GAOA_Milner_Picnic_Cabana_Replacement_Spec.pdf

PDF 249 KB Posted

Attached to
GAOA Milner Picnic Site Cabana Replacement
Solicitation number
140L2626Q0033
Issued by

About this file

This document is a set of technical specifications for the GAOA Milner Picnic Cabana Replacement project in the Twin Falls District of the Bureau of Land Management, located in Burley, Idaho, scheduled for June 2025.

The project involves replacement of two picnic shelter structures and associated site work. Primary work includes: site clearing and grubbing; excavation and grading; placement of crushed aggregate base courses; cast-in-place concrete for two slab pads and column footings; demolition and removal of existing shade structures and concrete; and installation of two pre-engineered steel shelters (one 16' x 16' square and one 16' x 32' rectangular) with hip roof design and 7'-6" minimum eave height. All bolts must be concealed within steel tubes, and field welding is prohibited. The shelters require a minimum five-year manufacturer warranty on the frame and a 30-year roofing warranty. Structural steel components must be ASTM A500 Grade C tube with ASTM A325 bolts and ASTM A563 nuts, finished with powder coat in a government-selected color. Metal roof panels must be aluminum-zinc alloy coated (Galvalume) with PVDF finish, minimum 24 gauge, factory precut with ribs running with roof pitch. Concrete specifications call for 4,000 psi strength at 28 days with maximum water-cementitious materials ratio of 0.45. The contractor is responsible for mobilization/demobilization, site preparation, erosion control, temporary facilities, and construction management. Payment is structured as lump sum for each bid item, with mobilization paid in phases based on overall project progress (25% at 5% completion, 50% at 10% completion, 100% at 50% completion).

View the file

Other files

File Type Posted
Sol_140L2626Q0033.pdf PDF
GAOA_Milner_Picnic_Cabana_Replacement_Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior

Bureau of Land Management

GAOA Milner Picnic Cabana Replacement

Twin Falls District

Burley, ID

June 2025

JUNE 2025 TABLE OF CONTENTS

GAOA MILNER PICNIC CABANA REPLACMENT 1

TABLE OF CONTENTS

SPECIFICATIONS ........................................................................................................................... # OF PAGES

DIVISION 01 - GENERAL REQUIREMENTS

011000 SUMMARY

011713 MOBILIZATION

012200 UNIT PRICES AND SCHEDULE OF VALUES

013100 PROJECT MANAGEMENT AND COORDINATION

013300 SUBMITTAL PROCEDURES

014000 QUALITY REQUIREMENTS

015000 TEMPORARY FACILITIES AND CONTROLS

016000 PRODUCT REQUIREMENTS

017300 EXECUTION REQUIREMENTS

017700 CLOSEOUT PROCEDURES

DIVISION 02

024119 SELECTIVE DEMOLITION

DIVISION 03 – CONCRETE

033000 CAST-IN-PLACE CONCRETE

DIVISION 13 – SPECIAL CONSTRUCTION

130470 PRE-ENGINEERED SHELTERS

DIVISION 31 - EARTHWORK

311000 SITE CLEARING

312000 EARTH MOVING

END OF TABLE OF CONTENTS

JUNE 2025 SUMMARY

GAOA MILNER PICNIC CABANA REPLACEMENT 011000-1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Use of premises.

3. Specification formats and conventions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: GAOA Milner Picnic Cabana Replacement.

1. Project Location: GAOA Milner Picnic Cabana Replacement is located along the Snake River in the Milner Recreation Site Boat Ramp area in Cassia County, Burley, Idaho.

B. The Work consists of the following:

1. Clearing and grubbing of construction area.

2. Rough grading, excavation, placement and compaction of fill and backfill.

3. Final grading and aggregate surfacing.

4. Cast in place concrete.

5. Installation of cabana shade structure.

C. Project will be constructed under a single prime contract.

1.3 USE OF PREMISES

A. General: Electrical power and water are not available on the site. The Contractor will be responsible to provide these services as needed during construction.

B. Sanitary Facilities: Contractor can use existing vault toilet facility but will be required to provide temporary wash facilities and drinking water for use of construction personnel. Comply with authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

C. Contractor shall have full use of premises for construction operations during construction period. Contractor's use of premises is limited only by Government right to perform work or to retain other contractors on portions of work.

D. Schedule operations so that Work is conducted during regular office hours which are 7:00 a.m.

to 5:00 p.m.

GAOA MILNER PICNIC CABANA REPLACEMENT 011000-2

E. Schedule and sequence operations necessary to complete the work, including coordination with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.

F. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. The picnic area of the site will be closed to the public during the duration of the construction project. The contractor is responsible for control of the area and maintaining the closure area, including fencing, signing, barricades, etc. to keep public out of construction areas.

2. Driveways and Entrances: Keep boat ramp and boat ramp parking area accessible and entrances serving vault toilet clear and available to public, Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Parking will be available on the south side of project. Coordinate with the CO for additional parking and material storage.

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

1.4 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into Divisions and Sections using the 50-division format and CSI/CSC's "MasterFormat" numbering system.

1. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the Specifications.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate.

Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications.

Requirements expressed in the imperative mood are to be performed by Contractor.

Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

GAOA MILNER PICNIC CABANA REPLACEMENT 011000-3

C. Terminology: In Divisions 2 through 33 specification sections, all references to “Owner” have been replaced with the term “Government” (when referring to the person acting for the Government). All references to “Architect” have been replaced with the term “Government”.

D. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the work of all Sections in the Specifications.

E. Contract Times: “Days” referred to in the Specifications are defined as calendar days.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

JUNE 2025 MOBILIZATION

GAOA MILNER PICNIC CABANA REPLACEMENT 011713-1

SECTION 011713 – MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the Contract. This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site, as well as construction management activities as described in Division 01 specifications and in the Contract Clauses, including applicable Federal Acquisition Regulations (FARs).

B. This item also includes the cost of transportation of Contractor’s personnel, materials, and equipment to and from the job site during accomplishment of the project.

C. The cost of any required bonds may also be included in mobilization.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall perform the necessary preparatory work and operations, including but not limited to, those required for the movement of personnel, equipment, supplies, and incidentals to the project site to assure completion of the project within the required time frames.

B. The contractor shall also perform all project coordination and construction management as described in Division 01 specifications or incidental/managerial work from other Divisions and FARs, including, but not limited to, following contract procedures for providing submittals, shop drawings, construction schedules, safety and traffic management plans, environmental compliance, maintaining project documents and records, and all associated work as described or otherwise required.

3.2 BASIC MOBILIZATION

A. Mobilization for contact work at or near major administrative or recreational sites as identified in the contract documents.

JUNE 2025 MOBILIZATION

GAOA MILNER PICNIC CABANA REPLACEMENT 011713-2

PART 4 - MEASUREMENT AND PAYMENT

4.1 PROGRESS PAYMENTS WILL BE MADE AS FOLLOWS:

A. When 5 percent or more of the original bid amount (per site) is earned from other pay items, 25 percent of the amount for mobilization will be paid.

B. When 10 percent or more of the original bid amount (per site) is earned from other pay items, 50 percent of the amount for mobilization will be paid.

C. When 50 percent or more of the total amount (per site) is earned, 100 percent of the amount bid for mobilization will be paid.

D. The total of all payments shall not exceed the original contract amount for this item.

END OF SECTION 017113

JUNE 2024 UNIT PRICES AND SCHEDULE OF VALUES

GAOA MILNER PICNIC CABANA REPLACEMENT 012200-1

SECTION 012200 - UNIT PRICES AND SCHEDULE OF VALUES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for unit prices and requirements to prepare schedule of values.

1.2 DEFINITIONS

A. Unit price is a price per unit of measurement for materials or services added to or deducted from the Contract Sum by appropriate modification, if estimated quantities of Work required by the Contract Documents are increased or decreased.

1.3 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

B. Government reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government expense, by an independent surveyor acceptable to Contractor.

C. List of Unit Prices: A list of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

1.4 SCHEDULE OF VALUES (Not Used)

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Application for Payment and Contractor's Construction Schedule.

2. Submit the Schedule of Values to Government at earliest possible date but no later than ten calendar days after the Notice to Proceed.

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the Schedule of Values:

a. Project name and location.

GAOA MILNER PICNIC CABANA REPLACEMENT 012200-2

b. Name of Government.

c. Contractor's name and address.

d. Date of submittal.

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate. Include separate line items under required principal subcontracts for operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training in the amount of 5 percent of the Contract Sum.

3. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

4. Provide a separate line item in the Schedule of Values for each part of the Work where

Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

5. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

6. Each item in the Schedule of Values and Applications for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

7. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Modifications or Construction Change Directives result in a change in the Contract Sum.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LUMP SUM PAYMENT ITEMS

A. Payment items for the work of this Contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below.

B. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved.

C. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

3.2 UNIT PRICE PAYMENT ITEMS (Not Used)

GAOA MILNER PICNIC CABANA REPLACEMENT 012200-3

A. Payment items for the work of this Contract for which unit price payments will be made are listed in the BIDDING SCHEDULE and described below.

B. Unit price items are inclusive of all materials, labor, parts, assembly, and installation in order to produce a unit of the product. All costs for items of work, which are not specifically mentioned to be included in a particular unit price payment item, shall be included in the listed unit price item most closely associated with the work involved.

C. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

D. Quantities regarding unit prices shall be assumed to follow the quantities listed in the bid schedule. If the Contractor suspects a change in the unit quantities, measurement can be made to adjust the final quantity of an item. If the quantity of an item cannot be measured at final condition the contractor shall produce construction documentation collected during construction to demonstrate the quantity.

3.3 SUMMARY OF BID ITEMS

A. The intent of the following paragraphs is to explain, in general, what is and what is not included in a bid item, and the limits or cut-off points where one bid item ends and another begins. If no bid item exists for a portion of the work, include the costs in a related bid item.

B. 011713 (01) - MOBILIZATION AND CONSTRUCTION MANAGEMENT: This item includes all preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; bonds, work layout; other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site. Construction management includes ongoing tasks such as environmental controls, temporary facilities and controls, temporary traffic control, and field office operations. Item also includes preparation and installation of erosion control measures and features. Item will be paid for as a lump sum.

C. 024119 (02) – DEMOLITION: This item includes labor and equipment necessary for the removal and disposal of two shade shelters, concrete pad, and concrete footings associated with the smaller shade shelter. Includes saw cutting the sidewalk to the smaller shelter to create a clean edge for the installation of the new concrete pad. Item will be paid for as a lump sum.

D. 033000 (03) – CONCRETE: This item includes labor, materials, and equipment to install concrete slabs, and column footings for the pre-engineered shelters in accordance with the specifications and drawings. Item will be paid for as a lump sum.

E. 130470 (04) – PREENGINEERED PICNIC SHELTERS: This item includes providing all labor, materials, engineering, and equipment necessary to install the picnic shelter per the specifications and drawings. Item will be paid for as a lump sum.

F. 312000 (05) – EARTH MOVING: This item includes labor and equipment to clear the areas identified on the plans for construction, excavation of soil materials to subgrade elevations, staking for new construction, placement and compaction of subbase materials, and placement

GAOA MILNER PICNIC CABANA REPLACEMENT 012200-4

and compaction of base course materials for new concrete pads in accordance with the plans.

Item also includes transport locally for disposal of unsuitable material as directed by the specifications and drawings. It will be paid for as a lump sum.

END OF SECTION 012200

JUNE 2025

GAOA MILNER PICNIC CABANA REPLACEMENT

SUBMITTAL PROCEDURES

013300 - 1

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Government's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Government's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.3 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Project name.

2. Date.

3. Name of Government.

4. Name of Contractor.

5. Name of firm or entity that prepared submittal.

6. Names of subcontractor, manufacturer, and supplier.

7. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals.

8. Category and type of submittal.

9. Submittal purpose and description.

10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

11. Drawing number and detail references, as appropriate.

12. Indication of full or partial submittal.

13. Location(s) where product is to be installed, as appropriate.

14. Other necessary identification.

15. Remarks.

16. Signature of transmitter.

B. Options: Identify options requiring selection by Government.

SUBMITTAL PROCEDURES

013300 - 2

C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Government on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

1.4 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package, and transmit to Government by sending via email. Include PDF transmittal form. Include information in email subject line as requested by Government.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.

Time for review shall commence on Government's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Government will advise Contractor when a submittal being processed must be delayed for coordination.

2. Resubmittal Review: Allow 15 days for review of each resubmittal.

D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Government's action stamp.

SUBMITTAL PROCEDURES

013300 - 3

1.5 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency, when required by pavilion/cabana manufacturer.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 30 by 42 inches.

C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Permanently attach label on unexposed side of Samples that includes the following:

a. Project name and submittal number.

b. Generic description of Sample.

c. Product name and name of manufacturer.

d. Sample source.

SUBMITTAL PROCEDURES

013300 - 4

e. Number and title of applicable Specification Section.

f. Specification paragraph number and generic name of each item.

3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics, and identification information for record.

4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

a. Samples not incorporated into the Work, or otherwise designated as Government's property, are the property of Contractor.

5. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit one full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Government will return submittal with options selected.

6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit two sets of Samples. Government will retain one Sample set; remainder will be returned.

1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.

2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least two sets of paired units that show approximate limits of variations.

D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of Government, and other information specified.

F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.

SUBMITTAL PROCEDURES

013300 - 5

G. Certificates:

1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide a notarized signature where indicated.

2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.

Include evidence of manufacturing experience where required.

4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

H. Test and Research Reports:

1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

4. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

1.6 DELEGATED-DESIGN SERVICES

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Government.

B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file and one paper copy of certificate, signed

SUBMITTAL PROCEDURES

013300 - 6 and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.

1.7 CONTRACTOR'S REVIEW

A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents.

Note corrections and field dimensions. Mark with approval stamp before submitting to Government.

B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

1. Government will not review submittals received from Contractor that do not have Contractor's review and approval.

1.8 GOVERNMENT'S REVIEW

A. Action Submittals: Government will review each submittal, indicate corrections or revisions required, and return it.

1. PDF Submittals: Government will indicate, via markup on each submittal, the appropriate action, as follows:

a. APPROVED: Where submittals are marked “Approved”, that part of the Work covered by the submittal may proceed provided it complies with requirements of the Contract Documents; final acceptance will depend upon that compliance.

b. APPROVED, SUBJECT TO COMPLIANCE WITH ATTACHED COMMENTS:

Where submittals are marked “Approved, Subject to Compliance with Attached Comments”, that part of the Work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the Contract Document; final acceptance will depend upon that compliance.

c. NOT APPROVED: Where submittals are marked “Not Approved”, do not proceed with that part of the Work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal in accordance with the notations; resubmit without delay. Repeat if necessary to obtain a different action mark.

B. Informational Submittals: Government will review each submittal and will not return it, or will return it if it does not comply with requirements. Government will forward each submittal to appropriate party.

SUBMITTAL PROCEDURES

013300 - 7

C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Government.

D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

E. Government will return without review submittals received from sources other than Contractor.

F. Submittals not required by the Contract Documents will be returned by Government without action.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013300

JUNE 2025 PRODUCT REQUIREMENTS

GAOA MILNER PICNIC CABANA REPLACEMENT 016000-1

SECTION 016000 - PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; product substitutions; and comparable products.

B. See Division 1 Section "Closeout Procedures" for submitting warranties for Contract closeout.

C. See Divisions 2 through 33 Sections for specific requirements for warranties on products and installations specified to be warranted.

1.2 SUBMITTALS

A. Substitution Requests: Submit one electronic copy of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified material or product cannot be provided.

b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Government and separate contractors that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated. Provide sufficient calculations and data to justify selection of proposed item and permit comparisons.

d. Product Data, including technical data, drawings, performance information, and descriptions of products and fabrication and installation procedures. Show complete layout of system, except that which is identical to Contract Documents, unless unchanged portion must be shown to indicate clearances. Include drawings, same (or larger) scale as Contract Drawings, marked to show differences. Include detail drawings of supports for equipment and load calculations, stamped and signed by a registered professional engineer.

e. Samples, where applicable or requested.

f. List of similar installations for completed projects with project names and addresses and names and addresses of COR’s and Government’s.

g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

GAOA MILNER PICNIC CABANA REPLACEMENT 016000-2

h. Research/evaluation reports evidencing compliance with building code in effect for Project, from a model code organization acceptable to authorities having jurisdiction.

i. Detailed comparison of Contractor's Construction Schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating lack of availability or delays in delivery.

j. Cost information, including a proposal of change, if any, in the Contract Sum.

k. Contractor's certification that proposed substitution complies with requirements in the Contract Documents and is appropriate for applications indicated.

l. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

2. Government Action: If necessary, Government will request additional information or documentation for evaluation within 7 days of receipt of a request for substitution.

Government will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Form of Acceptance: Modification.

b. Use product specified if Government cannot make a decision on use of a proposed substitution within time allocated.

B. Comparable Product Requests: Submit one electronic copy of each request for consideration.

Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Government Action: If necessary, Government will request additional information or documentation for evaluation within one week of receipt of a comparable product request. Government will notify Contractor of approval or rejection of proposed comparable product request within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Form of Approval: As specified in Division 1 Section "Submittal Procedures."

b. Use product specified if Government cannot make a decision on use of a comparable product request within time allocated.

C. Basis-of-Design Product Specification Submittal: Comply with requirements in Division 1 Section "Submittal Procedures." Show compliance with requirements.

1.3 DEFINITIONS

A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

GAOA MILNER PICNIC CABANA REPLACEMENT 016000-3

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature, that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility, except that products consisting of recycled-content materials are allowed, unless explicitly stated otherwise. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

C. Basis-of-Design Product Specification: Where a specific manufacturer's product is named and accompanied by the words "basis of design," including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of other named manufacturers.

1.4 QUALITY ASSURANCE

A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, product selected shall be compatible with products previously selected, even if previously selected products were also options.

1.5 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.

B. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Load and unload products in manner that protects from damage.

5. Inspect products on delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected.

C. Storage:

1. Store products to allow for inspection and measurement of quantity or counting of units.

GAOA MILNER PICNIC CABANA REPLACEMENT 016000-4

2. Store materials in a manner that will not endanger Project structure.

3. Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground, with ventilation adequate to prevent condensation.

4. Store cementitious products and materials on elevated platforms.

5. Store foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment.

6. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage.

7. Protect stored products from damage and liquids from freezing.

1.6 PRODUCT WARRANTIES

A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.

1. Manufacturer's Warranty: Preprinted written warranty published by individual manufacturer for a particular product and specifically endorsed by manufacturer to Government.

2. Special Warranty: Written warranty required by or incorporated into the Contract Documents, either to extend time limit provided by manufacturer's warranty or to provide more rights for Government.

B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution. Submit a draft for approval before final execution.

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

2. Specified Form: When specified forms are included with the Specifications, prepare a written document using appropriate form properly executed.

3. Refer to Divisions 2 through 33 Sections for specific content requirements and particular requirements for submitting special warranties.

C. Submittal Time: Comply with requirements in Division 1 Section "Closeout Procedures."

PART 2 - PRODUCTS

2.1 PRODUCT SELECTION PROCEDURES

A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and, unless otherwise indicated, that are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

GAOA MILNER PICNIC CABANA REPLACEMENT 016000-5

3. Government reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

4. Where products are accompanied by the term "as selected," Government will make selection.

5. Where products are accompanied by the term "match sample," sample to be matched is Government's.

6. Descriptive, performance, and reference standard requirements in the Specifications establish "salient characteristics" of products.

B. Product Selection Procedures:

1. Product: Where Specifications name a single product and manufacturer, provide the named product that complies with requirements.

2. Manufacturer/Source: Where Specifications name a single manufacturer or source, provide a product by the named manufacturer or source that complies with requirements.

3. Available Products: Where Specifications include a list of names of both products and manufacturers, provide one of the products listed, or an unnamed product, that complies with requirements. Comply with provisions in Part 2 "Comparable Products" Article for consideration of an unnamed product.

4. Available Manufacturers: Where Specifications include a list of manufacturers, provide a product by one of the manufacturers listed, or an unnamed manufacturer, that complies with requirements. Comply with provisions in Part 2 "Comparable Products" Article for consideration of an unnamed product.

5. Product Options: Where Specifications indicate that sizes, profiles, and dimensional requirements on Drawings are based on a specific product or system, provide the specified product or system. Comply with provisions in Part 2 "Product Substitutions" Article for consideration of an unnamed product or system.

6. Basis-of-Design Product: Where Specifications name a product and include a list of manufacturers, provide the specified product or a comparable product by one of the other named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with provisions in Part 2 "Comparable Products" Article for consideration of an unnamed product by the other named manufacturers.

7. Visual Matching Specification: Where Specifications require matching an established Sample, select a product that complies with requirements and matches Government's sample. Government's decision will be final on whether a proposed product matches.

a. If no product available within specified category matches and complies with other specified requirements, comply with provisions in Part 2 "Product Substitutions" Article for proposal of product.

8. Visual Selection Specification: Where Specifications include the phrase "as selected from manufacturer's colors, patterns, textures" or a similar phrase, select a product that complies with other specified requirements.

a. Standard Range: Where Specifications include the phrase "standard range of colors, patterns, textures" or similar phrase, Government will select color, pattern, density, or texture from manufacturer's product line that does not include premium items.

b. Full Range: Where Specifications include the phrase "full range of colors, patterns, textures" or similar phrase, Government will select color, pattern, density, or

GAOA MILNER PICNIC CABANA REPLACEMENT 016000-6

texture from manufacturer's product line that includes both standard and premium items.

2.2 PRODUCT SUBSTITUTIONS

A. Timing: Government will consider requests for substitution if received within 30 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Government.

B. Conditions: Government will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Government will return requests without action, except to record noncompliance with these requirements:

1. Requested substitution offers Government a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Government must assume. Government additional responsibilities may include compensation to Contractor for redesign and evaluation services, increased cost of other construction by Government, and similar considerations.

2. Requested substitution does not require extensive revisions to the Contract Documents.

3. Requested substitution is consistent with the Contract Documents and will produce indicated results.

4. Substitution request is fully documented and properly submitted.

5. Requested substitution will not adversely affect Contractor's Construction Schedule.

6. Requested substitution has received necessary approvals of authorities having jurisdiction.

7. Requested substitution is compatible with other portions of the Work.

8. Requested substitution has been coordinated with other portions of the Work.

9. Requested substitution provides specified warranty.

2.3 COMPARABLE PRODUCTS

A. Conditions: Government will consider Contractor's request for comparable product when the following conditions are satisfied. If the following conditions are not satisfied, Government will return requests without action, except to record noncompliance with these requirements:

1. Evidence that the proposed product does not require extensive revisions to the Contract Documents that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work.

2. Detailed comparison of significant qualities of proposed product with those named in the Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

3. Evidence that proposed product provides specified warranty.

4. List of similar installations for completed projects with project names and addresses and names and addresses of COR’s and Government’s, if requested.

5. Samples, if requested.

GAOA MILNER PICNIC CABANA REPLACEMENT 016000-7

END OF SECTION 016000

JUNE 2025 EXECUTION REQUIREMENTS

GAOA MILNER PICNIC CABANA REPLACEMENT 017300-1