GAMT III-Questions RFI_Sources Sought.pdf

PDF 153 KB Posted

Attached to
REQUEST FOR INFORMATION - SOURCES SOUGHT - Germany Air Mail Terminal (GAMT) III Federal contract opportunity
Solicitation number
08142020
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

This document contains a Request for Information for a Sources Sought notice regarding mail processing services at the Germany Air Mail Terminal III facility. The incumbent contractor will provide receipt, dispatch, handling, distribution, and transportation of mail for military, Department of Defense civilians, and contractors assigned within the European Theater and other areas of responsibility. The contractor will also manage postal equipment and supplies shipments. The government is seeking feedback on requirements and process weights by September 11, 2020. Pricing will be based on weight, and the contractor must be able to handle surges during contingencies by adding capacity and staffing. The preferred contract line item structure and any other questions or innovative solutions are also requested.

View the file

Other files for this federal contract opportunity

Other files attached to REQUEST FOR INFORMATION - SOURCES SOUGHT - Germany Air Mail Terminal (GAMT) III, newest first.
File Type Posted
GAMT III-RFI_DraftPWS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Germany Air Mail Terminal III (GAMT III) – Questions RFI

1. If the processing of registered mail was added to the PWS, a number of requirements would be added to include the handling of registered mail by U.S. citizens with a secret clearance only. If the decision were made pre-award, what impact would it have to your current proposal? What if it were added post-award?

2. If the government adds the requirement to process registered mail after the contract award date and you chose to not take on this additional requirement, would you be willing to share the mail processing facility (at a cost) with a different contractor who would process the registered mail?

3. Paragraph 4 of the PWS identifies how the government determines the weight of all mail processed. Considering payment is based on weight, will you require additional processes to validate these weights or do you accept the weights as listed on the AV-7s (for commercial air movement) or in AMPS (for surface container movement)?

4. How would you handle significant mail surges during natural disasters, pandemics, or wartime contingencies that may require additional manning and facility space?

5. What is the preferred CLIN structure for this requirement?

6. Are there any other questions/concerns for this requirement?

7. Are there any alternative or innovative solutions for this requirement?

File details come from the government source that posted it. Updated .