excess of the threshold amount provided in Section 287.017, Florida
Statutes, for CATEGORY TWO for a period of thirty-six (36) months from the date of being placed on the convicted vendors list.
3. Scope of Services
3.1 Scope Summary
The Vendor shall install vendor owned tank monitors in each of the County fuel tanks and deliver gasoline and diesel fuel anytime fuel levels drop to 20% remaining fuel or within TWENTY-FOUR (24) hours of receiving a delivery request from the County. The Public Works Director or their designee shall be the central point of contact if additional gasoline or diesel fuel deliveries are required.
At the time of delivery Vendor shall provide a fuel ticket which contains the applicable OPIS price.
Unleaded Gasoline/Tank Wagon
Gasoline, unleaded, antiknock (octane) index minimum 87 (RON+MON)/2, maximum allowable lead 0.05 gram per gallon, per A.S.T.M. specification D4814, complying with State of Florida gasoline inspection laws, (price will exclude state inspection fee and all tax). State inspection fee and all applicable tax to be added to invoice.
To be delivered via tank wagon.
No minimum delivery. Billing to be adjusted to 60 degrees F. temperature upon delivery.
Unleaded Gasoline/Transport Wagon
Gasoline, unleaded, antiknock (octane) index minimum 87 (RON+MON)/2, maximum allowable lead 0.05 gram per gallon, per A.S.T.M. specification D4814, complying with State of Florida gasoline inspection laws, (price will exclude state inspection fee and all tax). State inspection fee and all applicable tax to be added to invoice.
To be delivered via transport truck in full loads. Billing to be adjusted to 60 degrees F. temperature on transport delivery.
Diesel Fuel, Grade No. 2-Ultra Low Sulfur Fuel/Tank Wagon
Oil diesel fuel, grade no. 2-D ultra low sulfur fuel (0.5 mass % sulfur, 40 centane min.) for use in over the road diesel engine, per A.S.T. M. specification D975, complying with Florida Department of Agriculture and
Consumer Services Standards 5F02.001, (will exclude all tax). All applicable tax to be added to invoice. To be delivered as ordered via tank wagon. No minimum delivery. Billing to be adjusted to 60 degrees F.
temperature upon delivery.
Transport Wagon
Oil diesel fuel grade no. 2-D ultra low sulfur fuel (0.5 mass % sulfur, 40 centane min.) for use in over the road diesel engine, per A.S.T. M. specification D975, complying with Florida Department of Agriculture and
Consumer Services Standards 5F02.001, (will exclude all tax). All applicable tax to be added to invoice. To be delivered as ordered via transport truck in full loads. No minimum delivery. Billing to be adjusted to 60 degrees F. temperature on transport delivery.
Walton County Fuel Delivery Locations:
Department Address UL Tank Size DL Tank Size Delivery Hours
Public Works 113 Woodyard Rd.
DeFuniak Springs, FL 32435
4000 8000 6 a.m. – 4 p.m.
Mon-Thurs
District 1 3420 McKinnon Bridge Rd
Ponce de Leon, FL 32455
2000 9000 6 a.m. – 4 p.m.
Mon-Thurs
District 2 3479 Brown Road
DeFuniak Springs, FL 32433
1000 4000 6 a.m. – 4 p.m.
Mon-Thurs
District 3 401 Ranch Road
DeFuniak Springs, FL 32433
4000 6000 6 a.m. – 4 p.m.
Mon-Thurs
District 5 142 Community Way
Santa Rosa Beach, FL 32459
4000 6000 6 a.m. – 4 p.m.
Mon-Thurs
Landfill 1118 Institution Road
DeFuniak Springs, FL 32433
4000 6000 6 a.m. – 4 p.m.
Mon-Thurs
Landfill 2nd site 1118 Institution Road
DeFuniak Springs, FL 32433
4000 6000 6 a.m. – 4 p.m.
Mon-Thurs
TDC/ Blue Mountain Pit 924 South County Hwy 83
Santa Rosa Beach, FL 32459
4000 4000 6 a.m. – 4 p.m.
Sun - Sat
The use of tanks may vary during the term of the contract, and additional tanks may be installed or tanks may be replaced during the term of the contract.
Bulk Transport delivery shall be used for all locations listed above except the District 5 and TDC/Blue
Mountain Pit locations, which shall receive tank wagon deliveries.
Delivery:
Delivery to County’s tanks shall occur anytime tank monitors show that fuel levels have dropped to 20% of remaining fuel or within TWENTY-FOUR (24) hours after request is received unless specified otherwise by
County. The quantity will depend upon the County’s need at the time of request. Delivery of fuel shall be made to storage tanks identified above during the hours shown for each site. Failure to make timely deliveries as required may be considered grounds for cancelation of the contract.
Stick readings or dial readings before and after putting fuel into each tank must be noted on the delivery tickets. Delivery tickets for payment at each tank location must carry the signature of an authorized County employee. County reserves the right to withhold payment for delivery tickets without stick or dial readings and/or proper signatures.
Compliance with Occupational Safety and Health:
Vendors certify that all material, equipment, etc., contained in their offers meet all
Occupational Safety and Health Administration (OSHA) requirements.
Vendors further certify that, if awarded the contract, and the material, equipment, etc., delivered is subsequently found to be deficient in any OSHA requirement in effect on date of delivery, all costs necessary to bring the material, equipment, etc., into compliance with the aforementioned requirements shall be borne by the vendor.
In compliance with Chapter 42, Florida Statutes, a Material Safety Data Sheet (MSDS) shall accompany any item delivered under a contract from this solicitation. The MSDS shall include the following information:
A. The chemical name and the common name of the toxic substance.
B. The hazards or other risks in the use of the toxic substance, including
• The potential for fire, explosion, corrosiveness, and reactivity.
• The known acute and chronic health effects of risks from exposure, including the medical conditions which are generally recognized as being aggravated by the exposure to the toxic substance; and
• The primary route of entry and symptoms of over exposure.
C. The proper precautions, handling practices, necessary personal protective equipment and other safety precautions in the use of or exposure to the toxic substances, include appropriate emergency treatment in case of over exposure.
D. The emergency procedure for spills, fire, disposal, and first aid.
E. A description in lay terms of the known specified potential health risks posed by the toxic substance intended to alert any person reading this information.
F. The year and month, if available, that the information was compiled and the name, address, and emergency telephone number of the manufacturer responsible for preparing the information.
Safety Regulations:
Equipment shall meet all state and federal safety regulations.
Emergency Services:
Gasoline and diesel fuel are vital to the operation of the County and are required during emergency situations such as hurricanes and other catastrophes, whether manmade or natural. Time is of the essence during emergency situations, and the Vendor shall provide emergency contact information to ensure County can order and receive gasoline and/or diesel fuel at any time, day and guarantee delivery within 12 hours during an emergency.
Equipment Repair and Maintenance:
County shall be responsible for all equipment repair and maintenance. However, Vendor shall notify County of any malfunctioning tanks, pumps, meters, and other ancillary equipment of which Vendor becomes aware.
Price Adjustment:
County may request written price adjustments be made every twelve months, no less than 30 days prior to the requested effective date. Any increase price adjustment(s) shall be accompanied by written justification attesting that the request is a bona fide cost increase to the Vendor. All price adjustments shall be reviewed by the County’s designated representative. If an adjustment in price is approved, it shall be accomplished by written amendment to this Agreement and approved by the Board of County Commissioners.
4. Bid Schedule
This is a unit price bid. Bidders shall provide a markup (cents per gallon or percentage) over OPIS rack pricing for gasoline and diesel fuel, as specified in the Bid Schedule.
If a Bidder identifies a discrepancy between the scope of services described in the Contract Documents and the Bid Schedule, the Bidder shall notify the Purchasing Director no later than one week prior to the bid closing date.
The unit prices submitted shall be used as the basis for determining the value of any authorized additions or reductions to service areas during the term of the Contract.
Pricing shall be based on OPIS Pensacola rack average on the date of delivery, plus a fixed markup per gallon submitted in the Bid Schedule. The markup shall remain firm for the duration of the contract.
Walton County reserves the right to reject any or all bids and to award the Contract in accordance with the best interests of the County.
NOTE: The unit prices listed below will be used as the basis for computing the value of any change orders either additive or deductive. THE OWNER RESERVES THE RIGHT TO REJECT ANY OR ALL BIDS.
BULK TRANSPORT DELIVERY
Line Item Description Unit of
Measure Markup Unit Cost Total
1 Unleaded GL
2 Diesel #2 GL
TOTAL
TANK WAGON DELIVERY
Line Item Description Unit of
Measure Markup Unit Cost Total
1 Unleaded GL
2 Diesel #2 GL
TOTAL
5. Vendor Submissions
All subsections in this section require a response.
Important: Bidders are responsible for reviewing all required forms and documentation listed in this solicitation. If any forms require notarization—such as the Public Entity Crimes Statement or the Unauthorized Alien Affidavit—they must be properly executed and uploaded with your submission. Failure to include completed and notarized documents, where applicable, may result in your bid being deemed non-responsive.
5.1 LOCAL PREFERENCE APPLICATION*
I hereby certify under penalty of perjury that my business qualifies as a local vendor/contractor in accordance with Walton County Purchasing Policies and Procedures, Procedure No: PP017.
☐ My business maintains its principal place of business within Walton County; OR
☐ My business has maintained a permanent place or places of business within Walton County and has employed people who live in Walton County on a regular and continuing basis for at least six (6) months prior to the advertising of this Invitation to Bid; OR
☐ My business is not eligible for local vendor preference with Walton County.
*Response required
5.2 BIDDER'S DECLARATION AND UNDERSTANDING *
The undersigned, herein defined as the "Bidder," declares that the only persons or parties interested in this bid are those named herein, that this bid is, in all respects, fair and without fraud, that it is made without collusion with any employee or official of the County, and that the bid is made without any connection or collusion with any person submitting another bid on this Project.
The Bidder further declares that it has visited the Project site, inspected the plans and specifications, examined all the Contract Documents, and has satisfied itself to the quantities involved, including materials, equipment, and the conditions of work involved, including the fact that the description of work and materials, as included herein, is brief and is intended only to indicate the general nature of the Project and to identify the said quantities with the detailed requirements of the Contract Documents, and this bid is made according to the provisions and under the terms of the Contract Documents which are made a part of this bid.
☐ Please confirm
*Response required
5.3 CONTRACT EXECUTION AND CERTIFICATES OF INSURANCE*
The Successful Bidder shall acknowledge the terms and conditions of the Contract and return a signed
Contract to Walton County along with all required Certificates of Insurance (COI) within ten (10) business days after issuance of the Notice of Award, unless otherwise approved in writing by the County.
Upon receipt and approval of the signed Contract and Certificates of Insurance, Walton County will execute the Contract and provide a fully executed copy to the Successful Bidder.
The Successful Bidder shall not commence services until the Contract has been fully executed and the County has issued a Notice to Proceed.
Failure of the Successful Bidder to execute the Contract or provide the required Certificates of Insurance within the specified time may result in the County withdrawing the Notice of Award and proceeding with award to the next lowest responsive and responsible Bidder or taking such other action as deemed in the best interest of the County.
☐ Please confirm
*Response required
5.4 COMMENCEMENT OF SERVICES AND CONTRACT TERM*
The Successful Bidder shall begin providing services under the Contract within ten (10) business days after issuance of the Notice to Proceed, unless otherwise approved in writing by Walton County.
The term of the Contract shall be ONE (1) year from the date of complete contract execution, unless terminated earlier in accordance with the terms of the Contract and may be renewed for up to FOUR (4) additional ONE (1) year terms.
Services shall be performed in accordance with the scope of work and service schedule established between the Vendor and Walton County. The Vendor shall coordinate service dates with the County’s designated representative to ensure that all locations are serviced in accordance with the requirements of the Contract.
The Vendor shall perform all services in a timely and professional manner consistent with industry standards and the requirements set forth in the Contract Documents.
If scheduled services are not performed within the required service window established in the Contract, Walton County reserves the right to require corrective service at no additional cost or to deduct the cost of the missed service from the Vendor’s invoice.
☐ Please confirm
*Response required
5.5 SALES AND USE TAXES*
The Bidder agrees that any and all applicable federal, state and local sales and use taxes that are incurred by the Bidder are included in the stated bid price for the Project. The County is tax exempt from federal excise and state sales tax.
☐ Please confirm
5.6 Acknowledgment of Bid Schedule*
By confirming, if awarded the contract, the Bidder agrees to accept as full payment for the work proposed under this Project, as specified in the Bidding Documents prepared by Walton County, and based upon their own estimate of the quantities and costs, including the cost of any necessary fee or permit provided as part of their bid.
☐ Please confirm
*Response required
5.7 BID FORM*
Please download the below documents, complete, and upload.
• BID_FORM_(14).docx
*Response required
5.8 BID BOND*
Will you be utilizing Surety 2000 for submitting your Bid Bond?
☐ Yes
☐ No
*Response required
When equals "Yes"
Surety 2000 Electronic Bid Bond*
Please enter your Bid Bond information from Surety2000 below.
If you would like to use your preferred surety, please select "No" to the above question.
*Response required
When equals "No"
Bid Bond*
Please download the below documents, complete, and upload.
• 3.0_Walton_County_Florida_B...
*Response required
5.9 PREVIOUS EXPERIENCE AND CURRENT COMMITMENTS*
Please download the below documents, complete, and upload.
• PREVIOUS_EXPERIENCE_AND_CUR...
https://government-project.s3.us-west-2.amazonaws.com/88564/132b3318-2d92-4ca8-82dc-b8dcc3728e2a_BID_FORM_%2814%29.docx?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4HMNPEHF2%2F20260413%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260413T200011Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjELP%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJGMEQCIGFp1SfzWvjaOGVvFrW9GvtgS75neNPcoH9aI6etjeITAiApLFhKHq%2FhSqDdIaH8BOFvygReHSgRVkhCCrAMMYMf8CqMBQh8EAIaDDg5MjM2NDY4NzY3MiIMo7RRm6%2Fr%2B3M%2Bt37EKukE%2FIuiU46BOtEAW1y3%2BfU3NYwfmLZErTfvX5kDvgA%2B%2BiKcwgMUDm3fbdMrL%2F3TVtmMRYZ8ynPCY0EGXsBnNUQSRrGUWv5%2BS3eEaJ3ETI9fdjdjxOuzGzqVEb1j4CmDVtoGW6ymNIqui7eYmDpeSan1mPSFaYAkh8jFp07FVlb87YRKhbufwgedLPNlABLe93JLeujAESdPT5CCkQTQoQsxw%2Fg2O8DPfFotohdGpFpV2nPwmG3RpofnMUuIuDRgiHPnR7y%2F6ra4YYjykf%2ByqdbJZBgTbBKItWSED0xy1N6YVapN8DsQfGNuYp6vUZcUfOwBfMpEi%2F%2FkPdyGEtQd3%2BJrqFhPVCeP5nvd2yNJ4yD%2BaSqDMqyffMPcOAbFQDcXPnveiC3Uy%2FBXxhYucnyQJX53Nq2hZ1Cdr2i9GcpIRVbVm7IaCeJWugTjqQ9NjKQfzYmpea3V3g6GafeoSghHB%2F8fREx8rS6INsYNUs5zeP3eMpMkf7pBdmKSAEk7GmLviKs6HSakK2VYzWUfm8fnh%2F6WnNm%2F9b2klVT86AM6%2FrSqxW694jGDVExAuenoCgLcpBCaoGo482Hocbhan50JwOkgP1sUNC44WHv61Bm6BdzrLAPJoQb79gCzD57AOIxrDJ%2BnEFolrBaFxUtORIMSfBixytPgLn0OUyP9qdvjFORb3XGHgw28IfXTi99nEQvbau3w2%2BRLCk4n9JBH0nyMcvphFBjQ%2FpTVA26RYPyBlA4wRoT62ljwXSl8llkEjdniqn001mASMfV3wepNoolIw6VsSdt6WhxHMzFjXDqMxqw2b1QtLLJKkTBcSiow6YH1zgY6mgEzp33VXXBIIbXweSyw6MLGh5StPNWs%2BoeRH75DXr2d6rIIkhCa9ykwEC4DLuw2sHi1zrIjH0WkagK0I%2Fk1VTxQLxVqkc1LYbSUDynAehDvL04DEycjwV8goc6PZNABxhH3mJefbG9T5NHO2YrDrI0VKiEYIHuYXirnQO3PgBkAxHla13i87g8gcpQ%2FP%2BeGPBsl2S0%2FJrLwKCdy&X-Amz-Signature=27bbdd4958a41fb5cbf3cc55e6af434ea54cda484aba8be16be31b72376b58fa&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22BID_FORM_%2814%29.docx%22&x-id=GetObject https://government-project.s3.us-west-2.amazonaws.com/88564/0a36e9aa-78ff-44a3-aa6a-f4a1a116e837_3.0_Walton_County_Florida_Bid_Bond_V1.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4HMNPEHF2%2F20260413%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260413T200011Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjELP%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJGMEQCIGFp1SfzWvjaOGVvFrW9GvtgS75neNPcoH9aI6etjeITAiApLFhKHq%2FhSqDdIaH8BOFvygReHSgRVkhCCrAMMYMf8CqMBQh8EAIaDDg5MjM2NDY4NzY3MiIMo7RRm6%2Fr%2B3M%2Bt37EKukE%2FIuiU46BOtEAW1y3%2BfU3NYwfmLZErTfvX5kDvgA%2B%2BiKcwgMUDm3fbdMrL%2F3TVtmMRYZ8ynPCY0EGXsBnNUQSRrGUWv5%2BS3eEaJ3ETI9fdjdjxOuzGzqVEb1j4CmDVtoGW6ymNIqui7eYmDpeSan1mPSFaYAkh8jFp07FVlb87YRKhbufwgedLPNlABLe93JLeujAESdPT5CCkQTQoQsxw%2Fg2O8DPfFotohdGpFpV2nPwmG3RpofnMUuIuDRgiHPnR7y%2F6ra4YYjykf%2ByqdbJZBgTbBKItWSED0xy1N6YVapN8DsQfGNuYp6vUZcUfOwBfMpEi%2F%2FkPdyGEtQd3%2BJrqFhPVCeP5nvd2yNJ4yD%2BaSqDMqyffMPcOAbFQDcXPnveiC3Uy%2FBXxhYucnyQJX53Nq2hZ1Cdr2i9GcpIRVbVm7IaCeJWugTjqQ9NjKQfzYmpea3V3g6GafeoSghHB%2F8fREx8rS6INsYNUs5zeP3eMpMkf7pBdmKSAEk7GmLviKs6HSakK2VYzWUfm8fnh%2F6WnNm%2F9b2klVT86AM6%2FrSqxW694jGDVExAuenoCgLcpBCaoGo482Hocbhan50JwOkgP1sUNC44WHv61Bm6BdzrLAPJoQb79gCzD57AOIxrDJ%2BnEFolrBaFxUtORIMSfBixytPgLn0OUyP9qdvjFORb3XGHgw28IfXTi99nEQvbau3w2%2BRLCk4n9JBH0nyMcvphFBjQ%2FpTVA26RYPyBlA4wRoT62ljwXSl8llkEjdniqn001mASMfV3wepNoolIw6VsSdt6WhxHMzFjXDqMxqw2b1QtLLJKkTBcSiow6YH1zgY6mgEzp33VXXBIIbXweSyw6MLGh5StPNWs%2BoeRH75DXr2d6rIIkhCa9ykwEC4DLuw2sHi1zrIjH0WkagK0I%2Fk1VTxQLxVqkc1LYbSUDynAehDvL04DEycjwV8goc6PZNABxhH3mJefbG9T5NHO2YrDrI0VKiEYIHuYXirnQO3PgBkAxHla13i87g8gcpQ%2FP%2BeGPBsl2S0%2FJrLwKCdy&X-Amz-Signature=394158c8796e737d02622122736a5586eae9048f1c74eb48ed30934d95510e74&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%223.0_Walton_County_Florida_Bid_Bond_V1.pdf%22&x-id=GetObject https://government-project.s3.us-west-2.amazonaws.com/88564/56dbf75e-6f70-41ed-93e7-6c8fa8c4a095_PREVIOUS_EXPERIENCE_AND_CURRENT_COMMITMENTS.docx?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4HMNPEHF2%2F20260413%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260413T200011Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjELP%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJGMEQCIGFp1SfzWvjaOGVvFrW9GvtgS75neNPcoH9aI6etjeITAiApLFhKHq%2FhSqDdIaH8BOFvygReHSgRVkhCCrAMMYMf8CqMBQh8EAIaDDg5MjM2NDY4NzY3MiIMo7RRm6%2Fr%2B3M%2Bt37EKukE%2FIuiU46BOtEAW1y3%2BfU3NYwfmLZErTfvX5kDvgA%2B%2BiKcwgMUDm3fbdMrL%2F3TVtmMRYZ8ynPCY0EGXsBnNUQSRrGUWv5%2BS3eEaJ3ETI9fdjdjxOuzGzqVEb1j4CmDVtoGW6ymNIqui7eYmDpeSan1mPSFaYAkh8jFp07FVlb87YRKhbufwgedLPNlABLe93JLeujAESdPT5CCkQTQoQsxw%2Fg2O8DPfFotohdGpFpV2nPwmG3RpofnMUuIuDRgiHPnR7y%2F6ra4YYjykf%2ByqdbJZBgTbBKItWSED0xy1N6YVapN8DsQfGNuYp6vUZcUfOwBfMpEi%2F%2FkPdyGEtQd3%2BJrqFhPVCeP5nvd2yNJ4yD%2BaSqDMqyffMPcOAbFQDcXPnveiC3Uy%2FBXxhYucnyQJX53Nq2hZ1Cdr2i9GcpIRVbVm7IaCeJWugTjqQ9NjKQfzYmpea3V3g6GafeoSghHB%2F8fREx8rS6INsYNUs5zeP3eMpMkf7pBdmKSAEk7GmLviKs6HSakK2VYzWUfm8fnh%2F6WnNm%2F9b2klVT86AM6%2FrSqxW694jGDVExAuenoCgLcpBCaoGo482Hocbhan50JwOkgP1sUNC44WHv61Bm6BdzrLAPJoQb79gCzD57AOIxrDJ%2BnEFolrBaFxUtORIMSfBixytPgLn0OUyP9qdvjFORb3XGHgw28IfXTi99nEQvbau3w2%2BRLCk4n9JBH0nyMcvphFBjQ%2FpTVA26RYPyBlA4wRoT62ljwXSl8llkEjdniqn001mASMfV3wepNoolIw6VsSdt6WhxHMzFjXDqMxqw2b1QtLLJKkTBcSiow6YH1zgY6mgEzp33VXXBIIbXweSyw6MLGh5StPNWs%2BoeRH75DXr2d6rIIkhCa9ykwEC4DLuw2sHi1zrIjH0WkagK0I%2Fk1VTxQLxVqkc1LYbSUDynAehDvL04DEycjwV8goc6PZNABxhH3mJefbG9T5NHO2YrDrI0VKiEYIHuYXirnQO3PgBkAxHla13i87g8gcpQ%2FP%2BeGPBsl2S0%2FJrLwKCdy&X-Amz-Signature=baa297a59b64debd7139548b5a07303f923f960d7cd979029a323a567dca23e9&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22PREVIOUS_EXPERIENCE_AND_CURRENT_COMMITMENTS.docx%22&x-id=GetObject
5.10 SUBCONTRACTORS AND SUPPLIERS DECLARATION*
Please download the below documents, complete, and upload.
• SUBCONTRACTORS_AND_SUPPLIER...
*Response required
5.11 PUBLIC ENTITY CRIMES*
Please download the below documents, complete, and have notarized. An online notarization option will be provided for you when responding.
• PUBLIC_ENTITY_CRIMES_(13).pdf
*Response required
5.12 DRUG FREE WORK PLACE CERTIFICATION*
Identical tie bids: preference shall be given to businesses with drug-free workplace programs. Whenever two or more bids which are equal with respect price, quality, and service are received by the state or by any political subdivision for the procurement of commodities or contractual services, a bid received from a business that certified that it has implemented a drug-free work place program shall be given preference in the award process. Established procedures for processing tie bids will be followed in none of the tied
Consultants have a drug-free workplace program. In order to have a drug-free workplace program, a business shall:
A. Publish a statement notifying employees that the unlawful manufacture, distribution, dispensing, possession or use of a controlled substance is prohibited in the workplace specifying the actions that will be taken against employees for violations of such prohibition.
B. Inform employees about the dangers of drug abuse in the workplace, the business’s policy of maintaining a drug-free workplace, available drug counseling, rehabilitation providing employee assistance programs, and the penalties that may be imposed upon…
This is the start of the file's text. The full file is on GovTribe.